teck 2017 investor and analyst day

136
Investor and Analyst Day March 30, 2017

Upload: teckresourcesltd

Post on 09-Apr-2017

1.015 views

Category:

Investor Relations


1 download

TRANSCRIPT

Page 1: Teck 2017 Investor and Analyst Day

Investor and Analyst DayMarch 30, 2017

Page 2: Teck 2017 Investor and Analyst Day

Introduction

Forward Looking InformationBoth these slides and the accompanying oral presentation contain certain forward-looking statements within the meaning of the United States Private SecuritiesLitigation Reform Act of 1995 and forward-looking information within the meaning of the Securities Act (Ontario) and comparable legislation in other provinces.Forward-looking statements can be identified by the use of words such as “plans”, “expects” or “does not expect”, “is expected”, “budget”, “scheduled”,“estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”, or “believes”, or variation of such words and phrases or state that certain actions, eventsor results “may”, “could”, “should”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements involve known and unknown risks,uncertainties and other factors which may cause the actual results, performance or achievements of Teck to be materially different from any future results,performance or achievements expressed or implied by the forward-looking statements. These forward-looking statements include Adjusted EBITDA as reportedin the slides, statements relating to management’s expectations with respect to 2017 capital expenditure guidance and the components thereof, potentialEBITDA, our expectation that our Energy business unit will start contributing to EBITDA in 2018 and 2017 production and site cost guidance and the componentsthereof, benefits of our steelmaking coal operating strategy and the potential benefits of the anticipated synergies, projected strip ratios, projected 2017 totalcosts, projected 2017 truck productivity, projected 2017 mining and maintenance costs, projected 2017 sustaining capital costs, the objectives for oursteelmaking coal five year plan, the statement that steelmaking coal is a high margin business and the statement that Teck is planning to produce approximately27 million tonnes of coal for decades. These for forward-looking statements with respect to our base metals business unit include statements relating tomanagement’s expectations with respect to the goals and benefits of the base metals unit operating strategy, projected mill throughput, projected C1 unit costs,projected copper production and grade at Highland Valley and the plans to extend the mine life and enhance production at the operation, Antamina copper andzinc production guidance, CDA mill throughput and grade projection, the project projections and guidance on the “Quebrada Blanca Phase 2 Project” and“NuevaUnión Project” slides, projected throughput and grade at Red Dog, the statement that there is excellent extension potential at Red Dog, projected zinc andlead production performance at Trail and our goals for increasing value in base metals, statements relating to Fort Hills including statements relating tomanagement’s expectations with respect to production capacity and scheduling, expectations about the timing and budget to project completion and thestatement that Fort Hills is expected to generate 45 years of cash flows. These forward-looking statements relating to project delivery include the statement thatTeck is well positioned to deliver Quebrada Blanca Phase 2, including that the structure and systems are in place to ensure critical elements for success areaddressed, Teck’s expectations to demand, price, production and volatility of the commodities that we produce, as well as expectation that the energy market willbalance in 2017, WTI price expectations, anticipated energy supply shortfall, expected ramp-up time and Teck share of production relating to Fort Hills and ourapproach to market access for Fort Hills production, Teck’s long-term strategy, potential EBITDA, our expectation that our Energy business unit will startcontributing to EBITDA in 2018, the potential future growth options for Teck, projections regarding Quebrada Blanca Phase 2 copper production, costs, mine lifeand capital intensity, the benefits of our approach on NuevaUnión, projections and expectations regarding our Satellite Project, statements and expectationsregarding each of the projects included in Satellite Project, as well as the mineral resource, capital intensity and costs regarding each of our projects.Assumptions regarding Fort Hills also include the assumption that project development and funding proceed as planned, as well as assumptions noted on therelevant slides discussing Fort Hills.

These forward-looking statements involve numerous assumptions, risks and uncertainties and actual results may vary materially. These statements are based ona number of assumptions, including, but not limited to, assumptions noted in the various slides and oral presentation, assumptions regarding general businessand economic conditions, interest rates, the supply and demand for, inventories of, and the level and volatility of prices of coal, zinc, copper and gold and otherprimary metals and minerals produced by Teck as well as steel, oil, natural gas and petroleum, power prices, market competition, the accuracy of Teck’s reserveand resource estimates (including with respect to size, grade and recoverability) and the geological, operational and price assumptions on which these arebased, the resolution of environmental and other proceedings, our ongoing relations with our employees and partners and joint venturers, and the future

Page 3: Teck 2017 Investor and Analyst Day

Introduction

Forward Looking Informationoperational and financial performance of the company generally. The foregoing list of assumptions is not exhaustive. Adjusted EBITDA, potential EBITDA andfinancial metrics and ratios are based on or assume exchange rates, sales, commodity prices and production as disclosed in the footnotes associated with therelevant EBITDA metric and ratio. Assumptions regarding Quebrada Blanca Phase 2 and NuevaUnión include that the project is built and operated in accordancewith the current project plans and all permits are timely received. The foregoing list of assumptions is not exhaustive.

Events or circumstances could cause actual results to differ materially. Factors that may cause actual results to vary include, but are not limited to: factors notedin the various slides and oral presentation, unanticipated developments in business and economic conditions in the principal markets for Teck’s products or in thesupply, demand, and prices for metals and other commodities to be produced, changes in power prices, changes in interest or currency exchange rates,inaccurate geological or metallurgical assumptions (including with respect to the size, grade and recoverability of mineral or oil and gas reserves and resources),changes in taxation laws or tax authority assessing practices, legal disputes or unanticipated outcomes of legal proceedings, unanticipated operational difficulties(including failure of plant, equipment or processes to operate in accordance with specifications or expectations, cost escalation, unavailability of materials andequipment, government action or delays in the receipt of permits or government approvals, industrial disturbances or other job action, and unanticipated eventsrelated to health, safety and environmental matters), assumptions used to generate our economic analysis, decisions made by our partners or co-venturers,political events, social unrest, lack of available financing for Teck or its partners or co-venturers, and changes in general economic conditions or conditions in thefinancial markets. The amount and timing of actual capital expenditures is dependent upon, among other matters, being able to secure permits, equipment,supplies, materials and labour on a timely basis and at expected costs to enable the related capital project to be completed as currently anticipated. Fort Hills,Quebrada Blanca and NuevaUnión are jointly owned.

We assume no obligation to update forward-looking statements except as required under securities laws. Further information concerning assumptions, risks anduncertainties associated with these forward-looking statements and our business can be found in our Annual Information Form for the year ended December 31,2016, filed under our profile on SEDAR (www.sedar.com) and on EDGAR (www.sec.gov) under cover of Form 40-F, and management discussion and analysisreports and other public filings filed on www.sedar.com or www.sec.gov.

Page 4: Teck 2017 Investor and Analyst Day

Overview and StrategyMarch 30, 2017Don Lindsay, President and Chief Executive Officer

Page 5: Teck 2017 Investor and Analyst Day

Overview and Strategy

Safety at Teck

• Improved performance across safety metrics in 2016

• High Potential Injury frequency reduced by ~50% since 2013

Next phase of Courageous Safety Leadership

rolled out across operations

0

0.2

0.4

0.6

0.8

1

1.2

2013 2014 2015 2016

Freq

uenc

y (p

er 2

00,0

00 h

ours

wor

ked)

YTD High Potential Incident Frequency - Level 3YTD Serious High Potential Incident Frequency - Level 4YTD Potentially Fatal Occurrence Frequency - Level 5

High Potential Incident Frequency

3

Page 6: Teck 2017 Investor and Analyst Day

Overview and Strategy

Sustainability Highlights

Indigenous Relations

• 25 new agreements in 2016; agreements in place at all operations

• Major IBA signed with Ktunaxa Nation, strengthening certainty for Elk Valley coal operations

• Three agreements reached to date for Frontier Project

Tailings Management

• Follow industry best practices

• Independent tailings review boards for all major facilities & projects

• New internal governance reviews in addition to external facility inspections

• Contributed to MAC & ICMM tailings management reviews

4

Page 7: Teck 2017 Investor and Analyst Day

Overview and Strategy

Senior Management Update

Greg WallerSVP, Investor Relations

& Strategic Analysis

Fraser PhillipsSVP, Investor Relations

& Strategic Analysis

Retiring Joining

5

Page 8: Teck 2017 Investor and Analyst Day

Overview and Strategy

Capitalizing on the Turn in the Cycle

6

• Record results in Q4 2016Gross Profit $2.0 billionCash Flow from Ops $1.5 billionAdjusted Net Profit1 $930 million

• Generating significant cash flow• Reducing debt • Dividend review

1. Adjusted profit attributable to shareholders. Non-GAAP financial measures. See “Use of Non-GAAP Financial Measures” section of our quarterly news releases for further information.

