tariff determination of the waste heat recovery power ... no. 26 of... · whrb waste heat recovery...
TRANSCRIPT
Tariff Determination of the Waste Heat
Recovery Power Plant of M/s Sunvik
Steels Pvt. Ltd
Venkatesh Vunnam
Riya Rachel Mohan
Roshna N
Center for Study of Science, Technology and Policy
March 2017
Center for Study of Science, Technology and Policy (CSTEP) is a private, not-for-profit (Section 25)
Research Corporation registered in 2005.
Designing and Editing by CSTEP
Disclaimer
While every effort has been made for the correctness of data/information used in this report, neither
the authors nor CSTEP accept any legal liability for the accuracy or inferences for the material
contained in this report and for any consequences arising from the use of this material.
© 2017 Center for Study of Science, Technology and Policy (CSTEP)
No part of this report may be disseminated or reproduced in any form (electronic or mechanical)
without permission from CSTEP.
This report should be cited as: CSTEP, (2017). Tariff Determination of the Waste Heat Recovery Power
Plant of M/s Sunvik Steels Pvt. Ltd. (CSTEP-Report-2017-09).
March, 2017
Center for Study of Science, Technology and Policy # 18, 10th Cross, Mayura Street, Papanna Layout, Nagashettyhalli, RMV II Stage, Bangalore-560094 Karnataka, INDIA Tel.: +91 (80) 6690-2500 Fax: +91 (80) 2351-4269 Email: [email protected]
Website: www.cstep.in
Acknowledgements
The authors would like to express their gratitude to Karnataka Electricity Regulatory
Commission (KERC) for providing us an opportunity to conduct this study. The authors are
grateful to Mr. Jaganatha Gupta, Consultant (Tech), KERC, for his guidance and immense support
and to Mr. Seshadri, Deputy General Manager, KERC, for sharing the information and valuable
insights needed for the study. The authors would also like to thank Sunvik officials and the
Sponge Iron Manufacturing Association team for their time and support.
The authors also acknowledge the inputs provided by Dr. Krishnan S.S. (Advisor), Dr. Bellarmine
K.C., Mr. Thirumalai N. C., Ms. Rishu Garg, Mr. Ravi Lepakshi, Ms. Bhavna Sharma and other
colleagues from CSTEP. Last but not the least, this work would not have been possible without
the valuable support and encouragement from Dr. Anshu Bharadwaj, Executive Director, and Dr.
Jai Asundi, Research Coordinator, at CSTEP.
Acronyms and Abbreviations
AFBC Atmospheric Fluidised Bed Combustion
BESCOM Bangalore Electricity Supply Company Ltd
CERC Central Electricity Regulatory Commission
DCS Distributed Control System
DRI Direct Reduction Iron
ESCOM Electricity Supply Company
ESP Electro Static Precipitator
GCV Gross Calorific Value
GBI Generation-Based Incentive
KERC Karnataka Electricity Regulatory Commission
KPTCL Karnataka Power Transmission Corporation Limited
MCR Maximum Continuous Rating
MNRE Ministry of New and Renewable Energy
MoEFCC Ministry of Environment, Forest and Climate Change
MU Million Units
MW Mega Watt
O&M Operation and Maintenance Cost
PLF Plant Load Factor
PPA Power Purchase Agreement
R&M Repairs and Maintenance
RCC Reinforced Concrete
RE Renewable Energy
RoE Return on Equity
RPO Renewable Purchase Obligation
SHR Station Heat Rate
SSPL Sunvik Steels Private Limited
STG Steam Turbine Generator
TPD Tonnes per Day
TPH Tonnes per Hour
WACC Weighted Average Cost of Capital
WHR Waste Heat Recovery
WHRB Waste Heat Recovery Boiler
Executive Summary
Karnataka is one of the most industrialised states in India with an annual steel production
capacity of more than 10 Million tonnes. Many steel plants have Waste Heat Recovery
(WHR)-based Captive Power Plants (CPPs) that utilise the waste flue gas from the sponge
iron kiln. Currently, the surplus energy is exported to the grid using a short-term Power
Purchase Agreement (PPA) between generators and Electricity Supply Companies (ESCOMs)
which needs to be renewed frequently. Sponge iron manufacturers requested Karnataka
Electricity Regulatory Commission (KERC) to provide a preferential tariff for a long-term
PPA. With reference to this, KERC commissioned this study to identify key parameters for
tariff determination of Sunvik Steel’s WHR plant.
Sunvik Steels Pvt. Ltd has commissioned a 10 MW CPP for power generation by utilising
waste heat from sponge iron kiln operation. The heat from flue gases is tapped for steam
generation using three WHR boilers. Since the steam generation from flue gases varies with
sponge iron production, an Atmospheric Fluidised Bed Combustion (AFBC) boiler of 25
Tonnes per Hour (TPH) was installed to supplement any shortfall of steam and to ensure
continuous power generation. The power generated by the power plant is consumed
internally for steel manufacturing and other unit operations. The surplus energy is currently
exported to the grid at a tariff of Rs. 3.90/kWh.
The report focuses on the following aspects:
Assessment of capital cost of different components of a CPP
Station Heat Rate (SHR) and Plant Load Factor (PLF) of the plant
Assessment of technically viability of the plant without using AFBC
Monetary value of waste heat
Parameters for tariff calculation.
Methodology
CSTEP team conducted a site visit to Sunvik Steels’ CPP in Tumkur to check the actual plant
layout and processes. Also, CSTEP contacted several stakeholders, including steel
manufacturers owning waste heat recovery power plants, consultants, etc., to assess the
capital cost and technical viability of the project. In case of tariff determination, capital cost,
Operation and Maintenance (O&M) costs and the PLF of the plant were taken as per actual.
The tariff guidelines in KERC Order on Renewable Energy, 2015, were used to benchmark the
remaining parameters for tariff determination.
Key Findings
Capital cost: Sunvik Steels have incurred Rs. 6,814 lakhs for setting up the 10 MW waste heat
recovery-based CPP. The project cost is higher as compared to the standard value of Rs. 600
lakhs/MW due to the cost overrun incurred due to a delay in commissioning of the power
plant largely due to circumstances beyond their control.
SHR and PLF: From the time of commissioning, the average SHR of the plant is 3,876
kcal/kWh and the average PLF of the plant is 84%.
