Technical Assistance Consultant’s Report
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.
Project Number: 41614 March 2012
India: Capacity Development of the Assam Power Sector Utilities
For Assam State Electricity Board (ASEB)
Prepared by
Mercados – Energy Markets International
Madrid, Spain
in association with North Delhi Power Limited (NDPL)
New Delhi, India
AF-Mercados EMI 1
TA – 7378 – IND. CAPACITY DEVELOPMENT OF THE ASSAM POWER SECTOR UTILITIES FINAL REPORT PRESENTATION GUWAHATI 1 MARCH 2012
AF-Mercados EMI 2
INDEX
Introduction
Objectives for the Project
Project Management & Progress
Generation Process Management
Transmission Process Management
Distribution Process Management
Jorhat Pilot Project
Accounting - Financial Aspects
Human Resources Management
IT Management
Final Conclusions
AF-Mercados EMI 3
Introduction
Assam State Power Utilities
At state level, the Government of Assam (GOA) introduced the power sector reform policy, Power Policy Statement 2003 and restructured the Assam State Electricity Board (ASEB) into three entities-
Assam Power Generation Corporation Limited (APGCL);
Assam Electricity Grid Corporation Limited (AEGCL);
Assam Power Distribution Company Limited (APDCL)
Though ASEB technically is not the legal holding company, it however remains in many ways loosely a holding company mainly due to the constraints in clear separation between human resources and financial management between the entities
Future power sustenance and energy security still remain a big challenge for them.
Though the overall financial losses and operational performance is moving towards acceptable levels
A big concern: commercial losses, creation of adequate capacity, improvement in rural electrification and installation of
renewable energy based distributed generation
Several improvements necessary:
Organisational structure needs to be changed to respond to the dynamic market
Improved streamlined Business Processes to respond to changing environment
Better system to store, manage and retrieval including strong IT-based structure
Better Human Resource Management including recruitment process, performance management system
Adequate training and capacity building of the staffs to respond to changing environment
Well drafted Communication and Change Management Plan
AF-Mercados EMI 4
Objectives of the project Provide support towards unbundling of the companies, where the companies must perform as independent sustainable entities
The relationships between the companies are to be performed based on the market rules by means of
bilateral or trilateral transparent agreements.
For this purpose, this project will provide the recommendations, assistance and capacity building for the companies’ managers to ensure financial, managerial, and operational autonomy for utilities’
sustainability.
Key elements of scope of the project
Provide support for:
Improved structures, streamlined business processes (e.g. finance, commercial and regulatory, accounting,
O&M, planning, design, construction, HR, IT etc.) to respond to the changing environment and the
requirement thereof.
Define better systems to record, store and manage the data including IT-based systems that support
various organizational initiatives and other business processes;
Better human resource management including recruitment plans, performance management system;
Adequate training and capacity building of the staff to respond to the change agenda, and
Communication and change management plan.
AF-Mercados EMI 5
As-Is Assessment Gaps
Analysis Benchmarking
Action Plan (5years)
Field Assistance
Project Management
As-Is Assessment: Analysis of existing situation of aspects related to operations, finance,
HR, and IT.
Benchmarking: Benchmarking of relevant parameters in order to determine the targets/
objectives of different processes within the company.
Gaps Analysis: Identification of gaps
Development of detailed recommendations for reducing the above mentioned gaps.
Action Plan (5 years): Development of 5 years action plan, including capacity building needs
definition (in collaboration with companies’ managers).
Field Assistance: Implementation of specific activities for the capacity building needs
detected.
AF-Mercados EMI 6
Inception Report Interim Report 1 Interim Report 2 Interim Report 3 Interim Report 4 Draft Final Report Final Report
As-Is Assessment Gap Analysis
& Draft Action Plan
Detailed Action Plan
1. Detailing the overall work plan,
activities, assignment
methodologyapproach, and data
requirement
1. BPR Report
2. Financial Management
Report
3. HR
Strategy Report
4. IT Report
1. BPR Report 2
2. Financial
Report 2
3. HR Strategy Report 2
1. BPR Report
2. Financial Report
3. Capacity Building
Report -Training - 1
1. Assistance and Workshops
2. HR Strategy Report 3
3. Capacity Building Report 2
4. Final
Management Report
5. JPP
1. Draft Report including results of capacity building
activities & all materials in the
project
2. Final Report
including final versions of all the
materials in the project.
