technical assistance consultant’s report...105. the mean annual rainfall fluctuates between...
TRANSCRIPT
Technical Assistance Consultant’s Report
Project Number: 48440-002 November 2018
Islamic Republic of Afghanistan: Kabul Managed Aquifer Recharge Project (Financed by the Afghanistan Infrastructure Trust Fund)
Environmental Due Diligence Report on Proposed Pilot MAR Sites 3, 4 and 6
Part 2 of 3
Prepared by: Landell Mills Ltd.
Wiltshire, United Kingdom
For: Ministry of Finance, Afghanistan
Ministry of Energy and Water, Afghanistan
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
19
Photo 3: MAR Site 3, April 2018
4.2.2. Site 4: Badam Bagh
87. This Site 4 is located at Badam Bagh Research Farm, established in 1959 with the financial
assistance of USAID. This research firm covers an area of 80 hectares of land and its latitude is
34055” N and longitude is 69011” E, approximately 1840 meters above mean sea level.
88. At an initial stage of farm development they introduced fruit saplings like almond, apricot, plum,
quince, grapes, apples, peach, pear etc. species were imported from various countries like
Lebanon, Italy and USA for plantation. In the course of time, the fruit species consisted of both
local and imported verities. This research farm was one of the biggest research farms in the
country, but after the fall of Sardar Daud Khan’s government, the farm was completely destroyed.
89. Nevertheless, in 1995 the farm was rehabilitated with the assistance of the German Agro Action
(GAA) organization4. Since then the rehabilitation of the farm continues. Lately, organizations like
GAA, EC, JICA, ASAP5 and FAO have been actively working for the reconstruction of the farm.
90. This Badam Bagh Farm authority expressed their interest to support KMARP, and agreed to
provide land for project implementation within their boundaries. It is proposed to construct a gravity
fed injection well at Badam Bagh with MAR water sourced via Qarga Reservoir and a canal
/siphon system. The suggested system is illustrated in Figure 5 (overleaf) and the site of the MAR
injection well to receive gravity fed water is shown in Photo 4.
91. The total depth of the well will be 70 meters with a design of 18 inch diameter J55 grade steel
casing and torch slotted screens. The drilled diameter of the borehole should ideally be 24 inches.
An example of such drilling is shown below in Photo 5.
4 International NGO, German Agro Action (GAA)
5 ASAP (Accelerating Sustainable Agriculture Program) is designed to revitalise Afghanistan’s agriculture sector and to improve global
competitiveness of the country’s agribusiness sector. It is a nationwide program providing strategic support to Afghanistan’s public and private sectors with two objectives: a) increase agricultural sector jobs and income, b) increase Afghan’s confidence in their government.
20
92. During construction, it is envisaged that the land take could amount to 16 m2 with a completion
foot print of 1 m2. The borehole would be completed flush with ground level. Water would feed the
injection well via direct gravity flow from an irrigation channel.
93. Once every 2 years the borehole should be plumbed to ensure backfilling has not taken place. If
backfilling has occurred, the borehole should be cleaned via bailer attached to a percussion drilling
rig.
94. Two piezometers will also be constructed at this site with each completed with 2 inch diameter
schedule 80 PVC screens and casing. The footprint of the surface expression of the piezometers
would be 30 cm x 30 cm with the piezometers completed flush with ground level.
23
4.2.3. Site 6: Makroyan-e-4
95. Site 6 is situated at Makroyan-e-4, between Kabul River and Abdulhaq squire to Pol-e-Mahmood
Khan Road (GPS Location of BM: 34052”82’N; 69019”94’E). This site is characterized by a
seasonal nursery bed of various vegetables and flowers, and a small poultry farm under private
ownership (Photo 6).
96. The owner has agreed to allocate part of his land for the pilot KMARP facility on a rental or lease
basis.
97. The planned project intervention at this site is an Injection Well. The site has been selected to test
the ability of a shallow production well adjacent to the river to induce infiltration, partially treat the
river water by drawing the fluid through river gravels and ultimately use that water for MAR at a
deeper well nearby (Figure 6 and Figure 7).
98. An injection borehole, an induced infiltration borehole and a single piezometer will be constructed
at site 6. The total depth of the infiltration borehole will be 70 meters with a design as 18 inch
diameter J55 grade steel casing and torch slotted screens. The drilled diameter of the borehole
should ideally be 24 inches. During construction, it is envisaged that the land take could amount to
16 m2 with a completion foot print of 1 m2.
99. The total depth of the induced infiltration borehole will be 25 meters with a design as 18 inch
diameter J55 grade steel casing and torch slotted screens. The drilled diameter of the borehole
should ideally be 24 inches. During construction, it is envisaged that the land take could amount to
16 m2 with a completion foot print of 1 m2.
100. The induced infiltration well would be pumped with the intention of drawing water from the Kabul
River via river gravels to the pumped well. This flow through river gravels should treat the pumped
water sufficiently for MAR purposes. If this is proven to be the case, the water from the pumped
induced infiltration borehole would be discharged to the deeper injection well located further away
from the river as shown in Figure 7 below.
101. Once every 2 years the boreholes should be plumbed to ensure backfilling has not taken place. If
backfilling has occurred, the boreholes should be cleaned via bailer attached to a percussion
drilling rig.