Technical viability: The CPP is currently running at 84% PLF with a combination of a WHR
boiler (3 X 10 TPH) and an AFBC boiler (1 X 25 TPH). Since the flow rate of flue gas is highly
dependent on sponge iron production, the AFBC boiler was installed to provide steam at a
continuous rate. Steam from AFBC is also supplied to the 10 MW turbine, which otherwise
cannot run on full capacity. The PLF of the plant could reduce to 31% if the plant runs purely
on WHR boilers, leading to low turbine efficiency, high technical losses, etc.
Monetary value of waste heat: Since the flue gases from the sponge iron kilns were not used
for any other purpose, the monetary value for the waste flue gas is considered as nil for the
purpose of this study.
Parameters for tariff calculation: A two-part tariff, using fixed and variable costs, was
designed for the tariff calculation. The fixed costs included O&M costs, interest from term
loan, depreciation, interest on working capital and return on equity, whereas the variable
costs included the fuel cost. The fixed costs were levelised over the lifetime of the project,
whereas the variable cost was levelised for the remaining lifetime of the project. Based on
the parameters assumed, the tariff for Sunvik Steels’ CPP was calculated around Rs.
4.54/kWh.
Table of Contents
1. Introduction ........................................................................................................................................................ 1
1.1. Overview of Sunvik Steels Private Limited................................................................................... 1
2. Plant Overview ................................................................................................................................................... 3
2.1. Process Description ................................................................................................................................ 3
2.2. Working Principle of a WHRB ............................................................................................................ 5
2.3. Working Principle of AFBC Boilers .................................................................................................. 6
3. Co-generation Power Plant ........................................................................................................................... 7
3.1. Performance of Co-generation Power Plant ................................................................................ 7
4. Assessment of Capital Costs ......................................................................................................................... 8
4.1. Segregation of WHRB and AFBC Project Cost ............................................................................. 9
5. Determination of SHR .................................................................................................................................. 10
6. GCV of Flue Gas ............................................................................................................................................... 10
7. Monetary Value for Waste Flue Gas ....................................................................................................... 10
8. Lifetime of the Plant ...................................................................................................................................... 11
9. Plant Load Factor of the Plant .................................................................................................................. 11
10. Turbine Performance Assessment with WHRB................................................................................. 11
11. Determination of Tariff ................................................................................................................................ 12
11.1. Determination of Fixed Cost .......................................................................................................... 12
11.2. Determination of Variable Costs .................................................................................................. 14
11.3. Determination of Levelised Tariff ............................................................................................... 15
12. Parameters for Tariff Determination for the Waste Heat Recovery Project (excluding
AFBC) ……………………………………………………………………………………………………………………………16
13. Sensitivity Analysis ..................................................................................................................................... 17
14. Conclusion ....................................................................................................................................................... 18
Annexure I .................................................................................................................................................................. 20
Annexure II ................................................................................................................................................................. 21
Annexure III ............................................................................................................................................................... 22
Annexure IV ............................................................................................................................................................... 23
List of Figures
Figure 1: Schematic of a CPP .................................................................................................................................. 4
Figure 2: Working Principle of a WHRB ........................................................................................................... 5
Figure 3: Schematic Diagram of an AFBC Boiler............................................................................................ 6
Figure 4: Performance of a Co-generation Power Plant ............................................................................. 7
Figure 5: Tariff vs Project Cost and Fuel Mix ............................................................................................... 17
List of Tables
Table 1: Chronology of Events .............................................................................................................................. 2
Table 2: Technical Specifications of the Boilers ............................................................................................ 2
Table 3: Component-Wise Capital Cost of the Co-generation Power Plant (Rs. Lakhs) ............... 8
Table 4: Segregated Project Cost (Rs. Lakhs) ................................................................................................. 9
Table 5: Plant Performance Analysis .............................................................................................................. 10
Table 6: GCV of Flue Gas ....................................................................................................................................... 10
Table 7: Annual Power Generation from the SSPL CPP ........................................................................... 11
Table 8: Turbine Performance with Steam from WHRB ......................................................................... 11
Table 9: Electricity Generation by the Power Plant .................................................................................. 14
Table 10: Calculations of Per-Unit Fuel Cost ................................................................................................ 15
Table 11: Parameters for Tariff Determination for CPP (excluding AFBC)..................................... 16
Table 12: Parameters for Calculation of Tariff ............................................................................................ 21
Table 13: Calculation of Levelised Fixed Cost ............................................................................................. 22
Table 14: Calculation of Levelised Variable Cost ....................................................................................... 23
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in
1
1. Introduction
Iron and steel is the largest consumer of energy among all industrial sectors. This sector
accounts for about 10% of the total electricity and 27% of the total coal consumption of the
Indian industry, contributing to nearly 30%–35% of the sector’s production cost. Coal is used
as a reducing agent to convert iron ore to sponge iron, and large quantities of flue gases,
produced after the process, are released into the atmosphere. Steel plants try their best to
utilise the waste flue gases, derived from steel manufacturing, by limiting the purchase of
fuels and electric power from grid. Instead, the energy from waste flue gases is recovered
and used in power generation process, resulting in improved energy efficiency, reduction in
pollution and reduction in auxiliary energy consumption.
Karnataka is one of the most industrialised states in India and the top producer of iron and
steel in the country. Waste Heat Recovery (WHR) is an important Energy Efficiency (EE)
measure that could be harnessed by the state, especially for iron and steel industries.
Currently, the adoption of WHR technology in Karnataka is very low due to financial and
policy barriers like the high capital costs and low incentives. The existing WHR projects in
Karnataka are utilising the power generated from flue gases, for their self-consumption.
However, the excess power generated by the industry is allowed to be fed to the grid at a rate
fixed by the state regulatory commission. Industries have to sign a short-term Power
Purchase Agreement (PPA) with the state government and renew the tariff frequently. As of
now, there is no provision for a long-term PPA for WHR projects in Karnataka, which creates
insecurity within the project proponents to set up such technologies in their industries.
1.1. Overview of Sunvik Steels Private Limited
Sunvik Steels Private Limited (SSPL), established in 2003, deals with the manufacture of
sponge iron, mild steel ingots, Thermo Mechanically Treated (TMT) bars and fly ash bricks.
The plant is located in Jodidevarahalli village, Sira taluk, Tumkur district, Karnataka, and is
the first Integrated Steel Plant in Karnataka.
SSPL started with an annual manufacturing capacity of 30,000 MT of sponge iron in July
2004, which was later expanded to 1,00,000 MT in 2009. The chronology of events leading to
the company’s expansion from 2004 to 2010 is provided in Table 1. Steel manufacturing
being a power-intensive process, SSPL decided to be self-sufficient in power generation.
