tender 278 -2015 addendum no. 4 › inter › pmmd › callawards.nsf... · closing date: october...

80
Michael Pacholok Director Purchasing and Materials Management Division City Hall, 18 th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2 Allison Phillips Manager Professional Services October 9, 2015 (5 Pages + 2 attached files) ADDENDUM NO. 4 REQUEST FOR TENDER NO. 278-2015 CONTRACT NO. 15ECS-MI-01IS RE: ISLAND WATER TREATMENT PLANT – RESIDUALS MANAGEMENT FACILITY PHASE 1 UPGRADES CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender (RFT) No. 278-2015 document in your possession and be advised of the following: I. SPECIFICATIONS A4-S1 Section 02505 – Site Pipe and Fittings a) Replace Clause 2.3.1 with the following: The backwash waste distribution pipe shall have the diameter shown on the contract drawings and shall be Polyethylene (PE) Large Diameter Closed Profile Wall sewer pipe with minimum Ring Stiffness Constant (RSC) 250, conforming to ASTM F 894. Materials to meet the requirements of ASTM D 3350. Pipe jointing to be by mechanical couplings meeting the requirements of ASTM D 3212. b) Replace Clause 3.3.4 with the following: Pipe shall be jointed in strict accordance with ASTM D3212 and the manufacturer’s recommended practice. c) Add Clause 3.3.5: Pipe shall be installed in strict accordance with ASTM D 2321. d) Add clause 3.3.6: One flexible mechanical joint to be provided at locations where the pipe is held in fixed position by a rigid support or structure. The distance from the support or structure to be in accordance with the pipe manufacturer's recommended practice with a minimum distance of 500 mm. The purpose of the flexible joint is to prevent pipe failure due to uneven support under the pipe. A4-S2 Section 11242 Chemical Feed Equipment – pre-approved alternate vendors The following vendors are the pre-approved alternate vendors to the design standard for this project: - Aquafy Water Technologies (Morrflo) - Veolia Water Technologies (Norchem) A4-S3 Section 13010 – Process Control General – 1.8 RPU, OIT and HMI (SCADA) System Integrator 1

Upload: others

Post on 07-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

Michael Pacholok Director

Purchasing and Materials Management Division City Hall, 18th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2

Allison Phillips Manager Professional Services

October 9, 2015 (5 Pages + 2 attached files)

ADDENDUM NO. 4

REQUEST FOR TENDER NO. 278-2015

CONTRACT NO. 15ECS-MI-01IS

RE: ISLAND WATER TREATMENT PLANT – RESIDUALS MANAGEMENT FACILITY PHASE 1 UPGRADES

CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME)

Please refer to the above Request for Tender (RFT) No. 278-2015 document in your possession and be advised of the following: I. SPECIFICATIONS

A4-S1 Section 02505 – Site Pipe and Fittings

a) Replace Clause 2.3.1 with the following: The backwash waste distribution pipe shall have the diameter shown on the contract drawings and shall be Polyethylene (PE) Large Diameter Closed Profile Wall sewer pipe with minimum Ring Stiffness Constant (RSC) 250, conforming to ASTM F 894. Materials to meet the requirements of ASTM D 3350. Pipe jointing to be by mechanical couplings meeting the requirements of ASTM D 3212.

b) Replace Clause 3.3.4 with the following: Pipe shall be jointed in strict accordance with ASTM D3212 and the manufacturer’s recommended practice.

c) Add Clause 3.3.5: Pipe shall be installed in strict accordance with ASTM D 2321. d) Add clause 3.3.6: One flexible mechanical joint to be provided at locations where

the pipe is held in fixed position by a rigid support or structure. The distance from the support or structure to be in accordance with the pipe manufacturer's recommended practice with a minimum distance of 500 mm. The purpose of the flexible joint is to prevent pipe failure due to uneven support under the pipe.

A4-S2 Section 11242 Chemical Feed Equipment – pre-approved alternate vendors

The following vendors are the pre-approved alternate vendors to the design standard for this project: - Aquafy Water Technologies (Morrflo) - Veolia Water Technologies (Norchem)

A4-S3 Section 13010 – Process Control General – 1.8 RPU, OIT and HMI (SCADA)

System Integrator

1

Page 2: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

Michael Pacholok Director

Purchasing and Materials Management Division City Hall, 18th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2

Allison Phillips Manager Professional Services

Add to the list of approved system integrators “Eramosa Engineering”.

A4-S4 Section 13021 – Process Control Narrative

Replace section in its entirety with updated Process Control Narrative attached to this addendum.

A4-S5 Section 13105 – Instrument List

Change Tag No. “FIS-ACC-AIT-0001” to read “FIS-ACC-TIT-0001”

A4-S6 Section 13510 – PCS local area network

Replace section in its entirety with updated section attached to this addendum.

II. DRAWINGS

A4-D1 Drawing 1F-2015-10-17 S11 Section A detail Add a note for the existing raw water conduit “Once existing ceiling and wall is painted, install 75mm thick semi-rigid interior insulation with reinforced foil facing, Rockboard 40, by Roxul Inc or approval equivalent”.

A4-D2 Drawing 1F-2015-10-85 I25 Change Tag No. “FIS-POL-FSH-0001-FAH” to read “FIS-SES-FSH-0001-FAH”.

III. QUESTIONS

A4-Q1 Note on Dwg C1 instructs ‘Upon Completion of Work resurface entire existing asphalt pavement within contractor truck route with 75mm HL3, please clarify the limits of the work required.

A4 – A1 Answer

Note on drawing 1F-2015-10-3 C1to be revised as per the following: ‘Upon completion of work mill and resurface entire existing asphalt pavement within contractor truck route with 75 mm HL3 (Contractor to consider 300 tonnes HL3 as base scope)’.

A4-Q2 Please provide specification for Camlock nozzles and caps. Are these aluminum or

stainless steel?

A4 – A2 Answer Type B Stainless Steel couplings and appropriate Stainless Steel cap.

2

Page 3: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

Michael Pacholok Director

Purchasing and Materials Management Division City Hall, 18th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2

Allison Phillips Manager Professional Services

A4-Q3 Drawing M1 shows a 50mm water line feeding the wash down system and so does

drawing C1. The wash down piping on drawing P1 is 63 mm, is it the intent to feed the 63mm wash down piping header with a 50mm supply?

A4 – A3 Answer

Drawing 1F-2015-10-3 C1 – change notes that read “…50 MM Ø PVC INSULATED AND HEAT TRACED PLANT SERVICE WATER…” and “…50 MM Ø PVC INSULATED AND HEAT TRACED WASH DOWN WATER…” to read “63 MM Ø PVC INSULATED AND HEAT TRACED…” accordingly.

A4-Q4 Spec. Section 01110 Summary of Work on Page 3 of 6 calls for all the work to be

completed for Settling Basins 5 & 7 and fully commissioned including backwash waste distribution piping. However on drawing C1, it shows the new backwash waste distribution piping that feeds to Basins 9, 7 & 5 in the same location as the existing 900 dia. buried pipe feeding Basin No. 9, shown on drawing R1 to be removed. Please provide an elevation for the 900 buried pipe that needs to be removed and advise if it has to be removed prior to installing the backwash waste distribution piping.

A4 – A4 Answer

The existing 900 mm dia. feed to Settling Basin 9 is indicated incorrectly on Drawing R1. It actually runs along the west wall of the Basin from the existing flow splitting chamber indicated on Drawings P1 and P3. Also note that the existing pipe that feeds Settling Basin 9 is 65”x40” CMP ARCH pipe.

A4-Q5 Please clarify which pipeline Detail 1 on Dwg P7 applies to.

A4 – A5 Answer

For application of specific Standard Details refer to project plans, sections and profiles. If nothing is indicated on plans and sections, then the particular Standard Detail is not applicable.

A4-Q6 Drawing P3 detail 1 calls for a 1900 X 1829 Channel gate, detail 2 calls for a 2134 X

1829 gate and Specification 11286 on page 4 of 9 calls this gate out as 2100 x 1800 please advise correct size.

A4 – A6 Answer

All notes refer to nominal 84” x 72” channel gate. A4-Q7 Please give the handrail post spacing for the aluminum walkway to the perimeter of

the tanks.

A4 – A7 Answer As per section 05500, the design of the walkway handrail is by the manufacturer and must comply with the Ontario Building Code.

3

Page 4: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

Michael Pacholok Director

Purchasing and Materials Management Division City Hall, 18th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2

Allison Phillips Manager Professional Services

A4-Q8 It is noted in the documents Section 01359 – Special Project Procedures – “Due to

the Ferry schedule, the work day is reduced at the Island WTP” if we are to use our own private services for transportation of workers to and from the island are we able to extend the daily working hours? Currently from 7:00am – 3:00pm, are we able to push the working hours from 7:00am till 5:00pm? Or later?

A4 – A8 Answer

The work hours are to be as stated in Section 01359. A4-Q9 Are there any working days or working hour restrictions specific to the Island? Or

is it just the normal City of Toronto by-laws that apply?

A4 – A9 Answer The work hours and work days along with working restrictions are to be as stated in the contract documents.

A4-Q10 Would the city be able to provide some information on Barge Services for the

island? The contact info of any Barge Companies that the City may have used in the past or is aware of that do work around the island?

A4 – A10 Answer

The City does not have any information on Barge Services. A4-Q11 Please confirm the maximum Electrical Power available on-site that can be

dedicated towards construction use.