102. One piezometer will also be constructed at this site with completion using 2 inch diameter
schedule 80 PVC screens and casing. The footprint of the surface expression of the piezometer
would be 30 cm x 30 cm with the piezometer completed flush with ground level.
103. Finally, Photo 7 below presents an example of torch slotted screens used in low budget MAR
boreholes in Arabia. For the pilot KMARP boreholes there will be a requirement for a 10% open
area in the screened section of the boreholes.
26
Photo 6: Proposed injection well location at MAR Site 6, as designated by the arrow
Photo 7: Example of torch slotted screens used in low budget MAR boreholes in Arabia
27
5. Description of the Environment
5.1. Physical Resources of Project Area
5.1.1. Climate
104. The Kabul Province is located 1789-1791m above sea level in a narrow valley, wedged between
the Hindu Kush Mountains along the Kabul River. The Project area experiences a semi-arid
climate with precipitation concentrated in the winter and spring months. As described by the Kabul
Municipality, temperatures are relatively cool mainly due to high elevation of the city. Summer has
very low humidity, providing relief from the heat. Autumn features warm afternoons and sharply
cooler evenings. Winters are cold, with a January daily average of −2.3°C. Spring is the wettest time of the year, though temperatures are generally amiable. Sunny conditions dominate year-
round. The annual mean temperature is 12.1°C.
105. The mean annual rainfall fluctuates between 196.7mm and 430.7mm. Precipitation falls mostly in
winter-spring and is about 100-300mm in the many areas. Air humidity varies from 30% in the
summer to 80% in winter. During the period of February-May (3-6 times a month) strong winds
(speed of 15 km/sec and more) occur which cause dust blowing reducing visibility considerably. A
dry and dusty wind (the "Afghani") lasts around 30 hours normally in the summer and
accompanied by lowering of air temperature.
106. December to February is considered winter with cloudy weather with night temperature of -10°С. During this period, precipitation falls following drizzles (3 to 7 days in a month), and there is also
fog and snowfall in some areas.
107. Spring (March-April) is warm with a prevalence of unstable weather. Till the end of March frosts
are still possible. The greatest rainfall amount in a year (6 to 8 days in a month) falls mainly in the
form of downpours in spring. Summer (May-Sept) is hot with clear weather. The hottest months
are June, July, August (temperature of air in the afternoon is 28-35°С), at night 22-25°С. From the middle of August the heat starts gradually to fall down (temperature at night 15-18°С). Precipitation falls very seldom in the summer, and in July and August normally does not occur at all.
5.1.2. Topography
108. Kabul is part of a system of high level basins, the elevation of which varies from 1,500 to 3,600
meters, extends beyond the administrative borders of the present-day province and includes large
parts of the neighboring provinces Parvan and Kapisa on its northern flank. Drained by the Panjser
in the north and the Kabul River in the south, the Kabul-Panjser basin epitomizes a tectonic
depression zone framed by high mountains of old rugged crystalline and metamorphic Paleozoic
rocks6. The mountain ranges surrounding the basin are the southern slopes of the Hindu Kush,
reaching an average altitude of 5,000 meters in the north and east, and the Pagman chain with an
altitude of about 4,000 meters rising to the summit of the Taḵt-e Turkoman (4,696m) in the west
and southwest. The average elevation of the basin ground filled with probable Neogene and
Pleistocene sediments is about 1,800 meters. Having been deeply cut into the terrestrial
6 https://www.adb.org/sites/default/files/project-document/184540/42094-032-EDD-02.pdf
28
sediments interspersed with layers of clay, marl, and sandstone, the river system carved out deep
and narrow gorges.
109. The basin of Kabul is dominated by the Kabul River and a mountain range running in a northeast-
southwestern direction. Coming from the southwest, the river breaks through the mountain chain
and forms an impressive valley, which narrows further down in the ravine of Deh Mazang between
the Koh-e Asmaʾi (2,110m) in the north and the Koh-e-Ser Darvaza (2,222m) in the south.
110. On its western side the Afghan capital is flanked by the densely populated valley of Cardeh. The
valley is enclosed by the hills running from Absahr to the Sorḵ Kotal in the north; by the Koh-e
Asmaʾi and Koh-e Ser Darvaza in the east; by the Korug Mountain in the south, and in the west by
the Koh-e Cungur and a spur that slopes down from the ridge east of the Sorḵ Kotal.
111. The proposed four Pilot KMAR sites are within these undulating regions.
5.1.3. Geological Characteristics and Soils
112. The geology of the Kabul basin is discussed at length in Volume 2 (Knowledge Base) of
Technical Report 1.
113. The Kabul basin as a whole is a high altitude elongate plateau extending from 34o N in the south
to about 35o 40'N at its northern apex. It is bound on three sides by major active faults whose
movements have resulted in a series of tensional basins, two of which underlie Kabul City and are
contained within the project intervention area. On the west lies the Paghman/Darulman sub-basin,
and on the east lies the Central Kabul sub-basin, separated by a NW trending ridge of ancient
crystalline rocks. The sub-basins represent downthrown blocks (grabens) that were subsequently
filled in with sediment.
