technical audit

Upload: lengyianchua206

Post on 02-Jun-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Technical Audit

    1/33

  • 8/11/2019 Technical Audit

    2/33

    Agenda

    1

  • 8/11/2019 Technical Audit

    3/33

    1. Ground Rules

    2. Construction Project Stakeholders

    3. Technical v/s Operational Audit of Construction projects

    4. Reasons for auditing construction projects

    5. Type & Scope of Construction Project Audit

    6. Case studies

    7. Surprise Quality and Safety Inspections

    8. Value addition by Innovation

    9. Questions

    2

  • 8/11/2019 Technical Audit

    4/33

    Ground Rules

    3

  • 8/11/2019 Technical Audit

    5/33

    The real life case studies presented are based

    on actual events but modified forconfidentiality purposes

    Case studies are selected from presenters 29

    years of work experience Mobiles on silent mode please

    Questions at the end of presentation orthrough email

    4

  • 8/11/2019 Technical Audit

    6/33

    Construction Project Stakeholders

    5

  • 8/11/2019 Technical Audit

    7/33

    I smellmoney

    The Contractor

    I amalways

    right

    Third Parties

    What isyour

    scope?

    Auditor

    6

  • 8/11/2019 Technical Audit

    8/33

    Technical v/s Operational Audit of

    Construction projects

    7

  • 8/11/2019 Technical Audit

    9/33

    Normal audit teams generally consist of internal auditors with afinancial background

    Technical audit teams consist of Engineers, Quantity Surveyors,Planning Engineers, Contract Specialists, QA - QC Experts andalso include internal auditors with financial background

    Normal audit teams verify general compliance to the policies and

    procedures Technical teams verify compliance to the contractual requirement

    - contracts, specifications, codes and standards

    Quality and EHS site visits can be conducted by technical auditors

    8

  • 8/11/2019 Technical Audit

    10/33

    Reasons for auditing

    construction projects

    9

  • 8/11/2019 Technical Audit

    11/33

  • 8/11/2019 Technical Audit

    12/33

    Type & Scope of Construction

    Project Audit

    1211

  • 8/11/2019 Technical Audit

    13/33

    Project Development/Feasibility Master Plan & Design Brief

    Compliance to regulatory authority

    Type & conditions of contract

    Tender & Contract

    Value Engineering, Project Planning & Scheduling

    Contract Administration, Claim Management, Progress Payment

    Construction & Safety Method Statements

    Variation, Claims & Extension of Time

    Contracts Close out, Defect liability & maintenance

    Scope of Technical Audit Slide 1/2

    12

  • 8/11/2019 Technical Audit

    14/33

    Project QA/QC manual

    Project Quality Control Plan / Quality manual

    Project Quality Procedures

    Site inspection reports

    Inspection and test plan

    Test reports

    Non conformance report

    Material delivered/used and compliance to specification

    Safety Risk assessments and compliance to EHS

    Scope of Technical Audit Slide 2/2

    13

  • 8/11/2019 Technical Audit

    15/33

    Case study

    IIA UAE Regional Conference, March 2014

    Tender

    14

  • 8/11/2019 Technical Audit

    16/33

    Scope added to attract more contractors andachieve competitive rates

    Deleted after a month

    Instruction issued after a month

    Work deleted preliminaries not recovered

    Awarded to single source based on per unit area 9 different types of buildings

    Contract drawings were available for 8 types

    Awarded single source, lump sum, per square meter basis

    Constructed area was less then calculated area

    15

  • 8/11/2019 Technical Audit

    17/33

    Case study

    Value Engineering

    16

  • 8/11/2019 Technical Audit

    18/33

    Alternate material approved for cost savings

    Bituminous membrane with protection board

    Replaced with cementatious water proofing material

    No test for Chloride and Sulphide resistance

    Method of construction and project cost

    Bridge redesign due to change in pier spacing Changed from Cast in situ to post tension