Page 9: Teck 2017 Investor and Analyst Day

Diversified business model

Attractive portfolio of long life assets

Low half of the cost curve

Appropriate scale

Low risk jurisdictions

Overview and Strategy

Consistent Long-Term Strategy

7

Page 10: Teck 2017 Investor and Analyst Day

Overview and Strategy

Significant Cash Flow Generation

Potential EBITDA1

Less: Corporate

Steelmaking Coal

Copper

Zinc

1. Non-GAAP financial measures. See “Use of Non-GAAP Financial Measures” section of our quarterly news releases for further information. Estimates are based on the mid-point of our2017 production guidance ranges and assume a C$/US$ exchange rate of 1.30 and our typical steelmaking coal sales mix of 40% contract and 60% spot. The steelmaking coal priceassumption is based on a combination of the Q1 2017 expected realized price of US$200 to US$215 per tonne, and an assumed quarterly contract benchmark price of US$155per tonne and an average realized price of 92% of the contract price for the balance of the year. Base metal price assumptions are based on the 2017 year to date average copper priceof US$2.60 per pound and average zinc price of US$1.25 per pound. Actual prices will vary, and operating performance and sales may vary materially for a variety of reasons, causingthese production and sales estimates to be materially incorrect. These estimates are based on numerous assumptions, and are subject to various risks and uncertainties that may causeresults to vary materially. Please see the Cautionary Note on Forward-Looking Information at the beginning of this presentation for more specific information.

• Strong operating margins

• Increasing zinc production

• Significant leverage to coal, copper and zinc prices

2017 Based on Current Prices

Energy starts contributing EBITDA1 in 2018

>C$5 Billion

8

Page 11: Teck 2017 Investor and Analyst Day

Strong platform combined with diverse portfolio of options allows us to be selective for risk/reward opportunity and timing

Overview and Strategy

Staged Growth/Value Pipeline

In Construction Pre-Sanction

EnergyBuilding a new business through partnership

Fort Hills Frontier

Lease 421

Future OptionsMedium-Term Growth Options

ZincWorld-class resource combined with integrated assets

Red DogSatellite Deposits

Cirque

Trail #2 Acid Plant

Red DogMill Optimization

Teena

CoalWell established with capital efficient value options

Elk Valley Replacement Brownfield Quintette/Mt. Duke

Elk Valley Brownfield

Neptune Terminals to >18Mtpa Coal Mountain 2

CopperStrong platform with substantial growth options

San Nicolás (Cu-Zn)

QB Phase 2 NuevaUnión Mesaba

ZafranalHVC Brownfield

Schaft Creek

Antamina Brownfield

Galore Creek

9

Page 12: Teck 2017 Investor and Analyst Day

Overview and Strategy

Quebrada Blanca 2: Potential Tier 1 Asset

Top 15 copper producer globally‒ 300 ktpa copper equivalent production in first 5 years

Total costs (AISC) well in low half of cost curve‒ Exceptionally low strip ratio

Initial mine life 25 years with ~25% of reserves & resources‒ Optionality for expansion or much longer life

Attractive capital intensity‒ Development capital costs reduced significantly

Familiar, mining-friendly jurisdiction

10

Page 13: Teck 2017 Investor and Analyst Day

Overview and Strategy

NuevaUnión: A New Approach to Project Development

Teck and Goldcorp have combined Relincho & El Morro projects and formed a 50/50 joint venture company• Committed to building strong, mutually

beneficial relationships with stakeholders & communities

Capital smart partnership • Shared capital, common infrastructure• Shared risk, shared rewards

Benefits of combining projects include:• Longer mine life• Lower cost, improved capital efficiency• Reduced environmental footprint• Enhanced community benefits• Greater returns over either standalone project

11

Page 14: Teck 2017 Investor and Analyst Day

Overview and Strategy

Satellite Project: Overview

• Situation: Strong base metal (copper, zinc) growth options largely invisible to the market

• Objective: To surface the value of Teck’s copper development projects (ex-QB2 & NuevaUnión) in 3-5 years

• Routes to value realization include:‒ Prudent funding to increase certainty of

development‒ Work with development partner(s) to

advance in a timely manner‒ IPO, sell down and/or divest at the

appropriate time ‒ Build as a Teck project

• Led by Colin Joudrie, VP Business Development

Staged Growth/Value Pipeline

Future Options

ZincWorld-class resource combined with integrated assets

CopperStrong platform with substantial growth options

San Nicolás (Cu-Zn)

Mesaba

Zafranal

Schaft Creek

Galore Creek

12

Page 15: Teck 2017 Investor and Analyst Day

Overview and Strategy

Satellite Project: 5 Quality Base Metal Assets

Galore Creek (50%)• Rare significant copper-gold-silver

deposit in developing district• High average grade; potential for

first quartile C1 costs• Substantial design and engineering

work completed in 2012

Schaft Creek (75%)• Large copper-molybdenum-gold-

silver deposit • Long mine life; potential expansion• Continue to advance value added

field work, along with desk-top engineering and optimization studies

San Nicolás (79%)• High grade, open pit operation with

3-4 year timeline to production• Low first quartile costs, offering

quick payback• 2016 drill program and scoping

study improved understanding and augmented value

Mesaba (100%) • Very large copper‐nickel sulphide

resource• In a district with long mining history• Proximity to existing infrastructure,

and opportunities for significant development synergies

• Teck developed proprietary value-added mineral processing technology

Zafranal (80%)• Highly competitive mid-sized

copper-gold deposit• Pre-feasibility study published June

2016; indicates robust economics• Advancing Feasibility and

Environmental Impact Studies in 2017-2018

Substantial resources in mining friendly jurisdictions 13

Page 16: Teck 2017 Investor and Analyst Day

• Continuing to execute for higher production per share− No equity dilution− No operating assets sold− Investing in production growth from Fort Hills− Maintaining strong liquidity− Reducing debt & managing maturities

• Record quarterly results in Q4 2016

• Generating significant free cash flow

• Reducing debt

• High quality organic growth options

Overview and Strategy

Summary

14

Page 17: Teck 2017 Investor and Analyst Day

FinanceMarch 30, 2017Ron Millos, SVP Finance and Chief Financial Officer

Page 18: Teck 2017 Investor and Analyst Day

Achieved significant debt reduction

Generating significant cash flow

Disciplined capital spending

3

Finance

Financial Resources for the Future

Page 19: Teck 2017 Investor and Analyst Day

Finance

Achieved Significant Debt Reduction

1. As at March 8, 2017.2. Proforma ratio, excluding loss on debt repurchase. Our revolving credit facility requires a debt to debt-plus-equity ratio of <50%. Non-GAAP financial measures. See “Use of Non-GAAP

Financial Measures” section of our quarterly news releases for further information.

Notes Outstanding

Current Debt Portfolio1

Public notes outstanding US$5.1B

Average coupon 5.7%

Annual interest savings ~US$55M

Weighted average term to maturity ~15 years

Debt to debt-plus-equity ratio2 ~28%

Undrawn credit facility US$3.0B

Tender offer to purchase US$1B of outstanding public notes completed on March 8, 2016

4.0

4.5

5.0

5.5

6.0

6.5

7.0

7.5

30/09/2015 31/12/2015 30/09/2016 31/12/2016 31/03/2017

US$

Bill

ion

4

Page 20: Teck 2017 Investor and Analyst Day

Finance

Re-aligning Our Capital Structure

Current Dec. 31, 2012

Notes outstanding ~US$5.1B1 US$7.2BAssets $35.6B2 $34.6BEquity $17.6B2 $18.0BAdjusted EBITDA3 >$5B4 $4.3BRatios

Debt-to-debt plus equity3 ~27%1,5 29%Debt/EBITDA3 ~1.4x1,5 1.7x

1. As at March 8, 2017. 2. As at December 31, 2016.3. Non-GAAP financial measures. See “Use of Non-GAAP Financial Measures” section of our quarterly news releases for further information.4. EBITDA potential in 2017. Estimates are based on the mid-point of our 2017 production guidance ranges and assume a C$/US$ exchange rate of 1.30 and our typical steelmaking coal sales mix

of 40% contract and 60% spot. The steelmaking coal price assumption is based on a combination of the Q1 2017 expected realized price of US$200 to US$215 per tonne, and an assumed quarterly contract benchmark price of US$155 per tonne and an average realized price of 92% of the contract price for the balance of the year. Base metal price assumptions are based on the 2017 year to date average copper price of US$2.60 per pound and average zinc price of US$1.25 per pound. Actual prices will vary, and operating performance and sales may vary materially for a variety of reasons, causing these production and sales estimates to be materially incorrect. These estimates are based on numerous assumptions, and are subject to various risks and uncertainties that may cause results to vary materially. Please see the Cautionary Note on Forward-Looking Information at the beginning of this presentation for more specific information.

5. Proforma ratios, excluding loss on debt repurchase. Assumes a C$ to US$ exchange rate of 1.00 on December 31, 2012 and 1.34 currently.

5

Page 21: Teck 2017 Investor and Analyst Day

Finance

Higher Margin Despite Lower Prices

6 1 Before depreciation and amortization.* The Teck Commodities Index reflects an equal weighting of steelmaking coal, copper and zinc prices, with each price rebased to 100 in 2014.