114. All of the sub-basins, to some degree, can be described as closed basins, or alternatively
classified as undrained basins. Undrained means that under natural conditions inflows exceed
outflows and groundwater accumulates until levels reach near the surface where water is
discharged through evapotranspiration or through local discharge zones. Both these conditions
have been observed in the past and can be considered as a baseline for groundwater
management purposes. Historical records pre-dating the late 1990's drought show that water
levels of 2-3 meters below the ground surface were common occurrences. The swamps and
marshes that once existed north and west of the airport, exhibiting local discharge, is further
evidence of an undrained basin. In short, these sub-basins can be thought of as independent tanks
with small leaky faucets, with very little linking between them. If this is the case, it has important
implications for groundwater management, particularly strategies pertaining to safe yields and
rates of extraction. The same mitigation interventions in one sub-basin may not be met with equal
success in the other.
115. In general, the soils are formed under arid and semi-arid climatic conditions. Textural classes are
mostly clay loam to sandy loam. Soil pH and calcium carbonate contents are high.
5.1.4. Water Resources
116. The KMARP project area is located in the southern part of Kabul Basin, where the faults have
produced tensional forces that led to the fragmentation of the basin into a series of downthrown
blocks. The number of sub-basins and their names differ among various workers, but the most
29
common convention is to delineate them by hydrological catchments. All the sub-basin boundaries
are characterized by low mountain ranges that play an important role in directing groundwater flow.
117. The major rivers in the area are the Paghman and its tributaries Qarga and Gelkana joining the
Lower Kabul from the west; the Upper Kabul, the Logar, and the Chakari Rivers joining the Lower
Kabul from the south. These rivers maintain an intimate connection with the uppermost
groundwater system and are responsible for a substantial amount of recharge. The rivers carry
significant flow for only about seven months of the year, from November to June, with the Logar
River for a slightly longer period. Because the onset of rain normally approaches from the south,
the Logar, with an elongated southward extending catchment, begins flowing earlier in October.
118. An important thing to note is that in the Project’s assessment of the groundwater system7, the
catchment of the lower Logar River is not considered a separate sub-basin, but lies within the
Central Kabul sub-basin. The southern parts of the Shomali and Deh Sabz sub-basins are also
interpreted to be separate geohydrologic units. The sub-basins for the most part are internally
demarcated by older crystalline rocks, mainly Proterozoic gneisses estimated to be 2.5 billion
years old.
119. Historically, it has been thought that in Kabul there are four aquifers paralleling the major rivers
(the Logar, Upper Kabul, Paghman, and Lower Kabul aquifers), primarily based on the geo-electric
surveys of earlier reports. This simplified concept is challenged by the Project Team in Technical
Report 1. However, for this EDD report this concept will suffice. The location of the aquifers are
shown in Figure 1.
5.1.5. Seismology
120. The project sites are in Hercynian folded region and subjected to Alpine movements8 lies in
seismically active zone but does not lie directly on any fault line of Hindu Kush range.
5.1.6. Air Quality
121. The physical setting of Kabul is in valley at high altitude. Physically it is an environment where
pollutants can't disperse quickly. Kabul's lack of infrastructure, sanitation problems, and recent
population boom has resulted in dangerously high airborne contaminant levels. Levels of individual
hazardous compounds, such as carbon monoxide, lead, nitrogen oxide, and ozone are all
significantly above EPA primary and secondary standards, and levels of particulate matter are
more than 100 percent higher than World Health Organization recommended levels9. The NEPA of
Afghanistan has advised the Kabul residents to wear masks to protect them from particulate
matter.
5.1.7. Noise
122. No measurements of noise level were found for the KMARP Pilot sites. Levels are expected to be
typical of comparable Central Asian settings. Sites 3 and 4. Site 6 is in the city center.
7 See Technical Report 1
8 Processes of intensive folding, orogeny, and granitoid intrusive magmatism,manifested in Paleozoic geosynclines and responsible for fol
ded mountain systems, or Hercynides 9 https://www.adb.org/sites/default/files/project-document/151955/42094-032-EDD-01.pdf
30
5.1.8. Archaeological, Historical and Cultural Treasures
123. No historical or cultural sites are encountered at Site 3, Site 4 and Site 6.
5.2. Ecological Resources in Project Area
5.2.1. Fisheries
124. In Afghanistan’s mountain rivers, available fish species are Brown trout and Milk fish; these are
basically carp from the family Cyprinidae. However, fishing in the Kabul River has not been
detected within the urban limit.
125. It is observed that fish do not contribute much to the economy of the country and therefore not
much attention is paid to them as aquatic resources. No fish species in Afghanistan are classified
as endangered. No aquaculture or fisheries exist within the KMARP Project area.
5.2.2. Wildlife
126. Afghanistan’s Wildlife Conservation Society (WCS) has combined efforts with NEPA to establish
a list of 149 protected species found in Afghanistan. Although there has been extensive research
into types of wildlife and endangered species in Afghanistan, very little data exists specifically for
Kabul.
127. Within the city, the Koli Hashmat Khan reserve serves as a wetland stopping-point for birds that
migrate seasonally between South Asia and Central Asia. 107 species of bird have been recorded
by MAIL, though their numbers are reducing due to poor waste management, water pollution, and
over extraction of phragmite reeds for roof thatch. The United Nations has also declared the area
a protected conservation site and bird sanctuary and is now managed by MAIL and NEPA.
128. At other locations, it is estimated that within the Project area only a limited number of animal
species are present, due to the mainly urban nature of the site surrounds. No surveys have been
undertaken but it is expected that the species present at the Project sites are snakes, lizards and
frogs.
