tac12 report back outline:organization cessamag part a building injector control tac 2013 reporting...
TRANSCRIPT
1
TAC12 report back
Outline: OrganizationCESSAMag Part ABuildingInjectorControl
TAC 2013 Reporting back E.Huttel
2
OrganizationCentral sector serving machine and BL:Not formalized, new structure would need approval of council,
head of central sector to be assignedInformal practiced.
Control/ComputingStaff: One (A.Ismail) employed, one left (Z.Quazi), open positions not yet filledControl and Computing work together despite being in different sectors
New in 2013: Left in 2013Control-engineer: A.Ismail Z.QuaziElectrician: O.KahdarMagnets: M.EbbeniBeam-Dynamics: K.MaukyanPurchasing: M.SalamaBuilding/Safety: A.BasheerMaintenance: I.ZoubiAdministration: R.Ramadan(Nov.13)BL scientist for PX: R.Kaneez (Nov.13)
TAC 2013 Reporting back E.Huttel
3
CESSMagMagnets designed and design approved (Jun. 2013)Call for bids (Jul. 2013)Opening of Bids (Aug. 2013)Expert Meeting with externals cancelled due to extended of deadlineSelection: Dipole: TESLAQuadrupoles : ELYT + Turkey (coils)
Sextupoles: CERN + Cyprus + Pakistan
Clearance to vacuum chamber increased to > 1 mm
Split dipole: Not foreseen (expect problems due to long structure) Assembling of vacuum chamber solved (see girder design)
Systematic and random Multi-poles studied (later this talk)
Prices allow Power Supplies to be fully done by CERN
Contribution E.Huttel, A.Milanese, J.-P. BurnetTAC 2013 Reporting back E.Huttel
4
Crane:Still no maintenance contract
Specs have to be defined by us
Grounding: (ordered, built up 2014)A bus bar (0.5 X 250 mm Cu): In the Booster ring tunnel
In the Storage ring tunnelAround the experimental HallAdditional ground pits inside the Hall
Donated equipment:Items from free zone moved to SESAMEUnneeded equipment still at SESAME (difficult to get rid off, due to custom)
Hutches from Lure (who knows about it?)
Building
TAC 2013 Reporting back E.Huttel
Solar Panel: No approach
5
MicrotronNo operation since 2013 due to Booster built upNew PS for main magnetTo be done during commissioning:
Emittance Measurement (Quadrupole scan)
Injection Elements:New Power supplies for injection Septum and Kicker
PS (FUG), Switch (SOLEIL)Transformer oil changed and repairedSparks (inside Septum, conditioned to 100 kV)
To come next: PS Booster Extraction Septum (design done)PS Booster Extraction KickerSR Injection SeptumSR Injection Kicker
Injector
TAC 2013 Reporting back E.Huttel
Contribution M.Attal
6
ControlStaff: One in (A.Ismail) , one out (Z.Quazi), looking for two.Cooperation Control with Computing: yes (Regular Meetings)Expert Visit: PLCs installation (expert visit SOLEIL)
CSS installation (expert visit ANKA)LINUX 6: InstalledIntegration (Cooperation) with clients: (PS group (up to programming), RF, VAC)Black Boxes: Repository built up.
Booster-Control successfully built upVacuum-Valves/Safety: PLC EPICS CSSVacuum-Pressure: MOXA EPICS CSSRF: PLC EPICS CSSPS-Current: EPICS CSSPS-Safety: PLC EPICS CSSTiming: VME EPICS CSS
To be done: Data Save-Restore DatabaseAlarm handler Motion Control
See visit
Contribution A.Ismail/I.SalehTAC 2013 Reporting back E.Huttel
7
Radiation Safety:New license for Microtron commissioning from JNRCRadiation-monitors ordered and deliveredPersonal Safety System ordered, installation till Jan.2014Back-up-plan with JNRC?Contribution M.Mansour
Booster Diagnostics:Digital cameras, scopes purchasedYAG screen from ANKA broken
AOB
TAC 2013 Reporting back E.Huttel
8
Cooling system: Completed and successfully testedContribution F.Makahleh
Vacuum System: No in-kind contribution from PalestineSR vacuum system tenderedSelected supplier FMBContribution F.Makahleh
TAC 2013 Reporting back E.Huttel
Solid State Amplifier:Delivery of all equipment from SOLEIL items on hold by French government Feb 2013Delivery approved Aug 2013
Cavities:Donated cavities from ELETTRA inspected, tendering for new ones done
9TAC 2013 Reporting back E.Huttel
Girder
6 feeds3 struts used for transverse and longitudinal adjustment3 jacks used for vertical adjustment and clampingAdditional 3 vertical jacks used for clampingTolerances (flatness, positioning): 0.05 mm
10
Girder-Design
TAC 2013 Reporting back E.Huttel
Dipole to be moved out by trolley
Vacuum chamber lifted in from top
11
Which Girder-Tolerances Needed?