A4 – A11 Answer Refer to Section 01510 – temporary utilities. Contractor to assume that a 600V, 15A power source is available. The Contractor is responsible to supply their own power needs in excess of the available power within the existing plant panels as per section 01510.

A4-Q12 Please identify if there is any available extra space for a staging area that can be

used for material and equipment storage? I’ve inserted an image identifying the space we would prefer to use most below – area outlined in red - please let us know if this would be acceptable or not.

4

Page 5: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

Michael Pacholok Director

Purchasing and Materials Management Division City Hall, 18th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2

Allison Phillips Manager Professional Services

A4 – A12 Answer The construction staging area is shown on drawing 1F-2015-10-3 C1. There is no additional available space.

A4-Q13 Spec. Section 03250 Item 2.1.13 Crystalline Waterproofing: There is none shown

for the “reservoir” on the contract drawings. Please clarify.

A4 – A13 Answer There are no base scope crystalline waterproofing repairs. Crystalline waterproofing is associated with potential structural repairs that are captured under the schedule of prices.

Should you have any questions regarding this addendum, please contact Christine Sze, Senior Corporate Buyer, at (416) 392-0627 or by email at [email protected] Please attach this addendum to your RFT document and be governed accordingly. Tenderers are to acknowledge receipt of all addenda in their Tender in the space provided on the Tender Cover Page as per Section 1 – Tender Process Terms and Conditions, item 8 of the RFT document. All other aspects of the RFT remain the same. Yours truly, Allison Phillips Manager Professional Services

5

Page 6: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 1 of 42

1 ISLAND WTP RESIDUALS MANAGEMENT SYSTEM

1.1 OVERVIEW

.1 The prime objective of the Island WTP Residuals (Waste Backwash Water) Management System is to improve treatment of filter backwash waste water by

Direct discharging of backwash waste water from filters to the settling tanks;

Treat the flow appropriately to improve settleability by adding a polymer solution and remove chlorine residual by injecting sodium bisulphite (in the future Calcium Thiosulphate);

Accumulate treated backwash waste water in one of the 3 settling basins until it is ready for disposal;

Dispose of supernatant back to Lake Ontario;

Transfer sludge collected in the interim to one of the existing slow sand filter tanks for storage or ultimately to the future sludge dewatering facility when constructed.

1.2 PROCESS DESCRIPTION

.1 Process Definition

Refer to Drawings:

Drawing No. I4

Drawing No. I5

Drawing No. I6

Drawing No. I7

Drawing No. I8

Drawing No. I9

In addition to the existing sodium bisulphite (or calcium thiosulphite) feed system for de-chlorination of the stream, the following main components comprise the Residual Management System process.

Settling basins (3);

Backwash control chambers (2);

Polymer solution feed system (2)

Supernatant outlet valve (3)

Sludge transfer pumps (3)

Motorized de-sludge valves (9);

Motorized 3-way, sludge transfer pump discharge valves (3);

Motorized settling basin inlet sluice gates (3);

Settling basin level transmitters (3)

Pump well level transmitters (3)

6

Page 7: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 2 of 42

De-chlorination Agent

Polymer

Total Suspended Solids analyzers (2)

Total Chlorine Residual analyzers (2)

Programmable logic controller (1)

.2 Block Diagram

.3 Objectives

Proper collection and treatment of filter backwash waste water, and suitable disposal of supernatant and settled sludge is required to meet requirements of regulatory agencies.

.4 Process Control Strategy

Spent filter backwash water is directed to the duty settling basin by a series of motorized sluice gates. Consecutive backwashes are directed to the duty basin until liquid level in the tank reaches the pre-determined high water level. At that time, the tank is isolated from the system and liquid in the tank is allowed to stratify. The next backwash waste volumes are directed to the next duty settling tank.

Polymer and sodium bisulphite are injected into the backwash waste water stream based on the flow signal from the existing filter backwash flowmeter located downstream from the filters.

After liquid in the isolated tank has stratified supernatant from the tank is directed to Lake Ontario by opening the isolation valve on the supernatant collection header. Quality of discharge is monitored by Chlorine Residual and Total Suspended Solids analyzers located in the Intake Valve Chamber. If supernatant water quality exceeds pre-determined value on any of the parameters, supernatant discharge is terminated. In case of TSS parameter exceeding the pre-determined value the liquid in the tank is allowed to stratify further. If the chlorine residual value exceeds the pre-determined threshold, additional de-chlorination agent will have to be manually added to the tank effected. Supernatant disposal is also terminated when the liquid level in the tank is lowered to the pre-determined level.

When it is determined that the sludge collected is ready for disposal and slow sand filter tank(s) are available, sludge collected in the bottom of the basin is transferred to the tank(s) by the sludge transfer pump. Delivery of sludge to the sludge transfer pumping station is accomplished via automatically opening all three (3) motorized de-sludge valves simultaneously.

FLOW CONTROL

CHAMBERS

Filter Backwash Water Discharge

Supernatant to Lake Ontario

Sludge to existing Slow Sand Filters for Storage

DISPOSAL

SETTLING TANKS

7

Page 8: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 3 of 42

The operator decides which of the existing slow sand filter tanks will receive the sludge and makes appropriate system modifications by routing the sludge discharge hose to the selected tank.

When the sludge transfer pump is ready to start, the associated 3-way motorized discharge valve travels from drain to discharge position and the pump is activated. Liquid level in the sludge transfer pumping station is monitored by a level transmitter.

When all the sludge has been transferred or the selected slow sand filter tank is full as confirmed by visual observation, transfer is terminated by turning off the sludge transfer pump and commanding the associated 3-way motorized discharge valve to drain position. This will drain any remaining liquid from the sludge transfer pipe back to the sludge transfer pumping stations.

.5 Influent Sources

Spent water exiting filters after regular backwash sequence, containing impurities collected by the filter media and carrying chlorine residual. Polymer is added to the flow to improve settleability and sodium bisulphite is applied to de-chlorinate the flow.

.6 Effluent Destination

Spent backwash water is collected in the settling tanks and is allowed to stratify into supernatant and sludge constituents prior to disposal.

.1 Supernatant

Supernatant is discharged back to Lake Ontario while its quality (total suspended solids concentration and total chlorine residual) is monitored by on-line analyzers located in the Intake Valve Chamber.

.2 Sludge

Following stratification, sludge collected in the bottom of settling basin will flow via three de-sludge valves to the associated sludge transfer pumping station. The sludge will be then pumped to slow sand filter tank (currently) and residuals management facility (ultimately) for dewatering.

.7 Process Control Equipment/Devices

The following table outlines the process control equipment for Residual Management System:

Equipment Name (Quantity)

Equipment Number

Device Operation Control Objectives

Settling Basin Inlet Sluice Gates (3)

FIS-WWW-G- 0501 FIS-WWW-G- 0701 FIS-WWW-G- 0901

Opens and closes in response to control signal to directs spent backwash water to the duty settling basin.

To allow duty settling basin to fill and to isolate the basin from the system.

Settling Basins (3) FIS-WWW-T-0501 Collects spent To allow stratification into 8

Page 9: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 4 of 42

Equipment Name (Quantity)

Equipment Number

Device Operation Control Objectives

FIS-WWW-T-0701 FIS-WWW-T-0901

backwash water supernatant and sludge constituents.

Settling Basin Level Transmitters (3)

FIS-WWW-LIT-0501 FIS-WWW-LIT-0601 FIS-WWW-LIT-0901

Measures and transmits the liquid/sludge level within the settling basin.

Level trending; initiates settling basin fill stop; initiates supernatant discharge “stop”.

Settling Basin High-High Level Switches (3)

FIS-WWW-LSHH-0501 FIS-WWW-LSHH-0701 FIS-WWW-LSHH-0901

Alarm high-high level in the settling basin.

Acts as backup in the event of level transmitter failure.

Supernatant Discharge Valves (3)

FIS-WWW-V-0510 FIS-WWW-V-0710 FIS-WWW-V-0910

Opens and closes in response to control signals to minimize TSS spikes.

Allows for proper disposal of supernatant to Lake Ontario.

De-sludge Valves (9)

FIS-WWW-V-0511 FIS-WWW-V-0512 FIS-WWW-V-0513 FIS-WWW-V-0711 FIS-WWW-V-0712 FIS-WWW-V-0713 FIS-WWW-V-0911 FIS-WWW-V-0912 FIS-WWW-V-0913

Opens and closes in response to control signals to minimize sludge disturbance.

Delivery of the sludge to the pump well.

Sludge Transfer Pumps (3)

FIS-WWW-P-0500 FIS-WWW-P-0700 FIS-WWW-P-0900

Starts on sludge transfer manual initiation at HMI and automatically stops based on level transmitter signal.

Transfers sludge from the pump well to slow sand filter tank.

Three-way Sludge Transfer Pump Discharge Valves (3)

FIS-WWW-V-0515 FIS-WWW-V-0715 FIS-WWW-V-0915

Opens and closes in response to control signals to direct sludge to the appropriate destination.

To allow sludge transfer to the slow sand filter tank. Also to permit sludge to drain from forcemain and discharge hose to pump well to prevent product freezing.

Pump Well Level Transmitters (3)

FIS-WWW-LIT-0502 FIS-WWW-LIT-0702 FIS-WWW-LIT-0902

Measures and transmits pump well level.

Initiates pump stop on selected low level.

Pump Well High-High Level Switches (3)

FIS-WWW-LSHH-0502 FIS-WWW-LSHH-0702 FIS-WWW-LSHH-0902

Alarm high-high level in the pump well.