5.2.3. Flora
129. The North of Afghanistan forms part of the center of plant diversity for the mountains of middle
Asia. The northern high lands between 1000‐1500 m have steppe grass lands and low shrubs.
Small areas of Coniferous forest grow at high altitude and the woody plants in the mountainous
areas comprise sparse wild pistachio (Pistachia), almond (Amygdalis) and juniper wood land with
tree heights of 4‐10 meters. Above 3500m only low Alpine flora exists.
130. The available flora of the proposed KMARP Pilot sites and its area of influence is predominantly
scattered home garden vegetation (Site 6); fruits saplings like almond, apricot, plum, quince,
grapes, apples, peach, pear (Site 4); and no vegetation on Site 3.
131. No endangered flora exists in these sites.
5.2.4. Protected Areas
132. The Protected Areas in the country are listed in Table 2.
31
Table 2: List of significant protected areas in Afghanistan
Area Habitat Type
Ab-i-Istada Lake
Bande Amir Lakes
Darqad River floodplain
DashteNawar Desert plateau
Hamun-i-Puzak Lake
HariRud Valley
Imam Sahib River floodplain
Jalalabad Valley
Khost Foothills
Koli Hashmat Khan Wetland
North-western steppe Plains
Pamir-i-Buzurg Mountains
Pech and Waygal Valleys
Registan desert Desert
SafedKoh Mountains
SalangKotal Mountains
Small Pamir Mountains, valleys and rivers
133. Pilot MAR Sites 3, 4 and 6 have no protected, sensitive or designated sites within their area of
influence.
5.3. Human and Economic Development
5.3.1. Demography
134. The population of Kabul has fluctuated since the early 1980s to the present period. It was
believed to be around 500,000 in 2001 but then many Afghan expatriates began returning from
Pakistan and Iran where they had taken refuge from the decades of wars. Today, in 2018, the CIA
World Fact book estimates that Kabul's population is a little over 4 million10. It should be noted that
many Afghans from other provinces stay in Kabul on temporary bases, to spend time with relatives
due to fighting or for other reasons.
135. The population of the city reflects the general multi-ethnic and multi-lingual characteristics of
Afghanistan. There is no official government report on the precise ethnic make-up but according to
a map of National Geographic; the population of the city was estimated at 45% Tajiks, 25%
Hazaras, 25% Pashtuns, 2% Uzbeks, 1% Baloch, 1% Turkmen, and 1% Hindu11. Dari (Afghan
Persian) and Pashto are the most widely used languages in the city, although Dari serves as the
10
https://www.cia.gov/library/publications/the-world-factbook/geos/af.html 11
National Geographic Magazine, 2003
32
lingua franca. Nearly all the people of Kabul are Muslims, which includes the majority Sunnis and
minority Shias. A small number of Sikhs, Hindus and Christians are also found in the city.
5.3.2. Disease Profile
136. Within Kabul City most neighborhoods lack sanitation and residents frequently face diseases
caused by a lack of cleanliness. Kabul residents now fear polluted groundwater in the sprawling
city is posing a grave threat to their health. Children are the most common victims of water-borne
diseases, which peak in summer. NEPA says that without a remedy to the crisis, all of Kabul’s groundwater will soon become unfit for human consumption. NEPA says septic tanks have
contaminated groundwater 15 meters deep in many Kabul neighbourhoods. The agency says
currently more than 2,000 septic tanks are being dug around the city every year12.
137. The Project has undertaken disease mapping through a social survey around the city with various
health clinics and centers. This work is now completed and is reported on in Volume 2 of Technical
Report 3 (September 2018).
5.3.3. Public Consultation
138. Informal consultation has been undertaken with local people on the project pilot implementation
program. The resettlement due diligence report has found that no persons are affected negatively
by KMARP with a Category C classification at all locations.
139. In general, local people appear to support the project and are in favor of immediate
implementation for enhancing groundwater resources for domestic needs (Appendix 2).
12
Polluted Groundwater Threatens Health in Kabul, Gandhara, Radio Free Afghanistan, 02 August 2017
33
6. Pros and Cons of Proposed Interventions
140. Prior to the Screening of the Environmental Impacts at each site, we present the pros and cons of
the proposed interventions as shown in Table 3.
Table 3: Pros and Cons of Proposed Interventions
Scenario Pros Cons
Do nothing / no
intervention /
existing
situation
There are no benefits for the
existing situation to continue.
There is a negative balance between
recharge and discharge due to low
annual precipitation in the Kabul basin.
Therefore, all surface waters have now
largely disappeared from wetland areas
and rivers are largely made up of
effluent outside of the winter months.
Population growth and continued
groundwater extraction is causing a
rapid reduction in groundwater levels
within the deep aquifer in many parts of
the city.
Within the shallow aquifer,
contamination from soakaways is
causing health issues (see Volume 2 of
Technical Report 3).
There is a likelihood that subsidence is
occurring due to aquifer dewatering
(work ongoing).
Implement pilot
sites 3, 4 and 6
There will be an increase in
groundwater resources with proper
water management.
The technology will demonstrate
the feasibility of MAR for wider
implementation across the city
Help in sustaining permanent or
ephemeral groundwater outflows in
springs and base flow along Kabul
River. This often permits availability
of water all the year round, which is
important when surface water
contribution ceases.
34
Scenario Pros Cons
Help in sustaining of wetlands,
lakes, swamps, bogs and
meadows.
