tanker operations long laneway – 1 st arriving pumper p-1 fire bldg house?= 38mm x2 + 65mm backup...

15
TANKER OPERATIONS Long Laneway – 1 st arriving pumper P-1 FIRE BLDG House?= 38mm x2 + 65mm backup line Barn? = consider 2- 65mm right away Lay a Hi-Vol from the road Good location for I/C, Acct. & Entry Control? Another good location for I/C, Acct. & Entry Control?

Upload: hannah-gilbert

Post on 01-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

TANKER OPERATIONS

Long Laneway – 1st arriving pumper

P-1

FIREBLDG

House?= 38mm x2 + 65mm backup line

Barn? = consider 2- 65mm right away

Lay a Hi-Vol from the road

Good location for I/C, Acct. & Entry Control?

Another good location for I/C, Acct. & Entry Control?

TANKER OPERATIONS

Long Laneway – 1st arriving tanker

P-1

FIREBLDG

T-1If 1st Tanker arrives prior to a pumper, hook up to hi vol using 65mm female to stortz adapter then pump to P-1.

TANKER OPERATIONS

Long Laneway – 2nd arriving pumper

P-1

FIREBLDG

P-22nd arriving pumper, hook up to hi vol and pump to P-1.

(Wherever possible pump operators should maintain some water in the on board tank)

TANKER OPERATIONS

Long Laneway – 1st arriving tanker with 2nd arriving pumper

P-1

FIREBLDG

P-2

ASAP we should have a supply pumper in place to feed the attack pumper P-1 via hi vol at a long laneway rural fire

1st tanker has arrived and has set up a 65mm to pump to supply pumper P-2(All drivers need to assist each other throughout the event)

P-2

T-1

TANKER OPERATIONS

Long Laneway – 1st arriving tanker with 2nd arriving pumper

P-1

FIREBLDG

P-21st arriving tanker and all available drivers, set up porta-tank and dump while continuing 65mm pumping

T-1

All available drivers assist P-2 with set up 4” hard suction with draw down strainer.Set up 3” hard suction as well to supplement intake

TANKER OPERATIONS

P-1

FIREBLDG

P-2

T-1

Tanker 2 has arrived, pumped to P-2 and set up porta-tank and dump

Drivers, take assembled (from top of tanker) 6” hard suction with draw down strainer and 38mmredskin and place from tank to tank connecting redskin to P-2 outlet.

Long Laneway – 2nd arriving tanker with 2nd arriving pumper

Flow redskin at 550 to 700 kpa (80 to 100 psi) dependant on desired speed of transfer)

T-2

TANKER OPERATIONS

P-1

FIREBLDG

P-2

T-3

Tanker 3 has arrived and is pumping to P-2, set up porta-tank and dump

Drivers, take assembled (from top of tanker) 4” hard suction with draw down strainer and 38mmredskin and place from tank to original tank connecting redskin to P-2 outlet.

Long Laneway – 3rd arriving tanker with 2nd arriving pumper

AT THE HYDRANT

As soon as possible 3rd arriving Pumper (3) should leave his Firefighters at the fire scene and attend at the tanker fill location, whether it is a hydrant or a static source, pond steam etc.

P-3

P-3, ensure the hydrant is flushed and attach a minimum of 1 hi-vol and 2- 65’s from hydrant to truck intakes. (Certainly a hi-vol can be used in place of a 65)

Tanker Drivers assist

AT THE HYDRANT

Setting this up and pulling water from the system, diverting to tankers through your pump will greatly decrease tanker fill time, especially on a weaker hydrant.

P-3

Next, apply 2 lengths of hi-vol, 1 to each discharge of your choice – you may need 2 – 65mm female to stortz adapters, one from P-3 and one from a tanker

Tanker Drivers assistT-1

T-2Tankers have 50’ hi-vol on board

1st arriving Pumper – only feasible where Pumper can park safely within 10-15 ft of water source

AT A STATIC SOURCE (POND, STREAM ETC.) - OPTION 1

P-1

T-1

4” Hard Suction with screen on inlet with 4” hi-vol on discharge to tanker

1st arriving Pumper – only feasible where Pumper can park safely within 10-15 ft of water source

AT A STATIC SOURCE (POND, STREAM ETC.) - OPTION 1

P-1

T-1

Additionally, attach 3” hard suction with screen to 2nd inlet with an additional 65mm soft line to a 2nd discharge

T-2

AT A STATIC SOURCE (POND, STREAM ETC.) - OPTION 2

1st in Tanker

T-1 set up portable pump, hard suction, screen and bucket feeding 65mm soft line to tanker.(be advised Stn 1’s T-1 has a stortz to triple 65mm gated manifold (inset) – as soon as T-1 arrives it should insert this piece of equipment into the system–A-1 also has this item in inventory)

T-1

manifold

Drop your jerry can too

Jerry can

AT A STATIC SOURCE (POND, STREAM ETC.) - OPTION 2

1st in Tanker

Once the manifold has arrived, the feed line from the manifold to the tanker will be a length of hi-vol (don’t forget to open the gate on the pump side of the manifold)

T-1

AT A STATIC SOURCE (POND, STREAM ETC.) - OPTION 2

2nd arriving tanker

T-2 set up 2nd portable pump, hard suction screen and bucket to 2nd manifold intake – fill time now cut in half

T-2

Drop your jerry can too

AT A STATIC SOURCE (POND, STREAM ETC.) - OPTION 2

3rd arriving tanker

T-3 set up 2nd portable pump, hard suction screen and bucket to 2nd manifold intake – fill decreased by another 3rd

T-3

Drop your jerry can too