To monitor for high-high level.

Pump Well Low-Low Level Switches (3)

FIS-WWW-LSLL-0501 FIS-WWW-LSLL-0701 FIS-WWW-LSLL-0901

Alarm low-low level in the pump well.

To monitor for low-low level and interlock to stop pump if running.

9

Page 10: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 5 of 42

Equipment Name (Quantity)

Equipment Number

Device Operation Control Objectives

Polymer Feed Pumps (2)FIS-POL-P-1001 FIS-POL-P-1101

Pumps neat polymer from the storage tote to the mixing chamber.

Delivers the required dosage of polymer solution.

Polymer Pump VFD Drives (2)

FIS-POL-DRV-1001 FIS-POL-DRV-1101

Monitors and controls the speed of the metering pump.

Delivers the required dosage of polymer solution.

Polymer Skid Controllers (2)

FIS-POL-FRIC-1001 FIS-POL-FRIC-1101

PID logic control for pump speed and dilution water.

Controls the dosage of polymer.

Dilution Water Isolation Valves (2)

FIS-POL-V-1002 FIS-POL-V-1102

On/off control of water supply.

Supply water for dilution

Dilution Water Flow Meters (2)

FIS-POL-FE-1001 FIS-POL-FE-1101

Measures flow rate of dilution water

Feedback loop control to assure consistent dosage.

Dilution Water Flow Control Valves (2)

FIS-POL-V-1003 FIS-POL-V-1003

Automatically modulates to compensate for changes in incoming water flow rate.

Assure consistent dosage.

Mixers (2) FIS-POL-MX-1001 FIS-POL-MX-1101

Mixes neat polymer and dilution water.

To produce fully activated polymer.

Polymer Solution Flow Meters (2)

FIS-POL-FIT-1002 FIS-POL-FIT-1102

Measures flow rate of polymer solution being delivered to the system.

Flow is monitored and alarmed at SCADA.

Total Suspended Solids Analyzers (2)

FIS-WWW-AIT-0001 FIS-WWW-AIT-0003

Monitors quality of supernatant discharge. Operated in duty/standby approach.

To ensure that supernatant meets regulations prior to discharge into lake.

Total Chlorine Residual Analyzers (2)

FIS-WWW-AIT-0002 FIS-WWW-AIT-0004

Monitors quality of supernatant discharge. Operated in duty/standby approach.

To ensure that supernatant meets regulations prior to discharge into lake.

PLC Room Ambient Temperature Transmitter

FIS-WWW-TIT-0001 Monitors PLC Room ambient temperature.

To ensure PLC Room temperature is within acceptable range.

.8 Ancillary Process Description 10

Page 11: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 6 of 42

Spill management for the Polymer system consists of a level switch mounted in the containment area. A spill will trip FIS-POL-LSH-0001. An alarm will be annunciated at the HMI.

Eye Wash Shower in the Polymer Room is monitored by a Flow Switch, FIS-SES-FSH-0001. If the Eye Wash Shower is activated, high flow alarm will be annunciated at the HMI.

Temperature transmitter FIS-ACC-TIT-0001is located in the PLC Room to monitor ambient temperature. In the event of high or low temperature, the corresponding alarm will be SCADA generated.

1.3 CONTROL SYSTEM DESCRIPTION

.1 Description

.1 Controller Stations

Each sluice gate and valve comprises an integral actuator with the following control and indication functions:

Local/Remote (L/R) control mode selector switch

Open/Close pushbuttons

Opened/Closed indication

Position indication

Each sludge transfer pump is equipped with a VFD. The VFD includes the following control and indication functions:

Local/Remote (L/R) control mode selector switch

Start/Stop

Speed control function

Speed indication

Running status

Each package Polymer skid will be equipped with a Control Panel. At the Control Panel there will be the following operator accessible devices:

Local/Off/Remote control mode selector switch

Operator Interface (OI): used locally for - dosage and concentration entry, start/stop, viewing of polymer solution and dilution water flow rates, and view of alarms, status, run time, and trend screen.

When the control selector switch at the specific equipment is set to Local, the related device can be operated locally. This would be normally used for testing after maintenance.

For the PLC to have complete control of the Residual Management System, the L/R control selector switch at each device must be in the Remote mode.

11

Page 12: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 7 of 42

.2 Modes of Control

There are three modes of control for the Residual Management System process:

LOCAL MANUAL

COMPUTER MANUAL

COMPUTER AUTO

A. LOCAL MANUAL

To operate in this mode sludge transfer pumps:

The Local/Remote selector switch on the VFD for the given pump is set to Local.

Starting and stopping of pumps is done manually at the VFD. Speed adjustment for the desired pump is made at the pump drive.

To operate in this mode valves/gates:

The Local/Remote selector switch on the valve/gate is set to Local.

Valve/gate is opened/closed manually at the actuator.

To operate in this mode Polymer skid:

The Local/Off/Remote selector switch at the Polymer skid Control Panel is set to Local.

Polymer dosage, polymer concentration, pump speed, and pump start/stop are set at the package Operator Interface (OI), which is located on the package Control Panel.

This mode is only used in the event of PLC or SCADA failure, for maintenance purposes or for complete manual operation.

B. COMPUTER MANUAL

To operate in this mode sludge transfer pumps:

The Local/Remote selector switch on the drive for the given pump is set to

Remote;

The SCADA/MANUAL selection is made at the SCADA HMI; Starting and stopping of the pumps is done manually from the HMI; Speed adjustment is made at the HMI for the given pump

To operate in this mode valves/gates:

The Local/Remote selector switch on the LCP for the given pump is set to Remote;

The COMPUTER MANUAL selection is made at the SCADA HMI;

Open and close of the valves/gates is done manually from the HMI To operate in this mode package Polymer skid:

12

Page 13: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 8 of 42

The Local/Off/Remote selector switch on the skid Control Panel is set to Remote;

The COMPUTER MANUAL selection is made at the SCADA HMI; Polymer pump start/stop and backwash flow set point are manually entered

at the HMI. Polymer dosage and polymer concentration are set at the SCADA HMI and

transmitted to each polymer package controller. The package system performs control to ensure that correct polymer solution is produced and delivered to the system.

C. COMPUTER AUTO

To operate in this mode sludge transfer pumps:

The Local/Remote selector switch on the drive for the given pump is set to Remote;

The COMPUTER AUTO selection is made at the SCADA HMI for each pump;

Starting, stopping, and speed control of the pumps is done automatically. The pumps will be normally operated at constant speed; the best suited speed for the application will be site determined during project commissioning.

To operate in this mode valves/gates: The Local/Remote selector switch on the actuator for valve/gate is set to

remote; The SCADA/AUTO selection is made at the SCADA HMI for each

valve/gate; Open and close of the valves/gates is done automatically based on Control

Logic.

To operate in this mode package Polymer skid: The Local/Off/Remote selector switch on the skid Control Panel is set to

Remote The COMPUTER AUTO selection is made at the SCADA HMI; Polymer dosage and polymer concentration are entered at the SCADA HMI

and transmitted to each polymer package controller. Polymer pump start/stop and flow set point are performed automatically. The package system performs control to ensure that correct polymer

solution is produced and delivered to the system. In order for the system to function automatically as a whole, all automated equipment is required to be in remote control mode; the selection at the HMI should be set to Computer Auto for each device. This control mode is bumpless when switching from COMPUTER MANUAL TO COMPUTER AUTO or vice versa. Refer to section 1.3.2 for a description of the control logic.

13

Page 14: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 9 of 42

.2 Control Logic

.1 Normal Operation

The following will be operator selected/entered at the HMI:

Settling Basin “In-service” or “Out-of-Service”

Settling Basin Fill Sequence

The number of fill cycles to the settling basin. One “fill cycle” is defined as consecutive filter backwashes directed to the duty settling basin until the basin is filled to the selected (at the HMI) high water level

Duty Polymer Skid Sequence

Polymer concentration (in percent)

Polymer dosage, mg/L

Duty Total Suspended Solids (TSS) Analyzer (FIS-WWW-AIT-0001, 0004) Sequence

Duty Chlorine Residual Analyzer (FIS-AIT-0002, 0005) Sequence

The Settling Basin “In-service” or “Out-of-Service” will be operator selected at the HMI.

The inlet sluice gate to the associated Settling Basin will be automatically opened to receive Filter Backwash Wastewater when the basin is “In-service” and is scheduled in sequential order to receive the filter backwash wastewater. When the Settling Basin is not “In-service”, the inlet sluice gate is automatically closed.

Polymer and sodium bisluphite (in the future calcium thiosulphate) are injected into the backwash waste water stream based on the existing filter backwash flow “leaving” the filter.

The settling basin will receive multiple backwashes until the basin is filled to the selected (at HMI) high level. At the basin high level, the inlet sluice gate is automatically closed. The basin contents are then allowed to stratify for “stratification time” (initially set for twenty-four hours (24); adjustable at SCADA HMI from 24 to 72 hours). Once the stratification time is attained, the supernatant from the basin is directed to Lake Ontario by automatically opening the supernatant discharge valve to intermediate position, on the supernatant collection header. The valve intermediate position will be adjustable at the HMI. When the level in the basin is lowered to x.x metres (adjustable at HMI), the supernatant valve is opened fully. Quality of supernatant discharge is monitored by Chlorine Residual and Total Suspended Solids analyzers located in the Intake Valve Chamber. If the supernatant Chlorine Residual High-High Alarm is active after an adjustable time delay at the HMI, the supernatant discharge is terminated and manual introduction of de-chlorination agent to the settling basin is required. Similarly, if the supernatant TSS High-High Alarm is in effect after an adjustable

14

Page 15: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 10 of 42

time delay at the HMI, supernatant discharge is terminated and liquid in the basin is allowed to re-stratify further for “stratification time”.