Improving shallow water tables
accessible to perennial plants along
valley floors around lakes, or
elsewhere.
In areas of future MAR, where
shallow groundwater is polluted,
MAR would improve the situation
via dilute and disperse of the
existing poor quality water.
35
7. Screening Environmental Impacts and Mitigation Measures
7.1. Overview
141. This section presents information of the study team's assessment of the issues likely to arise as a
result of implementing KMARP’s pilot MAR sites.
142. The pilot MAR sites are classified as Category C (according to ADB Environmental Guidelines) as
they are likely to have minimal or no adverse environmental impacts. .
7.2. Soils and Geology
7.2.1. Construction period
143. Possible impacts include the minimum loss of top soil, insignificant damage to urban, existing
roads during transportation of construction material and equipment. The construction process will
not remove vegetation, not making upper soil layer susceptible to erosion and runoff. However, the
areas that will be subject to disturbance will be very small, and the potential impacts associated
with the establishment of Injection well; above surface receiving well; Spreading basins, etc. are
not considered significant, provided basic environmental management measures are implemented.
144. The roads will be used for carrying construction materials and equipment, if damaged, they shall
be repaired to their original condition by the contractor after completion of work.
145. Possible impacts also include oil leakage or hazardous material spills from vehicles and/or
equipment. The areas that will be subjected to disturbance will be very small and potential impacts
are considered insignificant. However, implementation of appropriate mitigation measures will
prevent or minimize the impacts.
7.2.2. Operational period
146. During operation, the potential for environmental impacts is insignificant. No severe adverse
impacts identified due to sedimentation, maintenance and use of access roads.
7.2.3. Recommendations
147. In order to minimize the potential of soil excavation/erosion, following mitigation measures are
recommended:
a. Areas disturbed during construction (e.g. excavation for foundation, materials etc.) should be
appropriately rehabilitated.
b. Proper maintenance of vehicles and equipment is recommended to avoid any leakage. Kits to
clean up any spillage should be made available at all construction sites and the contaminated
material should be disposed appropriately.
36
c. A detailed EMP should be compiled by the contractor, outlining site specific measures to be
implemented to minimize impacts on soil and topography.
7.3. Surface Water
7.3.1. Water quality testing on source waters
148. KMARP staff have sampled potential source waters for Managed Aquifer Recharge (MAR) for
hydrochemical analyses. The locations of both the sampled source waters and the associated
MAR sites are shown in Figure 8.
149. The water samples were analyzed at the DACAAR laboratory in Kabul and the results are
presented in Appendix 3 together with a statistical analysis of results and applicability to EU and
USEPA standards.
150. The results were compared with relevant European Union and United States standards as
surface water acceptable for forage crops as standards shown in Table 4, Table 5 and Table 6.
The sampled water results within the limits of laboratory technology in Kabul meet the USEPA and
EU requirements for forage crops which is also the standard applied to MAR criteria.
151. It should be noted that with respect to E.coli (Faecal Coliform) and the EU standards. One
sample had a count of >250. The class D standard which is still acceptable relates to water with
counts <10,000. The sample was in the range 250 to 1000 but it was too difficult to count the
colonies. Class C relates to counts < 1000.
152. Appendix 3 also includes the derogation clause from EU rules. This relates to high altitude which
is defined as > 1500 metres. This permits lower standards at high altitude. Kabul altitude varies
from 1700m to 2000m. The derogation clause mentions temperature. As the winter temperatures
in Kabul reach – 20oC, the derogation clause is relevant but perhaps not needed as the source
waters meet the required standards.
153. All the suggested MAR source waters naturally infiltrate into the ground along the river
courses. What is being suggested as MAR is merely enhancing that already occurring in nature in
western Kabul.
154. During MAR testing by the project, water quality will be monitored at the point of recharge and at
a point not far away (nearby borehole) to appreciate the difference between the two.
155. Verification of the effectiveness of MAR will include the use of a tracer (Suggest Lycopodium
spores if approved by the Afghan authorities as dye and radioactive tracers are beyond the testing
ability of local laboratories) in the water to see if injected water is also being picked up at nearby
sample testing.
38
Table 5: EU Classes of food crops
US EPA Recommended Limits for Constituents in Reclaimed Water for Irrigation
Table 6: Relevant USEPA Standard
")
")
")
")
")
")
Shakardara
Paghman
Dih Sabz
Kabul
Bagrami
Khaki JabbarMusayi
Chahar Asyab
100
101
102
103
104
105
106
142
143
144145
152
153
154
155
156
157
158
159
161
162
163
164
165181
192 193
194
195
196
57
46
28 59
50
55
51
2949
525444
53
56
43
58 48
47
27
26
site 4
site 6
site 5
site 2
site 3
site 1
504800 509800 514800 519800 524800 529800 534800
38
049
00
38
099
00
38
149
00
38
199
00
38
249
00
38
299
00
MAR Sites with Canals and Water Sample Points
Scale
1:140,0000 4.5 9 13.5 182.25Km Map Source: Landell-Mills, DACAAR
Projection: WGS1984Date: 4th Nov 2018
Kabul
¬ Ministry of Energy and Water
Hydrogeology Department
D
Kabul
Managed Aquifer Recharge Project
Legend
") MAR site
Water sample for site 3
Water sample for site 4
Water sample for site 5
Water sample for site 6
Canal
Canal feeding MAR site
Underground canal
River
Lake
Project Intervention Area
Musayi District Name
Water sample number143
FIGURE 8
40
7.3.2. Construction period
156. Dust generation can also be a problem during dry periods, especially as much of the project sites
are in an urban arid zone. However, the issue of dust is considered to be minimal as it can be
minimized by proper mitigation measures such as spraying of water on any access roads or on
site if required. Waste water will be generated during the construction phase near the camping
facilities provided to workers (for Site 3). No discharge of untreated sewage will be permitted,
septic tanks will be constructed at Site 3 work camp, for other sites, workers will travel from their
respective home.