• Average commodity prices dropped 11% in 2014-2016

• 8-point margin improvement, driven by cost management program‒ Implemented in 2013‒ Focused on productivity‒ Reduced unit costs ‒ Lowered corporate costs

Gross Profit Margin1 vs. Indexed Prices

Gro

ss p

rofit

mar

gin

(%)

Teck

Com

mod

ity P

rice

Inde

x

0.60

0.70

0.80

0.90

1.00

10%

20%

30%

40%

50%

2014 2015 2016

Gross Profit Margin (lhs) Teck Commodities Index* (rhs)

6

Page 22: Teck 2017 Investor and Analyst Day

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

2012 2013 2014 2015 2016 2017Guidance

New MineDevelopment

MajorEnhancements

Sustaining Capital

CapitalizedStripping

$M

Finance

Capital Expenditures

Total Capital Expenditures 2012-2017

7

Page 23: Teck 2017 Investor and Analyst Day

Finance

Significant Cash Flow Generation

Potential EBITDA1

Less: Corporate

Steelmaking Coal

Copper

Zinc

1. Non-GAAP financial measures. See “Use of Non-GAAP Financial Measures” section of our quarterly news releases for further information. Estimates are based on the mid-point of our2017 production guidance ranges and assume a C$/US$ exchange rate of 1.30 and our typical steelmaking coal sales mix of 40% contract and 60% spot. The steelmaking coal priceassumption is based on a combination of the Q1 2017 expected realized price of US$200 to US$215 per tonne, and an assumed quarterly contract benchmark price of US$155per tonne and an average realized price of 92% of the contract price for the balance of the year. Base metal price assumptions are based on the 2017 year to date average copper priceof US$2.60 per pound and average zinc price of US$1.25 per pound. Actual prices will vary, and operating performance and sales may vary materially for a variety of reasons, causingthese production and sales estimates to be materially incorrect. These estimates are based on numerous assumptions, and are subject to various risks and uncertainties that may causeresults to vary materially. Please see the Cautionary Note on Forward-Looking Information at the beginning of this presentation for more specific information.

• Strong operating margins

• Increasing zinc production

• Significant leverage to coal, copper and zinc prices

2017 Based on Current Prices

Energy starts contributing EBITDA in 2018

>C$5 Billion

8

Page 24: Teck 2017 Investor and Analyst Day

Finance

Tax Efficient Earnings in Canada

~$6 billion in available tax pools1, including:• $4.6B in loss carryforwards• $1.3B in Canadian Development Expenses

Applies to:• Cash income taxes in Canada

Does not apply to:• Resource taxes in Canada• Cash taxes in foreign jurisdictions

Multiples should reflect tax efficiency of earnings

1. As of December 31, 2016.9

Page 25: Teck 2017 Investor and Analyst Day

Achieved significant debt reduction

Generating significant cash flow

Disciplined capital spending

10

Finance

Financial Resources for the Future

Page 26: Teck 2017 Investor and Analyst Day

Business UnitsMarch 30, 2017Dale Andres, Senior Vice President, Base MetalsRobin Sheremeta, Senior Vice President, Coal

Page 27: Teck 2017 Investor and Analyst Day

Business Units

Agenda

Introduction

Base Metals

Steelmaking Coal

3

Page 28: Teck 2017 Investor and Analyst Day

Business Units

Safety is a Core Value

Our Key Focus Areas1. High Potential Risk Control 2. Occupational Health & Hygiene 3. Courageous Safety Leadership

We are Improving• High Potential Incidents: 12% reduction• Lost Time Injuries: 11% reduction• Total Recordable Injuries: 13% reduction

4

Page 29: Teck 2017 Investor and Analyst Day

Business Units

>$1B of Annualized Savings…

Largest savings from mining productivity

Annualized Savings from Major Cost Reduction Program Initiatives

- $100 $200 $300 $400

Other ($22M)

Components (life/cost) ($12M)

Plan optimization ($51M)

Pricing Improvements ($26M)

Equipment Rental Savings ($28M)

Admin savings ($79M)

Idling & Energy Savings ($66M)

Consumables ($77M)

Employee Cost Reduction ($191M)

Contractors/Consultants Reduction ($216M)

Mining Productivity ($354M)

2013 Initiatives 2014 Initiatives 2015 Initiatives 2016 Initiatives

CAD$ millions

5

Page 30: Teck 2017 Investor and Analyst Day

Business Units

“One Teck” Approach

Using common resources & shared learning to optimize assets & drive value

Our organizational structure enables collaboration, innovation & continual improvement

Driving a “One Teck” philosophy where it adds value• Safety• Tailings & water management• Truck shovel productivity• Strategic & group sourcing• Accelerated Maintenance Projects (AMP)

6

Page 31: Teck 2017 Investor and Analyst Day

Business Units

Innovation Drives How We Manage, Improve & Grow

Manage Improve Grow• Encourage & share front

line innovation• Advanced data analytics

• Automation• Sensor-based ore sorting

• Rethinking projects‒ QB Phase 2

• Partnerships ‒ NuevaUnión

Broad portfolio of existing, emerging & future technologies

7

Page 32: Teck 2017 Investor and Analyst Day

Business Units

Agenda

Introduction

Base Metals

Steelmaking Coal

8

Page 33: Teck 2017 Investor and Analyst Day

Base Metals

Operating Strategy

• Stable operations– Maintain cost discipline

• Improvement priorities driven by value– Long term competitiveness

• Manage risk & seize opportunities– Advance key extension & growth projects

9

Page 34: Teck 2017 Investor and Analyst Day

Base Metals

Continued Cost Focus in Copper

-

0.50

1.00

1.50

2.00

2.50

2012 2013 2014 2015 2016 2017

US$

/lb

C1 Unit Costs

After by-product credits Before by-products credits

• Focused mill throughput improvements− Additional 9% increase in 2017− Mitigating lower ore grades

• Significant benefits from cost reductions− Higher unit costs in 2017 due to lower

production phase at Highland Valley

Positioning our copper business for the future

0.30

0.35

0.40

0.45

0.50

50

60

70

80

90

2012 2013 2014 2015 2016 2017 2018-2020

Gra

de (%

)

Tonn

es (m

illion

s)

Mill Throughput

Throughput Grade

Mill throughput excludes Duck Pond which was permanently closed in July 2015. Unit cost guidance is based on the mid-point of guidance.10

Page 35: Teck 2017 Investor and Analyst Day

Base Metals

Highland Valley at Inflection Point

Focusing on cost and productivity improvements to unlock extension potential

• Lower grade Lornex & Highmont in 2017−Continued cost reduction efforts−Tailings construction to restart

• Advancing plans to extend mine life & enhance production−Add ball mill to grinding circuit to

improve recovery & throughput (~$70 M)−HVC 2040 prefeasibility underway

0.20

0.25

0.30

0.35

0.40

75

100

125

150

175

2012 2013 2014 2015 2016 2017 2018-2020

2021+

Grade (%

)

Cop

per (

kt)

Copper Production & Grade

Copper Production Grade R&R Grade

Guidance numbers are based on the mid-point of production guidance.11

Page 36: Teck 2017 Investor and Analyst Day

Base Metals

Rising Zinc Production at Antamina

• Large zinc production increase expected− >50% in 2017 vs. the last 5 years− Higher ratio of Cu-Zn ore

• Key projects advancing− New truck shop nearing completion− Tailings dam construction of next lift− Mine life extension studies progressing

World class asset delivering results

-

20

40

60

80

100

120

2012 2013 2014 2015 2016 2017 2018-2020

Prod

uctio

n (k

t)

Copper & Zinc Production

Zinc Copper

Guidance numbers are based on the mid-point of production guidance. Production numbers reflect Teck’s 22.5% share.12

Page 37: Teck 2017 Investor and Analyst Day

Base Metals

Chile Operations

• Plant debottlenecking continues at Carmen de Andacollo (CDA)− Offsetting lower grade & harder ore− >8% throughput in 2017, with crushing & other improvements

• Adapting Quebrada Blanca to current conditions− Conversion from heap/dump leach to dump leach only completed Q1 2017

• Community engagement key to success

0.35

0.40

0.45

0.50

0.55

0.60

35

40

45

50

55

60

2012 2013 2014 2015 2016 2017 2018-2020

Gra

de (%

)

Thro

ughp

ut (k

tpd)

CDA Mill Throughput & Grade

Throughput Grade

13

Page 38: Teck 2017 Investor and Analyst Day

Base Metals

Quebrada Blanca Phase 2 Project

Note: Based on Feasibility Study.1. 100% basis, in constant first quarter of 2016 dollars, excluding working capital and interest during construction. Teck owns a 76.5% share.2. Average production rates, copper equivalent production rates, C1 cash costs and initial development capital are based on the first full five years of operations. C1 cash costs are

net of by-product credits.