Normally supernatant disposal is terminated when the liquid level in the basin is lowered to the pre-determined level (invert of the supernatant pipe). If more than one fill cycle has been selected, then after successful supernatant discharge, the basin is once again placed into normal rotation with the other basins following a decanting cycle with no desludging. The associated inlet sluice gate will be opened at the appropriate time in anticipation of the next fill cycle.

When the last selected fill cycle is attained and the basin contents have been stratified, the supernatant is discharged as described above. Once the supernatant discharge is complete, a message will be displayed at the HMI that the sludge collected in the settling basin is ready for disposal. Sludge collected at the bottom of the settling basin is transferred to the slow sand filter tank by the sludge transfer pump. Delivery of sludge to the pump well is accomplished via three (3) motorized de-sludge valves.

Once the sludge transfer “start” is manually initiated at the HMI, the 3-way sludge transfer pump discharge valve is commanded to open to “intermediate (discharge) position”, and the three (3) de-sludge valves are also opened to intermediate position (adjustable position set point at the HMI); the duty sludge transfer pump is activated at the “sludge transfer pump start” level set point (adjustable at HMI). Liquid level in the sludge pump well is monitored by a level transmitter (LIT-0502/0702/0902); the signal is also used for transfer pump start and stop control.

When the liquid level in the pump well is lowered to the pre-determined level, the de-sludge valves are fully opened. When the “sludge transfer pump stop” level set point is reached, the sludge transfer pump is stopped, the de-sludge valves are closed, and the 3-way sludge transfer pump discharge valve is commanded to “open” for x minutes (adjustable at HMI). This will drain any remaining liquid from the sludge transfer pipe and the hose back to the pump well. Once “drain” for x minutes is attained, 3-way valve is commanded to close (Note: First close command signal will drive the valve to intermediate position; a second close signal will be required to drive the valve to closed position). The settling basin is now placed back into the normal rotation with the other basins. The associated inlet sluice gate will be opened at the correct time in anticipation of the next backwash.

The volume capacity to receive the Backwash Water in the current duty basin will be continuously calculated. If the next backwash volume is anticipated to exceed the available capacity of the duty settling basin, the aforesaid basin inlet sluice gate will be immediately closed and the inlet sluice gate associated with the next duty basin will be opened. The backwash waste water flow from the current filter will not be split between the two basins.

Polymer Control

When Backwash flow and Backwash pump running status are detected, the polymer skid duty pump will be commanded to start. The polymer feed rate will be flow paced based on the backwash wastewater flow rate “leaving” the filter.

15

Page 16: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 11 of 42

The polymer dosage and polymer concentration will be set at the SCADA HMI and transmitted (via 4-20 mA) to each package polymer controller.

The package polymer system controls polymer pump speed and dilution water in order to prepare the correct polymer solution and to deliver the precise dosage to the system.

When the Backwash wastewater flow is not detected and Backwash pump running status is off, the polymer skid duty pump will be commanded to stop.

Polymer feed rate (flow pacing) will be capped at 2200 L/sec of Backwash wastewater flow (adjustable at HMI).

Supernatant Quality Control

The Total Suspended Solids (TSS) analyzer (FIS-WWW-AIT-0001, 0004) duty sequence (Duty 1, Duty 2) will be selectable at the HMI. Similarly the Chlorine Residual analyzer (FIS-WWW-AIT-0002, 0005) duty sequence (Duty 1, Duty 2) will be also selectable at the HMI.

A High alarm will be generated based on measurement by respective analyzer if the High Set Point is exceeded for an adjustable time delay at the HMI.

A High-High alarm will be generated based on measurement by respective analyzer when the High-High Set Point is exceeded for an adjustable time delay at the HMI. In this instance the supernatant discharge is automatically terminated.

On TSS High-High alarm, the liquid in the basin will be allowed to re-stratify for “stratification time”.

.2 Fault Response Operation

PLC Failure: A PLC failure is detected through the absence of a 'heartbeat' signal from the SCADA system to the PLC. Upon PLC failure, a PLC Failed Alarm will be generated within the SCADA system.

Supernatant Outlet Valve Failure: If a supernatant valve fails to position correctly, generate an alarm.

De-sludge Valve(s) Failure: If a de-sludge valve fails to position correctly, generate an alarm.

De-sludge Valve(s) Failure to Open: Stop and prevent Sludge Transfer Pump start.

Sludge Transfer Pump Failure: If the pump fails during start-up, terminate the sludge transfer. If the pump fails during the sludge transfer, terminate the process and automatically drain the forcemain into the Pump Well.

Backwash Flow Meter Failure: If Backwash flow meter fails during the backwash sequence, the polymer feed rate will be maintained at the last (good) reading. Under this condition, the polymer feed will be stopped

16

Page 17: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 12 of 42

once the B/W pump is off and after an adjustable (at HMI) time delay. The adjustable time delay will begin once the B/W pump is off.

Duty Polymer Skid Failure: If the duty polymer skid fails to start or fails during operation, the skid duty is automatically switched to the other skid.

Level Transmitter (LIT) Failure in the Settling Basin (prior to Backwash): Isolate the associated Settling Basin by closing the Inlet Sluice Gate. The duty feed automatically switches to the next available basin.

Level Transmitter (LIT) Failure in the Settling Basin during Supernatant Discharge: Continue the supernatant discharge; close supernatant discharge valve after an adjustable (at HMI) time delay. The time delay starts when LIT failure is detected.

Level Transmitter (LIT) Failure in Pump Well during De-sludging: Stop the sludge transfer pump.

TSS Duty Analyzer Failure: If the duty analyzer fails, the analyzer duty is automatically switched to the other unit.

Chlorine Residual Analyzer Failure: If the duty analyzer fails, the analyzer duty is automatically switched to the other unit.

.3 Interlocks Contained in Software

The following is a summary of software interlocks for the Residual Management System.

Equipment Event Action Location Alarm

Settling Basin Inlet Sluice Gate

Settling Basin High Level CLOSE and prevent OPEN

PLC Settling Basin High Level Alarm

Sludge Transfer Pumps

Pump Well Low Level STOP and prevent START

PLC Pump Well Low Level Alarm

Three-way Sludge Transfer Pump Discharge Valve Closed

STOP and prevent START

PLC Sludge Transfer Pump Discharge Valve Closed

De-sludge Valve(s) Fail to Open

STOP and prevent START

PLC De-sludge valve(s) Fail to Open

Supernatant Outlet Valves

Supernatant Discharge Total Suspended Solids Concentration High (after time delay)

CLOSE and prevent OPEN

PLC Supernatant Total Suspended Solids Concentration High

Supernatant Discharge Chlorine Residual High (after time delay)

CLOSE and prevent OPEN

PLC Supernatant Chlorine Residual High

.4 Interlocks Contained in Hardware

17

Page 18: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 13 of 42

The following table outlines the interlocks contained in the hardware.

Equipment Event Action Alarm

Pump Well Low-Low Level Switch Activated

STOP and prevent START of Sludge Transfer Pump

Pump Well Low-Low Level

.5 Software Data Points

The following table outlines the input/output signals connected to RPU-1921.

Tag Name  Description 

FIS-WWW-G-0901-YN Settling Basin 0901 Inlet Sluice Gate

Computer Mode (DI)

FIS-WWW-G-0901-YA Settling Basin 0901 Inlet Sluice Gate

Not Available (DI)

FIS-WWW-G-0901-ZH Settling Basin 0901 Inlet Sluice Gate

Opened (DI)

FIS-WWW-G-0901-ZL Settling Basin 0901 Inlet Sluice Gate

Closed (DI)

FIS-WWW-G-0901-WA Settling Basin 0901 Inlet Sluice Gate

Torque Alarm (DI)

FIS-WWW-G-0901-VH Settling Basin 0901 Inlet Sluice Gate

Open Command (DO)

FIS-WWW-G-0901-VL Settling Basin 0901 Inlet Sluice Gate

Close Command (DO)

FIS-WWW-V-0910-YN Settling Basin 0901 Supernatant Outlet

Valve Computer Mode (DI)

FIS-WWW-V-0910-YA Settling Basin 0901 Supernatant Outlet

Valve Not Available (DI)

FIS-WWW-V-0910-ZH Settling Basin 0901 Supernatant Outlet

Valve Opened (DI)

FIS-WWW-V-0910-ZL Settling Basin 0901 Supernatant Outlet

Valve Closed (DI)

FIS-WWW-V-0910-ZI Settling Basin 0901 Supernatant Outlet

Valve Position Indication (AI)

FIS-WWW-V-0910-VC Settling Basin 0901 Supernatant Outlet

Valve Position Setpoint (AO)

18

Page 19: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 14 of 42

Tag Name  Description 

FIS-WWW-V-0911-YN Settling Basin 0901 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0911-YA Settling Basin 0901 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0911-ZH Settling Basin 0901 De-sludge Valve

Opened (DI)

FIS-WWW-V-0911-ZL Settling Basin 0901 De-sludge Valve

Closed (DI)

FIS-WWW-V-0911-ZI Settling Basin 0901 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0911-VC Settling Basin 0901 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0912-YN Settling Basin 0901 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0912-YA Settling Basin 0901 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0912-ZH Settling Basin 0901 De-sludge Valve

