team magnaritaville conceptual design review zachary cuseo, andrew fruge, shweta maurya, sydni...

11
Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev A 09-08-09

Upload: linette-joseph

Post on 20-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Team MagnaritavilleConceptual Design Review

Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie,

Tyler Knappe9/22/09

Fall 2009 Rev A

09-08-09

Page 2: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

BalloonSat C.A.T.E.O.S

• Magnetic Field Testing– Measure the earth’s magnetic field during flight– Prove that magnetic field strength varies with

altitude– Determine the orientation of the camera

throughout flight

– Attitude Determination in Satellites

Page 3: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Design

• Science Components– Magnetic field sensor– Faraday Cage

• Satellite Components– AVR Microcontroller– Heater– Camera

Page 4: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Drawings

Page 5: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Functional Block Diagram

Page 6: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Accomplishing the Mission

• Take data during flight• Recover data from magnetic field sensor and

camera• Interpolate data to determine magnetic field

strength and camera orientation• Give Chris a cookie

Page 7: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Organizational ChartPerson Job Specific Tasks

Zachary Cuseo Systems Engineer

This job involves making sure all the different systems work together in order to assure that the mission is successful and the desired data is obtained.

Tyler Knappe Code Monkey

This job involves programming the AVR to work with the rest of the box, specifically to gather data, take pictures, and control the inner temperature of the satellite.

Shweta Maurya Chief Financial Officer and Data Analyst

This job involves creating and editing diagrams and schematics, tempering and overseeing the budget, and translating the data into coherent analysis in LoggerPro software.

Andrew Fruge’Structures and Asst. Systems Engineer

This job involves creating, testing, and improving the outer foam core structure, as well as the Faraday Cage.  Andrew will also assist Zach with part of the Systems Engineering.     

Sydni Smith Internal Structures Engineer

This job involves arranging the inner components and building whatever stands or holders or shelves may be necessary to keep the inside of the satellite organized and in working condition.

Christopher Nie Electrical Engineer

This job involves being responsible for the power system, including the batteries, electrical connections between components, and the specific power requirements between components.

Page 8: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Schedule• 9/22 - Conceptual Design Review (CoDR) • 9/25 - Design Complete • 9/27 - Program AVR (Microcontroller, Camera, and Heater) • 9/29 - Hardware Ordering and Authority to proceed (ATP) • 10/6 - Design Document revision A/B • 10/8 - Critical Design Review (CDR) • 10/9 - Acquire hardware • 10/9 - External structure complete • 10/12 - Magnetometer testing (Faraday cage determination) • 10/16 - External testing complete (whip test, drop test, and stair test)• 10/16 - Internal component assembly complete• 10/25 - Internal testing complete (cold test, functional test, and data test)• 10/26 - Final assembly complete• 10/27 - Pre-launch inspection• 10/29 - Mission simulation• 11/3 - Launch readiness review and design document revision C• 11/6 - Final weigh-in and turn in• 11/7 - Launch day @ 6:50 am. ("Bad" weather launch days: 11/8 or 11/14)• 12/1 - Design document revision D and final presentation

*Team meeting will be every Sunday and during the week as needed.

Page 9: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Budget

Component Price Purchase Location  Total Cost

Magnetic Sensor $58  Vernier Software and Technology

N/A

Analog Proto Board Connector 

$10 Vernier Software and Technology 

N/A

Shipping $12 (Maximum Cost) Vernier Software and Technology

N/A

Batteries, Structures, Aluminum

~ $20 Locally  $100

Page 10: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

WeightComponent Weight

Magnetic Field Sensor and Connector 70 grams

Structure 280 grams

Satellite Components 500 grams

Total 850 grams

Page 11: Team Magnaritaville Conceptual Design Review Zachary Cuseo, Andrew Fruge, Shweta Maurya, Sydni Smith, Christopher Nie, Tyler Knappe 9/22/09 Fall 2009 Rev

Concerns

• Correlating magnetic field sensor data with camera data

• Properly isolating electromagnetic interference with Faraday Cage