According to Ministry of Power,1 “Captive power plants may be defined as plants meant for
catering to the needs of a particular industry/consumer or group of industries/consumers for
their own use, which should be not less than 50% of the total output of the plant.” The heat
energy from the waste gases discharged from the kiln (900C) is tapped for power
generation. Hence, with a view to capturing the energy from the waste gas, a 10 MW captive
power plant was installed in March 2010.
1 http://powermin.nic.in/en/content/policy-captive-and-co-generation-plants.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP
2
Table 1: Chronology of Events
Date Event July 2004 Commissioned first Direct Reduced Iron (DRI) kiln with annual manufacturing
capacity of 30,000 MT of sponge iron December 2005 Commissioned second DRI kiln and enhanced the sponge iron manufacturing
capacity to 60,000 MT per annum September 2006 Commissioned Furnace Melting Division with annual capacity of 75,000 MT June 2007 Commissioned Rolling Mill with annual capacity of manufacturing 75,000 MT of
TMT bars March 2009 Commissioned third DRI kiln and enhanced the sponge iron manufacturing
capacity to 1,00,000 MT per annum March 2010 Set up 10 MW WHR Boilers (WHRBs) and an Atmospheric Fluidised Bed
Combustion (AFBC) boiler-based CPP
The thermal energy available in the three DRI kilns, is captured by three WHRBs, of 10
Tonnes per Hour (TPH) capacity each, for the generation of steam. The remaining steam
required to be supplied to the turbine is generated using an AFBC boiler of 25 TPH capacity.
The technical specifications of the boilers are provided in Table 2.
Table 2: Technical Specifications of the Boilers
Boiler Type Number Steam Flow Rate (TPH) Pressure (kg/cm2) Temperature (C) WHRB 3 10 63 485 AFBC 1 25 63 485
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in
3
2. Plant Overview
Sponge iron is typically produced by direct reduction of iron ore with coal or coke as the
reducing agent. The objective of the reduction process is to remove oxygen in the iron ore
without melting the ore. Typically, rotary kilns of 1 to 4 m diameter and 30 to 100 m length
are used to carry out the DRI process in steel plants. In the SSPL Captive Power Plant (CPP),
they are mounted at a very minor slope and rotated at a speed of 0.5 to 2 revolutions per
minute by electric drive motors. The iron ore and coal are properly mixed and fed at the
upper end of the kiln, while air for the combustion of coal is supplied through the lower end
of the kiln. The flame travels upward to the kiln, counter-current to the solids, and the rotary
motion of the kiln enhances heat transfer. The temperature required for the DRI process
typically ranges from 800C to 1,200C. After completion of the reduction process, the
sponge iron and un-burnt carbon are discharged through the lower end of the kiln. The hot
gases formed during the reactions are released from the upper end of the kiln. The products
from the rotary kiln are cooled and then sponge iron is separated from un-burnt carbon. The
un-burnt carbon from the kiln, called “Dolochar,” has a reasonable amount of calorific value
which can be utilised further for effective heat recovery. The sponge iron plant at SSPL
consists of three kilns each with maximum capacity of 100 TPD. The coal used in the sponge
iron plant is generally imported from South Africa.
2.1. Process Description
The hot gases formed during the reduction reaction are at a temperature of around 900C.
Hot gases from each kiln are released at around 25,000 m3/h during the reduction process;
however, the actual quantity varies depending on the operational conditions in the kilns. The
average thermal energy content of the gases from each kiln is about 7.48 Million kcal/h. This
thermal energy from the hot flue gas can be used to produce 10 TPH of steam with pressure
of 63 kg/cm2 and temperature 485C. Therefore, to extract heat from waste gas, SSPL has
installed three WHRBs, each individually connected to a rotary kiln. Hot gases from the kiln
are passed through the WHRBs, a shell and a tube heat exchanger for generating steam. The
energy thus extracted from waste gas is sufficient to generate 6 MW of electricity.
In order to become self-sufficient in power and to maximise waste heat recovery, SSPL has
set up an AFBC boiler along with WHRBs. The primary fuel for the AFBC boiler is a mixture of
dolochar and imported coal. This boiler is designed to utilise 100% dolochar to comply with
the guidelines of the Ministry of Environment, Forest and Climate Change (MoEFCC). Based
on the actual operational data, the average coal-to-dolochar ratio used in the boiler is found
to be 60:40. The AFBC boiler installed in SSPL has capacity to generate 25 TPH of steam with
pressure of 63 kg/cm2 and temperature of 485C. The maximum power that can be
generated with this boiler at Maximum Continuous Rating (MCR) condition is 5.5 MW. This
reserve generation capacity is essential to compensate for any shortfall in energy generation
from the WHRBs. Figure 1 shows a schematic diagram of a waste heat recovery power plant.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
4 www.cstep.in © CSTEP
Figure 1: Schematic of a CPP
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 5
The steam from WHRBs and the AFBC boiler is collected and mixed at a common steam
distribution header and is supplied to a steam turbine. The maximum electricity that can be
generated from the CPP is 10 MW.
The power generated from the CPP is used for running the sponge iron plant, induction
furnace and rolling mill, and for the in-house requirements of the power plant. However,
SSPL also imports power from Karnataka Power Transmission Corporation Limited (KPTCL)
grid as required. The surplus energy is exported to the grid during the maintenance of the
steel plant.
Proper ash handling systems are provided to avoid settlement of dust inside the WHRBs.
SSPL has also installed Electro Static Precipitators (ESPs), each connected to the outlet of the
WHRBs and the AFBC boiler to remove particulate matter from flue gas. CPP has an air-
cooled condenser instead of water-cooled condenser, mitigating difficulties owing to
shortage of sufficient water. The water required for power plant operation is obtained from
bore wells set up in the plant premises. Raw water is treated at an in-house water treatment
plant before being fed into the boilers. The instrumentation and control system for the power
plant are based on a distributed control system and the entire power plant system can be
monitored and controlled remotely.
2.2. Working Principle of a WHRB WHRBs use medium-to-high temperature exhaust gases from energy-intensive plants such
as steel industries to extract thermal energy for steam and power generation. In steel plants,
the flue gases formed during reduction reactions exit at a high temperature of about 900C –
950C. Most of the WHRBs are usually water tube boilers in which water is circulated
through tubes as shown in Figure 2. This makes WHRBs a very effective option to generate
steam in a sustainable way. The steam generated from WHRBs can be used to generate
electricity.
In SSPL, the waste hot flue gases from the three kilns are supplied to the WHRBs. For
producing the additional steam, required for 10 MW power generation and for continuous
operation of the CPP under any circumstances, Fluidised Bed Combustion (FBC) boilers were
implemented along with the WHRBs.