Project Management
Project Workflow Chart
AF-Mercados EMI 7
1
9
8
7
6
5
4
3
2
10
11
12
Inception Mission
25 Oct to 3 Nov 2010
Draft Inception Report submitted
January Mission
Draft Interim Report 1 submitted
Final Inception Report submitted
Tripartite Meeting
Stakeholders Meeting:
15 Jan to 25 Jan 2011
Information Collection
2 Nov to 20 Dec 2010
Field Visit by Dist Expert :
Dibrugarh, Morigaon, Rangia and Nalbari
February Mission
15 Feb to 28 Feb 2011
Plant Visit by Gen. Expert: NTPS and KLHP
Finance Team: Stakeholders Meeting
Quarterly Progress Report
April Mission
Interim Report 2 Departmental Workshop
28 Mar to 9 Apr 2011
High Level Meeting with APDCL CGMs
Executive Summary with The Chairman, MDs
(ASEB) and ADB Experts
Field Visit by Dist Expert to Jorhat Circle
Draft Interim Report 2 submitted
May Mission
Workshop on Capital Investment
and Business Plan
5 May to 15 May 2011
Final Interim Report 1 submitted
August 2011
Final Interim Report 2 submitted
Draft Interim Report 3 submitted
22 Sept to 30 Sept 2011
September Mission
Training Program on IT
Workshop on HRSC
Visit by HR and IT Expert for Jorhat
Pilot Project
Project Progress Snapshot
November Mission
07 Nov to 26 Nov 2011 Visit by Team Leader and Dist. Expert to
Jorhat Pilot Project to review the progress
Training Program by Fin. Expert, Trans.
Expert and HR Expert
Final Interim Report 3 submitted
Draft Interim Report 4 submitted
December Mission
05 Dec to 30 Dec 2011
Training Program by Acc. Expert, Gen. Expert
and External Dist. Expert January Mission
02 Jan to 25 Jan 2012
Training Program by
Gen. Expert and
External Dist. Expert
Study Tour to NDPL
By APDCL
Major Milestones achieved
July Mission
11 Jul to 23 Jul 2011
Jorhat Pilot Project Kick-off
Workshop on Business Plans of utilities
Training Program on Generation Process
Training Program on Transmission Process
Training Module on Change Management
13 February Mission
07 Feb to 17 Feb 2012
Visit by Fin Expert for completion of APDCL Business Plan
Visit by AEGCL for Training Program in NPTI, Guwahati
Visit to Jorhat Pilot Project by Dist. Expert
Draft Final Report submitted
AF-Mercados EMI
Analysis of Current Performance:
8
Generation Process Management
Major Challenges:
Lack of monitoring for enhancing the efficiency of
power plants:
Introduction of comprehensive Daily,
Weekly and Monthly report.
Adopt a procedure of effective monitoring by
review and follow up of above reports.
Detailing out the responsibility and accountability
of employers towards plant performance.
Introduction of detailed periodic and preventive
maintenance schedule.
Introduction of effective procurement procedure
and Inventory management system.
Enhance basic IT infrastructure towards effective
communication system.
Planning and progress monitoring needs more attention. Monthly progress report is being prepared but essential detail not regularly filled up.
There is lack of a defined detailed benchmark maintenance plan.
An officer/department exclusively responsible for
efficiency, planning and progress monitoring not found.
Monitoring tools such as Primevera, MIS, Customized software, DBM, ERP are not available.
Communication system at plant level presents weaknesses that may become it to some extent unreliable.
Fuel supplies are not fully adequate. There is no online measurement of gas at plant end.
An efficient Inventory and spares management system was not found.
Environment, Health and Safety issues are not taken as serious as necessary at plant level.
Procurement procedures are longer than other peers. This results in delays beyond normal standards.
AF-Mercados EMI 9
Generation Process Management
S.No Parameter Unit Approved by CERC
As Presented by APGCL in its latest
tariff Petition
(09-10)
As approved by AERC in its latest
tariff order
(09-10) Open Cycle
Combined Cycle
LTPS
1 Gross Heat Rate Kcal / KWh 3125 2030 3585 3435
2 Availability % 80% 80% 74 50%
3 A u x i l i a r y P o w e r Consumption
% 1 3 8.05 5.59%
4 PLF % 80% 80% 69 50%
NTPS
1 Gross Heat Rate Kcal / KWh 3125 2030 3495 3266
2 Availability % 80% 80% 55 50
3 A u x i l i a r y P o w e r Consumption
% 1 3 5.17 3.0
4 PLF % 80% 80% 53 50
S.No
Parameter Unit A p p r o v e d by CERC
As Presented by APGCL in its latest tariff petition
(09-10)
As approved by AERC in its latest tariff order
(09-10)
Hydro Power Plant
1 Availability % 55-80%* Not available Not available
2 PLF % 55-80%* Not available Not available
3 Aux. Power Consumption % 1 0.5 0.5
AF-Mercados EMI 10
Short Term Activities Implementation
Status
• Daily, Weekly, Monthly, EHS report, Outage report, Review
and analysis report
The reports have been forwarded to Plant sites
but implementation status
not known
• Operation, Maintenance, Procurement, Corporate and
Financial planning
Maintenance Planning have been implemented
• Enhancement in the quantum of gas, negotiate supply agreement,
insure the stability and supply of
gas Status not known
Summary of Action Plan:
Medium/Long Term Activities
• Effec t ive procurement manual / Procedure, Detailing of spares (with
critical and lead time), Centralized
inventory/store
• Effective communication, Basic IT infrastructure, Internet, email to all users,
LAN, WAN, ERP, SAP and customized
software
• Conduct Energy Audit, RLA/LE studies for all the units. Prepare R&M plans for
all units based on studies. Implement
R&M in phased manner. Prepare plan for
retirement of units
• Establish a comprehensive training program for workers, operators,
supervisors senior engineer and
management enunciate transparent
policy for rewarding performance and for
useful innovation ideas
Generation Process Management
AF-Mercados EMI
Training/Assistance Sessions
Delivered:
Planning
Progress Review and Monitoring
Responsibility and Accountability
Communication
Information Management
Procurement
Inventory
Vendor/ Supplier Development
Environment, Health & Safety
Appreciation & Reward
Training and Motivation
Tariff and Regulatory
11
Company response:
Though at the beginning there was some misunderstandings among local
staff and experts, the reality is that the
company has much appreciated and
participated in all workshops and
activities proposed.
