telescope optical units ( tous)

20
Telescope Optical Units (TOUs) Overview of the TOU Team organization during PLATO 1.0 & TOU timeline and plans during phase B1/B2 Isabella Pagano (TOU PM) TOU Team Meeting Catania 11 June 2014

Upload: afia

Post on 23-Feb-2016

80 views

Category:

Documents


0 download

DESCRIPTION

Telescope Optical Units ( TOUs). Overview of the TOU Team organization during PLATO 1.0 & TOU timeline and plans during phase B1/B2. TOU Team Meeting Catania 11 June 2014. Isabella Pagano (TOU PM). ICU R. Cosentino. TOUs during PLATO 1.0 organization. Payload. PLATO Payload - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Telescope Optical  Units  ( TOUs)

Telescope Optical Units (TOUs)

Overview of the TOU Team organization during PLATO 1.0

& TOU timeline and plans during phase

B1/B2

Isabella Pagano (TOU PM)

TOU Team MeetingCatania 11 June 2014

Page 2: Telescope Optical  Units  ( TOUs)

TOU Meeting

TOUs during PLATO 1.0organization

Catania, 11 June 2014

PLATO PayloadManagement

PIPM: P. Bodin

Instrument System

CoordinatorP. Levacher

TOUR. Ragazzoni

Fast DPUG. Peter

Normal DPUPh. Plasson

AlgorithmsR. Samadi

AEU S. Fredon

ICUR. Cosentino

Prototype& FM AIVP. Levacher

Normal TOUR. Ragazzoni

Fast TOUW. Benz

FPA/FEED. Walton/M. Mas

Hardware & boot softwareM. Mas

Application softwarePh. Plasson

Camera ManagementD. Laubier

DPS ManagementB. Pontet

Payload

Page 3: Telescope Optical  Units  ( TOUs)

TOUs during PLATO 1.0organization

N-TOU and F-TOU delivered by IT in the PLATO 2.0 plan

Page 4: Telescope Optical  Units  ( TOUs)

TOU Meeting

• Provide optical – mechanical design performing as required by Science

• Compliant with the assigned budget• Feasible in the due time• Reliable in the given environments

TOUs during PLATO 1.0Our mandate

Catania, 11 June 2014

Page 5: Telescope Optical  Units  ( TOUs)

TOU Meeting

A large team:

• INAF– Padova– Catania– Milano

• Univ. Bern• Stockolms Obs.• Univ. Firenze

• Industrial Partners– Selex– Medialario-Sagem– Seso– RUAG– APCO Technologies

TOUs during PLATO 1.0How we managed

Catania, 11 June 2014

Page 6: Telescope Optical  Units  ( TOUs)

TOU Meeting

A large team:

• INAF– Padova– Catania– Milano

• Univ. Bern• Stockolms Obs.• Univ. Firenze

• Industrial Partners– Selex– Medialario-Sagem– Seso– RUAG– APCO Technologies

TOUs during PLATO 1.0How we managed

Catania, 11 June 2014

A huge number of meetings/telecons:

• TOU Team• Bilateral TOU-System Teams • TOU-FPA System Teams

Page 7: Telescope Optical  Units  ( TOUs)

TOU Meeting

• Design (Optics, Mechanics, Thermal, ..)• Demonstration Activities

– TOU AIV procedure– TOU Optical and Thermal Performances– TOU Optical Lenses Procurement

• Feasibility Studies– TOU MAIT and Management Plan– TOU optical coating plan– TOU aspherical lens manufacturability &

procurement plan– TOU AlBeMet® Structure Procurement Plan

TOUs during PLATO 1.0How we managed

Catania, 11 June 2014

Breadboard/

Prototype

Page 8: Telescope Optical  Units  ( TOUs)

TOU Meeting

• “pre-breadboard” the structure built with off-the-shelf lenses used to test GSE and procedures to be used with the breadboard.