TAC 2013 Reporting back E.Huttel
+/- [mm] Dipoleoptics
QFoptics
SupportSpecs
Shimrange
Shimresolution
GirderSpecs
horizontal 0.5 0.2 0.1? 0.5 0.05 0.05?
vertical 0.1 0.2 0.1? 0.5 0.05 0.05?
When having shims, why small tolerances for the girder?
12
Dipole-Multipole Tolerances
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
B4/B1=0.0002 B5/B1=0.0004 B6/B1=0.0003 B7/B1=0.0007 B8/B1=0.0007
B4/B1=0.0010
General RemarksWhich Dynamic aperture is needed (lifetime, injection)?Which program (OPA, AT, BETA)?Multipole contribution distributed (AT) or at exit/entrance (OPA)?
Selected radius is 20 mm for bend and 24 or QP, SP.B = Σ Bn xn-1, n=1 dipoleLimits in integrated strengths Bn[m-n+2] about the same for DP,QP,SP.TAC 2013 Reporting back
E.Huttel
B8/B1=0.0006B7/B1=0.0006
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
B4/B1=0.0020B4 in center
13
QF Magnetic Multipole Tolerances
TAC 2013 Reporting back E.Huttel
Quadrupole composed from 4 segments.Assembling Error: Causes random 6-, 8-pole components0.1 mm causes 2 10-4 dB/B @ r = 20 mmFinite Size: Causes systematic 12, 20 pole component12 pole mostly corrected by chamfer
Achievable:6,8-pole 12,20-pole
random σ systematicANKA 5 10-4 5 10-4
ALBA: 3 10-4 3 10-4
SOLEIL: 3 10-4 2 10-4
Tolerable: SESAME: dB/B < 20 10-4-60 -50 -40 -30 -20 -10 00
0.2
0.4
0.6
0.8
1
x [mm]
B [T
]
Good field region
14
DP,QP Random-Field-Error and Beta-Beat
Dipole dB/B = 1 10-3 orbit dist.: 2 mm
dk/k = 3 10-3 vert.beta beat: 0.6 m
QF dk/k = 3 10-3 horiz.beta beat: 0.4 m vert. beat beat: 0.1 m
QD dk/k = 3 10-3 horiz.beta beat: 0.1 m vert. beat beat: 0.2 m
TAC 2013 Reporting back E.Huttel
15
QP Multipole Tolerances
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
B10/B2 =0.0100
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
B10/B2 =0.0010
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
B6/B2 =0.0012
Random(per magnet) B4/B2 =0.0100
SystematicRandom
ALBA,IPAC10
TAC 2013 Reporting back E.Huttel
16
Random Multipole Errors Decapole due to Correctors
TAC 2013 Reporting back E.Huttel
Sextupole
Sextupole + Corrector→ Decapole
B5/B3 =780 10-4
Working point shifted
17
Dipole End Chamfer
0 200 400 600 800 1000 1200 14000.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
B'y, 2.5 GeV
s [mm]
norm
alize
d By
or G
[/]
Vertical focusing from edge
∫B’dl/B ρ = 0.401 (1/m)B’(0)l / B ρ = 0.378 (1/m)(∫B’dl- B’(0)l)/ B ρ = 0.023 (1/m)tan(θ )/ρ = 0.034 (1/m)
Opera give less focusing strength than optical model
No face rotation
CERN initial: Less vert. focusing, more sector magnet,made QF obsolete (or changed to QF)
CERN final, LEGO blocks, flexible, ok, Octupole?
