technical audit
TRANSCRIPT
-
8/11/2019 Technical Audit
1/33
-
8/11/2019 Technical Audit
2/33
Agenda
1
-
8/11/2019 Technical Audit
3/33
1. Ground Rules
2. Construction Project Stakeholders
3. Technical v/s Operational Audit of Construction projects
4. Reasons for auditing construction projects
5. Type & Scope of Construction Project Audit
6. Case studies
7. Surprise Quality and Safety Inspections
8. Value addition by Innovation
9. Questions
2
-
8/11/2019 Technical Audit
4/33
Ground Rules
3
-
8/11/2019 Technical Audit
5/33
The real life case studies presented are based
on actual events but modified forconfidentiality purposes
Case studies are selected from presenters 29
years of work experience Mobiles on silent mode please
Questions at the end of presentation orthrough email
4
-
8/11/2019 Technical Audit
6/33
Construction Project Stakeholders
5
-
8/11/2019 Technical Audit
7/33
I smellmoney
The Contractor
I amalways
right
Third Parties
What isyour
scope?
Auditor
6
-
8/11/2019 Technical Audit
8/33
Technical v/s Operational Audit of
Construction projects
7
-
8/11/2019 Technical Audit
9/33
Normal audit teams generally consist of internal auditors with afinancial background
Technical audit teams consist of Engineers, Quantity Surveyors,Planning Engineers, Contract Specialists, QA - QC Experts andalso include internal auditors with financial background
Normal audit teams verify general compliance to the policies and
procedures Technical teams verify compliance to the contractual requirement
- contracts, specifications, codes and standards
Quality and EHS site visits can be conducted by technical auditors
8
-
8/11/2019 Technical Audit
10/33
Reasons for auditing
construction projects
9
-
8/11/2019 Technical Audit
11/33
-
8/11/2019 Technical Audit
12/33
Type & Scope of Construction
Project Audit
1211
-
8/11/2019 Technical Audit
13/33
Project Development/Feasibility Master Plan & Design Brief
Compliance to regulatory authority
Type & conditions of contract
Tender & Contract
Value Engineering, Project Planning & Scheduling
Contract Administration, Claim Management, Progress Payment
Construction & Safety Method Statements
Variation, Claims & Extension of Time
Contracts Close out, Defect liability & maintenance
Scope of Technical Audit Slide 1/2
12
-
8/11/2019 Technical Audit
14/33
Project QA/QC manual
Project Quality Control Plan / Quality manual
Project Quality Procedures
Site inspection reports
Inspection and test plan
Test reports
Non conformance report
Material delivered/used and compliance to specification
Safety Risk assessments and compliance to EHS
Scope of Technical Audit Slide 2/2
13
-
8/11/2019 Technical Audit
15/33
Case study
IIA UAE Regional Conference, March 2014
Tender
14
-
8/11/2019 Technical Audit
16/33
Scope added to attract more contractors andachieve competitive rates
Deleted after a month
Instruction issued after a month
Work deleted preliminaries not recovered
Awarded to single source based on per unit area 9 different types of buildings
Contract drawings were available for 8 types
Awarded single source, lump sum, per square meter basis
Constructed area was less then calculated area
15
-
8/11/2019 Technical Audit
17/33
Case study
Value Engineering
16
-
8/11/2019 Technical Audit
18/33
Alternate material approved for cost savings
Bituminous membrane with protection board
Replaced with cementatious water proofing material
No test for Chloride and Sulphide resistance
Method of construction and project cost
Bridge redesign due to change in pier spacing Changed from Cast in situ to post tension
Contractor offered 20 million savings
Post tender value engineering, scope deleted, cost not
adjusted 10 items deleted from scope
Cost and quantity adjusted for 6 items
4 items no change, Project was lump sum
17
-
8/11/2019 Technical Audit
19/33
Case study
Project Schedule
18
-
8/11/2019 Technical Audit
20/33
Acceleration not achieved but cost paid
Project completion was moved forward for 3 months
Works completed 2 months from the original completion date
Acceleration cost paid in terms of full over time, cost of material,full equipment rent, additional material etc
Extension of time approved, penalties not
applied Contract was delayed , Scope reduced
Contractors delays not considered
Final result 5% penalty applied
Method of construction changed for time saving
Cast in situ to pre cast, no cast saving, only time saving
Not considered in EOT assessment
19
-
8/11/2019 Technical Audit
21/33
Case study
Scope Changes
20
-
8/11/2019 Technical Audit
22/33
Variation with additional preliminaries issued in
re measurable contract Developer added parallel parking
Works were within 20% (variation limit)
Variation issued with prelims for road diversions, additionallighting etc.
Variation issued for original work
Contractor to select the method of reclamation to negateadditional compaction
Results were not satisfactory Contractor applied for variation for ground improvement works
Ground improvement is not compaction, method use is Vibrocompaction
21
-
8/11/2019 Technical Audit
23/33
Case study
Final settlement
22
-
8/11/2019 Technical Audit
24/33
Loss of profit paid violating the contract clause
20% work deleted 17% new work added,
No change in project time line
Preambles No loss of profit will be payable on deleted works
As built quantities not measured and reconciled
Re measured contract, same buildings, different contractors
Final as built quantities were different for both
Client supplied material was more then installed
Project completed with savings
Item deleted cost paid,
No negative variations issued
Fire fighting system additional cost
23
-
8/11/2019 Technical Audit
25/33
Case study
Quality
24
-
8/11/2019 Technical Audit
26/33
Non conformance issued and closed withoutaction
Panel design is not aesthetically matching with adjacent panels
It is as per approved drawing
Hence closed with out action
NCR Corrective actions not agreed withConsultant
Design and build project
After repair consultant rejected
No agreed time line for corrective action
Material used was manufactured in Chinaspecified was from France
25
-
8/11/2019 Technical Audit
27/33
Surprise Quality and Safety Inspections
26
-
8/11/2019 Technical Audit
28/33
Honey comb
27
-
8/11/2019 Technical Audit
29/33
Asphalt without prime coat
28
-
8/11/2019 Technical Audit
30/33
Inspection at source
29
-
8/11/2019 Technical Audit
31/33
Value addition by Innovation
Control self assessments Formalization ofcommon contract conditions
Bridging the gap
Facilitate the lessons learned session
30
-
8/11/2019 Technical Audit
32/33
052 918 1299, 02 694 6800Senior Manager, Commercial Assurance,
PwC, UAE
Chairman, Construction Audit Subgroup,
IIA, UAE
-
8/11/2019 Technical Audit
33/33
Experts are at telephone length..
Thank You
This publication has been prepared for general guidance on matters of interest only, and does not constituteprofessional advice. You should not act upon the information contained in this publication without obtaining specificprofessional advice. No representation or warranty (express or implied) is given as to the accuracy or completeness ofthe information contained in this publication, and, to the extent permitted by law, PwC, UAE, its members, employeesand agents do not accept or assume any liability, responsibility or duty of care for any consequences of you or anyoneelse acting, or refraining to act, in reliance on the information contained in this publication or for any decision basedon it. 2014 PwC, UAE. All rights reserved. In this document, PwC refers to PwC, UAE which is a member firm ofPricewaterhouseCoopers International Limited, each member firm of which is a separate legal entity.
33