tank 85 foundation

16
Tank 85 Foundation View of poured auger pile. Setting up for next pile. This process repeated itself 310.

Upload: nicolas-fernando-cardona-valencia

Post on 12-Nov-2014

80 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: Tank 85 Foundation

Tank 85 Foundation Tank 85 Foundation

View of poured auger pile.

Setting up for next pile.

This process repeated itself 310.

Page 2: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Tying the cages for the poured piling.

Auger pile boring in progress.

New cage ready to place when gout is poured.

Page 3: Tank 85 Foundation

Tank 85 Foundation

The grout in some piling settled and was repaired. Grout was chipped to a clean surface and re-poured.

Pouring the repair.

Page 4: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Excavating to sub-grade for the mud slab.

Excavating continues while the mud slab is being poured.

Page 5: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Mud slab complete and form setting in progress. Laying out support bars for re-bar work to begin.

Form setting for the slab well under way.

Page 6: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

First mat of re-bar placed Oct. 24/25,06

Placing top mat Oct. 26/27,06

Page 7: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Re-bar is complete and ready for concrete pour Oct. 28, 06.

Page 8: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Tying wall dowels and support dowels Oct 27, 06.

Water-stop placed so it can be repositioned while the concrete is being poured

Page 9: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

5AM Oct 28,06. First two loads of concrete.

Pouring with two pump trucks

Page 10: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

5:45 AM, pour well under way.

Page 11: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Grading in progress prior to setting panels Nov. 2,06.

Preparing to set inner ring wall.

Page 12: Tank 85 Foundation

Tank 85 Foundation

7AM Sat. anchor bolts set and checked, re-bar complete, ready to pour.

Pour approximately 40 % at 9:30 AM

Page 13: Tank 85 Foundation

Tank 85 Foundation

Ring wall completely poured.

Ring wall stripped and grading for tank contractor started

Page 14: Tank 85 Foundation

Tank 85 Foundation

Liner installation well under way.

Liner nearly completed.

Page 15: Tank 85 Foundation

Tank 85 Foundation

Ramp in place for placing of sand and entrance of crane and materials. 11-13-06

First of many loads of sand, 11-14-06

Page 16: Tank 85 Foundation

Tank 85 Foundation

Sand fill covered for the night. 11-15-06

Compacting first lift of sand. Tested at 105-108.