    Contractor offered 20 million savings

    Post tender value engineering, scope deleted, cost not

    adjusted 10 items deleted from scope

    Cost and quantity adjusted for 6 items

    4 items no change, Project was lump sum

    17

  • 8/11/2019 Technical Audit

    19/33

    Case study

    Project Schedule

    18

  • 8/11/2019 Technical Audit

    20/33

    Acceleration not achieved but cost paid

    Project completion was moved forward for 3 months

    Works completed 2 months from the original completion date

    Acceleration cost paid in terms of full over time, cost of material,full equipment rent, additional material etc

    Extension of time approved, penalties not

    applied Contract was delayed , Scope reduced

    Contractors delays not considered

    Final result 5% penalty applied

    Method of construction changed for time saving

    Cast in situ to pre cast, no cast saving, only time saving

    Not considered in EOT assessment

    19

  • 8/11/2019 Technical Audit

    21/33

    Case study

    Scope Changes

    20

  • 8/11/2019 Technical Audit

    22/33

    Variation with additional preliminaries issued in

    re measurable contract Developer added parallel parking

    Works were within 20% (variation limit)

    Variation issued with prelims for road diversions, additionallighting etc.

    Variation issued for original work

    Contractor to select the method of reclamation to negateadditional compaction

    Results were not satisfactory Contractor applied for variation for ground improvement works

    Ground improvement is not compaction, method use is Vibrocompaction

    21

  • 8/11/2019 Technical Audit

    23/33

    Case study

    Final settlement

    22

  • 8/11/2019 Technical Audit

    24/33

    Loss of profit paid violating the contract clause

    20% work deleted 17% new work added,

    No change in project time line

    Preambles No loss of profit will be payable on deleted works

    As built quantities not measured and reconciled

    Re measured contract, same buildings, different contractors

    Final as built quantities were different for both

    Client supplied material was more then installed

    Project completed with savings

    Item deleted cost paid,

    No negative variations issued

    Fire fighting system additional cost

    23

  • 8/11/2019 Technical Audit

    25/33

    Case study

    Quality

    24

  • 8/11/2019 Technical Audit

    26/33

    Non conformance issued and closed withoutaction

    Panel design is not aesthetically matching with adjacent panels

    It is as per approved drawing

    Hence closed with out action

    NCR Corrective actions not agreed withConsultant

    Design and build project

    After repair consultant rejected

    No agreed time line for corrective action

    Material used was manufactured in Chinaspecified was from France

    25

  • 8/11/2019 Technical Audit

    27/33

    Surprise Quality and Safety Inspections

    26

  • 8/11/2019 Technical Audit

    28/33

    Honey comb

    27

  • 8/11/2019 Technical Audit

    29/33

    Asphalt without prime coat

    28

  • 8/11/2019 Technical Audit

    30/33

    Inspection at source

    29

  • 8/11/2019 Technical Audit

    31/33

    Value addition by Innovation

    Control self assessments Formalization ofcommon contract conditions

    Bridging the gap

    Facilitate the lessons learned session

    30

  • 8/11/2019 Technical Audit

    32/33

    [email protected]

    052 918 1299, 02 694 6800Senior Manager, Commercial Assurance,

    PwC, UAE

    Chairman, Construction Audit Subgroup,

    IIA, UAE

  • 8/11/2019 Technical Audit

    33/33

    Experts are at telephone length..

    Thank You

    This publication has been prepared for general guidance on matters of interest only, and does not constituteprofessional advice. You should not act upon the information contained in this publication without obtaining specificprofessional advice. No representation or warranty (express or implied) is given as to the accuracy or completeness ofthe information contained in this publication, and, to the extent permitted by law, PwC, UAE, its members, employeesand agents do not accept or assume any liability, responsibility or duty of care for any consequences of you or anyoneelse acting, or refraining to act, in reliance on the information contained in this publication or for any decision basedon it. 2014 PwC, UAE. All rights reserved. In this document, PwC refers to PwC, UAE which is a member firm ofPricewaterhouseCoopers International Limited, each member firm of which is a separate legal entity.

    33