temporary on-site power solutions legal and regulatory ... › files › 2019 › 11 › ... ·...

11
M-47715906-1 Temporary on-site power solutions Legal and regulatory requirements Data Centres Ireland 2019 John Dallas A&L Goodbody 19 November 2019

Upload: others

Post on 31-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

M-47715906-1

Temporary on-site power solutions –Legal and regulatory requirements

Data Centres Ireland 2019John Dallas – A&L Goodbody

19 November 2019

Page 2: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

About ALG

2

Page 3: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

Jason MilnePartner, Environmental & Planning

+353 1 649 2250

[email protected]

John DallasPartner, Energy, Infrastructure & Natural Resources

+353 1 649 2937

[email protected]

3

ALG Data Centres team

Paul DigginPartner, Commercial Property

+353 1 649 2258

[email protected]

Conor OwensPartner, Construction

+353 1 649 2084

[email protected]

Claire MorrisseyPartner, Commercial & Technology

+353 1 649 2246

[email protected]

Page 4: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

Context

4

1

Growth in electricity demand in the greater Dublin area

2

Limited grid capacity = network constraint in certain areas

3

Delays in securing firm import capacity

4

Semi-permanent on-site power solutions “plugging the gap”

Page 5: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

Electricity Regulation (principally Electricity Regulation Act, 1999)1

Electricity Generation as a Regulated Activity

5

Planning and Development Acts 2000 - 20192

Environmental Law (e.g. Industrial Emissions Regulations)3

Page 6: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

What do I need?

▪ Commission for Regulation of Utilities (Capacity > 1MW)

> Authorisation to Construct a Generating Station (S.16 1999 Act)

> Licence to Generate Electricity (s.14(1)(a) 1999 Act)

▪ Planning Permission

▪ Medium Combustion Plant Registration / Industrial Emissions Licence from EPA

▪ Greenhouse Gas Emissions Permit from EPA

▪ Gas Connection and Gas Supply

6

Page 7: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

Time Periods

7

Permit Time Period

CRU Authorisation to Construct 14 Weeks (CRU Guidance). No statutory period.

CRU Licence to Generate 14 Weeks (CRU Guidance). No statutory period.

Planning Permission 12 Weeks + (depends on further information requirements,

appeals etc.)

IE Licence 7 months (but likely to be longer in practice, e.g. further

information requests, oral hearing etc.)

Medium Combustion Plant Registration 1 month

Greenhouse Gas Emissions Permit 3 – 6 months. No statutory period.

Gas Connection Offer 12 – 16 weeks for a quotation for large industrial users. But

depends on complexity and capacity available in the area etc.

Page 8: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

Consequences of operating without permits

8

Permit Consequence Enforcement Body

CRU Authorisation

to Construct

Fine ≤ £100,000 (€126,973.80). CRU

CRU Licence to

Generate

Fine of ≤ €1,904 or up to 12 months imprisonment or both.

Potential sanctions against directors / officers of the company where the offence

was committed with consent or connivance of the individual or as a result of

their neglect.

CRU

Planning

Permission

Enforcement action under P&D Acts for construction / operation of

unauthorized development.

Local Authority

Third Parties

through the Courts

IE Licence Fine of up to €5,000 on summary conviction and €10 million per offence on

indictment.

EPA

Medium

Combustion Plant

Registration

Fine of up to €5,000 or 12 months in prison or both on summary conviction. On

indictment €500,000 or 3 years imprisonment or both.

EPA

Greenhouse Gas

Emissions Permit

Fine of up to €4,000 or 12 months in prison or both. €15m or 10 years

imprisonment, or both, for an indictable offence. €1,000 per day fine for

summary offence or €130,000 per day fine for indicatable offence where

emissions continue without a permit.

EPA

Page 9: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

Licence / Permit Conditions and Obligations

9

Condition Type

Time Periods • Planning Permission – time limit on operation of ‘temporary plant’.

• CRU Licences – 5 years to construct. Effectively 30 year permit to

operate subject to compliance with licence terms.

Operating Constraints • PP: Noise emissions at noise sensitive receptors.

• Other construction and operating conditions specific to the permission.

Change of Control • CRU licences may include change of control provisions, restrictions on

assignment of CRU licences and restrictions on transfer of the

generating business.

Information Obligations • Obligation to provide information / reports to the CRU (obligations are

more limited for < 10MW generating plant).

Emissions Monitoring /

Reporting & Verification

• Monitoring, reporting & verification obligations under greenhouse gas

emissions permit, IE licence and medium combustion plant regulations.

Page 10: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

On-site generation ‘as a service’

▪ Recognised from a regulatory perspective

▪ CRU Licence to Supply Electricity (s.14(1)(b) 1999 Act)

▪ ‘Turn-key’ model – service provider will need to procure and comply with the permits and registration obligations

10

Page 11: Temporary on-site power solutions Legal and regulatory ... › files › 2019 › 11 › ... · Legal and regulatory requirements Data Centres Ireland 2019 John Dallas –A&L Goodbody

Thank you