T A R G E T V A L U E D E L I V E R Y
OCTOBER 17, 2017
© LEAN CONSTRUCTION INSTITUTELCI Education& Training
Target Value DeliveryChristian Pikel, The ReAlignment Group
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
Lean Construction Institute Provider Number H561
LCI Training Block: Target Value DeliveryLCITB.TVD
Presenter NamePresentation date
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
8 LU Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner ofhandling, using, distributing, or dealing in any material or product._______________________________________Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
Participants will learn what is meant by Target Value Delivery, how it differs from more traditional delivery approaches and some key tools and techniques to implementing the approach.
The training will include hands-on workshops to teach the approaches for more integrated learning.
Course Description
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
01.At the end of this presentation, participants will be able to describe the culture required to support Target Value Delivery.
02.At the end of this presentation, participants will understand how to align project deliverables and customer-defined value.
03.At the end of this presentation, participants will be able to describe the major phases in the Target Value Delivery process and how they relate.
04.At the end of this presentation, participants will be able to describe the tools that support the Target Value Delivery process.
Learning Objectives
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
7
Learning Objectives
Participants will be able to describe the attributes of a team culture required to support Target Value Delivery.
Participants will understand how to align project deliverables with customer-defined value.
Participants will be able to describe the major phases in the Target Value Delivery process and how they relate.
Participants will be able to have some first-hand experience with the types of challenges and decisions which typically arise in TVD.
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
8
Unaware
Awareness
Understanding
Mastery
Competency
Continuous Learning Loop
Lean Journey Road to Mastery
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
9
8:00 AM –
8:30 AM –
9:45 AM –
12:00 PM –
Introductions
Target Value Delivery Presentation/Simulation
Break 15 minutes
Lunch
Target Value Delivery
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
10
Target Value Delivery
1:00 PM –
3:00 PM –
4:45 PM –
5:00 PM –
Continue
Break 15 minutes
Wrap up and Plus/Delta
Adjourn
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
12
Impeccable Coordination
Production System Design
Collective Enterprise Operating System
A New and Coherent way to Manage Work in Projects
T H R E E C O N N E C T E D O P P O R T U N I T I E S
P R O J E C T E L E M E N T S
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
13
1
2
3
4
5
6
Respect for people
Optimize the Whole
Generate Value
Eliminate Waste
Focus on Flow
Continuous Improvement
Six Tenets of Lean Construction
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
14
References
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
15
Introduction of simulation
Participants to decide on contract arrangement:• Lean Integrated Project Delivery (LIPD)• Design-Build• Other
1 0 M I N U T E S
Target Value Delivery Simulation
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
16
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
CORECOMPONENTSOF TVDPROCESS
PHASES OF TVD
CONSTRUCTION Chapter 14
Image courtesy of InsideOut Consulting & Southland Industries
Target Value Delivery (TVD) Overview
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
17
A disciplined management practice to be used throughout the project to ensure:• The facility meets the operational needs and values of the users
• The project is delivered within the allowable budget
• That innovation is promoted throughout the process to increase value and eliminate waste.
Target Value Delivery (TVD)
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
18
TVD is to be applied holistically to obtain maximum value.
Regardless of the project delivery framework, the owner, designers, builders, and key trades must be fully engaged from the onset.
TVD Culture
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
19
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 14
TEAM FORMING/ORGANIZATION Chapters 6 & 7
CORECOMPONENTSOF TVDPROCESS
PHASES OF TVD
CONSTRUCTION Chapter 14
Business Case Planning Phase
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
20
• The operational use/benefit proposition described by the owner that initiates the development of the project.
• The owner-provided purpose or “why” that becomes the anchor of the project.
• Sets the Allowable Cost.• Includes Value Definition Statements by the owner
for the project.
Business Case
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
21
Could we build X thing for $Y and have it by Z date?
• Could we open a replacement hospital in Castro Valley, CA for $300 million by early 2013?
• Could we find a way to increase overall visitor count by X% for a capital expenditure of $1 billion by 2020?
Framing the Business Case
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
22
• The absolute maximum Project Cost based on the Business Case.
• It becomes the subject of the Validation Phase
Allowable Cost:
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
23
The following slides outline “The Project” Business Case & relevant information
15 minutes total
The Project
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
24
O W N E R :Anytown Arizona Community Social Services Group
M I S S I O N S TAT E M E N T:“Strengthen our community by creating living condition stability, economic opportunity and supporting services
to those in need.”
