table of contents s. no particulars pagesmanireda.com/wp-content/uploads/2016/07/petition-for... ·...
TRANSCRIPT
1
TABLE OF CONTENTS
S. No Particulars Pages
1 Form 1 2
2 Form 2 3
3 Affidavit 4
4 Petition 5-24
5 Annexure-I Tariff norms 25
2
BEFORE THE HONOURABLE JOINT ELECTRICITY REGULATORY
COMMISSION FOR THE STATES OF MANIPUR AND MIZORAM, AIZAWL
FILE NO.
CASE NO.
(To be filled by the Office)
IN THE MATTER OF:
Petition for determination of generic levellised tariff for solar rooftop projects
under section 61 (h) and section 86 (1) (e) of the Electricity Act 2003 and Para 6.4
(7) of the National Tariff Policy
AND
IN THE MATTER OF:
MANIPUR RENEWABLE ENERGY DEVELOPMENT AGENCY, having its
registered office at SAI Complex Takyel, Imphal-795001 …....…Petitioner
Vs
Manipur State Power Distribution Company Limited (MSPDCL), having its
registered office at, Electricity Complex, Patta No. 1293 under 87 (2), Khwai Bazar,
Keishampat, Manipur-795001 ……Respondent
3
BEFORE THE HONOURABLE JOINT ELECTRICITY REGULATORY
COMMISSION FOR THE STATES OF MANIPUR AND MIZORAM, AIZAWL
FILE NO.
CASE NO.
IN THE MATTER OF:
Petition for determination of generic levellised tariff for solar rooftop projects
under section 61 (h) and section 86 (1) (e) of the Electricity Act 2003 and Para 6.4
(7) of the National Tariff Policy
AND
IN THE MATTER OF:
MANIPUR RENEWABLE ENERGY DEVELOPMENT AGENCY, having its
registered office at SAI Complex Takyel, Imphal-795001 …....…Petitioner
Vs
Manipur State Power Distribution Company Limited (MSPDCL), having its
registered office at, Electricity Complex, Patta No. 1293 under 87 (2), Khwai Bazar,
Keishampat, Manipur-795001 ……Respondent
4
AFFIDAVIT VERIFYING THE PETITION
I, son of ………………………… aged ………………………residing at
………………………… do hereby solemnly affirm and state as follows:
1. I am a Director / Secretary / …………………………………………… of
…………………………… Ltd., the petitioner in the above matter and am duly
authorized by the said petitioner to make this affidavit on its behalf.
2. The statements made in paragraphs 1-2, 5 of the petition herein now shown to
me and marked with the letter ‘A’ are true to my knowledge and the statements made in
paragraphs 3,4,6-57 are based on information received from various public sources and
I believe them to be true.
Deponent
Verification:
I, the deponent above named do hereby verify that the contents of my above affidavit
are true to my knowledge; no part of it is false and nothing material has been concealed
therefrom
Verified at ……….. on the day of …………….
Place: Aizawl
Deponent
5
THE PETITIONER MOST RESPECTFULLY SUBMIT AS UNDER:-
FACTS OF THE PETITION:
1) A. Manipur Renewable Energy Development Agency (MANIREDA) is an
autonomous government agency under the Department of Power, setup for
promoting renewable energy sources in the state. MANIREDA is filing this petition
with regards to determining tariff for solar rooftop projects in the state. Hereinafter,
MANIREDA is referred as Petitioner.
2) A. The Government of Manipur has notified for “Manipur Grid Interactive Rooftop
solar PV power policy” 2014, by issuing Gazette notification on 7th January 2015.
As per the policy all individuals,
residents/commercials/institutional/government/semi government building owners
are eligible to set up projects under this policy for a capacity of 1 kW to 500 kW.
3) It may be noted that this Hon’ble Commission issued Order “Determination of
generic levellised generation tariff for the FY2014-15 under Regulation 8 of
the Joint Electricity Regulatory Commission for Manipur & Mizoram (Terms and
Conditions for Tariff determination from Renewable Energy Sources) Regulations,
2010”, dated 5th January, 2015.