Opened (DI)

FIS-WWW-V-0912-ZL Settling Basin 0901 De-sludge Valve

Closed (DI)

FIS-WWW-V-0912-ZI Settling Basin 0901 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0912-VC Settling Basin 0901 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0913-YN Settling Basin 0901 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0913-YA Settling Basin 0901 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0913-ZH Settling Basin 0901 De-sludge Valve

Opened (DI)

FIS-WWW-V-0913-ZL Settling Basin 0901 De-sludge Valve

Closed (DI)

FIS-WWW-V-0913-ZI Settling Basin 0901 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0913-VC Settling Basin 0901 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0915-YN Settling Basin 0901 Sludge Transfer

Pump Discharge Valve Computer Mode (DI)

FIS-WWW-V-0915-YA Settling Basin 0901 Sludge Transfer Pump Discharge Valve Not Available

(DI)

19

Page 20: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 15 of 42

Tag Name  Description 

FIS-WWW-V-0915-ZH Settling Basin 0901 Sludge Transfer Pump Discharge Valve Opened (DI)

FIS-WWW-V-0915-ZL Settling Basin 0901 Sludge Transfer Pump Discharge Valve Closed (DI)

FIS-WWW-V-0915-ZA Settling Basin 0901 Sludge Transfer Pump Discharge Valve Intermediate

Position (DI)

FIS-WWW-V-0915-VH Settling Basin 0901 Sludge Transfer

Pump Discharge Valve Open Command (DO)

FIS-WWW-V-0915-VL Settling Basin 0901 Sludge Transfer

Pump Discharge Valve Close Command (DO)

FIS-WWW-P-0900-YN Settling Basin 0901 Sludge Transfer

Pump Computer Mode (DI)

FIS-WWW-P-0900-YA Settling Basin 0901 Sludge Transfer

Pump Not Available (DI)

FIS-WWW-P-0900-MN Settling Basin 0901 Sludge Transfer

Pump Running (DI)

FIS-WWW-P-0900-XA Settling Basin 0901 Sludge Transfer

Pump Fault (DI)

FIS-WWW-P-0900-MH Settling Basin 0901 Sludge Transfer

Pump Start Command (DO)

FIS-WWW-P-0900-MB Settling Basin 0901 Sludge Transfer

Pump Stop Command (DO)

FIS-WWW-P-0900-SI Settling Basin 0901 Sludge Transfer

Pump Speed Indication (AI

FIS-WWW-P-0900-SC Settling Basin 0901 Sludge Transfer

Pump Speed Setpoint (AO)

FIS-WWW-LSHH-0901-LAHH

Settling Basin 0901 Level High-High Alarm (DI)

FIS-WWW-LIT-0901-LI Setting Basin 0901 Level Indication (AI)

FIS-WWW-LIT-0901-XA Setting Basin 0901 Level Transmitter

Loss of Signal (DI)

FIS-WWW-LSHH-0902-LAHH

Setting Basin 0901 Pump Well Level High-High Alarm (DI)

FIS-WWW-LIT-0902-LI Setting Basin 0901 Pump Well Level

Indication (AI)

FIS-WWW-LIT-0902-XA Setting Basin 0901 Pump Well Level

Transmitter Loss of Signal (DI)

FIS-WWW-LSLL-0901-LALL

Setting Basin 0901 Pump Well Level Low-Low Alarm (DI)

20

Page 21: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 16 of 42

Tag Name  Description 

FIS-WWW-LSHH-0902-LAHH

Setting Basin 0901 Pump Well Level High-High Alarm (DI)

FIS-WWW-G-0701-YN Settling Basin 0701 Inlet Sluice Gate

Computer Mode (DI)

FIS-WWW-G-0701-YA Settling Basin 0701 Inlet Sluice Gate

Not Available (DI)

FIS-WWW-G-0701-ZH Settling Basin 0701 Inlet Sluice Gate

Opened (DI)

FIS-WWW-G-0701-ZL Settling Basin 0701 Inlet Sluice Gate

Closed (DI)

FIS-WWW-G-0701-WA Settling Basin 0701 Inlet Sluice Gate

Torque Alarm (DI)

FIS-WWW-G-0701-VH Settling Basin 0701 Inlet Sluice Gate

Open Command (DO)

FIS-WWW-G-0701-VL Settling Basin 0701 Inlet Sluice Gate

Close Command (DO)

FIS-WWW-V-0710-YN Settling Basin 0701 Supernatant Outlet

Valve Computer Mode (DI)

FIS-WWW-V-0710-YA Settling Basin 0701 Supernatant Outlet

Valve Not Available (DI)

FIS-WWW-V-0710-ZH Settling Basin 0701 Supernatant Outlet

Valve Opened (DI)

FIS-WWW-V-0710-ZL Settling Basin 0701 Supernatant Outlet

Valve Closed (DI)

FIS-WWW-V-0710-ZI Settling Basin 0701 Supernatant Outlet

Valve Position Indication (AI)

FIS-WWW-V-0710-VC Settling Basin 0701 Supernatant Outlet

Valve Position Setpoint (AO)

FIS-WWW-V-0711-YN Settling Basin 0701 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0711-YA Settling Basin 0701 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0711-ZH Settling Basin 0701 De-sludge Valve

Opened (DI)

FIS-WWW-V-0711-ZL Settling Basin 0701 De-sludge Valve

Closed (DI)

21

Page 22: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 17 of 42

Tag Name  Description 

FIS-WWW-V-0711-ZI Settling Basin 0701 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0711-VC Settling Basin 0701 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0712-YN Settling Basin 0701 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0712-YA Settling Basin 0701 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0712-ZH Settling Basin 0701 De-sludge Valve

Opened (DI)

FIS-WWW-V-0712-ZL Settling Basin 0701 De-sludge Valve

Closed (DI)

FIS-WWW-V-0712-ZI Settling Basin 0701 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0712-VC Settling Basin 0701 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0713-YN Settling Basin 0701 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0713-YA Settling Basin 0701 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0713-ZH Settling Basin 0701 De-sludge Valve

Opened (DI)

FIS-WWW-V-0713-ZL Settling Basin 0701 De-sludge Valve

Closed (DI)

FIS-WWW-V-0713-ZI Settling Basin 0701 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0713-VC Settling Basin 0701 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0715-YN Settling Basin 0701 Sludge Transfer

Pump Discharge Valve Computer Mode (DI)

FIS-WWW-V-0715-YA Settling Basin 0701 Sludge Transfer Pump Discharge Valve Not Available

(DI)

FIS-WWW-V-0715-ZH Settling Basin 0701 Sludge Transfer Pump Discharge Valve Opened (DI)

FIS-WWW-V-0715-ZL Settling Basin 0701 Sludge Transfer Pump Discharge Valve Closed (DI)

FIS-WWW-V-0715-ZA Settling Basin 0701 Sludge Transfer Pump Discharge Valve Intermediate

Position (DI)

FIS-WWW-V-0715-VH Settling Basin 0701 Sludge Transfer

Pump Discharge Valve Open Command (DO)

22

Page 23: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 18 of 42

Tag Name  Description 

FIS-WWW-V-0715-VL Settling Basin 0701 Sludge Transfer

Pump Discharge Valve Close Command (DO)

FIS-WWW-P-0700-YN Settling Basin 0701 Sludge Transfer

Pump Computer Mode (DI)

FIS-WWW-P-0700-YA Settling Basin 0701 Sludge Transfer

Pump Not Available (DI)

FIS-WWW-P-0700-MN Settling Basin 0701 Sludge Transfer

Pump Running (DI)

FIS-WWW-P-0700-XA Settling Basin 0701 Sludge Transfer

Pump Fault (DI)

FIS-WWW-P-0700-MH Settling Basin 0701 Sludge Transfer

Pump Start Command (DO)

FIS-WWW-P-0700-MB Settling Basin 0701 Sludge Transfer

Pump Stop Command (DO)

FIS-WWW-P-0700-SI Settling Basin 0701 Sludge Transfer

Pump Speed Indication (AI)

FIS-WWW-P-0700-SC Settling Basin 0701 Sludge Transfer

Pump Speed Setpoint (AO)

FIS-WWW-LIT-0701-LI Setting Basin 0701 Level Indication (AI)

FIS-WWW-LIT-0701-XA Setting Basin 0701 Level Transmitter

Loss of Signal (DI)

FIS-WWW-LSHH-0701-LAHH

Setting Basin 0701 Level High-High Alarm (DI)

FIS-WWW-LIT-0702-LI Setting Basin 0701 Pump Well Level

Indication (AI)

FIS-WWW-LIT-0702-XA Setting Basin 0701 Pump Well Level

Transmitter Loss of Signal (DI)

FIS-WWW-LSLL-0701-LALL

Setting Basin 0701 Pump Well Level Low-Low Alarm (DI)

FIS-WWW-LSHH-0702-LAHH

Setting Basin 0701 Pump Well Level High-High Alarm (DI)

FIS-WWW-G-0501-YN Settling Basin 0501 Inlet Sluice Gate

Computer Mode (DI)

FIS-WWW-G-0501-YA Settling Basin 0501 Inlet Sluice Gate

Not Available (DI)

FIS-WWW-G-0501-ZH Settling Basin 0501 Inlet Sluice Gate

Opened (DI)

23

Page 24: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 19 of 42

Tag Name  Description 

FIS-WWW-G-0501-ZL Settling Basin 0501 Inlet Sluice Gate

Closed (DI)