Figure 2: Working Principle of a WHRB
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 6
2.3. Working Principle of AFBC Boilers In an AFBC boiler, air is passed upward through a bed of inert solid particles, changing it to a
fluidised state. The fluidised bed is heated to a temperature higher than the ignition
temperature of coal and uniform fluidisation is maintained in the boiler. The particles are
suspended in air to provide enough surface area for combustion of coal. Coal is screened and
crushed to a size of () 6 mm for easy combustion, resulting in a release of high energy to
generate steam as shown in Figure 3. Compared to conventional pulverised coal combustion,
an AFBC boiler is techno-commercially more feasible for low- and medium-capacity steam
generation, and is easy to manage with respect to environmental issues by way of effective
management of ESP and ash handling systems.
Source: http://www.photomemorabilia.co.uk/FBC.html
Figure 3: Schematic Diagram of an AFBC Boiler
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 7
3. Co-generation Power Plant
According to Policy for Captive and Co-Generation Plants, 2
“A co-generation facility is defined as one which simultaneously produces two or more forms of
useful energy such as electric power and steam, electric power and shaft (mechanical) power
etc.
Two basic co-generation cycles have been identified: i. Topping Cycle: Any facility that uses fuel input for power generation and also utilises useful heat
for other industrial activities. In any facility with a supplementary firing facility, it would be required that the useful heat, to be utilized in the industrial activities, is more than the heat to be supplied to the system, through the supplementary firing, by at least 20%.
ii. Bottoming Cycle: Any facility that uses waste industrial heat for power generation by supplementing heat from any fossil fuel.”
SSPL can be categorised as a “Bottoming Cycle” co-generation power plant, which uses the waste industrial heat produced in a sponge iron kiln for power generation, while supplementing heat with coal firing.
3.1. Performance of Co-generation Power Plant SSPL’s co-generation power plant generates about 73.7 MU per annum, with 7.7 MU being
exported to the grid every year. On average, about 10% of the power generated is exported
by SSPL and the remaining is utilised for captive consumption. This is well within the range
of 50% as defined by Ministry of Power for CPPs. Figure 4 shows the gross power generated
and power exported to the grid from the time of commissioning of the power plant.
Figure 4: Performance of a Co-generation Power Plant
The input heat requirement, for generating steam in a WHRB, is completely met with flue
gases from the sponge iron plant’s kiln, which is based on the sponge iron production.
However, because the production varies, the WHRB cannot be relied upon solely for
producing power and meeting the company’s power requirement. It is observed that about
46%–50% of the steam input is from WHRB and the remaining is from AFBC.
2 http://powermin.nic.in/en/content/policy-captive-and-co-generation-plants.
0
10
20
30
40
50
60
70
80
90
2010-11 2011-12 2012-13 2013-14 2014-15 2015-16
Po
we
r (M
U)
Gross power generated (MU) Power exported to grid (MU)
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 8
4. Assessment of Capital Costs
Capital cost is the most significant component in tariff determination. This comprises cost of
plant and machinery, civil works, erection and commissioning, switch yard, transmission
lines, etc. The detailed breakup of the capital cost incurred by SSPL at the time of
commissioning of the power plant (2009–10) is provided in Table 3. The auditor’s certificate
certifying the total capital cost incurred by the power plant is provided in Annexure I. The
total project cost was verified and validated from the company’s balance sheets (2009–10).
Table 3: Component-Wise Capital Cost of the Co-generation Power Plant (Rs. Lakhs)
Particulars Components Cost
Boiler & Associated Equipment
Boilers 2,099
Boiler accessories 266.6
Electrical works 354.3
Civil works 588
Turbine and Alternator
Turbo Generator & Auxiliaries 460.6
Turbine accessories 724.1
Civil works 617
66/11 KV Switch Yard 66 KV Switch yard 140
Generator transformer 65.1
66 KV Transmission Line 66 KVA line erection & commissioning 12
Balance of Plant
Water treatment plant, laboratory
expenses 409
Freight Machinery 6.4
Pre-operative Expense 1,071.7
Total 6,813.7
For the purpose of assessing the capital costs of the WHR power project in an iron and steel
industry, we consulted various independent energy consultants on the typical capital cost of
a WHR power project. The average cost of a WHR power project of similar size (10 MW) is
between 5.5 and 6 Crore/MW. SSPL has, however, incurred 6.8 Crore/MW, which is much
higher compared to the standard rate. The project cost includes a pre-operative expense of
more than 10 Crore which contributes 15.72% of the total capital costs. The higher pre-
operative expenses were incurred due to a delay in commissioning of the plant, which is
largely due to circumstances beyond their control. Also, the high capital costs incurred by
SSPL for the WHR project are due to the inclusion of several energy-efficient measures in the
power plant like installing de-dusting systems to improve steam generation, variable-
frequency drive motors, automatic ash handling system, etc.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 9
4.1. Segregation of WHRB and AFBC Project Cost The WHRB-based power plant was conceptualised together with the AFBC-based plant to
ensure uninterrupted power supply to the process. The project consists of one common
turbine of 10 MW for which steam is supplied from WHRBs and AFBC through a common
steam header. The cost of setting up a 10 MW power plant will also be much lesser than
constructing 6 MW and 4 MW power plants, separately.
The power generation from WHRBs is entirely dependent on sponge iron kiln Operation and
Maintenance (O&M) requirements. The overall plant availability for a sponge iron plant is
around 60% annually. Also, during routine kiln operation, the WHRB boiler generates at
around 65%–75 % of its capacity due to numerous operational complexities. Due to the
above constraints in generating the rated steam in WHRBs, SSPL has installed an AFBC boiler
of 25 TPH steam generation capacity.
Also, it is not possible to clearly segregate the cost components of the WHRB part, from that
of the CPP, as common equipment like steam turbine generator, steam header, water
treatment plant, water storage Reinforced Concrete (RCC) tanks, electrical systems, switch
yard, Distributed Control System (DCS) and automation, ash silos, air compressors, building
cost, etc., are shared by both WHRB and AFBC systems.
This study tried to segregate the project cost between WHRB and AFBC through simple
apportionment. The costs of a boiler and its accessories were divided between WHRB and
AFBC based on the ratio of the designed steam output (i.e., 30:25), while the cost of turbine,
water treatment plant, freight expense and pre-operative expenses were divided based on
the electrical output ratio (i.e., 6:4). Since the switchyard and transmission line had to be
constructed irrespective of the power output, the cost incurred for construction of
switchyard and transmission lines are not segregated under WHRB and AFBC.