4) We would also like to submit that even though the Hon’ble Commission has
determined tariff for solar PV projects, the norms for determination of tariff for MW
size solar PV projects are different from norms for smaller size (kW scale) solar
rooftops projects. One of the major differences affecting the normalized cost of
kilowatt-scale photovoltaic power plants compared to megawatt-scale plants is the
cost of inverters and other equipment and accessories which are higher than
6
comparable cost for MW size solar projects. Therefore, it is suggested to kindly
determine separate tariff for solar rooftop (kW scale) projects based on the norms
proposed in this petition.
5) A. After announcement of the policy, many individuals and parties enquired the
Petitioner about the feed-in-tariff rate for injecting power from solar rooftop
projects feeding the solar power to the state power grid.
6) MANIREDA being the nodal agency for promotion of renewable energy in the state
is filing this Petition before the Hon’ble Commission for determination for generic
tariff for solar rooftop projects with capacity size from 1 kW to 500 kW. The
existing tariff approved by the Commission under its Order dated January 5, 2015
can be made applicable to MW size solar PV projects for capacity above 500 kW.
7) The Petitioner would like to humbly submit that other Regulatory Commissions
including Maharashtra Electricity Regulatory Commission (MERC), Gujarat
Electricity Regulatory Commission (GERC), Madhya Pradesh Electricity
Regulatory Commission (MPERC) and Karnataka Electricity Regulatory
Commission (KERC) have also determined separate tariffs for solar rooftop (kW
scale) and large MW size solar projects. The table below provides tariff approved
by various Regulatory Commissions for solar rooftops (kW) and MW size solar PV
projects
Regulatory
Commission
Financial Year Tariff for solar
rooftops
Tariff for solar
PV projects
MERC FY 2015-16 Rs 7.58/kWh Rs 7.08/kWh
7
Regulatory
Commission
Financial Year Tariff for solar
rooftops
Tariff for solar
PV projects
GERC FY 2015-16 Rs 8.42/kWh Rs 6.77/kWh
MPERC FY 2015-16 Rs 10.70/kWh Rs 10.44/kWh
KERC FY 2013-141 Rs 9.56/kWh Rs 8.40/kWh
JERC (Goa
and UT)
FY 2014-15 to FY
2016-17
Rs 9.43/kWh2 Rs 8.73/kWh3
8) The Petitioner would like to humbly submit that as per Section 61(h) and
Section 86(1)(e) of Electricity Act 2003 (hereinafter referred as EA 2003) the
State Electricity Regulatory Commissions are empowered to take necessary
measures for promotion of renewable energy based generation in the State. The
relevant text of Section 61 (h) and Section 86(1)(e) is reproduced below:
“61. Tariff regulations.- The Appropriate Commission shall, subject to the
provisions of this Act, specify the terms and conditions for the determination of
tariff, and in doing so, shall be guided by the following, namely: -
…
(h) the promotion of co-generation and generation of electricity from renewable
source of energy;
“86. (1) The State Commission shall discharge the following functions, namely:
-
1 The tariff for FY 2015-16 for MW size solar rooftops has been approved at Rs 6.51/kWh. However, tariff determination for kW scale projects is under draft stage. 2 Upto 500 kW 3 For projects more than 500 kW
8
(e) Promote cogeneration and generation of electricity from renewable sources
of energy by providing suitable measures for connectivity with the grid and sale
of electricity to any person, and also specify, for purchase of electricity from
such sources, a percentage of the total consumption of electricity in the area of
a distribution licence.”
9) The Para 6.4 (7) of the National Tariff Policy provides that the Electricity
Regulatory Commission endeavor to promote generation from renewable energy
projects and most specifically generation from solar rooftop projects. The relevant
text of the Para 6.4 (7) is cited below:
Appropriate Commission may provide regulatory framework to facilitate generation
and sale of electricity from renewable energy sources particularly from roof-top
solar system by any entity including local authority, Panchayat Institution, user
institution, cooperative society, Non-Governmental Organization, franchisee or by
Renewable Energy Service Company. The Appropriate Government may also
provide complementary policy support for this purpose.