Owner Business Case
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
25
• $4,500,000 Allowable Cost• HUD grant and private donations
• ‘Tiny Home’ low income housing community of 45 units• Approximately 40’x100’ lot sizes• Unit diversity 250 – 750SF
• (Single, Single Parent, Couple + 1 Child)
• 10 year rent to own model• Minimize Utility Costs (100 energy units / month)
Owner Business Case
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
26
Rent-To-Own: $1/SF for 10 years, simple payback
• Max allowable cost = 10 year rent – 5% Admin/HOA
• E.g. 550SF X $1 X120 = $66K – 5% = $62,700 ($114/SF)
Allowable Cost Breakdown
Land Purchase $1,141,000
Entitlements, Clearing/Grading & Utilities $550,000
Project Administration $225,000
Construction FundingBuilding, Landscape/Hardscape & Furnish $2,574,000
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
27
• 4.6 Acre Parcel• 40’x100’ Lot subdivisions• Main site, utility and roadworks by owner
Project Site
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
28
100’40’ 100’
40’
Project Plot
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
29
Total SF 225Notes Includes 40 SF Loft$/SF $109
Total Cost $24,525
Foundation & Framing $3,188 13%Skin & Roofing $3,679 15%
Glazing $1,962 8%Systems (MEP/E) $4,415 18%
Interiors (Incl Carpentry & Doors) $4,905 20%Finishes, Fixtures Furnish & Equip $2,943 12%
Design & Permitting $1,962 8%Landscape & Hardscape $1,472 6%
Year Completed 2015Inflation to 2017 5%
Location Cityville, MIGeographic Cost Index Diff to Anytown,
AZ -8%
Yearly Energy Costs $55
Owner Provided Benchmark Project
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
30
Owner Provided Benchmark Project
Total SF 390Notes Includes 90 SF 2nd Fl$/SF $116
Total Cost $45,240
Foundation & Framing $3,434 14%Skin & Roofing $4,415 18%
Glazing $2,943 12%Systems (MEP/E) $3,679 15%
Interiors (Incl Carpentry & Doors) $4,415 18%Finishes, Fixtures Furnish & Equip $2,453 10%
Design & Permitting $1,962 8%Landscape & Hardscape $1,226 5%
Year Completed 2015Inflation to 2017 5%
Location Cityville, MIGeographic Cost Index Diff to Anytown,
AZ -8%
Yearly Energy Costs $65
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
31
Total SF 360Notes Single Floor$/SF $108
Total Cost $38,880
Foundation & Framing $3,188 13%Skin & Roofing $4,415 18%
Glazing $1,472 6%Systems (MEP/E) $4,169 17%
Interiors (Incl Carpentry & Doors) $4,660 19%Finishes, Fixtures Furnish & Equip $3,924 16%
Design & Permitting $1,472 6%Landscape & Hardscape $1,226 5%
Year Completed 2015Inflation to 2017 5%
Location Cityville, MIGeographic Cost Index Diff to Anytown,
AZ -8%
Yearly Energy Costs $40
Owner Provided Benchmark Project
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
32
• Define what the customer wants from the process. • Are composed of high level statements that
describe expected outcomes, or “value” that the project will deliver.
• Should not be ranked or weighted.• Should include all stakeholder input.
Value Definition Statements
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
33
To Create:• Community & environment fosters respect and restoration of self
esteem.• Sustainable design for reasonable future costs to residents and
association. • Economic stabilizing opportunity for community residents.• Safe environment for residents.• Equity building opportunity based on target rent model.• Stakeholder alignment from from all CCSS programs (Housing, Food,
Jobs, Health, Publications).• Create added value opportunities through savings.
Value Definition Statements
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
34
Transition to Validation Phase
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
35
Business CasePlanningChapter 2
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
CORECOMPONENTSOF TVDPROCESS
PHASES OF TVD
CONSTRUCTION Chapter 14
Validation Phase
Image courtesy of InsideOut Consulting & Southland Industries
ValidationChapter 3
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
36
• The project team determines whether the project is viable based on the outputs of the Business Case Phase.
• Output is team understanding and alignment:• Scope definition• Value Definition & CoS• Target Cost
Validation Phase
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
37
• The cost goal established by the delivery team as the “target” for its design and delivery efforts.
• Should be set at less than best-in-class past performance.
• Creates a sense of necessity to drive innovation and waste reduction into the design and construction process.