T h e w o r k s h o p s w e r e h i g h l y
appreciated especially the workshop
on Tariff.
The Genera t ion exper ts have
forwarded various performance report
template which has been forwarded to
the Plant site.
Training sessions at the plant site
requested by APGCL in future
Generation Process Management
AF-Mercados EMI 12
Way Forward:
Organization should be strengthened to meet the requirements of new thermal and hydroelectric
projects monitoring cost control and dispute resolution. Financing arrangements should be formalized
for meeting the needs of new projects, expansion projects and R&M projects. Details of financing are
provided in the section in Financial Management.
A strong Planning and Monitoring Cell reporting directly to the Managing Director should be set up.
It should be provided with latest monitoring tools. MIS should be fully computerized.
Employee costs and administration costs should be reduced through rationalization and
relocation of surplus staff to new projects.
Rigorous energy audit should be done to reduce auxiliary consumption.
Internal audit should be performed on a continuous basis to reduce costs.
Agreements with gas suppliers should have two way sharing mechanism with penalty to both buyer
and seller for not meeting minimum guaranteed levels. State Government and Government of India
should be requested to accord greater priority to the power sector in gas allocation.
Gas turbines at both LTPS and NTPS are very old. More attention may be given to R&M measures
investigating different options.
Prepare plan for retirement of old units
In-house training and training of operating personnel and officers at better maintained power stations
is advisable.
Generation Process Management
AF-Mercados EMI
Analysis of Current Performance:
Lack of:
Updated Load Forecasting &
S y s t e m s t r e n g t h e n i n g
implementation
Standardization of designs
Scheduled Maintenance and
control (SCADA) of transmission
system
13
Transmission Process Management
Major Challenges:
There is a weakness in the long term grid
planning due to the lack of updated LFC studies
Design of new assets may require some
technological upgrade and standardization.-
Transmission lines
The schedule maintenance works in transmission
system including Condition monitoring ,RLA in
subs ta t ions and rou t ine inspect ion o f Transmission line insulators requires special
attention to in order to maintain the availability of
transmission system to maximum extent
AF-Mercados EMI
Analysis of Current Performance:
Lack of:
IT Implementation in various
areas
Elaboration of manuals
Development of quality plans
Transmission Process Management
Major Challenges:
Improvement required for the monitoring of
the works and quality for the
construction of new assets
Lack of MIS for the management of
the grid, including GIS, mapping of Transmission
lines ,substations, extension of existing
SCADA. Eventually, installation of own optic
fibre cable
Training in several aspects of the operation is
needed
Providing Manuals for various
departments in AEGCL
14
AF-Mercados EMI 15
Transmission Process Management
Short Term Activities Implementation Status
Expediting the process of SCADA work.
Currently only Data Acquisition is available and
the project of laying of
OPGW hasn’t started yet as
it’s in the 2nd phase.
Procurement:
• E-tendering Software Under consideration
• Project Management Software
ADVERTISEMENT EOI for ERP published by AEGCL
Defining a Metering Architecture
ABT meters in inter-phase levels with APDCL and for
inter-state too.
Summary of Action Plan:
Medium/Long Term Activities
Reduction of Transmission system losses
Standardization of Transmission line Tower designs
Preparation of Manuals Construction Practices
IT implementat ion and
software requirement
Transmission loss reduction
SCADA implementation in all Sub stations
Transmission system maintenance-Hot Line equipments
Imparting continuous Training to the Staff
AF-Mercados EMI
Training/Assistance Sessions
Delivered:
16
Transmission Process Management
Company response:
AEGCL highly appreciated the workshop especially on the topics
r e g a r d i n g t h e A n a l y s i s o n
Transmission Losses.
Practical Workshop on Hot
Line Maintenance would be really
helpful
Requested workshop on the following
topics were requested by AEGCL:
E-Tendering
SAS (Sub-s ta t ion Automat ion
System)
Maintenance, Erection, Construction
and Operation of 400 KV sub-station,
Energy Audit in Transmission system.
Transmission system loss Reduction
Emerging Technologies in
Transmission system
Gas Insulated substations
DPR & Budget proposal preparation
Sub-Station Integration & Automation (SCADA)
Training in NPTI, Guwahati on following topics: Substation Automation System
Erection & construction of 400 KV Sub-
Station
Operation & maintenance of 400 KV Sub-
station
AF-Mercados EMI 17
Transmission Process Management
Way Forward:
To achieve the objective of bringing AEGCL on par with national & international standards
Conducting yearly LFC studies and modify the long term system development programmes suitably to achieve the energy loss Target levels of 4 % initially & 2% finally
Optimisation of procurement process to reduce the planned project implementation period & quality
improvement in new assets created
Standardization of Transmission line tower & foundation designs
Asset mapping of Transmission lines & Substations
Adhering to schedule maintenance works of Transmission lines & Substations and procurement of all the required testing & maintenance equipments like hot line, thermo vision cameras, C.B testing kits
SCADA implementation & making all the substations unmanned in phased manner
Capacity building on Hot Line Maintenance
Preparation & providing of manuals for all the activities of AEGCL
Imparting regular training in all departments of AEGCL
AF-Mercados EMI
Analysis of Current Performance:
Monitoring mechanism seems to be weak. Lack of result-oriented procedures in commercial and operational areas
As on date there is no specific plan or timeline decided to replace all defective and electromechanical
meters of APDCL.