Explanation: “Renewable Energy Service Company” means an energy service
company which provides renewable energy to the consumers in the form of
electricity.
10) Considering immense potential for development of solar power including solar
rooftops, the government of India revised the solar capacity addition target under
National Solar Mission from 20 GW to 100 GW by FY 2021-22. Out of the 100
GW solar target, 40 GW capacity addition is targeted from solar rooftop projects.
9
11) The Petitioner humbly submits that the Ministry of New and Renewable Energy has
also allocated a target of 105 MW to be developed in the state of Manipur under the
Jawaharlal Nehru National Solar Mission (JNNSM) program. With constraints on
availability of land and difficult terrain, significant portion (50 MW) of this target
will have to be met through development of solar rooftop. Hence, it is essential to
ensure a conducive tariff framework for solar rooftop exists in the state of Manipur,
to ensure that solar rooftop capacity addition takes place. Any delay in announcing
tariff for solar rooftops will hamper investments planned in the state. The year wise
solar rooftop capacity addition targets (in MW) for the state of Manipur is tabulated
below:
Category 2015-
16
2016-
17
2017-
18
2018-
19
2019-
20
2020-
21
2021-
22
Total
Roof-top
solar
4 3 6 8 9 10 10 50
12) Petitioner humbly submits that Manipur has a good potential of Solar Energy.
About 280-300 sunny days are available in the State which provides an excellent
potential for installation of Rooftop and other Small Solar Power Plants in the State.
The sunshine period per day on an average comes to about 8-10 hours, of which
effective solar energy would be for about 4.5 - 6 hours per day.
13) Renewable Energy in general and solar energy in particular is not only cheaper and
faster to implement but also offers solutions to various social and economic
10
difficulties facing Manipur, including energy access to remote areas, employment
generation etc.
14) The grid connected rooftop solar photovoltaic power generation plants, generates
electricity at the consumption center and hence contributes to reducing the network
losses of the distribution licensee. The electricity generation shall also contribute to
meeting the demand and supply gap and shall also enable the obligated entities for
complying with their solar purchase obligation targets as specified by appropriate
Electricity Regulatory Commissions’. India has a huge potential for deployment of
grid connected rooftop solar photovoltaic power generation plants and the MNRE
envisages harnessing this potential.
GROUNDS OF THE PETITION:
15) The Electricity Act vide Section 61(h) and Section 86(1)(e) of EA 2003empowers
the State Electricity Regulatory Commissions to take necessary measures for
promotion of renewable energy based generation in the State.”
16) National Electricity Policy issued by Government of India dated February 12, 2005
has been a guiding benchmark for various Orders issued by the Hon’ble
Commission for the promotion of Renewable energy sources. National Electricity
Policy provides that the renewable energy potential should be exploited fully to
create additional power capacity and private participation should be encouraged by
providing necessary promotional measures.
11
5.2.20 Feasible potential of non-conventional energy resources, mainly small
hydro, wind and bio-mass would also need to be exploited fully to create
additional power generation capacity. With a view to increase the overall share
of non-conventional energy sources in the electricity mix, efforts will be made to
encourage private sector participation through suitable promotional
measures”..(Emphasis Added)
17) Further, the Tariff Policy (TP) notified by the Central Government in pursuance of
the Section 3 of the EA 2003 has stipulated that Appropriate Commission to
determine ‘preferential tariffs’ for procurement of power by distribution licensees
from non-conventional energy sources. The Tariff Policy also mandates
development of suitable regulatory framework to facilitate generation and sale of
electricity from rooftop solar projects.