7.3.3. Operational period
157. During operation phase the water quality will not be affected by dust or soil erosion; except
surface run-off. However, these impacts will be temporary and insignificant.
7.3.4. Recommendations
158. The following mitigation measures are recommended:
a. Provide sanitary latrines at work site and camps to avoid any pollution of ground water and
surface water from sewage and maintain hygienic environment.
b. A detailed EMP should be compiled by the contractor, outlining site specific measures to be
implemented to minimize impacts on surface water.
7.4. Solid Waste
7.4.1. Construction period
159. Two types of waste will be generated during the construction phase including debris and
domestic refuse from construction camps (Site 3). Earth work can produce amounts of soil and
unmanaged domestic waste and litter can create unhygienic conditions for workers and
communities in the vicinity.
160. However, it is believed that by following the mitigation measures there will be no adverse impacts.
7.4.2. Operational period
161. No solid waste should be generated during the operation, except for regular maintenance and
repair work of MAR facilities.
7.4.3. Recommendations:
162. To minimize the potential of unhygienic and un-scenic sights in and around construction area, the
following mitigation measures are recommended:
Any spoil generated by the construction activities should be disposed of at an approved location. For
the temporary storage of excavated earth should be done in a manner to avoid any inconvenience
to the daily activities of the workers and local people.
41
Littering should be prevented by providing adequate number of containers which shall be emptied
on regular basis.
After completion of construction, the site shall be properly cleaned of any construction wastes, litter
etc., and properly rehabilitated.
7.5. Other Impacts
7.5.1. Aquifer storage recovery (ASR)
163. This is a powerful technology for water resources management and environmental protection,
enabling storage deep underground when water is available, for recovery when needed to meet
urban, agricultural, ecosystem, industrial, recreational, emergency and other water uses. Water is
stored in suitable aquifers, or water-bearing formations, forming large subsurface reservoirs that
are safe from losses due to evaporation, transpiration, seepage or contamination.
164. Other recognized benefits include:
Large quantities of water can be stored underground, reducing the need to construct large and
expensive surface reservoirs.
ASR systems are considered to be more environmentally friendly than surface reservoirs.
Aquifer storage offers more protection from tampering than surface storage.
165. The practice may stabilize or reverse declining water levels in an aquifer that has experienced
long-term declines due to heavy pumping (such as in Kabul City).
7.5.2. Contaminants into Aquifers used for Potable Supply
166. The basic environmental concerns related to artificial recharge projects are associated with the
potential for the entry of contaminants into aquifers used for potable supply. However, this issue
will be checked once the pilot projects are operational and water quality will be analyzed
accordingly.
167. Reed beds are being considered for treatment of source waters for Managed Aquifer Recharge at
Koli Hashmat Khan. Reed beds are a popular and sustainable choice for wastewater and sludge
management. Reed bed systems are an effective, sustainable and low maintenance method of
sewage treatment. While aesthetically pleasing to the eye, they require no electricity and, once
matured, provides an ecological habitat for a wide range of species. With the help of common reed
plants, reed beds are used as a method of removing pollutants from greywater.
168. The Common Reeds (Phragmites Australis) transfer oxygen directly from their root systems and
through their stems. The root systems are met by a multitude of micro-organisms with areas of
varying oxygen levels. As a result, the wastewater stored in reed beds is treated and recycled. The
reed bed filters the water just as the conventional biological filter bed systems of sewage treatment
plants.
169. It is worth noting that in the event that the use of reed beds is refused, the project proposes the
use of a reverse osmosis plant to treat the sourced MAR water derived from rivers via canals to
42
the MAR site. This is an expensive alternative and as such the “Pros”13 as listed below for reed
beds must be emphasized:
minimizes solids
reduces water content
minimal day-to-day operation
no requirement of highly trained operators
no mechanical and electrical equipment are needed
pumping not necessary as the system works on gravity
provides sufficient storage time to stabilize biosolids prior to disposal
blowers to aerate are not required as the aeration is facilitated by reeds
170. Unconsolidated sand and gravel aquifers in Kabul at shallow depth usually have intergranular
porosity and contain water primarily under unconfined or water-table conditions. The hydraulic
conductivity of the aquifers is variable, depending on the sorting of aquifer materials and the
amount of silt and clay present, but generally it is high near the Logar and Kabul rivers The
unconsolidated sand and gravel aquifers are susceptible to contamination because of their
generally high hydraulic conductivity and the almost ubiquitous use of soak aways to dispose of
liquid waste (both domestic and petroleum products).
171. Such polluted groundwater is cleansed as it flows through an aquifer via the process14 of 1) Dilute
and disperse and also 2) via natural attenuation.