FIS-WWW-G-0501-WA Settling Basin 0501 Inlet Sluice Gate

Torque Alarm (DI)

FIS-WWW-G-0501-VH Settling Basin 0501 Inlet Sluice Gate

Open Command (DO)

FIS-WWW-G-0501-VL Settling Basin 0501 Inlet Sluice Gate

Close Command (DO)

FIS-WWW-V-0510-YN Settling Basin 0501 Supernatant Outlet

Valve Computer Mode (DI)

FIS-WWW-V-0510-YA Settling Basin 0501 Supernatant Outlet

Valve Not Available (DI)

FIS-WWW-V-0510-ZH Settling Basin 0501 Supernatant Outlet

Valve Opened (DI)

FIS-WWW-V-0510-ZL Settling Basin 0501 Supernatant Outlet

Valve Closed (DI)

FIS-WWW-V-0510-ZI Settling Basin 0501 Supernatant Outlet

Valve Position Indication (AI)

FIS-WWW-V-0510-VC Settling Basin 0501 Supernatant Outlet

Valve Position Setpoint (AO)

FIS-WWW-V-0511-YN Settling Basin 0501 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0511-YA Settling Basin 0501 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0511-ZH Settling Basin 0501 De-sludge Valve

Opened (DI)

FIS-WWW-V-0511-ZL Settling Basin 0501 De-sludge Valve

Closed (DI)

FIS-WWW-V-0511-ZI Settling Basin 0501 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0511-VC Settling Basin 0501 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0512-YN Settling Basin 0501 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0512-YA Settling Basin 0501 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0512-ZH Settling Basin 0501 De-sludge Valve

Opened (DI)

24

Page 25: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 20 of 42

Tag Name  Description 

FIS-WWW-V-0512-ZL Settling Basin 0501 De-sludge Valve

Closed (DI)

FIS-WWW-V-0512-ZI Settling Basin 0501 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0512-VC Settling Basin 0501 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0513-YN Settling Basin 0501 De-sludge Valve

Computer Mode (DI)

FIS-WWW-V-0513-YA Settling Basin 0501 De-sludge Valve Not

Available (DI)

FIS-WWW-V-0513-ZH Settling Basin 0501 De-sludge Valve

Opened (DI)

FIS-WWW-V-0513-ZL Settling Basin 0501 De-sludge Valve

Closed (DI)

FIS-WWW-V-0513-ZI Settling Basin 0501 De-sludge Valve

Position Indication (AI)

FIS-WWW-V-0513-VC Settling Basin 0501 De-sludge Valve

Position Setpoint (AO)

FIS-WWW-V-0515-YN Settling Basin 0501 Sludge Transfer

Pump Discharge Valve Computer Mode (DI)

FIS-WWW-V-0515-YA Settling Basin 0501 Sludge Transfer Pump Discharge Valve Not Available

(DI)

FIS-WWW-V-0515-ZH Settling Basin 0501 Sludge Transfer Pump Discharge Valve Opened (DI)

FIS-WWW-V-0515-ZL Settling Basin 0501 Sludge Transfer Pump Discharge Valve Closed (DI)

FIS-WWW-V-0515-ZA Settling Basin 0501 Sludge Transfer Pump Discharge Valve Intermediate

Position (DI)

FIS-WWW-V-0515-VH Settling Basin 0501 Sludge Transfer

Pump Discharge Valve Open Command (DO)

FIS-WWW-V-0515-VL Settling Basin 0501 Sludge Transfer

Pump Discharge Valve Close Command (DO)

FIS-WWW-P-0500-YN Settling Basin 0501 Sludge Transfer

Pump Computer Mode (DI)

FIS-WWW-P-0500-YA Settling Basin 0501 Sludge Transfer

Pump Not Available (DI)

FIS-WWW-P-0500-MN Settling Basin 0501 Sludge Transfer

Pump Running (DI)

25

Page 26: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 21 of 42

Tag Name  Description 

FIS-WWW-P-0500-XA Settling Basin 0501 Sludge Transfer

Pump Fault (DI)

FIS-WWW-P-0500-MH Settling Basin 0501 Sludge Transfer

Pump Start Command (DO)

FIS-WWW-P-0500-MB Settling Basin 0501 Sludge Transfer

Pump Stop Command (DO)

FIS-WWW-P-0500-SI Settling Basin 0501 Sludge Transfer

Pump Speed Indication (AI)

FIS-WWW-P-0500-SC Settling Basin 0501 Sludge Transfer

Pump Speed Setpoint (AO)

FIS-WWW-LIT-0501-LI Setting Basin 0501 Level Indication (AI)

FIS-WWW-LIT-0501-XA Setting Basin 0501 Level Transmitter

Loss of Signal (DI)

FIS-WWW-LSHH-0501-LAHH

Setting Basin 0501 Level High-High Alarm (DI)

FIS-WWW-LIT-0502-LI Setting Basin 0501 Pump Well Level

Indication (AI)

FIS-WWW-LIT-0502-XA Setting Basin 0501 Pump Well Level

Transmitter Loss of Signal (DI)

FIS-WWW-LSLL-0501-LALL

Setting Basin 0501 Pump Well Level Low-Low Alarm (DI)

FIS-WWW-LSHH-0502-LAHH

Setting Basin 0501 Pump Well Level High-High Alarm (DI)

FIS-POL-CP-1000-YN Polymer Skid 1000 Computer Mode (DI)

FIS-POL-P-1001-MN Polymer Pump 1001 Running (DI)

FIS-POL-P-1001-YA Polymer Pump 1001 Not Available (DI)

FIS-POL-FE-1001-FAL Polymer Skid 1000 Dilution Water Low

Flow Alarm (DI)

FIS-POL-CP-1000-XA Polymer Skid 1000 General Alarm (DI)

FIS-POL-P-1001-MH Polymer Pump 1001 Start Command

(DO)

FIS-POL-P-1001-MB Polymer Pump 1001 Stop Command

(DO)

FIS-POL-FIT-1002-FI Polymer Skid 1000 Polymer Solution

Flow Indication (AI)

26

Page 27: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 22 of 42

Tag Name  Description 

FIS-POL-FIT-1002-XA Polymer Skid 1000 Polymer Solution Flow Transmitter Loss of Signal (DI)

FIS-POL-FRIC-1000-FC Polymer Skid 1000 Filter Backwash

Water Flow Set Point (AO)

FIS-POL-FRIC-1000-ACA Polymer Concentration (AO)

FIS-POL-FRIC-1000-ACB Polymer Dosage (AO)

FIS-POL-UPS-1000-EAL Polymer Skid PLC UPS Battery Low

Voltage (DI)

FIS-POL-UPS-1000-XA Polymer Skid PLC UPS Failure (DI)

FIS-POL-UPS-1000-EAL Polymer Skid PLC UPS Power Failure

(DI)

FIS-POL-LSH-0001-LAH Polymer Room Containment Spill Alarm

FIS-POL-CP-1100-YN Polymer Skid 1100 Computer Mode (DI)

FIS-POL-P-1101-MN Polymer Pump 1101 Running (DI)

FIS-POL-P-1101-YA Polymer Pump 1101 Not Available (DI)

FIS-POL-FE-1101-FAL Polymer Skid 1100 Dilution Water Low

Flow Alarm (DI)

FIS-POL-CP-1100-XA Polymer Skid 1100 General Alarm (DI)

FIS-POL-P-1101-MH Polymer Pump 1101 Start Command

(DO)

FIS-POL-P-1101-MB Polymer Pump 1101 Stop Command

(DO)

FIS-POL-FIT-1102-FI Polymer Skid 1100 Polymer Solution

Flow Indication (AI)

FIS-POL-FIT-1102-XA Polymer Skid 1100 Polymer Solution Flow Transmitter Loss of Signal (DI)

FIS-POL-FRIC-1100-FC Polymer Skid 1100 Filter Backwash

Water Flow Set Point (AO)

FIS-POL-FRIC-1100-ACA Polymer Concentration (AO)

27

Page 28: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 23 of 42

Tag Name  Description 

FIS-POL-FRIC-1100-ACB Polymer Dosage (AO)

FIS-POL-UPS-1100-EAL Polymer Skid PLC UPS Battery Low

Voltage (DI)

FIS-POL-UPS-1100-XA Polymer Skid PLC UPS Failure (DI)

FIS-POL-UPS-1100-EAL Polymer Skid PLC UPS Power Failure

(DI)

FIS-SPC-UPS-1921-EAL RPU-1921 UPS Battery Low Voltage (DI)

FIS-SPC-UPS-1921-XA RPU-1921 UPS Failure (DI)

FIS-SPC-UPS-1921-EA RPU-1921 UPS Power Failure (DI)

FIS-SPC-PS-1921C-XA RPU-1921 24VDC Power Supply

Redundancy Fail (DI)

FIS-SPC-ASH-1921-XA RPU-1921 Smoke/Heat Alarm (DI)

FIS-SES-FSH-0001-FAH Polymer Room Eyewash Shower Flow

Alarm High (DI)

FIS-ACC-TIT-0001-TI PLC Room Ambient Temperature

Indication (AI)

FIS-ACC-TIC-0001-XA Heat Tracing General Alarm (DI)

FIS-ACC-TIC-0002-XA Heat Tracing General Alarm (DI)

FIS-ACC-TIC-0003-XA Heat Tracing General Alarm (DI)

The following table outlines the additional input/output signals connected to existing RPU-1821.