The relevant extract of clause 6.4 of the NTP is as under -
Pursuant to provisions of section 86(1)(e) of the Act, the Appropriate
Commission shall fix a minimum percentage of the total consumption of
electricity in the area of a distribution licensee for purchase of energy from
renewable energy sources, taking into account availability of such resources
and its impact on retail tariffs. Cost of purchase of renewable energy shall be
taken into account while determining tariff by SERCs. Long term growth
trajectory of Renewable Purchase Obligations (RPOs) will be prescribed by the
Ministry of Power in consultation with MNRE.
…………………………………..
Within the percentage so made applicable, to start with, the SERCs shall also
reserve a minimum percentage for purchase of solar energy from the date of
12
notification of this policy which shall be such that it reaches 8% of total
consumption of energy, excluding Hydro Power, by March 2022 or as notified
by the Central Government from time to time.
6.4.7 Appropriate Commission may provide regulatory framework to facilitate
generation and sale of electricity from renewable energy sources particularly
from roof-top solar system by any entity including local authority, Panchayat
Institution, user institution, cooperative society, Non-Governmental
Organization, franchisee or by Renewable Energy Service Company. The
Appropriate Government may also provide complementary policy support for
this purpose. (Emphasis Added)
Principles for determination of Preferential tariff on Cost-Plus basis
18) It is evident from provisions of NTP that preferential tariff for renewable energy is
to be determined by the Appropriate Commission, in accordance with Section 61 of
the Electricity Act 2003. While determining tariff it is necessary to ascertain
benchmark costs and underlying assumptions thereof.
19) In this section, the Petitioner has given its views on key assumptions that may be
considered keeping in mind ground realities and need to encourage development of
solar rooftop projects in the state.
A. Capital Cost
20) In its Tariff Order dated January 5, 2015, the Hon’ble Joint Electricity Regulatory
Commission (Manipur and Mizoram) had approved a capital cost of Rs 691
13
lakhs/MW for solar PV projects in the state to be commissioned in FY 2014-15.
This capital cost was fixed in line with capital cost approved for solar PV projects,
by CERC in generic tariff Order for FY 2014-15.
21) However, the approved capital cost is not apropos to the kilowatt-scale rooftop
projects in the state. One of the major differences affecting the normalized cost of
kilowatt-scale photovoltaic power plants compared to megawatt-scale plants is the
cost of inverters and other equipment and accessories which are higher than
comparable cost for MW size solar projects. Therefore, the capital cost approved by
the Hon’ble JERC does not represent the capital cost for kW size solar rooftop
projects. Besides, with regard to the approachability the Manipur is situated at a
difficult terrain and bringing plant and machinery for smaller project would be even
costlier, the fact which need to be taken into account while considering capital cost
of the solar projects in the Manipur.
22) The capital cost for solar rooftop projects (kW scale projects) as compared to MW
size projects, as approved by various Regulatory Commissions (for FY 2015-16) is
tabulated below.
Regulatory
Commission
Financial
Year
Capital cost for kW
scale solar rooftops
(Rs/Wp)
Capital cost for
MW size solar
projects (Rs/Wp)
GERC FY 2015-16 Rs 80/Wp Rs 61.50/Wp
KERC FY 2015-16 Rs 75/Wp4 Rs 57.50/Wp
4 As per discussion paper dated 16 November 2015
14
Regulatory
Commission
Financial
Year
Capital cost for kW
scale solar rooftops
(Rs/Wp)
Capital cost for
MW size solar
projects (Rs/Wp)
JERC (Goa and
UT)
FY 2014-15 to
FY 2016-17
Rs 82/Wp5 Rs 75/Wp6
23) Apart from the capital cost approved by Regulatory Commissions, the weighted
average capital cost discovered through bidding undertaken by Solar Energy
Corporation of India for implementation of 24 MW grid connected rooftop solar PV
projects (Phase IV-Part 2-Part A, dated 16 July 2015) for various states in the
eastern region is tabulated below:
State Capacity in kW Weighted average Unit rate
(Rs/Wp)
West Bengal 375 kW Rs 75/Wp
Jharkhand 187.50 kW Rs 79.80/Wp
Odisha 375 kW Rs 74.60/Wp
24) The Petitioner would also like to humbly submit that the benchmark capital cost for
solar rooftop projects as fixed by MNRE is Rs 75/Wp. Considering that cost of
transporting solar rooftop plant and machinery in Manipur is significantly higher
than the national average and almost account for 10-15% of the total hardware cost,
the actual capital cost for setting solar rooftop project in Manipur is comparatively
higher than the national benchmark cost of Rs 75/Wp.