(ALBA, ASRS) PreferredTAC 2013 Reporting back E.Huttel
18
Beam Based Alignment Procedure:Select QP close to BPMDo orbit scan through QPModulate QP current (Producing additional kick, when beam not in center)Orbit with no orbit modulation when QP is modulated gives BPM offset
Can the QF used for vertical and horizontal plane?H-kick (0.2 mrad) Offset at QF: 2.0 mm 5% QF-Modulation: orbit change: 0.5 mm V-kick (0.2 mrad) Offset at QF: 1.5 mm 5% QF-Modulation: orbit change: 0.4 mm
10% QD modulation: orbit change 0.1 mm
Conclusion: BBA works with QF in horizontal and vertical planeNo individual PS needed for QD for BBA
TAC 2013 Reporting back E.Huttel
19
Insertion device and Beta-Beat
SESAME: PD-Beamline
Wiggler-Parameter
Length 2 m
Period 60.5 mm
No. Pols 63
Magnet gap 14 / 10 / (7) mm
Vacuum gap 12 / 8 / (5) mm
Field 1.1 / 1.5 / (1.9) T
Without local correction the PX wiggler will produce a beta-beat of +/- 4 %
Individual QD-PS favored but not necessary
TAC 2013 Reporting back E.Huttel
20
Power Supply Procurement
Cost of magnet system allows to purchase complete PS-package in framework of CESSMAg
CERN resumes PS package
Change in concept
(Before: QP-PS in series, Purchasing as complete package turn-key from Industry)
Now: QP-PS in series, PSI-Controller, Voltage-source, DCCT; Assembling at CERN
Advantage: Better performance in respect of:
Maintenance
Adjustment of Beta-Beat
Beam-Based Alignment
Integration of Insertion-devices
Cost: More manpower needed for development and assembling
Concept endorsed by Review-Committee (J.F.Bouteille, R.Kunzi, R.Visintini, F.Bouvet)
TAC 2013 Reporting back E.Huttel
21
Combined/Individual QP-PS and Air Conditioning-Limits
Pro Combined Pro Individual
Less expensive invest & operation Easier to repair (exchange)
More efficient (water) cooling Easier for Beam Based Alignment
Easier to synchronize Beta Beat can be adjusted
Less (cables) heat-load in the tunnel Easier to adjust insertion devices
AC-Limits Combined Individual Revised *)Individual
Tunnel 30 kW 14 kW 44 kW 30 kW
Hall 60 kW 7 kW+RF 21 kW+RF 20 kW+RF
RF: 700 kW AC, 5% eff. into air 35 kW air or Water?
*): 2 QF in series, cable length reduced to 60 m
Conclusion: AC is compatible with Individual powered QF/QDTAC 2013 Reporting back E.Huttel
CERN: a revision of the installed cooling capacity is recommended.SESAME: The capacities of SESAME have to be accepted (cost- limited).
22
Needed stability for Dipole and Quadrupole PS
Booster Storage-Ring-QF
Storage-Ring-QD
Units
Needed Tune Stability .01 .01 .01
Needed stability in k .007 .001 .005 1/m2
Δk/k .005 .0005 .005
Einj/Efinal .025 .32 .32
ΔIinj/Ifinal for QF 130 160 1600 ppm
Defines Tracking stability ( c Iqp-Idp)/Ldp
Defines PS Stability
SR corrector vert.
Beam size .030 mm
Max change .003 mm
Max kick 0.5 mrad
Orbit max kick 5 mm
Kick for .003 mm .000200 mrad
Relative strength .000400
SESAME ALBA SOLEIL
8h stability QP 50 15 10 ppm
8 h stability crr 50 100 20 ppm
Resolution 16 18 18 bit
16 bit - 15 ppm
Needed stability
TAC 2013 Reporting back E.Huttel
23
SynchronizationBooster 1s 50 ppm step all 50 µs
SR 240 s 50 ppm step all 15 ms
SR Trigger precision: 1ms
Trigger for each step or external start trigger and following internal clock?
Clocks needed to be synchronized if only triggered for start ?
Old Concept:Off-shelf controller : All PS from same provider to warranty synchronization?
New Concept:PSI Controller for all devices: Synchronization warrantied.
More fun with development.
TAC 2013 Reporting back E.Huttel
PS Controller
EthernetPSI Gate wayPSI controllerDACADCPWMDCCT
EthernetPSI Gate wayPSI controllerPWMDCCT
Commercial PSVoltage source
Final PS built up by CERN/SESAME
Commercial PS Power source
EthernetPS controllerPWMDCCT
Commercial PSCurrent source
32 QF-PS (3 kW) ( 1 magnet in series)16 QD-PS (3 kW) ( 2 magnets in series)1 SF-PS (2 x 3 kW ?) (32 magnets in series)1 SD-PS (4 x 3 kW ?) (32 magnets in series)1 DP-PS (440 kW) (16 magnets in series)
EthernetPSI Gate wayPSI controllerSerial outSerial inPWMDCCT
24Foreseen for DP Foreseen for QP Foreseen for Corr
Commercial PSVoltage source
To be developed by
CERN?SESAME?
TAC 2013 Reporting back E.Huttel
26
Questions
TAC 2013 Reporting back E.Huttel
New concept accepted.Individual PS for QF.PSI Controller for all PS.DAC card and off-shelf PS.
DAC development by CERN or SESAME?Responsibility and Supervision by CERNManpower from SESAME in limits of its capacity26 Person months for 1 year?