Project Capital1

US$4.7billion

Copper Equivalent Production2

300,000tonnes per year

Molybdenum Production2

7,700tonnes per year

Mine Life

25+years

Copper in Reserves

14.2billion pounds

C1 Cash Costs2

US$1.28per pound

• Initial mine life uses ~25% of reserves & resources• AISC well in the low half of the cost curve, with low sustaining capex• Permitting on track

14

Page 39: Teck 2017 Investor and Analyst Day

Base Metals

NuevaUnión Project

Initial Project Capital

US$3.5billion

Copper Production1

190,000tonnes per year

Gold Production1

315,000ounces per year

Mine Life

32+years

Copper in Reserves2

16.6billion pounds

Gold in Reserves2

8.9million ounces

Note: Conceptual based on preliminary design from the PEA.1. Average production rates and copper equivalent production are based on the first full ten years of operations.2. Total copper and gold contained in mineral reserves as reported separately by Teck and Goldcorp.3. Capital estimate for Phase 1a based on preliminary design shown in 2015 dollars on an unescalated basis.

• Copper equivalent production of 250 kt per year• Prefeasibility study completion expected at end Q3 2017• Proactive & participatory community engagement approach

15

Page 40: Teck 2017 Investor and Analyst Day

Base Metals

Preparing Red Dog for the Future

• Harder ore & lower grades at Aqqaluk− Higher grade Qanaiyaq pit started

• NANA royalty to 35% in 2H 2017• Advancing studies to maintain current

production levels− Value Improvement Project #2 to

increase throughput by >20%− Maintain mine life to 2032

5

10

15

20

2012 2013 2014 2015 2016 2017 2018-2020

2

3

4

5

Gra

de (%

)

Thro

ughp

ut (M

t)

Throughput to Offset Grade Decline

Throughput Zinc Grade

16

Page 41: Teck 2017 Investor and Analyst Day

Base Metals

Excellent Extension Potential at Red Dog

Focusing on near-mine & district satellite areas, particularly:

• Anarraaq - new mineral resource

• Aktigiruq - 18km drill program

LikSu

Aktigiruq

Anarraaq

AqqalukPaalaaq

MainQanaiyaq

~15 km

17

Page 42: Teck 2017 Investor and Analyst Day

Base Metals

Solid Feed Base & Performance at Trail

• Annual production records set in 2016− Zinc: 312 kt− Lead: 99 kt− Silver: 24 Moz

• Red Dog & Pend Oreille are important feed sources

• Investing in No. 2 Acid Plant− Improved reliability and stability

80

90

100

110

120

2012 2013 2014 2015 2016 2017

% C

ompa

red

with

201

2 B

ase

Solid Production Performance

Zinc Lead

Guidance numbers are based on the mid-point of production guidance.18

Page 43: Teck 2017 Investor and Analyst Day

Base Metals

Increasing Value in Base Metals

• Driving results through operating excellence

• Targeted improvements to enhance value

• Life extension options at core assets

• Advancing QB Phase 2 & NuevaUnión

19

Page 44: Teck 2017 Investor and Analyst Day

Business Units

Agenda

Introduction

Base Metals

Steelmaking Coal

20

Page 45: Teck 2017 Investor and Analyst Day

Steelmaking Coal

Operating Strategy

• Maximize synergies in Elk Valley:– Provides flexibility & optionality

• Sustain:– Top quartile haul truck productivity– Low operating costs

• Achieve:– Top quartile maintenance performance– Maximize plant production

• Reduce operating risk: – Invest in new equipment (e.g. shovel)

21

Page 46: Teck 2017 Investor and Analyst Day

$70

$75

$80

$85

$90

$95

$100

2012 2013 2014 2015 2016 2017

$/to

nne

Total Costs1

Steelmaking Coal

Strip Ratio Supports Future Production

• Low strip ratio in 2016 due timing of permitting

• Strip ratio increase expected in 2017‒ Coal Mountain near end of life‒ New developments have higher

strip ratios & better quality coal• Going forward, strip ratio expected

to trend lower 4

5

6

7

8

9

10

11

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021

Cle

an S

trip

Rat

io

Clean Strip Ratio

1. Total costs are site costs plus transportation costs. 2017 is based on the mid-point of guidance.

~~0

22

Page 47: Teck 2017 Investor and Analyst Day

$3

$4

$5

$6

$7

2012 2013 2014 2015 2016 2017

Cos

t per

BC

MTM

Truck/Shovel Mining Costs1,3 *

Steelmaking Coal

Operating With Excellence • Drive mining productivity improvements

‒ Up 21% in the last 5 years‒ Additional 3% improvement in 2017

• Cost reduction efforts reduced truck/shovel mining costs1,3

‒ Down 16% in the last 5 years‒ Additional 2% reduction in 2017

• Total site costs2,3 down 30% in 2012-2016 60%

70%

80%

90%

100%

110%

2012 2013 2014 2015 2016 2017

Perc

enta

ge o

f Tar

get

Truck Productivity*

Disciplined approach to cost control * 2017 numbers are based on the mid-point of production guidance.1. Truck/shovel mining costs are site costs directly attributable to mining and maintenance excluding processing costs and overhead costs. 2. Total site costs are site costs, inventory write-downs, and capitalized stripping., excluding depreciation.3. Non-GAAP financial measure. See “Use of Non-GAAP Financial Measures” section of our quarterly press releases for further information.

23

Page 48: Teck 2017 Investor and Analyst Day

Steelmaking Coal

Competitive Position on Margin Curve

$(20)

$-

$20

$40

$60

$80

$100

US$

per

Ton

ne

Operating Margin1

Source: Wood Mackenzie

• High quality hard coking coal assets provide strong margins

• Competitive mining costs

• Operations well positioned in a volatile market

Teck

1. Quality-adjusted operating margin, based on Wood Mackenzie’s data set for 2016 and utilizing an FOB port equivalent benchmark price of US$131 per tonne for the highest quality products. Assumes a Canadian dollar to US dollar exchange rate of 1.30 and an Australian dollar to US dollar exchange rate of 1.37.24

Page 49: Teck 2017 Investor and Analyst Day

Steelmaking Coal

Sustaining Capex Supports Long Term Vision

• Investing in mobile equipment lasting >15 years

• Sustaining capital is close to long term average in 2017

• Investing in risk reduction

2017 numbers are based on the mid-point of production guidance.

3.50

11.50

3.50 4.50

11.00

13.00

10.00

6.50

2.50 1.50

5.00

-

2

4

6

8

10

12

14

16

-

50

100

150

200

250

300

350

400

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

$/to

nne

(cle

an)

$M

Steelmaking Coal Sustaining Capital

Long-Term Average

~$7.00/tonne

$140

M

Sustaining Capital (LHS) Sustaining Capital Per Tonne (RHS)

25

Page 50: Teck 2017 Investor and Analyst Day

Steelmaking Coal

Five Year Plan: Sustain 27 Million Tonnes1

Objectives• Manage transition from Coal

Mountain

• Pursue incremental production capacity in remaining Valley mines

• Evaluate Cardinal River mine life extension

• Maintain optionality with Quintette& Coal Mountain Phase 2

1. Subject to market conditions.

-

4

8

12

16

20

24

28

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

Pro

duct

ion

(mill

ion

tonn

es)

Conceptual Production Profile

Fording River Greenhills (80%) ElkviewLine Creek Cardinal River Coal MountainAdditional Elk Valley

26

Page 51: Teck 2017 Investor and Analyst Day

• Safe and productive operations• High margin business• Planning to produce ~27 Mt for decades

27

Steelmaking Coal

Summary

Page 52: Teck 2017 Investor and Analyst Day

ProjectsMarch 30, 2017Tim Watson, SVP, Project Development and Engineering Alex Christopher, SVP, Exploration, Projects and Technical Services

Page 53: Teck 2017 Investor and Analyst Day

Projects

Agenda

Fort Hills

Quebrada Blanca Phase 2

3

Page 54: Teck 2017 Investor and Analyst Day

Fort Hills

Project Overview• Nameplate capacity increased to 194 kbpd• Steady state production increased to 186 kbpd• First oil end of 2017• Expect to achieve 90% of nameplate capacity by end 2018

Source: Fort Hills Energy Limited Partnership, Fall 2016.4

Page 55: Teck 2017 Investor and Analyst Day

Fort Hills

Project Progress

Progress as of February 28, 2017

>80% Construction complete

• Final installation of all modules & process vessels • Ore preparation mechanically complete• 55% progress on first oil scope1

• Site work now focused on piping, electrical & instrumentation

3 of 6 Major project areas turned over to Operations

• Permanent power infrastructure energized• Mine operations on schedule for overburden

stripping & mine development• Mine administration building occupied• Ore preparation plant turned over to Operations

58% Operations personnel hired

• >1,000 operations staff hired • Workforce training systems in place for mining &

process operators• Experienced operations team

1. Facilities required to start Fort Hills oil production from the first train in secondary extraction.5

Page 56: Teck 2017 Investor and Analyst Day

Six Major Project Areas Target Date / Status

1. Mining1 Completed

2. Ore Prep1 Completed

3. Major Infrastructure1 Completed 4. Primary Extraction & Tailings

‒ Primary Extraction‒ Tailings

April 2017August 2017

5. Utilities June 2017

6. Secondary Extraction (First Train) First Oil in December 2017

1. Construction completed. Turned over to operations.2. Facilities required to start Fort Hills oil production from the first train in secondary extraction.