Target Cost
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
38
• Value Definition Statements
Steps to Defining Success
• Value Definition output informs Conditions of Satisfaction (CoS)
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
39
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
CONSTRUCTION Chapter 14
Core Components
CORECOMPONENTSOF TVDPROCESS
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
40
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
PHASES OF TVD
CONSTRUCTION Chapter 14
Team Forming/Organization
Image courtesy of InsideOut Consulting & Southland Industries
CORECOMPONENTSOF TVDPROCESS
TEAM FORMING/ORGANIZATION Chapters 6 & 7
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
PD SD CD PR CA OPDDTime
Effort/Effect
PD: Pre-designSD: Schematic designDD: Design developmentCD: Construction documentationPR: ProcurementCA: Construction AdministrationOP: Operation
Graphic courtesy of Patrick MacLeamy AIA / HOK
Ability to impact cost and functional capabilities1
1
Cost of design changes2
2
Traditional design process33
4
IPD design process4
Early Team Involvement
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
42
A high performing team is built on a strong foundation of trust among all members.
There is a culture of respect that enables members to effectively delivery against CoS.
High performing teams break down barriers through innovation and continuous improvement.
They break down traditional silos to maximize skills and optimize performance.
Characteristics of High Performing Teams
1
2
3
4
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
43
How would you go about building your team?What characteristics would be important?What interview questions might you ask?
1 5 M I N U T E S
Team Forming Exercise
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
44
• Are developed by the team informed by the Value Definition Statements.
• Measureable statements that inform a project team about which tests a project must pass to be accepted as a success.
• Inform the decision-making process of the team.
Conditions of Satisfaction (CoS):
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
45
Conditions of Satisfaction Exercise:
1 5 M I N U T E S
Develop some CoS for the project
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
46
Quantitative• Energy efficient design
• Low monthly utility cost• High % of daylighting• Innovative water management system
• Meet the Allowable Cost• 25% workforce inclusion (Underemployed /
Community Residents – min. 10% each)• Community engagement:• Regularly (weekly) updated progress signage
at visible location• Social Media Updates (min. 3 per week)
0 5 M I N U T E S
Team-Developed CoS:
• Regularly (weekly) updated progress signage at visible location
• Social Media Updates (min. 3 per week)• “Town Hall” community feedback events (min. 1
per quarter)• Robust, proactive protection of the safety of our
workers and community:• Weekly team safety walk-throughs• Short-falls remediated immediately (no more
than 24 hours)• System for immediate reporting of safety
problems identified by workers and community members
• All team members earn a fair profit
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
47
Qualitative:• TVD team actively builds and sustains a
culture of respect for all team members
• TVD team creates design that supports a culture self-respect for customer
• TVD team actively seeks innovation to reduce waste and wasteful activities, streamline processes, and improve the flow of work
Method of Measuring Success:Monthly measurement of progress against CoS:
• Quantitative – Current results calculated and reported by CM
• Qualitative– Survey completed by all TVD team members
• Continuous Improvement session held to review results, and determine steps to correct short-falls against targets
Team-Developed CoS:
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
48
Core Team
Senior or Executive Management
Work Clusters – cross discipline representation
Project Team Organization
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
49
Develop an initial Work Cluster organization based on the next slide.
Assign cross discipline roles.
1 0 M I N U T E S
Work Cluster Exercise
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
50
0 5 M I N U T E S
SMT
Core Group
WC1L
A
WC2L
A
WC3L
A
WC6L
A
WC5L
A
WC4L
A
SMT - Facilitators Core Group - All
Landscape & Hardscape
Skin Roofing & Insulation
Plumbing Heating/Cooling & Energy
Interiors
Finishes Fixtures & Furniture
Windows
Work Cluster Organization
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
51
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
CONSTRUCTION Chapter 14
Image courtesy of InsideOut Consulting & Southland Industries
Big Room
CORECOMPONENTSOF TVDPROCESS
BIG ROOM Chapter 8
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
52
• Mindset of intense focus on advancing work.
• Enables cross-functional team collaboration.
• Refers to the collaborative behavior of a team and the work they are producing.
Big Room is:
Big Room is a commitment to a project, the team, and to working together!