• “breadboard” the structure built to test alignment in warm and cold environment before the I-PRR

• “prototype” the structure built after the I-PRR, during the Phase B1 (in the PLATO 1.0 context) , obtained from the breadboard, replacing the L1 and L2 lenses.

BreadBoard/Prototype

Catania, 11 June 2014

Page 9: Telescope Optical  Units  ( TOUs)

TOU Meeting

At I-PRR (deadline April 2011)• PMC TOU plans Source: TOU Team - Date: 4 May 2011

• PLATO TOU Project Management Plan: Source: Selex, 20 April 2011

• PLATO TOU MAIT Plan: Source: Selex, 20 April 2011

• PLATO aspherical lens (ref.11-6219 ed03): preliminary technical, management proposal – Source: Medialario/Sagem-Reosc, 3 May 2011

• PLATO Coating - Source: Selex, 22 April 2011

• PLATO TOU Design Report: Source: TOU Team, Date 18 April 2011 - included in the 02_Payload-design-report_draft11.pdf

TOUs during PLATO 1.0What we delivered - Officially

Catania, 11 June 2014

Page 10: Telescope Optical  Units  ( TOUs)

TOU Meeting

Not included in any package to ESA but delivered to CNES and O. Piersanti (former ESA PM) between March and July 2011:• CaF2 lens blank: Thermal Vacuum Test Report - Filename: PLATO-

CAMTOLE-RP-154-CNES, Issue 1, Rev. 0, Date: Jul 21st 2011, Prepared by: H. Pasquier - delivered to Piersanti

• Vibration Test Report: L3 CaF2 Vibration Test Dummy - Filename: Test_509_PLATO_dummy_lens_mount__report.pdf - Authors: M. Greber, D. Piazza, K. Seiferlin, P. Christiansen, 20th Jun 2011 - delivered to CNES and Piersanti

• PLATO TOU Breadboard/Prototype: Design and AIT Report filename: PLATO-INAF-TOU-RP-0013-issue02-rev0-2.pdf- Authors: J. Farinato, V. Viotto, D. Piazza et al., Issue 2, Rev. 0, Date: 13 Jul 2011 - delivered to CNES and Piersanti

TOUs during PLATO 1.0What we delivered – Unofficially 1/2

Catania, 11 June 2014

Page 11: Telescope Optical  Units  ( TOUs)

TOU Meeting

• AlBeMet® Structure Procurement Report - author "APCO Technologies” – delivered to CNES on May 12 2011

• Study on the aspherical lens performed by RUAG - delivered to CNES oo 18 Jul 2011

Less relevant…

• PLATO TOU - Letter of Interest - author: SAGEM/REOSC - delivered to Osvaldo Piersanti (ESA) (March 2011)

• PLATO TOU - Letter of Interest - author: SESO - delivered to Osvaldo Piersanti (ESA) (March 2011)

TOUs during PLATO 1.0What we delivered – Unofficially 2/2

Catania, 11 June 2014

Page 12: Telescope Optical  Units  ( TOUs)

TOU Meeting

• Optical Design Consolidation• see Magrin presentation for details

• Breadboard activities – see Farinato et al. presentation for details

• Mechanical Design– Finite Element Model of the current mechanical design,

including evaluation of the first eigenfrequency. • Interfaces

– Verification of the interfaces of the finite element model with the lenses and their effects.

• Filter design– Engineering consolidation

TOUs during PLATO 1.0What we left open

Catania, 11 June 2014

Page 13: Telescope Optical  Units  ( TOUs)

TOU Meeting

PLATO 2.0 TOU 2.0

Catania, 11 June 2014

Page 14: Telescope Optical  Units  ( TOUs)

TOU Meeting

– Phase B1 kick-off: Jul 2014– Science Management Plan approval: Nov

2015– Payload Development and Consolidation

Review: March 2015– SRR data package: 1 Nov 2015– SRR: completed by Jan 2016– Mission adoption & IPC approval: Feb-Mar

2016

PLATO 2.0 timeline – Phase B2Jul 2014-Jan 2016

Catania, 11 June 2014

Premises

Page 15: Telescope Optical  Units  ( TOUs)