Analysis of Bulk Consumers (IRCA) billing is done manually. There is no analysis of meter data.
Energy Accounting is carried out through manual input of data. Feeders’ Meters have serious problems.
APDCL relies on the Load Dispatch Centre report for future demand projection. No evident own
procedure.
There is no monitoring from a central location. Commercial processes are not standardised and no
standard process document (like ISO document) exist.
Imprecise and manual usage of De-centralised database for commercial function. Low support on
systems.
Proper monitoring of meter reading performance cycle time and efficiency was not found
Meter replacement for consumer owned meters is done only after consumer pays the charges. This contributes to loss in billing efficiency
18
Distribution Process Management
AF-Mercados EMI 19
Major Challenges:
APDCL requires restructuring to have focussed group for loss reduction measures and efficient operational processes like Network Planning and
Preventive Maintenance Management. An authorized loss reduction leader shall be a positive reference.
Development and Implementation of systems and results-oriented procedures with effective review mechanism is seen as the key aspects for success.
The organization must be optimized in terms of quantity and skills. Results-
oriented mind-set is mandatory. Reorganization of roles and positions is also necessary.
Increase Pressure level for monitoring activities and large customers’ control
Distribution Process Management
AF-Mercados EMI 20
Summary of Action Plan:
Medium/Long Term Activities Expected Benefits
Creation of Centralized Commercial database Ease of monitoring from a centralized location Uniform business processes across the utility
Building exception logics into the IT system which throw out exceptional cases such as High
Consumption, Low Consumption etc
Accurate Billing leading to loss reduction
Increased Revenue Generation
Automatic meter reading through modems for the HT consumers
Accurate Billing leading to loss Reduction
Increased Revenue Generation
GIS based consumer indexing
Central repository for the assets Reduction in cycle time for field activities
Easy reference for Network Load
flow studies
Utility wide rollout of ERP Project life cycle tracking Project Monitoring
Zonal Headquarters to be shifted to respective zone Effective monitoring of functions
Centralized Consumer Call Centre for urban consumers
Centralized Consumer Complaint Registration, Tracking and Monitoring
Enhanced Consumer Satisfaction
Distribution Process Management
AF-Mercados EMI 21
JORHAT PILOT PROJECT
Short Term Activities Implementation Status
Data Analysis – IRCA consumers
• To ascertain correct billing • To ascertain tampering/meter defective cases
Sporadic analysis of certain cases by MTI
• Complaint Data Analysis Data being captured, analysis are yet to be done.
Field Activity – IRCA consumers
• Data Downloading for Private Consumers Data downloading of some consumers are being done (including consumers with load >500 KW)
• Metering Rectification Action taken against cases analyzed
• Action against theft Cases reported sporadically
• Verification of dues against disconnected cases Action reported from one sub-division
Data Analysis – Small consumers
• Exceptional cases with zero/Low consumption Activity started after November Mission, resulted into replacement of around 1900 meters.
• Complaint Data Analysis Data being captured, analysis are yet to be done. This will give benefit in next summer for proper monitoring.
Summary of Action Plan:
AF-Mercados EMI 22
JORHAT PILOT PROJECT
Short Term Activities Implementation Status
Field Activity– Small consumers
• Verification of zero/low consumption cases Result reported
• Replacement of stopped cases
Special Activities
• Follow up of dues against high outstanding cases
Result reported
• Follow up against consumers with average consumption more than connected load
Result reported
Summary of Action Plan:
AF-Mercados EMI 23
JORHAT PILOT PROJECT
Replacement of Stopped Meters
Present Posi4on Poten4al Benefit
Number of stopped
meters replaced
Increase in monthly
consump6on (in
KWh)
Increase in Monthly
Revenue (in USD)
Number of
defec6ve meters as
on 31.01.2012
Poten6al Increase
in monthly
consump6on (in
KWh)
Poten6al Increase
in Monthly
Revenue (in USD)
1521 156244 15625 6766 695034 69506
Meter Data Analysis of IRCA Consumers
Present Posi4on Poten4al Benefit
Number of Cases
Inspected
Assessment
Amount (in USD)
Increase in monthly
revenue (in USD)
Number of Cases to
be inspected
Poten6al
Assessment
Amount (in USD)
Poten6al Increase
in monthly revenue
(in USD)
228 41520 5716 540 98336 13537
AF-Mercados EMI 24
JORHAT PILOT PROJECT
Number of
cases with Load
enhanced
Total load
increased (in
KW)
Increase in Fixed
Charges per
month (in USD)
Number of
cases observed
Total load to be
increased (in
KW)
Potential
Increase in Fixed
Charges per
month (in USD)
1060 2890 2525 1546 4215 3682
Load Enhancement through Consumption Analysis
Present Position Potential Benefit
Cumulative impact of potential increase in monthly revenue and collection will result in
increase of billing efficiency by 4% (from 63% to 67%) and collection efficiency by
1% (from 93% to 94%). The AT&C Loss in Pilot Project Area can be reduced to 36%
from present level of 41%.