Table 4 shows the segregated project cost for the 10 MW CPP.
Table 4: Segregated Project Cost (Rs. Lakhs)
Particulars 10 MW CPP Cost 6 MW WHRB Related Cost
4 MW AFBC Related Cost
Boiler & Associated Equipment 3,308 1,620 1,688 Turbine and Alternator 1,802 1,081 721 66/11 KV Switch Yard 205
66 KV Transmission Line 12 Balance of Plant and Pre-
operative Expenses 1,487 892 595 Total 6,814 3,810 3,221
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 10
5. Determination of SHR
Station Heat Rate (SHR) is the thermal energy required to generate one unit of electricity.
The AFBC unit in SSPL is operated with 60% coal and 40% dolochar. The average Gross
Calorific Value (GCV) of the fuel mix is 4,468 kcal/kg. On the other hand, the WHRB system
utilises the heat content of the flue gases coming out of the sponge iron kilns. The average
SHR is estimated as 3,876 kcal/kWh, as shown in Table 5. The yearly data of the CPP have
been analysed to draw key findings from the plant. Table 5: Plant Performance Analysis
Parameter Average Value AFBC Fuel consumption (tonnes) 35,374 Average GCV of fuel (kcal/kg) 4,468 Thermal Energy from AFBC (Gkcal) 158 WHRB Steam flow rate (tonnes/year) 1,52,243 Boiler efficiency (%) 81.5 Enthalpy of steam (kJ/kg) 2,861 Enthalpy of steam (kcal/kg) 684 Thermal energy in steam (Gkcal) 104 Thermal energy in flue gas (Gkcal) 128 Total power generation (MU) 74 SHR (kcal/kWh) 3,876
6. GCV of Flue Gas
The volumetric flow rate of the exhaust gas is 25,000 Nm3/h with a density of 1.31 kg/m3.
Based on the analysis, the heat content of the kiln exhaust gas is found to be 228 kcal/kg. The
parameters used in calculating the GCV of flue gas are provided in Table 6.
Table 6: GCV of Flue Gas
Parameter Value
Volumetric flow, m3/h 25,000
Density, kg/Nm3 1.31
Mass flow, kg/h 32,825
Heat content of exhaust gas, Million kcal/h 7.48
Heat content of kiln exhaust, kcal/kg 228
7. Monetary Value for Waste Flue Gas
Coal is used as a reducing agent as well as a fuel to generate heat for heating the raw
material. The flue gas emitting from the DRI kiln, which is generally released to the
environment as a waste gas, has about 36% of the thermal energy of the coal fed to the kiln.3
Since this flue gas is not used for any other purpose, its monetary value is considered as nil
for purposes of this study.
3 http://file.scirp.org/pdf/OJEE_2014091514403413.pdf.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 11
8. Lifetime of the Plant
The lifetime of boilers is generally 20 years, which can be considered as the lifetime of the
power plant. Also, according to Central Electricity Regulatory Commission (CERC)4, the
lifetime for tariff computation in bagasse-based co-generation plants, which use similar
equipment, is determined as 20 years.
9. Plant Load Factor of the Plant
PLF of a plant is the ratio between the actual energy generated and the maximum possible
energy that can be generated from the plant working at its rated power over a year. The
actual generation of the power plant from the time of commissioning is shown in Table 7.
Based on the data, the PLF of the power plant at SSPL is estimated as 84%.
Table 7: Annual Power Generation from the SSPL CPP
Year Gross Power Generation (MU)
2010–11 70.9
2011–12 75.3
2012–13 74.5
2013–14 77.7
2014–15 70.8
2015–16 73.3
Average 73.7
10. Turbine Performance Assessment with WHRB
The total heat from the plant or the extractable energy from the flue gases is used for the
power generation process. Based on last six years data, the average steam generated from
WHRB system was 18 TPH. As shown in Table 8, the power generation by utilising steam
from the standalone WHRB system is estimated to be 3.7 MW, with a corresponding PLF of
31%.
Table 8: Turbine Performance with Steam from WHRB
Parameter Value
Installed capacity, MW 10
Steam pressure, kg/cm2 64
Steam temperature, C 480
Inlet steam enthalpy, kJ/kg 3,389
Exit steam enthalpy, kJ/kg 2,432
Enthalpy difference, kJ/kg 957
WHRB steam flow, TPH 18
Power generation, MW 3.7
4 http://cercind.gov.in/2016/orders/sm_3.pdf
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 12
The WHRB system cannot provide continuous steam supply at the desired conditions to
ensure efficient operation of the 10 MW turbine. The turbine will operate at lower efficiency
in the absence of AFBC steam due to a part load condition. Therefore, it is recommended to
utilise steam from both the WHRB and AFBC boilers for power generation.
11. Determination of Tariff
Levelised tariff is a tool for making investment decisions. It ensures realisation of the
present-day value of investment to investors. As a generic approach used in a biomass co-
generation power plant, a two-part tariff approach was considered in the tariff
determination. The tariff was divided into two parts – fixed cost and variable cost. Fixed
costs include all cost components which do not depend on the electricity generated by the
power plant, whereas variable costs include components which are directly dependent on
the running of the project activity. Coal costs are volatile over the lifetime of the project and
were considered under variable costs.
“KERC Order on Renewable Energy” dated 01/01/2015 (referred to as “KERC RE Tariff
Regulations, 2015”)5 was used as the basis to benchmark a few parameters for tariff
determination. It mentions the parameters used for determination of tariff with regard to
mini-hydel, bagasse-based co-generation and Rankine cycle-based biomass renewable
energy projects. Since the project under study is a co-generation power plant, a few of the
parameters mentioned for tariff determination of a bagasse-based co-generation plant can be
compared.
11.1. Determination of Fixed Cost
Fixed costs include interest from term loan, depreciation, return on equity, interest on
working capital and O&M costs for a power plant. The levelised fixed cost is calculated for the
lifetime of the project activity (i.e., 20 years).
Capital Costs
Since KERC RE Tariff Regulations, 2015, do not mention any benchmark capital cost for a
waste heat recovery co-generation power plant, the actual capital cost has been used in the
calculation of the tariff. The total cost of the plant, as on the commissioning date, is Rs. 6,814
lakhs. The detailed breakup of the capital costs is mentioned inTable 3. As on 1 December
2016, SSPL has incurred an additional expenditure of Rs. 27.3 lakhs on the capital cost.
However, this cost is not included in the tariff calculation in this study.