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
53
Big Room
For the remainder of the day, we will operate as a Big Room:
Represent Core Team as a whole
Break into Work Clusters to problem Solve
Hold Core Team Integrating Events
0 2 M I N U T E S
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
54
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
CONSTRUCTION Chapter 14
Project Planning
CORECOMPONENTSOF TVDPROCESS
PROJECT PLANNING Chapter 9
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
55
Milestone Planning
Phase “Pull” Planning
Make Ready Planning
Weekly Work Planning
Learning/Improving
Set milestones
Specify handoffs
Make work ready
Make promises
PPC/Variance
SHOULD
CAN
WILL
DID
Last Planner® System in Construction
5 Connected Conversations
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
56
L P S C O N S T R U C T I O N :
• Is linear and the flow is “tangible materials”
• Milestones must be clearly defined by expected outcome which will be observable
• Pull Plans identify work structure and duration
L P S D E S I G N :
• Is continuously emerging based on newinformation and the flow is “information”
• Milestones must be clearly defined by expected outcome which will describe what we expect to know
• Milestones should include work product and work deliverables and may be “decision points” as mini-milestones.
• Pull Plans identify work needed and date needed
LPS For Design
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
57
Last Planner® System in Design
5 Connected Conversations
Milestone Planning
Phase “Pull” Planning
Make Ready Planning
Weekly Work Planning
Learning/Improving
Set milestones
Specify handoffs
Make work ready
Make promises
PPC/Variance
SHOULD
CAN
WILL
DID
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
58
Milestone Planning
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
59
What might some of the milestones be for the project starting with end of project and working backwards?
1 0 M I N U T E G R O U P D I S C U S S I O N
Project Milestone Plan
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
60
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
CONSTRUCTION Chapter 14
Cost Modeling
CORECOMPONENTSOF TVDPROCESS
COST MODELING: PREDICTING COST AND VALUE Chapter 10
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
61
• Model of the cost components & systems of a project.• Structured to allow the costs to be continually updated. • Provides the team with a constantly up to date cost
model. • Should allow for projecting ‘what-if’ scenarios based on
value decisions that have yet to be made.
Cost Modeling
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
62
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
CONSTRUCTION Chapter 14
Continuous Estimating
CORECOMPONENTSOF TVDPROCESSCONTINUOUS ESTIMATING Chapter 11
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
63
SD DD CD Pricing Construction
T R A D I T I O N A L P R I C I N G / V A L U E E N G I N E E R I N G M O D E L
T V D D E S I G N M O D E L
TVD Continuous Estimating Model
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
64
Cost Benchmarking
Conceptual
Production
Types of Estimating
1
2
3
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
65
Level of Accuracy: Best +/- 10% Good +/- 15%• Starts at Business Case Phase• Refined during Validation Phase• Informs the Cost Model• Establishes project assumptions• Normalizing project to allow comparison• Identify risks• Informs team of what ‘can be done’
Cost Benchmarking
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
66
What systems and components ?What benchmarks to create the model?
What should a cost model track?
2 0 M I N U T E S
Develop Cost Model
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
67
Component BenchmarkModel % Base Cost
(Knowns) Risk TVD Options(Range)
Path Back(Opportunity) Current
Landscape & Hardscape
Skin & Roofing (& Insulation)
Windows
Plumbing, Heating/Cooling & Energy
Interiors
Finishes, Fixtures & Furniture
GCs, Design Fees & Profit
Total
Cost Model
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
68
Risk
Path Back
Hot Topics
CWE/ Cost Model Tracking
Cost Model (Simple Approach)
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
69
Level of Accuracy: Best +/- 5% Good +/- 10%• Goal is to provide cost information before the team moves forward
with decisions based on conversation, sketches, and conceptual information.
• Convert CoS & Business Case (Program) into a budget – what we desire.
• Gain just enough detail to inform team decisions.• Implemented with Set-based Design approaches.
Conceptual Estimating
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
70
Component Current Projection Allowable Target Delta +/-
Landscape & Hardscape
Skin & Roofing (& Insulation)
Windows
Plumbing, Heating/Cooling & Energy
Interiors
Finishes, Fixtures & Furniture
Total
Budget Tracker Summary
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
71
Level of Accuracy: Best +/- 1% Good +/- 3%• Most traditional form of estimating.• Driven by what has been documented in the design phase and
confirms estimates developed during earlier conceptual stages.
Production Estimating
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
72
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
CONSTRUCTION Chapter 14
Conceptual Design
CONCEPTUAL DESIGN Chapter 12
CORECOMPONENTSOF TVDPROCESS
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
73
Criteria development
Organize information
Set-based design
Integration Photo Credit: InsideOut Consulting, Inc.