Potential benefits to the APDCL is approximately 21 million USD annually for
reduction of AT&C Loss by 5%
Number of
cases resolved
Amount realized
(in USD)
Number of
Disconnected
Cases as on
February'12
Amount to be
realized (in USD)
2333 284721 3883 385455
Present Position Potential Benefit
Disconnected cases with Outstanding Dues
AF-Mercados EMI
Training/Assistance Sessions
Delivered:
Programme on AT&C Loss Reduction Best
Practices
Review and Monitoring Mechanism
Training Module on Change Management
Practical demonstration on Meter Data Analysis
Workshop on Best Practices of IT in Power Sector
Workshop on Employee Motivation and Morale
Workshop on Network Planning in GIS
Environment
25
JORHAT PILOT PROJECT
Company response:
Useful information
Prioritisation in AT&C Loss reduction
initiatives carried out considering best
practices in TPDDL.
Response in the Pilot has been poorer
and slower than expected according to
real conditions in the company.
Personnel management is considered
to be major hindrance for performance
improvement.
AF-Mercados EMI 26
Synopsis and Way Forward
Initiatives undertaken has measurable impact on Billing and Revenue Realisation.
Initiatives and experience in Pilot Project should be replicated across the organisation
for effective reduction in Losses.
Initiatives have been identified and planned in July’11. However, these have been taken up effectively in November’11
Allocation of dedicated resources is crucial for continuous improvement in performance.
The initiatives undertaken in Pilot Project, have been reviewed through Weekly MIS till date. This has resulted in measurable benefits.
Regular review at appropriate levels are crucial for success.
New areas like revenue realization against SPPS consumers have been introduced in Pilot Project area.
The initiatives for Loss Reduction requires to be continuously reviewed and improved
further.
AF-Mercados EMI
Analysis of Current Performance
(All Companies):
Accounting System
Reconciliation and Classification of Opening
Balances
Weak Internal Control and Audit Process
No Audit Committees (required under Sec 292 A
of Companies Act
Accounting manuals and handbooks not available and not updated since 1985
Accounting system not capable to detect and
prevent fraud and errors
Manual System with limited Automation
AERC requirements not complied with (asset registers, capex justifications etc) including
delay in providing information on a timely basis
Un-satisfactory record keeping
27
Accounting/Financial Management Systems
Major Challenges:
Development of an effective accounting
system that facilitates identification of gaps
and its timely redressal
Critical to ensure corporate discipline
Prov ide gu idance, ins t ruc t ions and
handholding at all levels
Creating systems, structures and incentive
mechanism for the publicly-owned and
monopoly companies such as APDCL,
AEGCL and APGCL to aim towards financial
independence, focus on profitability and delivery of quality public service.
AF-Mercados EMI
Analysis of Current Performance
(All Companies):
Financial Management System
Financial autonomy w.r.t. projects funded from
external sources
Strengthening of Finance Department – by
upgrading the current position of Finance Heads
Weak Risk Management Practices (Fuel risk cover, insurance of employees, cash in transit etc)
Budget Management - No expenditure audit since
APDCL inception – Variance analysis is weak
Working Capital Management- deficiencies in
billing, un-cleared cheques, no ageing analysis of receivables, ad hoc bill clearance etc
Inventory Management Policy/Practices need
upgradation - no stores manual, stocks of 8-10 yrs
in inventory, differences in physical verification,
accumulation of obsolete material etc
28
Accounting/Financial Management Systems
Major Challenges:
Development of an effective financial
system that facilitates identification of gaps
and its timely redressal
Essential for complete financial bundling
and independency
Critical to manage risks imposed by changing environment and understand its
implications
Creating systems, structures and incentive
mechanism for the publicly-owned and
monopoly companies such as APDCL,
AEGCL and APGCL to aim towards f inanc ia l independence, focus on
profitability and delivery of quality public
service
AF-Mercados EMI
Analysis of Current Performance
(Common to all Companies):
Business Plan and Capital Investment Plan
Absence of long-term business plans
except in case of APGCL (though not
comprehensive)
Lack of capacity for long-term business
and capital investment planning as
indicated by:
Failure to complete & update the BP
templates (did not have action plans,
measurable targets and financial
plans prepared by previous external
experts)
Undertake economic evaluation on a
pe r p ro jec t bases o f Cap i ta l
Investment Plans
29
Accounting/Financial Management Systems
Major Challenges:
Appreciation of having long-term
business plans separately for each
company
Capacity building around tools for
business and investment planning;
and ensuring that the same occurs on
an ongoing basis
AF-Mercados EMI 30
Short-Term Activities Implementation
Status
ACCOUNTING SYSTEM
Completion of break up of opening balance among 3 companies Constitution of Audit Committee
Complied
Maintenance of Subsidiary Books – Identification and monitoring;
Audit Observation by Internal Audit & CAG –
Compliance
In Progress
Appointment of regular Director (F) Appointment of Cost Auditor by all the three
companies and installation of cost accounting
system
No action on appointment of Finance Director. APDCL
appointed external accountants as cost
auditor for 2011-2012.