5 For projects up to 500 kW (in all territories of JERC except Lakshadweep and Andaman and Nicobar) 6 For projects more than 500 kW (in all territories of JERC except Lakshadweep and Andaman and Nicobar)
15
25) The capital cost for solar rooftop projects in Manipur is estimated at Rs
82/kW. The various cost heads are tabulated below:
Cost Head Cost (Rs’000/kW)
Solar module cost 36
Invertor cost 10
Mounting structure 7
Balance of systems (transformers, wiring,
meters etc.)
6
Transportation and insurance cost 9
Installation cost including civil and electrical
works
6
Contingency at 3% 3
Taxes 6
Total cost 82
26) Apart from the capital cost discussed above, there is separate cost component of
agency charges which account for 11.75% of the total cost estimate. The same was
levied by the Govt. of Manipur under Office Memorandum dated October 26, 2013.
The agency charges is levied on the works undertaken through government
agencies. Therefore any solar rooftop installation work undertaken by government
agencies will have to pay 11.75% on the total estimated cost of Rs 82000/kW.
16
27) Accordingly, the Petitioner hereby humbly requests to approve the benchmark
capital cost for solar rooftop projects as Rs 82000/kW. Any agency charges
should be pass through at actuals.
B. Capacity Utilization Factor and annual degradation
28) Capacity utilization factor (CUF) represents important parameter that influences the
economics of a solar rooftop project. The Hon’ble Commission in its generic tariff
Order dated 5th January 2015 has considered normative CUF of 19% solar PV
projects, in line with CERC RE Tariff Regulations
29) Apart from CERC various other State Electricity Regulatory Commissions
including MERC, GERC, MPERC, KERC have notified normative CUF of 19% for
solar PV projects including rooftops.
30) Accordingly, the Petitioner hereby humbly requests that the normative CUF of
19% be considered for solar rooftop projects.
C. Depreciation
31) The Para 5.8.2 of the National Electricity Policy provides that appropriate
depreciation reserves should be created so as to fully meet the debt service
obligations. The said clause is reproduced below for reference:
“5.8.2. The public sector should be able to raise internal resources so as to at
least meet the equity requirement of investments even after suitable gross
budgetary support from the Government at the Centre and in the states in order
to complete their on-going projects in a time-bound manner. Expansion of
public sector investments would be dependent on the financial viability of the
17
proposed projects. It would, therefore, be imperative that an appropriate
surplus is generated through return on investments and, at the same time,
depreciation reserve created so as to fully meet the debt service obligation.
This will not only enable financial closure but also bankability of the project
would be improved for expansion programmes, with the Central and State level
public sector organizations, as also private sector projects, being in a position
to fulfil their obligations toward equity funding and debt
repayments.”(Emphasis Added)
32) Considering debt service obligation of 70% of the capital cost and repayment period
of 12 years, the annual debt service obligation works out to 5.83%.