Tag Name Description

FIS-WWW-AIT-0004-AI Supernatant Total Suspended Solids

Indication (AI)

FIS-WWW-AIT-0004-XA Supernatant Total Suspended Solids

Analyzer Fault (DI)

28

Page 29: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 24 of 42

Tag Name Description

FIS-WWW-AIT-0005-AI Supernatant Chlorine Residual Indication

(AI)

FIS-WWW-AIT-0005-XA Supernatant Chlorine Residual Analyzer

Fault (DI)

.6 Associated Alarms

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

FIS-WWW-LIT-0901-YA

Settling Basin 0901 Level Transmitter Loss of Signal

LOW NO

FIS-WWW-LIT-0901-XAHH-R

Settling Basin 0901 Level Alarm HI HI

LOW NO

FIS-WWW-LIT-0901-XAH-R

Settling Basin 0901 Level Alarm HI

LOW NO

FIS-WWW-LIT-0901-XALL-R

Settling Basin 0901 Level Alarm LO LO

LOW NO

FIS-WWW-LIT-0901-XAL-R

Settling Basin 0901 Level Alarm LO

LOW NO

FIS-WWW-LIT-0901-XAHC-R

Settling Basin 0901 Level Out of Range Alarm HI

LOW NO

FIS-WWW-LIT-0901-XALC-R

Settling Basin 0901 Level Out of Range Alarm LO

LOW NO

FIS-WWW-LIT-0902-YA

Settling Basin 0901 Pump Well Level Transmitter Loss of Signal

LOW NO

FIS-WWW-LIT-0902-XAHH-R

Settling Basin 0901 Pump Well Level Alarm HI HI

LOW NO

FIS-WWW-LIT-0902-XAH-R

Settling Basin 0901 Pump Well Level Alarm HI

LOW NO

FIS-WWW-LIT-0902-XALL-R

Settling Basin 0901 Pump Well Level Alarm LO LO

LOW NO

FIS-WWW-LIT-0902-XAL-R

Settling Basin 0901 Pump Well Level Alarm LO

LOW NO

FIS-WWW-LIT-0902-XAHC-R

Settling Basin 0901 Pump Well Level Out of Range Alarm HI

LOW NO

FIS-WWW-LIT-0902-XALC-R

Settling Basin 0901 Pump Well Level Out of Range Alarm LO

LOW NO

29

Page 30: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 25 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

FIS-WWW-LSHH-0901-LAHH

Settling Basin 0901 Level HI HI Alarm

LOW NO

LOW FIS-WWW-LSLL-0901-LALL

Settling Basin 0901 Pump Well Level LO LO Alarm

LOW NO

LOW FIS-WWW-LSHH-0902-LALL

Settling Basin 0901 Pump Well Level HI HI Alarm

LOW NO

FIS-WWW-G-0901-YA

Settling Basin 0901 Inlet Sluice Gate Not Available

LOW NO

FIS-WWW-G-0901-WA

Settling Basin 0901 Inlet Sluice Gate Torque Alarm

LOW NO

FIS-WWW-G-0901-ZHUXA-R

Settling Basin 0901 Inlet Sluice Gate Uncommanded Open

LOW NO

FIS-WWW-G-0901-ZLUXA-R

Settling Basin 0901 Inlet Sluice Gate Uncommanded Close

LOW NO

FIS-WWW-G-0901-ZHXA-R

Settling Basin 0901 Inlet Sluice Gate Fail to Open

LOW NO

FIS-WWW-G-0901-ZLXA-R

Settling Basin 0901 Inlet Sluice Gate Fail to Close

LOW NO

FIS-WWW-G-0901-ZXA-R

Settling Basin 0901 Inlet Sluice Gate Unknown Position

LOW NO

FIS-WWW-V-0910-YA

Settling Basin 0901 Supernatant Outlet Valve Not Available

LOW NO

FIS-WWW-V-0910-ZCXA-R

Settling Basin 0901 Supernatant Outlet Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0910-ZAHC-R

Settling Basin 0901 Supernatant Outlet Valve Position Out of Range High

LOW NO

FIS-WWW-V-0910-ZALC-R

Settling Basin 0901 Supernatant Outlet Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0911-YA

Settling Basin 0901 De-sludge Valve Not Available

LOW NO

30

Page 31: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 26 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

FIS-WWW-V-0911-ZCXA-R

Settling Basin 0901 De-sludge Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0911-ZAHC-R

Settling Basin 0901 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0911-ZALC-R

Settling Basin 0901 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0912-YA

Settling Basin 0901 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0912-ZCXA-R

Settling Basin 0901 De-sludge Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0912-ZAHC-R

Settling Basin 0901 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0912-ZALC-R

Settling Basin 0901 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0913-YA

Settling Basin 0901 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0913-ZCXA-R

Settling Basin 0901 De-sludge Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0913-ZAHC-R

Settling Basin 0901 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0913-ZALC-R

Settling Basin 0901 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0915-YA

Settling Basin 0901 Sludge Transfer Pump Discharge Valve Not Available

LOW NO

FIS-WWW-V-0915-ZHUXA-R

Settling Basin 0901 Sludge Transfer Pump Discharge Valve Uncommanded Open

LOW NO

FIS-WWW-V-0915-ZLUXA-R

Settling Basin 0901 Sludge Transfer Pump Discharge Valve

LOW NO

31

Page 32: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 27 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

Uncommanded Close

FIS-WWW-V-0915-ZHXA-R

Settling Basin 0901 Sludge Transfer Pump Discharge Valve Fail to Open

LOW NO

FIS-WWW-V-0915-ZLXA-R

Settling Basin 0901 Sludge Transfer Pump Discharge Valve Fail to Close

LOW NO

FIS-WWW-V-0915-ZMXA-R

Settling Basin 0901 Sludge Transfer Pump Discharge Valve Fail to Reach Intermediate Position

LOW NO

FIS-WWW-V-0915-ZXA-R

Settling Basin 0901 Sludge Transfer Pump Discharge Valve Unknown Position

LOW NO

FIS-WWW-P-0900-YA

Settling Basin 0901 Sludge Transfer Pump Not Available

LOW NO

FIS-WWW-P-0900-XA

Settling Basin 0901 Sludge Transfer Pump Fault

LOW NO

FIS-WWW-P-0900-MNXA-R

Settling Basin 0901 Sludge Transfer Pump Fail to Start

LOW NO

FIS-WWW-P-0900-MLBXA-R

Settling Basin 0901 Sludge Transfer Pump Fail to Stop

LOW NO

FIS-WWW-P-0900-MNUXA-R

Settling Basin 0901 Sludge Transfer Pump Uncommanded Start

LOW NO

FIS-WWW-P-0900-MLBUXA-R

Settling Basin 0901 Sludge Transfer Pump Uncommanded Stop

LOW NO

FIS-WWW-P-0900-SIDB-R

Settling Basin 0901 Sludge Transfer Pump Fail to Reach Setpoint

LOW NO

FIS-WWW-P-0900-SAHC-R

Settling Basin 0901 Sludge Transfer Pump Speed Out of Range High

LOW NO

FIS-WWW-P-0900-SALC-R

Settling Basin 0901 Sludge Transfer Pump Speed Out of Range Low

LOW NO

32

Page 33: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 28 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

FIS-WWW-LIT-0701-YA

Settling Basin 0701 Level Transmitter Loss of Signal

LOW NO

FIS-WWW-LIT-0701-XAHH-R

Settling Basin 0701 Level Alarm HI HI

LOW NO

FIS-WWW-LIT-0701-XAH-R

Settling Basin 0701 Level Alarm HI

LOW NO

FIS-WWW-LIT-0701-XALL-R

Settling Basin 0701 Level Alarm LO LO

LOW NO

FIS-WWW-LIT-0701-XAL-R

Settling Basin 0701 Level Alarm LO

LOW NO

FIS-WWW-LIT-0701-XAHC-R

Settling Basin 0701 Level Out of Range Alarm HI

LOW NO

FIS-WWW-LIT-0701-XALC-R

Settling Basin 0701 Level Out of Range Alarm LO

LOW NO

NO

FIS-WWW-LIT-0702-YA

Settling Basin 0701 Pump Well Level Transmitter Loss of Signal

LOW NO

FIS-WWW-LIT-0702-XAHH-R

Settling Basin 0701 Pump Well Level Alarm HI HI

LOW NO

FIS-WWW-LIT-0702-XAH-R

Settling Basin 0701 Pump Well Level Alarm HI

LOW NO

FIS-WWW-LIT-0702-XALL-R

Settling Basin 0701 Pump Well Level Alarm LO LO

LOW NO

FIS-WWW-LIT-0702-XAL-R

Settling Basin 0701 Pump Well Level Alarm LO

LOW NO

FIS-WWW-LIT-0702-XAHC-R

Settling Basin 0701 Pump Well Level Out of Range Alarm HI

LOW NO

FIS-WWW-LIT-0702-XALC-R

Settling Basin 0701 Pump Well Level Out of Range Alarm LO

LOW NO

FIS-WWW-LSHH-0701-LAHH

Settling Basin 0701 Level HI HI Alarm

LOW NO

LOW NO FIS-WWW-LSLL-0701-LALL

Settling Basin 0701 Pump Well Level LO LO Alarm

LOW NO

LOW NO FIS-WWW-LSHH-0702-LALL

Settling Basin 0701 Pump Well Level HI HI Alarm

LOW NO

NO FIS-WWW-G-0701-YA

Settling Basin 0701 Inlet Sluice Gate Not Available

LOW NO

FIS-WWW-G-0701-WA

Settling Basin 0701 Inlet Sluice Gate Torque Alarm

LOW NO

FIS-WWW-G- Settling Basin 0701 Inlet LOW NO 33

Page 34: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 29 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