Fort Hills

Major Milestones

Other Milestones Target Date / Status

Power Transmission & Distribution1 Completed

50% First Oil Scope2 Completed

Five of six major project areas tracking to plan

6

Page 57: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1

~5km x ~5km

7

Page 58: Teck 2017 Investor and Analyst Day

Fall 2014

Fall 2015

Fort Hills

Ore Preparation: Crusher

Source: Fort Hills Energy Limited Partnership

1

8

Page 59: Teck 2017 Investor and Analyst Day

Fort Hills

Ore Preparation: Crusher

Fall 2016

Source: Fort Hills Energy Limited Partnership

1

9

Page 60: Teck 2017 Investor and Analyst Day

Fall 2014

Fall 2015

Fort Hills

Ore Preparation: Slurry Prep

Source: Fort Hills Energy Limited Partnership

1

10

Page 61: Teck 2017 Investor and Analyst Day

Fort Hills

Ore Preparation: Slurry Prep

Fall 2016

Source: Fort Hills Energy Limited Partnership

1

11

Page 62: Teck 2017 Investor and Analyst Day

Fort Hills

Ore Preparation: Hydro-Transport Lines

Fall 2016

Source: Fort Hills Energy Limited Partnership

1

12

Page 63: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1 2Primary Extraction & Tailings

~5km x ~5km

13

Page 64: Teck 2017 Investor and Analyst Day

Fort Hills

Primary Extraction: Primary Separation Cell

Fall 2014

Fall 2015

Source: Fort Hills Energy Limited Partnership

2

14

Page 65: Teck 2017 Investor and Analyst Day

Fort Hills

Primary Extraction: Primary Separation Cell

Fall 2016

Source: Fort Hills Energy Limited Partnership

2

15

Page 66: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1

3

Utilities

2Primary Extraction & Tailings

~5km x ~5km

16

Page 67: Teck 2017 Investor and Analyst Day

Fall 2015

Fall 2014

Fort Hills

Utilities

Source: Fort Hills Energy Limited Partnership

3

17

Page 68: Teck 2017 Investor and Analyst Day

Fort Hills

Utilities

Fall 2016

Source: Fort Hills Energy Limited Partnership

3

18

Page 69: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1

3

Utilities

River Water Intake4

2Primary Extraction & Tailings

~5km x ~5km

19

Page 70: Teck 2017 Investor and Analyst Day

Fall 2015

Fall 2014

Fort Hills

River Water Intake

Source: Fort Hills Energy Limited Partnership

4

20

Page 71: Teck 2017 Investor and Analyst Day

Fort Hills

River Water Intake

Fall 2016

Source: Fort Hills Energy Limited Partnership

4

21

Page 72: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1

3

Utilities

River Water Intake4

5

Substation

2Primary Extraction & Tailings

~5km x ~5km

22

Page 73: Teck 2017 Investor and Analyst Day

Fort Hills

Main Substation

Fall 2016

Source: Fort Hills Energy Limited Partnership

5

23

Page 74: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1

3

Utilities

River Water Intake4

5

Substation

6

TPL Tank Farm

2Primary Extraction & Tailings

~5km x ~5km

24

Page 75: Teck 2017 Investor and Analyst Day

Fort Hills

Tank Farm: Trans Canada Pipeline Limited

Fall 2016

Source: Fort Hills Energy Limited Partnership

6

25

Page 76: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1

3

Utilities

River Water Intake4

5

Substation

6

TPL Tank Farm

7

EastTank Farm

~50 km

2Primary Extraction & Tailings

~5km x ~5km

26

Page 77: Teck 2017 Investor and Analyst Day

Fort Hills

East Tank Farm

Fall 2016

Source: Fort Hills Energy Limited Partnership

7

27

Page 78: Teck 2017 Investor and Analyst Day

Ore Prep

MINE

Athabasca River

Highway#63

Fort Hills

Site Plot Plan

1

Secondary Extraction83

Utilities

River Water Intake4

5

Substation

6

TPL Tank Farm

7

EastTank Farm

~50 km

2Primary Extraction & Tailings

~5km x ~5km

28

Page 79: Teck 2017 Investor and Analyst Day

Fort Hills

Secondary Extraction Plot Plan

Source: Fort Hills Energy Limited Partnership

8

29

Page 80: Teck 2017 Investor and Analyst Day

Fort Hills

Secondary Extraction Aerial View

Spring 2013

Source: Fort Hills Energy Limited Partnership

8

30

Page 81: Teck 2017 Investor and Analyst Day

Fort Hills

Secondary Extraction

Fall 2014

Fall 2015

Source: Fort Hills Energy Limited Partnership

8

31

Page 82: Teck 2017 Investor and Analyst Day

Fort Hills

Secondary Extraction

Fall 2016

Source: Fort Hills Energy Limited Partnership

8

32

Page 83: Teck 2017 Investor and Analyst Day

Fort Hills

Secondary Extraction

Fall 2016

Source: Fort Hills Energy Limited Partnership

8

33

Page 84: Teck 2017 Investor and Analyst Day

Fort Hills

Secondary Extraction Aerial View

Source: Fort Hills Energy Limited Partnership

Fall 2016

8

34

Page 85: Teck 2017 Investor and Analyst Day

Fort Hills

Summary

• Tracking to plan for first oil at end of 2017• Expect 90% of nameplate capacity by end 2018• Expect to generate 45 years of cash flows from

steady state production of 186 kbpd

Source: Fort Hills Energy Limited Partnership, Fall 2016.35

Page 86: Teck 2017 Investor and Analyst Day

Projects

Agenda

Fort Hills

Quebrada Blanca Phase 2

36

Page 87: Teck 2017 Investor and Analyst Day

Quebrada Blanca Phase 2

Feasibility Study Overview

Project Capital1

US$4.7billion

Capital Intensity2

~US$16,000$/tonnes annual CuEq

C1 Cash Costs2

US$1.28per pound

Note: Based on Feasibility Study.1. 100% basis, in constant first quarter of 2016 dollars, excluding working capital and interest during construction. Teck owns a 76.5% share.2. Average production rates, copper equivalent production rates, C1 cash costs and initial development capital are based on the first full five years of operations. C1 cash costs are

net of by-product credits.

• Competitive capital intensity• Tier 1 metal producer• AISC well in the low half of the cost curve• Very low strip (included as cash cost) and low sustaining capital

Throughput

140,000tonnes per day

Copper Equivalent Production2

300,000tonnes per year

Molybdenum Production2

7,700tonnes per year

37

Page 88: Teck 2017 Investor and Analyst Day

Quebrada Blanca Phase 2

Long Life with Resource Optionality

• LOM Reserves• 1.26 billion tonnes (P&P), at 0.51% Cu and 0.019% Mo

• Resources • 1.32 billion tonnes (M&I), at 0.38% Cu and 0.016% Mo• 2.14 billion tonnes (Inferred) at 0.37% Cu and 0.018% Mo

• Initial mine life uses only ~25% of reserves & resources• Attractive mine life to payback ratio

Initial Mine Life

25years

Copper in Reserves

14.2billion pounds

Copper in Resources

11.1(M&I) 17.5(I)billion pounds

Note: Based on Feasibility Study and NI43-101 disclosure(1) Mineral Reserves are constrained within an optimized pit shell and scheduled using a variable grade cut-off approach based on NSR values that averages US$15.07/t over the planned life of mine. The life-of-mine strip ratio is 0.52.(2) Both Mineral Resource and Mineral Reserve estimates consider long-term commodity prices of US$3.00/lb Cu and US10.0/lb Mo and other assumptions that include: pit slope angles of 30–44º, variable metallurgical recoveries that average approximately 91% for Cu and 76% for Mo and operational costs supported by a Feasibility Study.(3) Mineral Resources are reported using a NSR cut-off of US$10.36/t. Mineral Resources also include mineralization that is within the Mineral Reserves pit between NSR values of US$10.36/t and US$15.07/t which has been classified as Measured and Indicated, as well as material classified as Inferred that is within the Mineral Reserves pit. In addition Mineral Resources include 23.8 million tonnes of hypogene material grading 0.54% copper that has been mined and stockpiled during our existing supergene operations..