33) Based on the same principle, Hon’ble CERC has allowed a depreciation rate of
5.83% for first 12 years and balance depreciation spread over useful life and thereby
allowing solar project developers to recover debt amount. The relevant Regulation
is cited below for reference
"(1) The value base for the purpose of depreciation shall be the Capital Cost of
the asset admitted by the Commission. The Salvage value of the asset shall be
considered as 10% and depreciation shall be allowed up to maximum of 90% of
the Capital Cost of the asset. (2) Depreciation per annum shall be based on
‘Differential Depreciation Approach' over loan period beyond loan tenure
over useful life computed on ‘Straight Line Method’. The depreciation rate for
the first 12 years of the Tariff Period shall be 5.83% per annum and the
18
remaining depreciation shall be spread over the remaining useful life of the
project from 13th year onwards. (3) Depreciation shall be chargeable from the
first year of commercial operation. Provided that in case of commercial
operation of the asset for part of the year, depreciation shall be charged on pro
rata basis"(Emphasis Added)
34) In the light of above facts, the Hon’ble Commission is requested to consider the
depreciation rate in line with CERC Regulation at the rate of 5.83% for first
12 year and the remaining depreciation amount be spread over the remaining
tenure of the useful life
D. Operation & Maintenance Expense
35) O&M expense primarily includes three major components viz., the employee
expenses, administrative and general expenses and the expenses towards repair and
maintenance.
36) The major O&M cost incurred for a solar PV plant is towards the activities such as
scheduled maintenance including cleaning of PV panels, unscheduled maintenance
at the solar PV plant and the associated labour & material cost.
37) The normative O&M cost approved by various State Electricity Regulatory
Commissions is tabulated below.
SERC Financial Year Normative O&M
MERC FY 2015-16 Rs 1300 /kW with 5.72% annual escalation
19
RERC FY 2015-16 Rs 1300 /kW with 5.85% annual escalation
KERC FY 2015-16 Rs 1800/kW7 with 5.72% escalation
38) In the light of above facts, this Hon’ble Commission is requested to consider
the normative O&M of 2% of base capital cost (Rs 82000/kW) or Rs 1640/kW
with 5.72% annual escalation.
E. DEBT-EQUITY RATIO
39) Sub-Regulation (1) of Regulation 13 of the JERC RE Tariff Regulations provides
that the debt- equity ratio of 70:30 is to be considered for determination of generic
tariff based
40) Based on the debt equity ratio of 70:30, the debt and equity components of
the normative capital cost for determination of tariff for the solar rooftop RE
projects have been worked out under the petition.
F. Interest on Debt
41) CERC under its RE Tariff Regulations has specified norm for interest on debt as
average SBI Base rate for first six months of the previous year plus 300 basis points.
The relevant clause is cited below for reference:
“(a) The loans arrived at in the manner indicated in the Regulation 13 shall be
considered as gross normative loan for calculation for interest on loan. The
normative loan outstanding as on April 1st of every year shall be worked out by
7 Considered as 2% of capital cost
20
deducting the cumulative repayment up to March 31st of previous year from the
gross normative loan.
(b) For the purpose of computation of tariff, the normative interest rate shall be
considered as average State Bank of India (SBI) Base rate prevalent during the
first six months of the previous year plus 300 basis points.
(c) Notwithstanding any moratorium period availed by the generating company, the
repayment of loan shall be considered from the first year of commercial operation
of the project and shall be equal to the annual depreciation allowed"
42) Accordingly, the average SBI base rate prevalent during first six months of the year
FY 2015-16 has been considered for computation of applicable interest rate. The
average SBI Base Rate of first six months of FY 2015-16 was 9.77%. Therefore,
interest on debt for FY 2015-16 works out to 12.77% (i.e. 9.77%) plus 300 basis
points
43) The normative interest on loan approved by various State Electricity Regulatory
Commissions is tabulated below.
SERC Financial Year Normative interest on loan
GERC FY 2015-16 SBI base rate (average of first six months of
previous financial year) plus 300 basis point
KERC FY 2015-16 12.50%
21
MPERC FY 2015-16 12.75%
RERC FY 2015-16 SBI base rate (average of first six months of
previous financial year) plus 300 basis point
44) Thus, the Petitioner requests the Hon’ble Commission to approve the
normative interest rate on loan as 12.77% and a loan tenure of 12 years for
determination of tariff for solar rooftops.