172. Therefore, the idea of source water being injected into the aquifer and contaminants diluting and
dispersing is expected at the pilot projects.
7.6. Site-Specific Screening
7.6.1. Site 3: Doghabad
173. This is a quarry site adjacent to Kabul River. Table 7 presents possible subjective environmental
impacts during pre-construction, construction, operation and maintenance phases. Likewise, Table
8 focuses on impacts during construction. The Screening Checklist can be found in Appendix 1.
174. The analysis of results indicates that, there will be minimal impacts during the construction period
on land use, waste generation, and localized noise and dust generation. Any temporary impacts
will be mitigated as required.
175. This site will have a positive impact by increasing underground aquifer storage. Soil moisture will
lead to increased vegetation growth. There is no need for tree cutting by the project, no families
will suffer and none lose their agriculture land, houses and structures. Additionally there will not be
any adverse impacts on public assets/structures such as mosques, clinic, schools, irrigation
sources and natural resources.
13
Reed Bed, A Green Waste Treatment Option 14
Natural Attenuation of Aromatic Hydrocarbons in a Shallow Sand Aquifer
43
176. Therefore, the work at Site 3 is classified as Category C as it is likely to have minimal or no
adverse environmental impacts.
Table 7: Environmental and Social Impacts Screening Matrix at Site 315
Environmental Components
Physical Biological Social and Socioeconomic
Aspects
Physical Activities
Lan
d u
se
So
il E
rosio
n
Su
rfac
e /G
rou
nd
Wate
r
Air
Qu
ality
an
d D
ust
Waste
gen
era
tio
n
Flo
ra
Fau
na
Lan
d a
cq
uis
itio
n
Ag
ricu
ltu
re / F
arm
ing
Healt
h a
nd
Safe
ty
Pre
ss
ure
on
Pu
blic
Uti
liti
es
Pu
blic In
frastr
uctu
res
No
ise a
nd
Vib
rati
on
s
Cu
ltu
ral
Pro
pe
rtie
s
Arc
ha
eo
log
ical
He
rita
ge
Gen
der
Issu
es
Pre-Construction Phase
0 N +2 N N +1 N N +2 N -1 N N N N 0
Construction Phase
-1 N -1 0 -1 0 N N 0 N -1 N 0 N N 0
Operation and Maintenance Phase
N N N N N +2 N N +2 0 N N N N N 0
Key: -2=High Negative Impact; -1=Low Negative Impact; 0=insignificant/Negligible impact; +2=High
Positive Impact; +1=Low Positive Impact; N=No Impact
Table 8: Impacts during Construction at Site 316
No Consequences of project activities
Potential impacts
Suitable mitigation
Remark
1 Trees cutting No - In this site no need for tree cutting
2 Agriculture Land No - This site is located in a private land, not for any agricultural use.
3 Borrow pit No - No need for borrow pit
15
Source: Field Survey, 16 April 2018 16
Source: Analysis of Field Survey, 16 April 2018
44
No Consequences of project activities
Potential impacts
Suitable mitigation
Remark
4 Land acquisitions No - No need for Land acquisitions. They will contract with land owner as per monthly payment.
5 Erosion No - Project construction work will not cause any soil erosion and sliding
6 Spills/leaks
Producing of hazardous materials, oil spills and work side accidents
Yes
All fuel and chemical storage (if any) shall be sited on an impervious base within a bund and secured by fencing. The storage area shall be located away from any watercourse or wetlands.
7 Noise
Yes Yes
Noise will be generated during construction, but no settlements are located nearby. Additionally, work will only be carried out during normal working hours
8 Resettlement
No - No need for resettlement
9 Air quality
Yes Yes For dust control on the construction activities will require watering for dust control
10 Water quality
No - Kabul River is adjacent to this site but during construction time construction best practice will be followed to prevent any water pollution
11 Common properties and infrastructures No -
In this site no common properties and infrastructures available
12
Construction activities (waste generation)
Minor Yes
Improper disposal of construction wastes may lead to soil contamination in surrounding environment. Waste will be collected and dumped at designated place determined by the Municipality and NEPA.
13 Contaminated materials No -
No contaminated materials located on-site (e.g., asbestos, lead-based paint, underground storage tanks, chemical storage containers) that will require removal prior to construction
14 Threatened/ endangered species
No -
No threatened/endangered species or species of concern and their critical habitat are within the project area , hence, no special provisions or measures required to avoid, minimize, or mitigate direct and indirect species impacts
45
No Consequences of project activities
Potential impacts
Suitable mitigation
Remark
15 Buildings on the site
No - No building on site is located within 0.5 km radius of a local, state, or district
16 Archaeological artifacts
No - No archaeological artifacts, cultural resources, or human remains on or located within a 0.5 km radius of the site
17 Tribal lands, Traditional Cultural Properties
No - No tribal lands, traditional cultural properties, or other resources (e.g., traditional fishing areas) are located on or adjacent to the subject site.
46
7.6.2. Site 4: Badam Bagh
177. Table 9 presents possible subjective environmental impacts during pre-construction, construction
operation and maintenance phases. Likewise, Table 10 focuses on impacts during construction.
The Screening Checklist can be found in Appendix 1.
178. The KMARP Pilot located in this Badam Bagh research farm is expected to have a positive
impact to the farm and associated hinterland in expanding water storage in the underground
aquifer, accelerating water transmissibility, and retaining soil moisture, increasing cropping
intensity.