38

Page 89: Teck 2017 Investor and Analyst Day

Quebrada Blanca Phase 2

Key Infrastructure Components

• Mine & 140 kt/d concentrator,• Tailings facility for 1.26 Bt• Concentrate pipeline (164 km) • Port & filter plant at Punta Patache• Desal plant & pipeline (160 km) • Supporting roads and infrastructure• 3rd party power and transmission

Common corridor for

• Water pipelines

• Concentrate pipelines

• Power lines

39

Page 90: Teck 2017 Investor and Analyst Day

Quebrada Blanca Phase 2

Existing Site – Expanded Footprint

• Concentrator located west of existing QB mine pit

• QB2 pit is open to east (existing plant site) and at depth

• Waste dumps located north & south of existing pit

• Tailings Management Facility (TMF) located directly south of the concentrator

2 Km

40

Page 91: Teck 2017 Investor and Analyst Day

Quebrada Blanca Phase 2

Project Wide Optimization Since 2012

CONCENTRATOR TAILINGS FACILITY METALLURGY

Increased milling rate+5 kt/d (135 to 140 kt/d)

New Location: 7 km vs 45 km from concentrator

Updated recovery to reflect use of desalinated water

Deleted two ore reclaim feeders and coarse ore stockpile cover

Reduced capacity: 25-year life vs 38-year life

+ 6% Cu recovery (absolute values)+ 19% Mo Recovery

Reduced layout footprint of process facilities PIPELINES PORT

Removed SAG mills discharge screens and optimized pebble

crushing circuit

Reduced Tailings Transport System length by relocating Tailings

Management Facility

Consolidated all port facilities into one area

Changed flotation cells in cleaning circuit

Reduced Reclaim Water System length and optimized use of gravity

flow in the system

Optimized port layout and concentrate storage shed capacity

Eliminated flotation regrind building

Mass Earthworks 18% Concrete 31% Structural Steel 24%41

Page 92: Teck 2017 Investor and Analyst Day

Quebrada Blanca Phase 2

Attractive Production Metrics

Category UnitAnnual Average

First 5 Years

First 10 Years LOM

Mining Total material moved million t 97.7 96.2 82.4

Processing Total ore processed million t 50.7 50.9 50.9Head grade – copper % 0.60% 0.56% 0.51%Head grade – molybdenum % 0.020% 0.021% 0.019%

Production1 Copper production thousand t 275 258 238Molybdenum production thousand t 7.7 8.2 7.3Copper equivalent production thousand t 301 286 262

Cash Costs2 Before by-product credits USD/lb Cu 1.51 1.59 1.64After by-product credits USD/lb Cu 1.28 1.33 1.39

Category UnitTotal(1)

LOM

Capital Costs3 Initial capital costs US $M 4,714Sustaining capital costs US $M 492Closure costs US $M 184

1. Copper equivalent figures are calculated by converting margin from molybdenum by-products into equivalent copper tonnages at project price assumptions.2. C1 cash costs allocate all costs to the payable copper produced and are inclusive of all stripping costs during operations. C1 cash costs after by-product credit are

presented assuming US$10 per pound of molybdenum. 3. Capital based on Q1 2016 pricing, study +/- 15% accuracy. Partial years not included in averages.

42

Page 93: Teck 2017 Investor and Analyst Day

$0

$5,000

$10,000

$15,000

$20,000

$25,000

2008 2009 2010 2011 2012 2013 2014 2015

US$

per

Ann

ual T

onne

CuE

qPr

oduc

tion

Quebrada Blanca Phase 2

Competitive Capital Intensity

Source: Mining Council, Central Bank of Chile, Rothschild

QB2’s capital intensity is comparable with recent Chilean projects

Capital Intensity of Chilean Copper Projects

QB2 Range

43

Page 94: Teck 2017 Investor and Analyst Day

Quebrada Blanca Phase 2

Robust Economics and Tier 1 Attributes

Copper Price (US$ per pound) $2.75 $3.00 $3.25 $3.50Net present value at 8% (US$ millions) 565 1,253 1,932 2,604Internal rate of return (%) 9.7% 11.7% 13.5% 15.2%Payback from first production (years) 6.8 5.8 5.0 4.4

Annual EBITDAFirst Full Five Years (US$M pa) 856 1,002 1,148 1,294First Full Ten Years (US$M pa) 781 918 1,055 1,192Life of Mine (US$ million pa) 685 811 937 1,063

NI 43-101 Case

Long life (25 years plus optionality)Attractive production metrics (top 15 copper producer globally)Low cost (low half of AISC cost curve)Competitive capital intensity (~$16k per tonne)Attractive jurisdiction for long term ownership

44

Page 95: Teck 2017 Investor and Analyst Day

MarketingMarch 30, 2017Andrew Stonkus, Senior Vice President, Marketing and SalesRéal Foley, Vice President, Coal MarketingGlenn Burchnall, Director, Energy Marketing and Logistics

Page 96: Teck 2017 Investor and Analyst Day

Marketing

Agenda

Overview

Steelmaking Coal

Base Metals

Energy

Summary

3

Page 97: Teck 2017 Investor and Analyst Day

Global growth expected to increase to 3.4%, from 3.1% in 2016

• India expected to be the fastest-growing large economy at 7.6%

• China plans to keep growth >6.5%, per the 13th Five Year Plan

• Growth expected to pick up in commodity-exporting emerging markets & developing economies (EMDEs)

• Japan’s growth expected to pick up modestly to 1%1

• US at full employment; US$1 trillion infrastructure package could increase GDP growth to 2.3% in 20172

Global GDP is still growing & may exceed expectations if fiscal stimulus in major economies is implemented

Source: IMF1. EIU forecast of 1% in 2017, fro 0.8% in 2016.2. IMF and EIU forecast GDP growth to increase to 2.3% in 2017, compared with 1.6% in 2016.

Marketing

World Economy in 2017

4

Page 98: Teck 2017 Investor and Analyst Day

• Transition to a more consumer-based economy

• Infrastructure construction remains a key pillar

• Supply-side reforms, e.g. coal and steel capacity reductions

• Copper demand expected to be strong, driven by power grid and new electric vehicle (NEV) sectors

• Zinc demand expected to remain solid, driven by infrastructure (2017E: >US$2 trillion investment) autos & higher zinc intensity

Investment remains the key to achieving growth goals

Marketing

China’s 13th Five-Year Plan

5

Page 99: Teck 2017 Investor and Analyst Day

Marketing

Agenda

Overview

Steelmaking Coal

Base Metals

Energy

Summary

6

Page 100: Teck 2017 Investor and Analyst Day

7

Steelmaking Coal Marketing

Good Market Fundamentals

• Price volatility easing

• Demand growth in emerging markets

• China supply constraints

• Limited restarts

Page 101: Teck 2017 Investor and Analyst Day

Coal Price Assessments

Source: Argus Plotted to March 17, 2017

• Price induced closures globally

• Supply disruptions from weather & temporary mine failures

• Q4 inventory build by mills due to further supply disruption concerns

• Price induced supply response

• Q1 inventory drawdown by mills as no further disruptions

Supply and demand driven volatility

Steelmaking Coal Marketing

Price Volatility Easing

60

90

120

150

180

210

240

270

300

$ / to

nne

Quarterly Contract Settlement Argus FOB Australia

8

Page 102: Teck 2017 Investor and Analyst Day

500

600

700

800

900

$0

$20,000

$40,000

$60,000

$80,000

$100,000

1986

1989

1992

1995

1998

2001

2004

2007

2010

2013

2016

2019

f

Nominal GDP, Billion USD(LHS) Crude Steel Production, Mt(RHS)

Ex-China

Steelmaking Coal Marketing

Improving Steel Demand & Output Globally

Steel Demand

YoY Growth 2017

Global +0.5%

China -2.0%

Developing, ex-China +4%

Developed +1.1%Source: WSA

• Chinese steel demand could be stable given 2017 is a leadership transition year

• Global steel demand expected to grow overall

GDP and Crude Steel Production

500

800

1,100

1,400

1,700

2,000

$0

$40,000

$80,000

$120,000

1986

1991

1996

2001

2006

2011

2016

2021

f

Global

0

300

600

900

$0

$5,000

$10,000

$15,000

$20,000

1986

1989

1992

1995

1998

2001

2004

2007

2010

2013

2016

2019

f

China

Source: WSA, IMF

9

Page 103: Teck 2017 Investor and Analyst Day

25

30

35

40

45

50

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Milli

on to

nnes

Coking coal output 2015 Coking coal output 2016

Seaborne coal utilization increased by ~2 Mt YoY

Source: Fenwei

China's Coking Coal Imports & Stock ChangesChina’s Coking Coal Production

Approximate Period of 276 Operating Days Policy 35

13

3

8

36

24

2

9

0

5

10

15

20

25

30

35

40

Seaborne Landborne Stock at sixports

Stock at sampleend users

Milli

on to

nnes

2015 2016

Steelmaking Coal Marketing

China’s Operating Day Policy Influence on Demand

Source: China Customs, Mysteel(Dec. 31)(Dec. 31)