Debt Equity Ratio
Debt equity mix of a project is an important parameter that influences the return on
investments of a developer. In this regard, KERC RE Tariff Regulations, 2015, have prescribed
70:30 as the debt equity ratio for co-generation power plants. The same ratio has been
considered for the tariff calculation in this study.
5 http://www.ireeed.gov.in/policyfiles/429-FinalREOrder.pdf.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 13
However, Sunvik Steels had availed loans of Rs. 5,249 lakhs, including secured and unsecured
loans (i.e., 77% of capital cost), for the project, while the remaining amount was financed
through equity.
Interest from Term Loan
KERC RE Tariff Regulations, 2015, have assumed loan tenure of 12 years with 12.5% as the
interest on the term loan for co-generation power plants. These values have been considered
in the calculation of WHR power tariff.
Sunvik Steels had availed secured loans at 13.25% interest rate for 6 years (including 6
months moratorium) from three banks for the project activity. The loans were availed from
Canara Bank, State Bank of Patiala and State Bank of India as a consortium loan.
Operation and Maintenance Costs
O&M costs majorly include labour charges, Repairs and Maintenance (R&M) of the plant and
machinery, electrical maintenance and the refractory materials used in AFBC. Since KERC RE
Tariff Regulations, 2015, does not mention the O&M costs incurred by a waste heat recovery
co-generation plant, the average of the actual O&M cost incurred by SSPL for the past 6 years
has been taken for the tariff calculation in this study. Sunvik Steels has assigned the O&M to
Operational Energy Group India Ltd on a fixed contract basis. Hence, the accounts for the
O&M costs are maintained separately for the power plant. The O&M costs for the past 6 years
(from the time of commissioning of the power plant) were obtained from the company’s
balance sheets from 2010–11 to 2015–16, which were audited by a charted accountant.
The average O&M expense for the power plant for the past 6 years is Rs. 211.1 lakhs per
annum. The annual escalation rate for the O&M costs is considered as 5.72%, as suggested
by the KERC RE Tariff Regulations, 2015, for a bagasse-based co-generation power plant.
Depreciation
Depreciation has been calculated on the capital costs of the power plant using the Straight-
Line Method (SLM). The depreciation expense is calculated on 90% of the capital assets after
considering a salvage value of 10% on capital assets. In line with KERC RE Tariff Regulations,
2015, a depreciation rate of 5.83% is applied for the initial 12 years and the remaining
depreciable amount is distributed across the remaining lifetime of the project.
Return on Equity
Return on Equity (RoE) is considered as 16% in line with the KERC Tariff Regulations, 2015.
Discount Rate
The normative Weighted Average Cost of Capital (WACC) is considered as the discount rate
for the purpose of tariff calculation. WACC is calculated as follows:
𝑊𝐴𝐶𝐶 =(𝐸𝑞𝑢𝑖𝑡𝑦 % ∗ 𝑅𝑜𝐸) + (𝐷𝑒𝑏𝑡 % ∗ 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑜𝑛 𝑡𝑒𝑟𝑚 𝑙𝑜𝑎𝑛)
(𝐸𝑞𝑢𝑖𝑡𝑦 % + 𝐷𝑒𝑏𝑡 %).
The discount rate has been calculated as 13.55% for the tariff calculation in this study.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 14
Interest for Working Capital
According to KERC, the working capital required for a biomass co-generation plant is the
amount equivalent to 2 months’ receivables. As suggested by KERC RE Tariff Regulations,
2015, 13.25% was considered as the interest for working capital for the tariff determination
in this study.
Net Electricity Generation
The average gross electrical energy generated by the 10 MW power plant is 73.74 MU per
annum. According to CERC’s RE tariff Regulations, 2016, the auxiliary consumption for a
biomass project using an air-cooled condenser is higher than that of a project using a water-
cooled condenser. CERC suggests 12% auxiliary consumption for an air-cooled condenser
after stabilisation of the power plant. The average net generation by the power plant is 64.89
MU. The actual net generation data are provided inTable 9.
Table 9: Electricity Generation by the Power Plant
Particulars Value
Capacity of the power plant 10 MW
Plant Load Factor (PLF) 84.18%
Gross generation 73.74 MU
Auxiliary consumption 12%
Net generation 64.89 MU
Levelised Per Unit Fixed Cost
The total fixed cost is the sum of the interest on loan, depreciation, RoE, O&M expense and
interest on working capital. The per-unit fixed cost is calculated by dividing the total fixed
cost by the net generation:
Per Unit Fixed Cost (Rs./kWh)
=Interest on loan + Depreciation + RoE + O&𝑀 + Interest on working capital
Net Generation.
The discounted per-unit fixed cost is calculated and levelised over the lifetime of the project
activity to calculate the levelised per-unit fixed cost:
Levelised per unit fixed cost =∑ [Per unit fixed cost𝑘
20
𝑘=1∗ Discount rate𝑘]
∑ Discount rate𝑘20𝑘=1
.
The levelised per-unit fixed cost for this project, under given assumptions and
available information, is Rs. 2.08/kWh.
11.2. Determination of Variable Costs
Since there is no monetary value for the flue gas released from the sponge iron kiln, only the
fuel cost required to generate steam from AFBC is considered under variable cost. The
levelised variable cost is calculated for the remaining lifetime of the project (i.e., 7th to 20th
year).
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 15
Fuel Cost
Sunvik Steels uses a mix of imported coal and dolochar as fuel in the AFBC boiler. The latter
constitutes 35%–40% of the total fuel consumption by AFBC in SSPL. Based on the past 6
years’ coal consumption, the power plant can be seen to have consumed an average of 21,224
MT of purchased coal and 14,150 MT of dolochar annually. Since dolochar is also mixed with
coal to generate steam in AFBC, the quantity of coal required and the cost incurred by the
power plant are calculated as shown in Table 10.
Table 10: Calculations of Per-Unit Fuel Cost
Particulars Unit Value Fuel mix: Coal % 60% Coal rate Rs./MT 4,832 Fuel mix: Dolochar % 40% Dolochar coal rate Rs./MT 2,200 Weighted average fuel cost Rs./MT 3,779 Annual fuel consumption (including dolochar) MT 35,374 Annual fuel cost (@3.28% escalation rate) Rs. lakhs 1,381 Net generation of the power plant MU 64.89 Per unit fuel cost Rs./kWh 2.13
Coal was escalated at 3.28% annually to include the inflation in coal price. The cumulative
annual growth rate of the Wholesale Price Index (WPI) of coal from 2009–10 to 2015–16 was
considered as the escalation rate.