Conceptual Design
1
2
3
4
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
74
“Product Development for the Lean Enterprise”, Michael Kennedy
Set-Based Design
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
75
From CPR Program
Set-Based Example
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
76
From CPR Program
Integration Event
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
77
Project Team
Work Cluster
Set Log• Identify ideas/sets• Status• Date of LRM Decision
Work Cluster
Set/Idea
Create A3 • Set Alternates• CoS Alignment• Cost Model Impact• Schedule Impact
Recommendation Integration Event• Evaluate
Recommendations• Integrate into design
Brainstorm• Identify ideas/sets• Create Set Log
Project Team
Work Cluster
Set/Idea
Work Cluster Flow
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
78
Create
Initiate Ideas
IdentifyStake-holders
Analyze Options
Include$$$
Impact
AnalyzeTo
CoS
RecommendTo
Core Team
AnalyzeTo
Cost Model
AcceptRejectRevise
Analyze Converge Decide
Work Cluster
Integration Event
Decision Flow Model
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
79
5 0 M I N U T E S
Each table represents a Work Cluster to study a component.
Work Clusters study and evaluate sets per the Cost Model:• Target Cost • CoS• Alignment with Business Case• Schedule• Other
Validation Phase
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
80
Report by Work Cluster• Align on 1 concept to move into Value Delivery Phase• Align on Target Cost
Challenge QuestionAre there any changes to the original Business Case that would create a more compelling value proposition?
3 0 M I N U T E S
Validation Phase Integration Event
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
81
Transition to Value Delivery Phase
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
82
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
CORECOMPONENTSOF TVDPROCESS
PHASES OF TVD
CONSTRUCTION Chapter 14
Value Delivery: Steering to the Target
Value Delivery: Steering to Target in Design and ConstructionChapter 4
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
83
• Work progresses in small batches toward intermediate milestones/decision points.
• The design is continually evaluated to the Target Cost & CoS.
• Teams explore innovative ways to achieve goals and add more value.
Value Delivery Phase
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
84
5 0 M I N U T E S
Work Clusters explore extreme ideas for carrying the concept forward
Challenge Questions• Are there design options at the system level that can be designed to
meet the CoS within the Target Cost?• What implications for overall value and costs should be explored during
Design?• What design, procurement and construction options should be
considered to generate value & eliminate waste?
Value Delivery Phase
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
85
Work Clusters share outcomes
3 0 M I N U T E S
Integration Event
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
86
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
CONSTRUCTION Chapter 14
Production Design
CORECOMPONENTSOF TVDPROCESS
PRODUCTION DESIGN Chapter 13
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
87
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
Value PostConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
PHASES OF TVD
Construction
CONSTRUCTION Chapter 14
CORECOMPONENTSOF TVDPROCESS
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
88
Transition to Value Post Construction
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
89
Image courtesy of InsideOut Consulting & Southland Industries
Business CasePlanningChapter 2
ValidationChapter 3
Value Delivery: Steering to Target in Design and ConstructionChapter 4
BIG ROOM Chapter 8
PROJECT PLANNING Chapter 9
COST MODELING: PREDICTING COST AND VALUE Chapter 10
CONTINUOUS ESTIMATING Chapter 11
CONCEPTUAL DESIGN Chapter 12
PRODUCTION DESIGN Chapter 13
TEAM FORMING/ORGANIZATION Chapters 6 & 7
CORECOMPONENTSOF TVDPROCESS
PHASES OF TVD
CONSTRUCTION Chapter 14
Value Post Construction
Chapter 4
Value PostConstruction
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
90
• For the owner, value is realized only after the facility is constructed and serving it intended purpose.
• The business case and values are reviewed for actual outcomes.
Value Post Construction
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
91
Business outcomes
• Final cost of design & construction
• Final schedule• Operational performance
of finished building• Quality & use
Project process outcomes
• Project quality, safety & appropriate integration of stakeholder input
Value outcomes
• Revisit the value-based decisions team made throughout process
Measuring Outcomes
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
92
What new actions or ideas that you learned today can you take back to your project?
Write down on Take Away Sheet 5 M I N U T E S
Share with your neighbor 5 M I N U T E S
Discussion Question
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
93
Unaware
Awareness
Understanding
Mastery
Competency
Continuous Learning Loop
Lean Journey Road to Mastery
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
94
Plus/Delta
© LEAN CONSTRUCTION INSTITUTE
T A R G E T V A L U E D E L I V E R Y
95