Issuance of guidelines for Classification of Expenditure of an Capital Maintenance as Capital, Revenue Or Deferred Revenue Expenditure
Formation of Accounting Application Committee / Cell Separately for each Company)
Outsourcing of the work to prepare Internal Control System
Development of Standard format for the Statement
of Non Adherence / Part Adherence of Accounting Polices
No Progress
Summary of Action Plans
Medium/Long Term Activities
ACCOUNTING SYSTEM
Revision of Service Rules for Accounting E x e c u t i v e s a n d s t a f f i n c l u d i n g qualification criteria and performance
based promotion system. A step towards this direction was made with the recent
appointment of additional finance and accounting staff with computer skills
Computerization; Prepare Accounts
Hand Book, Manuals & Standard Formats
Formation of Accounting Application
Committee
Creation of Fixed Asset Register and Capitalization of completed works that
are still classified of CWIP. Fixed asset register of APDCL as of 31.03.2011 was prepared and under review by AERC.
Updating Stores Manual
Constitute Internal Audit team in APGCL,
strengthen teams at APDCL and AEGCL
Set up a proper Accounting Record Room at Corporate Offices of the Companies
IFRS Convergence
Accounting/Financial Management Systems
AF-Mercados EMI 31
Short-Term Activities Implementation
Status
FINANCIAL MANAGEMENT SYSTEM
Mandate for financial Autonomy of Utilities from ASEB
No Action Taken
Restructuring of GOA and other loans outstanding
Proposal to convert
outstanding GOA
loans to equity
submitted by
APDCL on 31.03.2010
Dismantling of centralized cash mechanism No Action Taken
Timely deposit of collection at APDCL to reduce banking float time, policy for
payment through cheque above a specified
bill amount; recovery of dues from
employees and other utilities undertaking.
No Action Taken
Up gradation of billing software to give age wise defaulter list for further actions.
No Action Taken (done on annual
bas i s f o r P i l o t
Area)
Summary of Action Plans
Medium/Long Term Activities
FINANCIAL MANAGEMENT SYSTEMS
Deployment of Risk management framework for analysis of various risk associated and developing strategies to
mitigate the same with in all utilities.
Adoption of systematic process for Budget control like implementation of ERP module.
Formulation of working capital management policy
Fully computerized of billing like temporary connections
Adoption of computerized inventory management system
Adoption of rate contract mechanism for decentralized procurements.
Accounting/Financial Management Systems
AF-Mercados EMI
Capacity Building, Training Sessions Delivered:
ACCOUNTING SYSTEMS
Phase – I (5 main topics)
Accounting Documents
Works & Accounting Classification (Control of Capital Works
in Process and Distribution Between Capital & Revenue & Deferred Revenue Expenditure)
Basic Accounting Policies and Costing
Costing (Costing Records & Structure and Cost Audit)
Inventory Control
32
Company response:
ACCOUNTING SYSTEMS
Attendants enthusiastic and responsive
Low participation in certain cases however with facilitation of PMU this was addressed
Attendants indicated need for such trainings and workshops on a continued basis
Phase - II (12 main topics) Legal Compliances-Compliance with Schedule VI of the
Companies Act 1956 Compliances – Accounting Standards & IFRS-Compliance
with Accounting Standards
GAAP & IFRS Control & Monitoring System-Internal Audit, Internal Control
and Audit Committee Accounting Documents-Development of Accounting
Manual, Chart of Account, Monthly Reporting System &
maintenance of Subsidiary & Control Books Fixed Assets Registers, Contract Registers, Work Register & Register of Abandoned & Decommissioned Assets
Work & Accounting Classifications-Control of Capital Work in progress and Distribution between Capital & Revenue &
Deferred Revenue Expenditure Costing-Costing Records & Structure and Cost Audit;
Inventory Control-Inventory Control & Accounting including
physical Verification & write - off.
Accounting/Financial Management Systems
AF-Mercados EMI
Capacity Building, Training Sessions Delivered:
FINANCIAL MANAGEMENT
SYSTEMS
Workshop on Risk Management
framework
BUSINESS AND CAPITAL
INVESTMENT PLANNING
Series of Workshops on Capital
Investment and Applied Business
Planning
33
Way Forward:
Strong commitment from top management on strategic issues particularly related to financial independence, filling key positions, and initiating new systems
Focus on action plans – Short-term (pending actions); Medium and Long-term
Training arrangements for regular training and upgradation
Accounting/Financial Management Systems
Company Response:
FINANCIAL MANAGEMENT SYSTEMS – Risk Management
Participants were keen to understand the framework and how the same can be
implemented in their companies.