Two QD in series?
16 bit (one module less) or 18 bit?
Public tender or contracting EEI for dipole PS?
27
Cavities
TAC 2013 Reporting back E.Huttel
Invitation to Bid: Sep. 133 bids received : Nov. 13 (RI, ELETTRA, TOSHIBA)
Specification:Number: 4Frequency: 499.65 MHzShunt Impedance: > 3.3 MΩMax Cavity Voltage: > 650 kVMax Window Power: > 120 kW
HOM-Damping Properties: Wave guide (BESSY) ++Beam-Pipe (KEK/PF) +Temperature (ELETTRA) 0
28
Purchasing Cavities
TAC 2013 Reporting back E.Huttel
Two old ELETTRA cavities (reduced performance) available.Preferred:
Purchasing of 4 new cavities ( ELETTRA, BESSY, KEKII/PF)Invitation to bid: Sep. 2013Opening of Bids: Nov. 2013 (2.2 M$, 2.1 M$, 4.3 M$)
Italy-INFN Contribution 1 M€Initial proposal 2 new ELETTRA cavities
Meeting Trieste Aug 2013, Agreed with INFN:SESAME can decide items to be purchasedMoney should be transferred to SESAMA account
INFN Proposal Oct.2013:Two new ELETTRA cavities for 0.85 M €
30
What to do?
TAC 2013 Reporting back E.Huttel
2 Cavities 3 Cavities 4 Cavities
Energy [GeV] 2.3 2.5 2.5
Uloss-tot [keV] 440 615 615
Overvoltage 2.5 2.5 3
P window [kW] 80 80 80
P cavity [kW] 48 42 34
U cav [kV] 550 520 460
I beam [mA] 140 180 300
31
Comparing Cavities
TAC 2013 Reporting back E.Huttel
Parameter Units BESSY ELETTRA KEKII/PFRshunt MΩ 3.4 3.3 3.5
Q 29000 39000 39000
Umax kV 730 650 700
Pcavmax kW 80 65 70
Pwindowmax kW 120 120 180
R-HOM-Lmax kΩ 11 100000 20
R-HOM-Tmax kΩ/m 54 10000000 80000
Values from E.Weihreter
RF Amplifier
TAC 2013 Reporting back E.Huttel 32
Intended : Use 500 MHz solid state amplifier (0.6 kW Module) developed at SOLEIL
Needed: 4 x 80 kW from 4 x 10 x 16 x 0.5 kW
Status: 16 Modules combined and tested by SOLEIL.40 kW tower will be built up by SOLEIL for THOMX (Beginning 2014).
Export of Technology from SOLEIL to SESAME on halt (May 2013)Export approval received (Aug.2013)
Intended: Built up of one 80 kW tower (Demonstrator) by SOLEIL, sold to SESAME.Participation of SESAME.Licensing of 500 MHz technology from SOLEIL to SIGAM-PHI-Electronics?Purchasing of further 3 towers from SIGMA-PHI-Electronics? Cost?
500 MHz 80 kW Solid-State-Amplifier
X 16 X 10 4 x
Syn.Rad. Losses: (200 mA 600 kV) / 4 = 30 kWCavity Losses: (500 kV)2 / (6 MΩ)= 40 kW4 Cavities: 280 kW
0.65 kW 10 kW 80 kW
TAC 2013 Reporting back E.Huttel
33
34
RF-Amplifier-CRYELECTRA
TAC 2013 Reporting back E.HuttelSame transistor, same power-supply as SOLEIL
35
Visit ILSF / Test of ILSF Amplifier
TAC 2013 Reporting back E.Huttel
Same transistor same performance:Pout: 650 WGain: 20 dBEfficiency: 55%
Pulsed Magnets Parameter
TAC 2013 Reporting back E.Huttel38
Element Type Length Kick Pulse length
L [µH] U [V] I [A] C [µF] Field
Injection Septum
ElectrostaticHalf sine
R: 2 mL: 0.5 m
14.5° 250 µs 220110 000
3.75 10 MV/m
Injection Kicker
StriplineHalf sine
L: 0.3 m 3 mrad 6 µs 2 220 100 1.6 0.001 T
Extraction Bumper
Iron MagnetHalf sine
L 0.17 m 5 mrad 1.7 ms 700 200 150 440 0.080 T
Extraction Kicker
StriplineFlat-top
L: 1 m 2 mrad 40 ns190 ns
1 25000 280 50 Ω20 m PFN
0.005 T
Extraction Septum
C magnet, eddy currentHalf sine
R: 5.73 mL: 1m
10° 560 µs 10 220 4000 3500 0.465 T