179. The analysis of results indicates that, there will be minimal impacts during the construction period
on land use, waste generation, and localized noise and dust generation. Any temporary impacts
will be mitigated as required.
180. Furthermore, this site will have more positive impacts by increasing underground water level and
also available soil moisture will increase vegetation growth and survival rate. . There is no need for
tree cutting by the project, no families will suffer and none lose their agriculture land, houses and
structures. Additionally there will not be any adverse impacts on public assets/structures such as
mosques, clinic, schools, irrigation sources and natural resources.
181. Therefore, the work at Site 4 is classified as Category C as it is likely to have minimal or no
adverse environmental impacts.
47
Table 9: Environmental and Social Impacts Screening Matrix at Site 417
Environmental Components
Physical Biological Social and Socioeconomic Aspects
Physical Activities
Lan
d u
se
So
il E
rosio
n
Su
rfac
e /G
rou
nd
Wate
r q
uality
Air
Qu
ality
an
d D
ust
Waste
gen
era
tio
n
Flo
ra
Fau
na
Lan
d a
cq
uis
itio
n
Ag
ricu
ltu
re / F
arm
ing
Healt
h a
nd
Safe
ty
Pre
ssu
re o
n P
ub
lic U
tiliti
es
Pu
blic In
frastr
uctu
res
No
ise a
nd
Vib
rati
on
s
Cu
ltu
ral
Pro
pe
rtie
s
Arc
ha
eo
log
ical
He
rita
ge
Gen
der
Issu
es
Pre-Construction Phase
0 N +2 N N +1 N N +2 N -1 N N N N 0
Construction Phase
-1 N -1 0 -1 0 N N 0 N -1 N 0 N N 0
Operation and Maintenance Phase
N N N N N +2 N N +2 0 N N N N N 0
Key: -2=High Negative Impact; -1=Low Negative Impact; 0=insignificant/Negligible impact +2=High
Positive Impact; +1=Low Positive Impact; N=No Impact
Table 10: Impacts during Construction at Site 418
No Consequences of project activities
Potential impacts
Suitable mitigation
Remark
1 Trees cutting No - In this site no need for tree cutting
2 Agriculture Land Yes – positive -
This site is located on government land. This is an agricultural farm, the project will enhance agricultural activities by raising local water levels.
17
Source: Field Survey, 19 April 2018 18
Source: Analysis of Field Survey, 19 April 2018
48
No Consequences of project activities
Potential impacts
Suitable mitigation
Remark
3 Borrow pit No - No need for borrow pit
4 Land acquisitions No - No need for Land acquisitions.
5 Erosion No - Project construction work will not adversely impact by soil erosion and sliding
6 Spills/leaks
Yes (Producing of hazardous materials, oil spills and work side accidents)
Yes
All fuel and chemical storage (if any) shall be sited on an impervious base within a bund and secured by fencing. No watercourse or wetlands are located around this site.
7 Noise
Yes Yes
Temporary construction noise will not affect any people. The site is out from residential area. Additionally, work will only be carried out during normal working hours
8 Resettlement
No - No need for resettlement
9 Air quality
Yes Yes For dust control on the construction activities sufficient watering will be performed.
10 Water quality
No - Adjacent to this site, no river, irrigation canal, stream are located. Therefore, no negative impact on water quality
11 Common properties and infrastructures No - Not applicable for this site.
12 Construction activities (waste generation) Yes Yes
Improper disposal of construction wastes may lead to soil contamination in surrounding environment. Waste will be collected and dumped at designated place determined by the Municipality and NEPA.
13 Contaminated materials
No -
No contaminated materials located on-site (e.g., asbestos, lead-based paint, underground storage tanks, chemical storage containers) that will require removal prior to construction.
14 Threatened/endangered species
No -
No threatened/endangered species or species of concern and their critical habitat are within the project area, hence, no special provisions or measures required to avoid,
49
No Consequences of project activities
Potential impacts
Suitable mitigation
Remark
minimize, or mitigate direct and indirect species impacts.
15 Buildings on the site No - No building on site is located within 0.5 km radius of a local, state, or district.
16 Archaeological artifacts No - No archaeological artifacts, cultural resources, or human remains on or located within a 0.5 km radius of the site
17 Tribal lands, Traditional Cultural Properties
No -
No tribal lands, traditional cultural properties, or other resources (e.g., traditional fishing areas) are located on or adjacent to the subject site.
50
7.6.3. Site 6: Makroyan e-4
182. Table 11 presents possible subjective environmental impacts during pre-construction,
construction, operation and maintenance phases. Likewise, Table 12 focuses on impacts during
construction. The Screening Checklist can be found in Appendix 1.
183. The analysis of results indicates that, there will be minimal impacts during the construction period
on land use, waste generation, and localized noise and dust generation. Any temporary impacts
will be mitigated as required. The seasonal vegetable garden, nursery bed and associated
vegetation, will require removal and replantation at an adjacent area within this territory, but the
area effected will be small.
184. No destruction of existing water canals and structures will be required. The generation and
handling of construction and other waste, and health and safety of construction workers will be
carefully addressed following the EMP. Mitigation measures will be taken to minimize the
temporary impacts following environmental best practice.
185. Therefore, the work at Site 6 is classified as Category C as it is likely to have minimal or no
adverse environmental impacts.