G. Interest on Working Capital
45) The Petitioner would like to submit that the Hon’ble Commission in generic RE
Tariff Order dated January 5, 2015 has specified norm for interest on working
capital norm in line with CERC Regulations. The same is cited below:
“(1) The Working Capital requirement in respect of wind energy projects, Small
Hydro Power, Solar PV and Solar thermal power projects shall be computed in
accordance with the following:
Wind Energy / Small Hydro Power /Solar PV / Solar thermal
a) Operation & Maintenance expenses for one month;
b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity
calculated on the normative CUF;
c) Maintenance spare @ 15% of operation and maintenance expenses
…………..
22
(3) Interest on Working Capital shall be at interest rate equivalent to the average
State Bank of India Base Rate prevalent during the first six months of the previous
year plus 350 basis points”
46) Considering the above regulation average SBI base rate of 9.77% for first six
months of FY 2015-16, the interest on working capital for FY 2015-16 works out to
13.27% (i.e. 9.77% plus 350 basis points)
47) Thus, the Petitioner requests the Hon’ble Commission to approve the interest
rate on working capital as 13.27% in line with CERC Regulations. The
components of working capital to include 1 month of O&M cost, 15% of O&M
cost towards maintenance spares and 2 month of receivables for debtors
H. Return on Equity
48) The Petitioner would like to submit that the Hon’ble Commission in generic RE
Tariff Order dated January 5, 2015 has specified return on equity norms as cited
below:
Sub-Regulation (1) of amended Regulation 16 of the RE Tariff Regulations
provides that the value base for the equity shall be 30% of the capital cost for
generic tariff determination. Sub-Regulation (2) of the said Regulation
stipulates the normative return on equity (ROE) as under:
(a) 20% per annum for the first 10 years, and
(b) 24% per annum from the 11th year onwards.
23
49) CERC under its RE Tariff Regulations has also specified norm for return of equity
of 20% pre-tax for the first 10 years followed by 24% pre-tax for 11th year onwards.
50) Similar provisions with regards to normative ROE of 20% pre-tax for the first 10
years followed by 24% pre-tax for 11th year onwards, is approved by other State
Electricity Regulatory Commissions including MERC, RERC for solar rooftop
projects.
51) Considering post tax ROE of 16% and the current corporate and MAT tax
rates (including corporate tax rate of 34.61% and MAT rate of 21.34%), we
request the Hon’ble Commission to consider pre-tax ROE of 20.34% for the
first 10 years followed by 24.47% pre-tax from 11th year onwards
I. Discount Factor
The discount factor considered for the purpose of levellised tariff computation is
equal to the Post Tax weighted average cost of the capital on the basis of normative
debt: equity ratio (70:30) specified in the Regulations. Considering the normative debt
equity ratio and weighted average of the post-tax rates for interest and equity
component, the discount factor is calculated. Interest Rate considered for the loan
component (i.e.70%) of Capital Cost is 12.77% (as explained earlier). For equity
component (i.e. 30%) rate of Return on Equity (ROE) considered at Post Tax ROE of
16% considered. The discount factor derived by this method for all technology is
10.65% i.e. ((12.77% × 0.70 × (1 – 34.61%)) + (16.0% × 0.30)).
J. Proposed Tariff
52) The summary of assumptions proposed by the Petitioner is tabulated below:
24
Parameters Value Assumption Remarks
Capital cost for FY
2015-16
Rs 82000/kW Benchmarking with capital
cost approved by various
SERCs and discovered
through bidding route
CUF and deration 19%
As per principle followed by
JERC generic tariff order
dated January 5, 2015 for
solar PV projects
Useful life 25 years As per standard practice
Debt: Equity ratio 70:30 As per standard practice
Term on loan 12 years As per principle followed by
Hon’ble JERC generic tariff
order dated January 5, 2015
Interest on Debt 12.77% As per principle followed by
Hon’ble JERC generic tariff
order dated January 5, 2015
Return on Equity Pre- Tax 20.34% (first
10 years) & 24.47%
(from 11th year
onwards)
As per principle followed by
Hon’ble JERC generic tariff
order dated January 5, 2015
Depreciation rate 5.83% (for first 12
years) and 1.54%
(from 13th year
onwards)
As per principle followed by
Hon’ble JERC generic tariff
order dated January 5, 2015
O&M expenses per
annum
2% of capital cost OR
Rs 1640/kW with
annual escalation of
5.72%
Benchmarking with O&M
norm approved by various
SERCs
25
Parameters Value Assumption Remarks
Components of working
capital
1 month of O&M cost,
15% of O&M cost
towards maintenance
spares and 2 months of
receivables for debtors
As per principle followed by
Hon’ble JERC generic tariff
order dated January 5, 2015
Interest on Working
Capital
13.27%. As per principle followed by
Hon’ble JERC generic tariff
order dated January 5, 2015.