10

Page 104: Teck 2017 Investor and Analyst Day

Coal Capacity Reduction Target

2017 coal capacity reduction target @ 150Mt

Steel Capacity Reduction Target

140

65

50

25

0

20

40

60

80

100

120

140

160

2016-2020target

2016 actual 2017 target 2018-2020remaining

target

Milli

on to

nnes

800

290

150

360

0

100

200

300

400

500

600

700

800

900

2016-2020target

2016 actual 2017 target 2018-2020remaining

target

Mill

ion

tonn

es

Source: Governmental announcementsSource: Governmental announcements

Steelmaking Coal Marketing

Capacity Reductions Continue in China

11

Page 105: Teck 2017 Investor and Analyst Day

Seaborne Coking Coal Imports

Hegang Project• Inland plant relocating to coastal area• Capacity: crude steel 20Mt• Status: Timeline not announced

Guofeng Project• Inland plant relocating to coastal area• Capacity: crude steel 8Mt, hot metal 8Mt• Status: Construction to be started in 2017;

completion in 2021

Shougang Jingtang Plant• Expansion• Capacity: crude steel 9.4Mt (phase 2)• Status: Construction started in 2015; completion in

2018

Shandong Steel Rizhao Project• Greenfield project• Capacity: crude steel 8.5Mt• Status: Construction started in 2015; completion

in 2017

Liusteel Fangcheng Project• Greenfield project• Capacity: Phase 1 crude steel ~10Mt• Status: Timeline for blast furnace not announced

Large users and coastal steel projects to support seaborne demand

1021 21 22 25

25

39

26

13 11

0

10

20

30

40

50

60

70

2012 2013 2014 2015 2016

Small users 14 large users

Steelmaking Coal Marketing

Large Users Increasing Seaborne Imports

2 projects under construction3 approved projects

Source: China Customs

12

Page 106: Teck 2017 Investor and Analyst Day

Source: CRU; Wood Mackenzie

Seaborne Steelmaking Coal Imports (Average of CRU and Wood Mackenzie, Change 2021 vs. 2016)

China’s import demand is currently stronger,and coastal plants depend on seaborne imports

Steelmaking Coal Marketing

Strong Demand Fundamentals ex. China

265

275

285

295

305

2016 Brazil Vietnam Europe& CIS

India Other 2021,ex.

China

China 2021

Mt

13

Page 107: Teck 2017 Investor and Analyst Day

India’s Hot Metal Capacity; Projects and Operations

Seaborne Steelmaking Coal ImportsRequired to Meet India Hot Metal Production

Seaborne steelmaking coal imports forecasted to increase by >25%

Steelmaking Coal Marketing

Growing India Steelmaking Coal Imports

0

10

20

30

40

50

60

70

80

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

HMP forecast by CRUHMP forecast by Wood MackenzieSeaborne Steelmaking Coal Imports (average Wood Mackenzie and CRU)

Source: WSA, CRU, Wood Mackenzie

Mt

Actual HMP (WSA)

z

14

Page 108: Teck 2017 Investor and Analyst Day

Steelmaking Coal Marketing

Supply Response to Prices

Seaborne Steelmaking Coal Exports (Cumulative change since January 2016 vs. corresponding period in 2015)

Source: Global Trade Atlas, T.Parker, Argus

Steelmaking coal exports still lower than previous period

0

50

100

150

200

250

300

350

-7-6-5-4-3-2-101234

Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17

Australia USA Canada Monthly Avg. of Argus FOB Australia (RHS)

US$

/t

Mt

15

Page 109: Teck 2017 Investor and Analyst Day

• ~14 Mt restarts announced:− ~1/3 is HCC− Gradual implementation expected

• Majority of restarts announced by:− New owners− Junior companies− Mozambique

Steelmaking Coal Marketing

Restarts Coming Gradually

0

2

4

6

8

10

12

14

16

2016 2017 2018 2019 2020

USA Australia Canada Mozambique

Mt

Announced Restarts: Seaborne Steelmaking Coal Exports

Few restart announcements since October 2016

Source: Wood Mackenzie; CRU; company reports

As at March 15, 201716

Page 110: Teck 2017 Investor and Analyst Day

17

Steelmaking Coal Marketing

Good Market Fundamentals

• Prices doubled in past year

• India leading demand growth

• China cutting production capacity

• Seaborne steelmaking coal exports lower in past year

Page 111: Teck 2017 Investor and Analyst Day

Marketing

Agenda

Overview

Steelmaking Coal

Base Metals

Energy

Summary

20

Page 112: Teck 2017 Investor and Analyst Day

21

Base Metals Marketing

Strong Fundamentals

Copper• Global mine production growth slowing• Deficits starting to develop

Zinc• Concentrate market in significant deficit• Smelters cutting production• Reported stocks declining

Page 113: Teck 2017 Investor and Analyst Day

Base Metals Marketing

Slowing Copper Mine Production Growth

10,000

12,000

14,000

16,000

18,000

20,000

22,000

24,000

26,000

28,000

30,000

Thou

sand

Ton

nes

Mine Production SXEW Scrap Demand

Copper Mine Production Peaks in 2019 Uncommitted Projects Increasingly Delayed

Existing and Fully Committed Mines

Committed and operating mine production peaking & replacement projects delayed

Source: Wood Mackenzie, CRU, ICSG, Teck

0

2,000

4,000

6,000

8,000

10,000

12,000

2018FLast Year

2018FToday

2020FLast Year

2020FToday

2022Last Year

2022Today

Thou

sand

Ton

nes

Base Highly Probable Probable Possible

15%in

Base Case

15% in

Base Case

10% in

Base Case

22

Page 114: Teck 2017 Investor and Analyst Day

52% 43%

25%

37%23%

20%

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

11th - 5yr PlanCompleted

12th - 5yr PlanCompleted

13th - 5year PlanEstimate

RM

B tri

llion

Transmission Distribution-Urban Distribution-Rural

Base Metals Marketing

Chinese Copper Demand to Remain Strong

Source: CEC, ICA Source: NEA, ICA

Significant Power Grid Investment

282

202

7148

2119

-7 -75

-100

-50

0

50

100

150

200

250

300

Ktpa

Potential Annual Growth in Most Sectors

23

Page 115: Teck 2017 Investor and Analyst Day

-300

-200

-100

0

100

200

300

400

500

600

Month of Forecast

-300

-200

-100

0

100

200

300

400

500

600

Month of Forecast

Wood Mackenzie 2017 Refined Balance Wood Mackenzie 2018 Refined Balance

Base Metals Marketing

Wood Mackenzie Copper Outlook Moved to DeficitTh

ousa

nd t

onne

s

24

Improved fundamentals supporting stronger prices

2018 market also moved into deficit

Thou

sand

ton

nes

Market now in deficitdespite lower demand

Page 116: Teck 2017 Investor and Analyst Day

Base Metals Marketing

Global Stocks Stable Despite Price Decline

-

50

100

150

200

250

300

350

400

450

500

0

200

400

600

800

1,000

1,200

1,400

1,600

1,800

2011 2012 2013 2014 2015 2016 2017

US¢/lb

Thou

sand

tonn

es

Chinese Bonded LME COMEX SHFE LME Price

• Price correction late 2016 as more balanced market expected

• Total stocks (including bonded), in days of global consumption:‒ Today: 29 days‒ Early 2013: ~45

days‒ Average this decade

~33 days

Copper Stocks

Source: CRU, SHFE, LME, CME, Teck

plotted to mid-March 2017

Lower prices have not translated into increased stocks

25

Page 117: Teck 2017 Investor and Analyst Day

• At 2.1% global demand growth, 521 kt new supply needed annually

• Mine production falls ~230 kt per year after 2019

• Market finely balanced through 2018‒ Could materially change with

similar disruption level as 2015

• Structural deficit starts 2019

• Projects delayed today will not be available by 2019

Forecast Copper Refined Balance

Base Metals Marketing

Long-Term Copper Mine Production Still Needed

Source: ICSG, Wood Mackenzie, Teck

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

1,000

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

Thou

sand

tonn

es

26

Page 118: Teck 2017 Investor and Analyst Day

27

• Global mine production growth slowing

• Demand growth positive

• Deficits starting to develop

• Global stocks are low

• Market needs new projects

Base Metals Marketing

Copper Market Moving to Deficit

Page 119: Teck 2017 Investor and Analyst Day

8,000

10,000

12,000

14,000

16,000

18,000

20,000

2010 2013 2016 2019 2022 2025

Thou

sand

Ton

nes

Mine Production Secondary Demand

Base Metals Marketing

Slowing Zinc Mine Production Growth

Zinc Mine Production Has Peaked Uncommitted Projects Increasingly Delayed

Existing and Fully Committed Mines

Committed and operating mine production peaking & replacement projects delayed

Source: Wood Mackenzie, CRU, ILZSG, Teck

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

2018LastYear

2018Today

2020LastYear

2020Today

2022FLastYear

2022Today

Thou

sand

Ton

nes

Base Highly Probable Probable Possible

28

Page 120: Teck 2017 Investor and Analyst Day

Source: SMM, Antaike, Teck

0

50

100

150

200

250

300

350

400

450

500

Jan-

11

Jul-1

1

Jan-

12

Jul-1

2

Jan-

13

Jul-1

3

Jan-

14

Jul-1

4

Jan-

15

Jul-1

5

Jan-

16

Jul-1

6

Jan-

17

Chinese Zinc Concentrate Port Stocks

Source: Teck, LME, SHFE, RBC

Zinc Treatment Charges

Low concentrate stocks reflected in low TCs

3,000

3,500

4,000

4,500

5,000

5,500

6,000

6,500

0

50

100

150

200

250

Jan-

10Ju

l-10

Jan-

11Ju

l-11

Jan-

12Ju

l-12

Jan-

13Ju

l-13

Jan-

14Ju

l-14

Jan-

15Ju

l-15

Jan-

16Ju

l-16

Jan-

17

Imported spot TCs Domestic spot TCs

kdm

t

Impo

rted

TC ($

/dm

t)