The discounted per-unit coal cost was calculated and levelised from the current year (i.e., 7th
year of operation) to the end of the lifetime of the project activity to calculate the levelised
per-unit variable cost:
Levelised per unit variable cost =∑ [Per unit coal cost𝑘
20
𝑘=7∗ Discount rate𝑘]
∑ Discount rate𝑘20𝑘=7
.
The levelised per-unit variable cost for this project, under given assumptions and
available information, is Rs. 2.46/kWh.
11.3. Determination of Levelised Tariff
Levelised tariff is the sum of the levelised per-unit fixed cost and variable cost.
The levelised tariff for this project, under given assumptions and available
information, is Rs. 4.54/kWh.
The parameters used for calculating the tariff are provided in Table 12 in Annexure II. Also,
the detailed calculation of fixed and variable costs are provided in Annexure III and
Annexure IV, respectively.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 16
12. Parameters for Tariff Determination for the Waste Heat
Recovery Project (excluding AFBC)
It is not technically viable to run the 10 MW turbine with 18–20 TPH of steam (steam only
from WHRB) as discussed in SectionError! Reference source not found. However, since
KERC desires to analyse the scenario of tariff for a CPP power plant (excluding AFBC), this
study has attempted to identify the parameters for tariff determination. Since AFBC is
excluded from the system, there will not be any variable cost component. Hence, the tariff for
this scenario would be the levelised fixed cost. The parameters to calculate the levelised fixed
tariff are the same as shown in Section 11. Since the AFBC component has been removed
from the system, the values for the following parameters will be different as compared to the
values mentioned in Section 11.
Capital Cost
The boiler cost for AFBC is generally 25% higher than that of a WHRB boiler.6 After removing
the cost of an AFBC boiler from the system, the capital cost for tariff determination can be
taken as Rs. 5,126 lakhs.
PLF of the Power Plant
The PLF of the power plant excluding AFBC will be very low as described in Section 9. The
plant will be running at 31% PLF, which is not a healthy operational parameter.
The parameters to be used in the calculation of tariff are shown in Table 11.
Table 11: Parameters for Tariff Determination for CPP (excluding AFBC)
Parameters Value Units Source
Turbine capacity 10 MW Based on purchase orders
PLF of the plant 31% % Refer Section 9
Auxiliary consumption 12% % As per CERC tariff order, 2016
Capital cost 5,126 Rs. Lakhs Cost excluding AFBC boiler cost
Debt 70% % As per KERC tariff order, 2015
Equity 30% % As per KERC tariff order, 2015
Loan tenure 12 Years As per KERC tariff order, 2015
Interest rate 12.50% % As per KERC tariff order, 2015
RoE 16% % As per KERC tariff order, 2015
WACC 13.55% % Calculated
Depreciation 5.83% Of capital cost (for 1st 12 years)
As per KERC tariff order, 2015
Salvage value 10% % Assumption
Total O&M expense 3% Of capital cost
Escalation rate for O&M 5.72% % As per KERC tariff order, 2015
Working Capital-Receivables
2 Months As per KERC tariff order, 2015
Interest on working capital 13.25% % As per KERC tariff order, 2015
6 http://www.thesij.com/papers/IFBM/2013/March-April/IFBM-010105.pdf.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 17
13. Sensitivity Analysis
The tariff computed in case of SSPL’s CPP under given assumptions and available
information, includes the AFBC component which utilises dolochar released from the DRI
kiln. Generally, the dolochar consumption in the boiler varies between 20% and 40% of the
total fuel consumption. A sensitivity analysis was performed to analyse the variation in tariff
for varying project costs and fuel mix (coal: dolochar). Effective utilisation of dolochar leads
to lower coal consumption in the boiler. As the quantity of dolochar increases, the tariff for
the CPP reduces due to the low cost of dolochar as shown in Figure 5. For every 10%
increment in dolochar quantity in the fuel mix, it is observed that the tariff reduces by about
Rs. 0.17/kWh. In case of SSPL, the coal-to-dolochar ratio is 60:40 at a project cost of Rs. 6,814
lakhs for the 10 MW CPP.
Figure 5: Tariff vs Project Cost and Fuel Mix
3.80
4.00
4.20
4.40
4.60
4.80
5.00
6000 6500 6814 7000
Ta
riff
(R
s/k
Wh
)
Project cost (Rs. Lakhs)
60:40 70:30 80:20
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 18
14. Conclusion
Karnataka currently does not consider waste heat recovery (WHR) from industries as a
source of renewable energy and has no added incentive for industries to adopt such projects.
This has led to very low penetration of such technologies in this state. This study was
conducted to examine various technical and financial parameters of the 10 MW WHR-based
power plant of Sunvik Steel Pvt Ltd. (SSPL). Various components of the Captive Power Plant
(CPP), including capital cost, power generation, Station Heat Rate (SHR), Plant Load Factor
(PLF) and parameters for tariff determination were looked into.
In sponge iron production, waste flue gases at high temperature are generated and released
into the environment. The heat from the flue gases is tapped and used in steam generation.
SSPL has installed a 10 MW turbine to be self-sufficient in power. In addition, since the steam
generation from flue gases varies significantly with sponge iron production, an Atmospheric
Fluidised Bed Combustion (AFBC) boiler of 25 TPH was installed to supplement the
remaining steam requirement. AFBC in SSPL uses a mixture of coal and dolochar as the
primary fuel for combustion, using 25%–40% dolochar in the total fuel mix. The steam
produced by AFBC contributes to 47%–52% of the total steam in the steam header.
The net power generated by the power plant is consumed internally for steel manufacturing
and other unit operations. The surplus energy is exported to the grid, which contributes
around 10% of the annual gross generation, which is in line with the definition of CPP. The
plant runs at a PLF of about 84% with an SHR of about 3,876 kcal/kWh.
Based on the study, it is understood that due to the inherent lower plant availability of
sponge iron kiln (approximately 60%), power generation with the WHRB system is only 3.7
MW against the expected capacity of 6 MW. Therefore, it is necessary to utilise steam from
both WHRB and AFBC boilers for power generation to meet the plant’s energy requirements
and achieve higher turbine efficiency.
A levelised tariff approach was used in calculating the tariff for the electricity generated by
the CPP. The per-unit fixed cost was levelised over the entire lifetime of the project (i.e., 20
years), while the per-unit variable cost was levelised for the remaining project lifetime (i.e.,
14 years). By assuming no monetary value for the waste flue gas, the various components of
tariff were calculated as:
Levelised fixed cost: Rs. 2.08/kWh
Levelised variable cost: Rs. 2.46/kWh
Levelised tariff: Rs. 4.54/kWh.