Average SBI Base Rate
(9.77%) plus 350 basis point
53) MNRE in its notification dated 4th March 2016, has notified subsidy benefit to the
account of 70% of benchmark capital cost for grid connected solar rooftop projects
installed in the North east. However, the subsidy benefit is only limited to
residential, institutional (hospitals, education institutes etc.) and no subsidy is
provided to commercial and industrial users. Therefore, it is suggested to determine
separate tariff for entities availing subsidy and not availing subsidy.
54) Based on the above assumptions the levellised tariff for solar rooftop projects with
and without subsidy benefits is tabulated below.
Category Levellised Tariff (Rs/kWh)
Without subsidy Rs 9.49/kWh
With 70% subsidy Rs 4.41/kWh
26
55) The work sheet (assumption sheet) is attached as Annexure I.
PRAYERS
The Petitioner would like to request the Hon’ble Commission:
1) To kindly admit this Petition and grant an opportunity in person before Hon’ble
Commission during hearing on the above matter
2) To determine solar rooftop tariff for projects size from 1 kW to 500 kW on the
power injected into the grid for FY 2016-17, as per cost plus basis regime as
outlined in this Petition.
3) To kindly exempt payment of petition filing fees
4) To condone any inadvertent omissions/ errors/ short comings and permit
Petitioner to add/ change/ modify/ alter this filing and make further submissions
as may be required at a future date.
Date:
Place: (PETITIONER)
27
Annexure I-Tariff assumption sheet
S. No.Assumption
HeadSub-Head Sub-Head (2) Unit Tariff Parameter
1 Power Generation
Capacity
Installed Power Generation Capacity kW 1
Capacity Utilization Factor % 19.00%
Deration Factor % 0.00%
Useful Life Years 25
2 Project Cost
Capital Cost/MW Benchmark cost by MNRE Rs/kW 75000
Cost without subsidy benefit Rs/kW 82000
Cost considering 70% subsidy Rs/kW 29500
3 Sources of Fund
Tariff Period Years 25
Debt: Equity
Debt % 70%
Equity % 30%
Total Debt Amount Rs 20650
Total Equity Amout Rs 8850
Debt Component
Loan Amount Rs 20650
Moratorium Period years 0
Repayment Period(incld Moratorium) years 12
Interest Rate % 12.76%
Equity Component
Equity amount Rs 8850
Return on Equity for first 10 years % p.a 20.34%
RoE Period Year 10
Return on Equity 11th year onwards % p.a 24.47%
Weighted average of ROE 22.82%
Discount Rate 10.64%
4 Financial Assumptions
Fiscal Assumptions
Income Tax(from 11th to 20) % 34.61%
MAT Rate (for first year) % 21.34%
80 IA benefits Yes/No Yes
Depreciation
Depreciation Rate for first 12 years % 5.83%
Depreciation Rate 13th year onwards % 1.54%
5 Working Capital
O&M Charges Months 1
Receivables for Debtors Months 2
Maintenance and Spares % 15%
Interest On Working Capital % 13.26%
6 Operation & Maintenance
power plant (First year) Rs 1640
Total O & M Expenses Escalation % 5.72%