Dom

estic TC (R

MB/t)

Base Metals Marketing

Concentrate Stocks at Historic Lows

29

Page 121: Teck 2017 Investor and Analyst Day

0

200

400

600

800

1,000

1,200

1,400

1,600

1,800

50¢

100¢

150¢

200¢

250¢

LME Stocks SHFE Price

Base Metals Marketing

Zinc Metal Market Moving Towards TightnessU

S¢/lb

Plotted to March 15, 2017

Source: LME/SHFE

Daily Zinc Prices & Stocks

Stocks are drawing down & nearing 2006’s critical level

Stocks inflection point in 2005/2006

Stoc

ks

30

Page 122: Teck 2017 Investor and Analyst Day

Base Metals Marketing

Zinc Stocks Approaching Critical LevelsU

S¢/lb

Data Plotted from 2000 to March 15, 2017Source: LME, SHFE, Wood Mackenzie

Zinc Prices vs. Days of Reported Stocks

• Significant mine closures completed

• Mine production has fallen

• Asian metal production curtailments

• Inventories declining

• Treatment charges have tightened significantly

Days of stocks

50¢

100¢

150¢

200¢

250¢

0 10 20 30 40 50 60 70

2007

2003

2004

20062005

Jan 2014Jan 2013

Jan 2015

Jan 2016

Mar 15, 2017

Dec 31, 2016

31

Page 123: Teck 2017 Investor and Analyst Day

Base Metals Marketing

Committed Zinc Supply Insufficient for Demand

Forecast Zinc Refined Balance

Source: Wood Mackenzie, Teck

• Insufficient mine supply to constrain refined production− 2014-2020: demand increase of

2.8 Mt vs. supply increase 792 kt

• Market in deficit from 2014

• Inventory that has funded the deficit will be depleted in 2017

• Market moving into significant deficit‒ Demand growth projections

outpacing supply response(6,000)

(5,000)

(4,000)

(3,000)

(2,000)

(1,000)

0

1,000

Thou

sand

tonn

es

32

Page 124: Teck 2017 Investor and Analyst Day

33

Base Metals Marketing

Structural Deficits in Zinc

• Concentrate market in significant deficit

• Smelters cutting production

• Short term production restarts needed

• Stocks declining & insufficient to meet demand

Page 125: Teck 2017 Investor and Analyst Day

Marketing

Agenda

Overview

Steelmaking Coal

Base Metals

Energy

Summary

34

Page 126: Teck 2017 Investor and Analyst Day

• Price upside limited by US production growth in short term

• Production cuts & demand growth expected to balance market in 2017

• Consensus expectations for WTI of US$75 per barrel by 2025

Energy Marketing

Market Moving Towards Balance

World Liquid Fuels Production & Consumption

-3

-1

1

3

5

84

88

92

96

100

mbp

d

Implied stock change and balance (right axis)World production (left axis)World consumption (left axis)

Source: EIA Short Term Energy Outlook March 2017

North American Rig Count & US Production

5000

6000

7000

8000

9000

10000

200

700

1,200

1,700

Jan-

11

Jan-

12

Jan-

13

Jan-

14

Jan-

15

Jan-

16

Jan-

17

kbpd

Rig

cou

nt u

nits

US Rig Count CAD Rig Count US 4-week Production Avg.

Source: Baker Hughes, EIA

WTI Benchmark Price (US$/bbl)

Source: IHS, Sproule, Deloitte

$0$20$40$60$80

$100$120

US$

/bbl

2014-2016 Historical 2017-2025 Forecast (Real $)

35

Page 127: Teck 2017 Investor and Analyst Day

Strategic Objectives• Successful commissioning & start-up• 12-month ramp up to 90% capacity • Maximize sales volumes & bitumen netbacks• Market diversification

Energy Marketing

Guiding Principles for Fort Hills Marketing

Key Commercial Activities• Bitumen production*: 37 kbpd• Diluent acquisition: 11 kbpd• Blend sales: 48 kbpd

* Under “steady state” operating conditions.Source: Fort Hills Energy Limited Partnership36

Page 128: Teck 2017 Investor and Analyst Day

WTI-WCS* differentials forecast to improve with export pipeline capacitySource: CAPP 2016 Supply Forecast, Lee & Doma, Teck* Western Canadian Select heavy blend.

3,000

3,500

4,000

4,500

5,000

5,500

6,000

6,500

7,000

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

kbpd

Western Canada Supply Western Canada Supply GrowthTotal Pipeline & Local Refining Total Pipeline, Local Refining & Rail

TransMountain & Enbridge

Keystone XL

Excess Pipeline Capacity

Western Canada Supply/Demand Balance

Energy Marketing

Recent Pipeline Announcements Constructive

Constrained Pipeline Capacity ; Rail

Available

37

Page 129: Teck 2017 Investor and Analyst Day

• US/Canadian heavy refining capacity exceeds Canadian heavy crude oil production

• US Gulf Coast provides largest market for growth

• TransMountain & Keystone XL pipelines will provide increased access to deep water ports

Disposition & Refining Capacity For Canadian Heavy (kbpd)

0600

12001800

2015 2019

Western Canada

0600

12001800

2015 2019

US Rockies0

60012001800

2015 2019

Eastern US/Canada0600

12001800

2015 2019

US West Coast

0600

12001800

2015 2019

US Midwest

0600

12001800

2015 2019

US Gulf Coast

0

1000

2000

3000

4000

2015 2019

kbpd

US/Canada Heavy Crude Refining Capacity

AdditionalCapacityAvailable forCanadian Heavy

Canadian HeavyUsage

Source: CAPP, EIA, Lee & Doma Energy Group

Additional Capacity Available for Canadian Heavy

Canadian Heavy Usage

Energy Marketing

US Midwest/Gulf Coast Key Markets

38

Page 130: Teck 2017 Investor and Analyst Day

Blended Bitumen Pipelines

TransCanada Energy East

Enbridge/Enbridge Flanagan South

TransMountain

TransCanada Keystone, Keystone XL

Market Hub

Deep Water Port

In Service Pipeline

Proposed Pipeline

Hardisty or Common Carriage to Midwest / USGC

Cushing

Flanagan

HardistyEdmonton

Saint John

US Gulf Coast

Europe

Asia

Vancouver

Steele City

Asia SuperiorMontreal

Asia Europe

• Fort Hills partners have secured long-term pipeline access to Hardisty‒ Significant Canadian market hub‒ Access to common carriage and

contract capacity pipelines

• Will secure contracted pipeline access‒ North American refining centres &

deep water ports‒ Targeting contracts for 20-25 kbpd

of capacity on export pipelines

• Balance to be sold at Hardisty, or nominated on Enbridge

Energy Marketing

Portfolio Approach to Market Access

Access to deep water ports will add market capacity & diversification 39

Page 131: Teck 2017 Investor and Analyst Day

Energy Marketing

Hardisty is Canada’s “Cushing”• Crude oil storage: 29 mbbls, 425 kbbls contracted by Teck• Export pipeline takeaway capacity: 3.7 mbpd

– Enbridge common carrier– Keystone & Express pipelines– Origination point for 2 proposed pipelines

• Rail car loading capability: 120 kbpd

Source: Gibson Energy40

Page 132: Teck 2017 Investor and Analyst Day

Energy Marketing

Target Customers

• High quality bitumen that is attractive to refiners

• Targeting key customers throughout North America

• Term contracts under negotiation

Source: Suncor41

Page 133: Teck 2017 Investor and Analyst Day

Energy Marketing

Summary

42

• Marketing an established, well accepted type of crude

• Well positioned with significant storage at Hardisty market hub

• Developing a portfolio of market access opportunities to diversified markets

Source: Enbridge

Page 134: Teck 2017 Investor and Analyst Day

Marketing

Agenda

Overview

Steelmaking Coal

Base Metals

Energy

Summary

43

Page 135: Teck 2017 Investor and Analyst Day

44

Marketing

Summary

Copper• Global mine production growth slowing• Deficits starting to developZinc• Concentrate market in significant deficit• Smelters cutting production• Reported stocks declining

Steelmaking Coal• Price volatility easing• Good demand growth forecast

Energy• Established type of crude • Portfolio of market access opportunities

Page 136: Teck 2017 Investor and Analyst Day

Investor and Analyst DayMarch 30, 2017