BUSINESS AND CAPITAL INVESTMENT PLANNING
APGCL - enthusiastic as manifested by involvement/participation of all DGMs at
the initial and culminating session of the Business Planning exercise; permanent Technical Working Group members supplemented by other technical staff when necessary; constant presence and involvement in workshops
AEGCL – participation was lukewarm with only one Technical Working Group
member consistently attending all workshops; constant replacement of TWG members except for one resulting in incomplete evaluation of capital investment
plan and Business Plan
APDCL – weak participation with no permanent member of the TWG although
staffs assigned evinced interest in the issues BUT were constantly changed. Result: incomplete evaluation of Capital Investment Plan and inability to draw up
Business Plan
AF-Mercados EMI
Analysis of Current Performance:
Both -HR Organization and staffing, are inadequate. Lack of mid-level executives
HRM processes relatively out-dated. Not
performance driven, nor supporting
accountability. No integration between the HR
processes, Manpower Planning & Recruitment processes not streamlined
No comprehensive plan in place to address
large scale retirement in the next 4-5 years
Unmotivated staff-especially at field level,
stagnation at lower executives levels.
Formal training of Executives is virtually
nonexistent
Data base & retrieval , for planning &
implementing HR Policy/processes not available
Common seniority cadre across the three utilities
for senior executives.
Functions such as HR, IT, Legal, Commercial
grossly inadequate.
34
Human Resource Management
Major Challenges:
Essential if the Utilities are to now operate as
business corporate efficient entities
Reflected in dual charge of posts at senior levels, and several gaps in the staffing of sanctioned
posts
Partly leadership and partly lack of performance
based policies (over emphasis on seniority)
No opportunities to upgrade /new knowledge and
skills & a business Orientation. Training needed to support new structure & processes.
Level of Impact & Implications of the policy
changes cannot be easily ascertained
Long term commitment & consolidation of
expertise becomes difficult
Critical functions for improving operational and commercial performance; working as Business
entity
AF-Mercados EMI
Analysis of Current Performance:
Absence of a comprehensive communication
Plan and defined processes for communication
with the various internal and external stakeholders
Various circulars related to employee benefits
and rules are now in a myriad of memorandums,
regulations, rules, revisions etc..
Lack of mechanisms for receiving operational/
organizational suggestions and feedback from employee
35
Human Resource Management
Major Challenges:
Vital for any reforms-to inform, involve ,
inspire and motivate the various constituents
AF-Mercados EMI 36
Short Term Activities Implementation
Status
1.Enhancing HR Function : road map
i.Hiring of CGM Distribution
(professionally qualified through open
recruitment)
ii. Approve preliminary HR/Training
organization and staffing
iii. Inducting professionals as Executive
trainees
On-Going
Implemented
(through internal
transfer)
Pending
Implemented
2.Develop and establish a Human Resources
Steering Committee (HRSC)
On Going
3.Creation of Legal Section Pending
4. Enhancing the effectiveness of the Performance Appraisal system
Pending
Summary of Action Plan:
Medium/Long Term Activities
1. Human Resources Information System
2.Manpower Planning System & Recruitment Planning
3.Preparation of plan to address Retirement
4. Automated Attendance Records
5.Motivating Employees: Performance Linked Incentives; incentivize postings
at remote project sites; stagnation in
career growth
6.Development /Updating Promotion system
Human Resource Management
AF-Mercados EMI 37
Short Term Activities Implementation
Status
5.Develop process for approving & updating organization charts and
monitoring & reporting sanctioned posts Pending
6.Manpower Norms (Distribution) & Outsourcing
On Going
Training
Training Needs Assessment (Training) – Implementing recommendations
On Going
Implementing proposed training policy & norms & road map
Pending
Training systems for making nominations
Pending
Summary of Action Plan:
Human Resource Management
Medium/Long Term Activities
1. Training Organization Structure & Staffing for the three utilities
2. Developing training resources for effective implementation
3. Induction Level training for HR professionals recruited
4 . C a r e e r L i n k e d T r a i n i n g Interventions
AF-Mercados EMI
Training/Assistance Sessions
Delivered:
Management of Change
Develop ing Execut ives fo r Improved
Performance 1
HRSC: Road Map for 13 Key HR Areas
Overview of HR Mgmt
Employee Motivation & Morale
Enhancing Capacity of HR Functionaries
Study Visit for APDCL Team to study NDPL practices
38
Company response:
Appreciated the interactive workshops on M a n p o w e r P l a n n i n g , C h a n g e
Management (use of two real live cases)
and requested further training on such
topics
Workshop on HRSC, Emp loyee
Motivation and Morale was also highly
appreciated and the core team has
started working on the key issues.
Action areas for application in APDCL,
based on Study Visit to NDPL included.
AMR Data monitoring & analysis as done
by NDPL, IT interventions, processes/
practices related to regular review of
activities at various levels, the role of HR
role in bringing about change in the work
culture
Human Resource Management
AF-Mercados EMI 39
Way Forward:
Strengthening HR Organization & Staffing, without which the recommendations cannot be implemented
HRSC is a good mechanism to drive change on a continuous basis-but this needs to be sustained and
given due impetus and direction. Chairman/his Secretariat need to get closely involved with approvals
etc and also monitoring.