TOU Meeting

– Industrial ITT for Phases B2/C/D/E1: Apr-Sep 2016

– Industrial Prime contractor kick-off: Oct 2016– System PDR: by 2017 (tbc)

– System CDR: by mid-2020 (tbc)• Payload CDR by 2018 (tbc)

– Delivery of all Cameras: Q4 2021– PLATO Launch: Q1 2024

PLATO 2.0 timeline – Phase B2C/D/E1Q1 2016-Q1 2024

Catania, 11 June 2014

Premises

Page 16: Telescope Optical  Units  ( TOUs)

TOU Meeting

• PLATO Phase B1 objective is the adoption of the PLATO mission by SPC in Feb-March 2016.

• The PLATO System Requirements Review (SRR) to be completed by January 2016 is a major input to PLATO mission adoption.

• The SRR is a formal review (category 1 i.e organized by ESA inspector general, D/SRE is the chairman).

• The primary objective of the SRR is to review in detail:– The final payload and spacecraft system specifications,– The payload and spacecraft design definition,– The payload and spacecraft development and verification program,– Mission programmatic and cost.

Phase B1: SRR Objectives 1/2

Catania, 11 June 2014

Premises

Page 17: Telescope Optical  Units  ( TOUs)

TOU Meeting

• The camera development schedule is critical, and is actually defining the schedule critical path for the spacecraft. Hence:– The camera detailed design activities (including AIV plans and Ground

System Equipment design) shall be completed before the SRR,– The critical bread-boarding activities (e.g. electronics Demonstration

Models, optics) shall be initiated during phase B1,– Consortium input to the SRR shall demonstrate that the camera

Engineering Model - which is fully representative of the flight model except for some electronics parts - will be completed by early 2017,

– A detailed development plan of the payload shall demonstrate by SRR that:

• serial production phase will start by mid-2017,• the first batch of 8 cameras will be delivered in November 2020,• the last batch of cameras will be delivered by November 2021.

Phase B1: SRR Objectives 2/2

Catania, 11 June 2014

Premises

??

Page 18: Telescope Optical  Units  ( TOUs)

Our proposal: deliver all ready but undelivered documents:

• Design:– Consolidated TOU Design Report (Optical Design, Mechanical Design,

Thermal Analysis, Stray-light Analysis, Optical Material Analysis and Coating Design, ..)

• Breadboard:– Consolidated BreadBoard AIV report

• NEW: including a critical review of results and assessment of some open issues

• CaF2 tests

• AIV Design:– Consolidated TOU MAIT and Management Plan – Consolidated AlBeMet® Mechanical Structure Procurement

Assessment Study– NEW: F-TOU Filters Design Procurement Assessment Study

TOUs during PLATO 2.0Phase B1 goal

Page 19: Telescope Optical  Units  ( TOUs)

TOU Meeting

• Design:– Engineering of TOU Design (Optical Design, Mechanical Design,

Thermal Analysis, Stray-light Analysis, Optical Material Analysis and Coating Design, ..)

• Breadboard Prototype– Lens set like the FM one (change of 2 lenses and replacement of

one lens previously accepted with no conformance issue because short in time

– optical quality test (in term of PSF shape and dimension) on the whole FoV.

• AIV Design:– Finalized TOU MAIT and Management Plan – Finalized AlBeMet® Mechanical Structure Procurement Study– Consolidated: F-TOU Filters Design Procurement Assessment Study

TOUs during PLATO 2.0Phase B2 goal

Catania, 11 June 2014

Page 20: Telescope Optical  Units  ( TOUs)

TOU Meeting

Our proposal:• During Phase B1, industry will deliver consult

and services.• We’ll work to have ASI delivers a ITT for

Phase B2/C contract, not later than March 2015.

• Goal:– TOU Prime Contractor at work at beginning of

Phase B2, but clearly identified before the SRR.

When Industrial Prime Contractor?

Catania, 11 June 2014