It was also noted that the tariff varies with varying quantity of fuel mix used in AFBC. With a
10% increase in dolochar quantity in the fuel mix, the tariff reduces by Rs. 0.17/kWh. An
efficient policy framework needs to be developed to encourage the consumption of dolochar
in AFBC to reduce the cost of generation.
Since it does not seem technically viable to run the 10 MW turbine with only WHR-based
steam, the tariff for the same was not calculated. The project cost for the existing system,
excluding AFBC boiler cost, was estimated as Rs. 4,860 lakhs, with reduction of the PLF of the
plant (excluding steam from AFBC) to 31%.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 19
The policy framework for renewable energy projects is well defined unlike WHR based co-
generation systems. Though WHR-based power projects have helped in displacing an
equivalent amount of CO2 emissions which would have been emitted from conventional
sources of energy, there is no additional benefit to the industries.
This project also helps in reducing the burden of power supply on the state and central
generation, transmission and distribution networks, by generation of a large share of the
steel plant’s demand, and also helps the power supply situation by exporting excess power to
the grid. To make progress in this regard, the industries should be provided with a long-term
PPA, with periodic escalation, to sell the surplus power which reduces the uncertainty of
future tariffs. Also, it is suggested to provide Generation-Based Incentives (GBIs) similar to
that provided by Ministry of New and Renewable Energy (MNRE) for wind and solar projects
to improve the market penetration of such technologies in the country in order to help the
national goal of electricity for all.
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
www.cstep.in © CSTEP 20
Annexure I
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
© CSTEP www.cstep.in 21
Annexure II Table 12: Parameters for Calculation of Tariff
Parameters Value Units Source
Turbine capacity 10 MW Based on purchase orders
PLF of the plant 84% % Based on last 3 years’ data
Auxiliary consumption 12% % As per CERC tariff order, 2016
Capital cost 6,814 Rs. Lakhs As per CA-certified cost sheet
Loan Details
Debt 70% % As per KERC tariff order, 2015
Equity 30% % As per KERC tariff order, 2015
Loan tenure 12 Years As per KERC tariff order, 2015
Interest rate 12.50% % As per KERC tariff order, 2015
RoE 16% % As per KERC tariff order, 2015
WACC 13.55% % Calculated
Depreciation
Depreciation 5.83% Of capital cost (for 1st 12 years)
As per KERC tariff order, 2015
Salvage value 10% % Assumption
Depreciable amount 6,132 Rs. Lakhs Calculated
Depreciation amount between 13th and 20th year
230.27 Rs. Lakhs Calculated
O&M Expense
Total O&M expense 211 Rs. Lakhs Average of last 6 years’ data
Escalation rate for O&M 5.72% % As per KERC tariff order, 2015
Coal Cost
Wt. average coal cost 3,779 Rs./tonne Calculated based on actual
Wt. average GCV of coal 5,543 kcal/kg Calculated based on actual
Escalation rate on coal cost
3.28% % WPI for coal
Working Capital
Receivables 2 Months As per KERC tariff order, 2015
Interest on working capital
13.25% % As per KERC tariff order, 2015
Tariff at which power is sold to BESCOM
3.9 Rs./kWh As per invoice submitted to BESCOM
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
22 www.cstep.in © CSTEP
Annexure III Table 13: Calculation of Levelised Fixed Cost
Amount in Rs Lakhs 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Interest on loan capital 571 522 472 422 373 323 273 224 174 124 75 25
Depreciation 358 358 358 358 358 358 358 358 358 358 358 358 230 230 230 230 230 230 230 230
Return on equity 327 327 327 327 327 327 327 327 327 327 327 327 327 327 327 327 327 327 327 327
O&M 211 223 236 250 264 279 295 312 330 348 368 389 412 435 460 486 514 544 575 608
Interest on working capital 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56
Total 1523 1485 1449 1412 1377 1342 1309 1276 1244 1213 1183 1155 1025 1048 1073 1100 1128 1157 1188 1221
Net Generation (Mn kWh) 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65
Fixed Cost (Rs/kWh) 2.35 2.29 2.23 2.18 2.12 2.07 2.02 1.97 1.92 1.87 1.82 1.78 1.58 1.62 1.65 1.69 1.74 1.78 1.83 1.88
WACC 13.55%
Discount factor 1.00 0.86 0.75 0.65 0.56 0.48 0.42 0.36 0.31 0.27 0.23 0.20 0.17 0.15 0.13 0.11 0.10 0.08 0.07 0.06
PV of fixed cost (Rs/kWh) 2.35 1.98 1.67 1.41 1.19 1.00 0.84 0.71 0.60 0.50 0.43 0.36 0.28 0.24 0.22 0.19 0.17 0.15 0.13 0.12
Levelised fixed cost (Rs/kWh) 2.08
Interest on term loan 1 2 3 4 5 6 7 8 9 10 11 12
Opening Balance 4770 4372 3975 3577 3180 2782 2385 1987 1590 1192 795 397
Closing balance 4372 3975 3577 3180 2782 2385 1987 1590 1192 795 397 0
Repayment 397 397 397 397 397 397 397 397 397 397 397 397
Interest on loan capital 571 522 472 422 373 323 273 224 174 124 75 25
Interest on working capital
Receivables 422 422 422 422 422 422 422 422 422 422 422 422 422 422 422 422 422 422 422 422
Interest on working capital 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56 56
Tariff Determination of the Waste Heat Recovery Power Plant of M/s Sunvik Steels Pvt. Ltd
23 www.cstep.in © CSTEP
Annexure IV Table 14: Calculation of Levelised Variable Cost
Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Cost of coal 1381 1426 1473 1521 1571 1623 1676 1731 1788 1847 1907 1970 2034 2101
Per unit variable cost (Rs/kWh) 2.13 2.20 2.27 2.34 2.42 2.50 2.58 2.67 2.76 2.85 2.94 3.04 3.14 3.24
Discount factor 1 0.86 0.75 0.65 0.56 0.48 0.42 0.36 0.31 0.27 0.23 0.20 0.17 0.15
Discounted Per unit variable cost (Rs/kWh) 2.13 1.90 1.70 1.51 1.35 1.21 1.08 0.96 0.86 0.77 0.69 0.61 0.55 0.49
Levelised variable cost (Rs/kWh) 2.46
# 18, 10th Cross, Mayura Street, Papanna Layout
Nagashettyhalli, RMV II Stage, Bangalore-560094
Karnataka, INDIA
Ph: +91 80 6690-2500
www.cstep.in