Out of a list of 13 HR activities-with road maps provided to HRSC, short term critical tasks have
somewhat been avoided by HRSC and opted for long term activities with no immediate impact! One wonders if this is to postpone immediate responsibility. Short term critical areas to be accorded
priority .
Plan to address imminent retirement of many key management and other staff
Recruitment of executives at mid levels (selectively) is important. For instance 8 HR professionals
recruited at induction level, but there is no one to provide them leadership and guidance-especially at this
stage.
Suggest the utilities consider starting with ‘pilots’ in some areas-such as job descriptions; performance
–linked appraisal etc.
Institutionalize/institute a mechanism, wherein the reports by the consultants are made easily
accessible and deliberated upon, to glean applicable recommendations by the concerned groups
within the Utilities. (For instance, even a high powered committee such as HRSC had formed a task force on Training-without realizing that the assignment was done by the Consultants). Similarly, reports by
earlier consultants on PAS; Draft HR Policy etc.
Human Resource Management
AF-Mercados EMI 40
Way Forward:
To institute Email Messaging system -important for effective communication
Development of Communication Strategy, including key messages for the various
stakeholders; identifying change champions
Prepare employee handbook (user-friendly) to clarify and explain in a simple/succinct
format the numerous HR rules; benefits etc.
Human Resource Management
AF-Mercados EMI
Analysis of Current Performance:
No AMR in distribution utilities
No storage and backup system
No specialized hardware for handling calls at Customer Care Offices
Inappropriate UPS & Battery system
No Effective and up-to-date security system
RMS application developed by CMC under
APDRP is in use
No Customer Indexing or Asset Management through GIS
No Mail or messaging system; EMS/NMS
Proper MIS system is not in place
All the 5 utilities have different websites
No ERP/ SCADA/ GIS/ Plant Management/ Mail Messaging System for Generation utility
No Network connectivity between offices No
Data Centre or Data Recovery Centre
41
IT Infrastructure
Major Challenges:
IT Department non-existent
Standalone Systems
Lack of Integration
Lack of implementation
Manual intervention
Lack of IT awareness
Lack of proper IT infrastructure
L a c k o f p r o p e r s e c u r i t y
mechanism
Lack of critical IT modules for
HR, Finance, ERP, Procurement
etc
Diversified Billing Systems
AF-Mercados EMI 42
Short Term Activities Implementation
Status
Basic IT at different offices Absent
Mail Messaging System Envisaged for Jorhat Pilot Project
Identity & Access Mgmt. & System Security Absent
Storage & Data Back Up Absent
Centralized Metering, Billing and Collection Application
Absent
MIS & Asset Management Absent
Knowledge Management System Absent
Employee Help Desk System Absent
ERP Absent
Summary of Action Plan:
Medium/Long Term Activities
Automatic Meter Reading
GIS
Energy Accounting & Auditing
Centralized Customer Care Center
Data Center
Data Recovery Center
WAN
SCADA for Distribution
IT Infrastructure
AF-Mercados EMI
Training/Assistance Sessions
Delivered:
Workshop on IT Best Practices in Power
Utilities
Workshop on expectations from R-APDRP
(Part-A) Scheme
System Security and BCP Planning
Program on Enterprise Resource Planning
System
Analysis processes
43
Company response:
A P D C L r e q u e s t e d f u r t h e r benchmarking information on IT
Organisation and same has been
provided
The company has lately shown an
interest in having modern Mail
systems in the company.
This represents an important step-up
in the level of involvement for
developing the IT infrastructure in the
company.
Way Forward:
For implementing any IT system – Pre-Requisite is to establish IT Organisation within utilities and implement basic IT Infrastructure like Desktops, LAN , connectivity of all
offices (WAN). These Pre-requisite are currently missing and needs to be implemented
IT Infrastructure
AF-Mercados EMI 44
The Project has been delivered and implemented successfully according to the defined objectives and scope.
Many constraints for the three companies were found out:
Generation: Low efficiency and availability;
Transmission: Current efficiency level may be under risk;
Distribution: High losses and very low operational efficiency.
Action and Business plans have been developed in coordination with the staff
where recommendations for improvement of the companies’ operations in particular from a monitoring, accountability and results-oriented perspective have
been provided.
Assistance, Workshops, and study tour have been very successful and appreciated.
In particular, the Jorhat Pilot has shown (to the extent possible) that implementation of the short-term actions bring positive results. Implementation of
the action plan must continue and be escalated to the rest of the organization.
Final Conclusions
AF-Mercados EMI 45
Recommendations for further projects development that support the implementation of the Action Plan:
Metering Reliability Improvement. Replacement of defective meters (approx 162,000
(8.5%) ).
AMR implementation for IRCA and Large Commercial Clients and Feeders (6000
approx.).
Development of new plants facilities to replace existing ones.
Procurement and Implementation of MIS, in particular:
Basic IT Infrastructure
SCADA/EMS/DMS/GIS
CC&B (Commercial and Billing system) with a centralized database/Central Call Centre
ERP
Development of a Training Centre and institutional mechanism for creating linkages
with Institute of Management (IM), and Indian Institute of Technology (IIT).
Development of a comprehensive communication plan and infrastructure (internal &
external).
Final Conclusions