0701-ZHUXA-R Sluice Gate Uncommanded Open

FIS-WWW-G-0701-ZLUXA-R

Settling Basin 0701 Inlet Sluice Gate Uncommanded Close

LOW NO

FIS-WWW-G-0701-ZHXA-R

Settling Basin 0701 Inlet Sluice Gate Fail to Open

LOW NO

FIS-WWW-G-0701-ZLXA-R

Settling Basin 0701 Inlet Sluice Gate Fail to Close

LOW NO

FIS-WWW-G-0701-ZXA-R

Settling Basin 0701 Inlet Sluice Gate Unknown Position

LOW NO

FIS-WWW-V-0710-YA

Settling Basin 0701 Supernatant Outlet Valve Not Available

LOW NO

FIS-WWW-V-0710-ZCXA-R

Settling Basin 0701 Supernatant Outlet Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0710-ZAHC-R

Settling Basin 0701 Supernatant Outlet Valve Position Out of Range High

LOW NO

FIS-WWW-V-0710-ZALC-R

Settling Basin 0701 Supernatant Outlet Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0711-YA

Settling Basin 0701 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0711-ZCXA-R

Settling Basin 0701 De-sludge Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0711-ZAHC-R

Settling Basin 0701 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0711-ZALC-R

Settling Basin 0701 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0712-YA

Settling Basin 0701 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0712-ZCXA-R

Settling Basin 0701 De-sludge Valve Fail to Reach

LOW NO

34

Page 35: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 30 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

Position Set Point

FIS-WWW-V-0712-ZAHC-R

Settling Basin 0701 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0712-ZALC-R

Settling Basin 0701 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0713-YA

Settling Basin 0701 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0713-ZCXA-R

Settling Basin 0701 De-sludge Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0713-ZAHC-R

Settling Basin 0701 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0713-ZALC-R

Settling Basin 0701 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0715-YA

Settling Basin 0701 Sludge Transfer Pump Discharge Valve Not Available

LOW NO

FIS-WWW-V-0715-ZHUXA-R

Settling Basin 0701 Sludge Transfer Pump Discharge Valve Uncommanded Open

LOW NO

FIS-WWW-V-0715-ZLUXA-R

Settling Basin 0701 Sludge Transfer Pump Discharge Valve Uncommanded Close

LOW NO

FIS-WWW-V-0715-ZHXA-R

Settling Basin 0701 Sludge Transfer Pump Discharge Valve Fail to Open

LOW NO

FIS-WWW-V-0715-ZLXA-R

Settling Basin 0701 Sludge Transfer Pump Discharge Valve Fail to Close

LOW NO

FIS-WWW-V-0715-ZMXA-R

Settling Basin 0701 Sludge Transfer Pump Discharge Valve Fail to Reach Intermediate Position

LOW NO

FIS-WWW-V- Settling Basin 0701 LOW NO 35

Page 36: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 31 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

0715-ZXA-R Sludge Transfer Pump Discharge Valve Unknown Position

FIS-WWW-P-0700-YA

Settling Basin 0701 Sludge Transfer Pump Not Available

LOW NO

FIS-WWW-P-0700-XA

Settling Basin 0701 Sludge Transfer Pump Fault

LOW NO

FIS-WWW-P-0700-MNXA-R

Settling Basin 0701 Sludge Transfer Pump Fail to Start

LOW NO

FIS-WWW-P-0700-MLBXA-R

Settling Basin 0701 Sludge Transfer Pump Fail to Stop

LOW NO

FIS-WWW-P-0700-MNUXA-R

Settling Basin 0701 Sludge Transfer Pump Uncommanded Start

LOW NO

FIS-WWW-P-0700-MLBUXA-R

Settling Basin 0701 Sludge Transfer Pump Uncommanded Stop

LOW NO

FIS-WWW-P-0700-SIDB-R

Settling Basin 0701 Sludge Transfer Pump Fail to Reach Setpoint

LOW NO

FIS-WWW-P-0700-SAHC-R

Settling Basin 0701 Sludge Transfer Pump Speed Out of Range High

LOW NO

FIS-WWW-P-0700-SALC-R

Settling Basin 0701 Sludge Transfer Pump Speed Out of Range Low

LOW NO

FIS-WWW-LIT-0501-YA

Settling Basin 0501 Level Transmitter Loss of Signal

LOW NO

FIS-WWW-LIT-0501-XAHH-R

Settling Basin 0501 Level Alarm HI HI

LOW NO

FIS-WWW-LIT-0501-XAH-R

Settling Basin 0501 Level Alarm HI

LOW NO

FIS-WWW-LIT-0501-XALL-R

Settling Basin 0501 Level Alarm LO LO

LOW NO

FIS-WWW-LIT-0501-XAL-R

Settling Basin 0501 Level Alarm LO

LOW NO

FIS-WWW-LIT-0501-XAHC-R

Settling Basin 0501 Level Out of Range Alarm HI

LOW NO

FIS-WWW-LIT-0501-XALC-R

Settling Basin 0501 Level Out of Range Alarm LO

LOW NO

36

Page 37: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 32 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

FIS-WWW-LIT-0502-YA

Settling Basin 0501 Pump Well Level Transmitter Loss of Signal

LOW NO

FIS-WWW-LIT-0502-XAHH-R

Settling Basin 0501 Pump Well Level Alarm HI HI

LOW NO

FIS-WWW-LIT-0502-XAH-R

Settling Basin 0501 Pump Well Level Alarm HI

LOW NO

FIS-WWW-LIT-0502-XALL-R

Settling Basin 0501 Pump Well Level Alarm LO LO

LOW NO

FIS-WWW-LIT-0502-XAL-R

Settling Basin 0501 Pump Well Level Alarm LO

LOW NO

FIS-WWW-LIT-0502-XAHC-R

Settling Basin 0501 Pump Well Level Out of Range Alarm HI

LOW NO

FIS-WWW-LIT-0502-XALC-R

Settling Basin 0501 Pump Well Level Out of Range Alarm LO

LOW NO

FIS-WWW-LSHH-0501-LAHH

Settling Basin 0501 Level HI HI Alarm

LOW NO

LOW FIS-WWW-LSLL-0501-LALL

Settling Basin 0501 Pump Well Level LO LO Alarm

LOW NO

LOW FIS-WWW-LSHH-0502-LALL

Settling Basin 0501 Pump Well Level HI HI Alarm

LOW NO

FIS-WWW-G-0501-YA

Settling Basin 0501 Inlet Sluice Gate Not Available

LOW NO

FIS-WWW-G-0501-WA

Settling Basin 0501 Inlet Sluice Gate Torque Alarm

LOW NO

FIS-WWW-G-0501-ZHUXA-R

Settling Basin 0501 Inlet Sluice Gate Uncommanded Open

LOW NO

FIS-WWW-G-0501-ZLUXA-R

Settling Basin 0501 Inlet Sluice Gate Uncommanded Close

LOW NO

FIS-WWW-G-0501-ZHXA-R

Settling Basin 0501 Inlet Sluice Gate Fail to Open

LOW NO

FIS-WWW-G-0501-ZLXA-R

Settling Basin 0501 Inlet Sluice Gate Fail to Close

LOW NO

FIS-WWW-G-0501-ZXA-R

Settling Basin 0501 Inlet Sluice Gate Unknown Position

LOW NO

FIS-WWW-V- Settling Basin 0501 LOW NO

37

Page 38: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 33 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

0510-YA Supernatant Outlet Valve Not Available

FIS-WWW-V-0510-ZCXA-R

Settling Basin 0501 Supernatant Outlet Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0510-ZAHC-R

Settling Basin 0501 Supernatant Outlet Valve Position Out of Range High

LOW NO

FIS-WWW-V-0510-ZALC-R

Settling Basin 0501 Supernatant Outlet Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0511-YA

Settling Basin 0501 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0511-ZCXA-R

Settling Basin 0501 De-sludge Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0511-ZAHC-R

Settling Basin 0501 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0511-ZALC-R

Settling Basin 0501 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0512-YA

Settling Basin 0501 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0512-ZCXA-R

Settling Basin 0501 De-sludge Valve Fail to Reach Position Set Point

LOW NO

FIS-WWW-V-0512-ZAHC-R

Settling Basin 0501 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0512-ZALC-R

Settling Basin 0501 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0513-YA

Settling Basin 0501 De-sludge Valve Not Available

LOW NO

FIS-WWW-V-0513-ZCXA-R

Settling Basin 0501 De-sludge Valve Fail to Reach Position Set Point

LOW NO

38

Page 39: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 34 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

FIS-WWW-V-0513-ZAHC-R

Settling Basin 0501 De-sludge Valve Position Out of Range High

LOW NO

FIS-WWW-V-0513-ZALC-R

Settling Basin 0501 De-sludge Valve Position Out of Range Low

LOW NO

FIS-WWW-V-0515-YA

Settling Basin 0501 Sludge Transfer Pump Discharge Valve Not Available

LOW NO

FIS-WWW-V-0515-ZHUXA-R

Settling Basin 0501 Sludge Transfer Pump Discharge Valve Uncommanded Open

LOW NO

FIS-WWW-V-0515-ZLUXA-R

Settling Basin 0501 Sludge Transfer Pump Discharge Valve Uncommanded Close

LOW NO

FIS-WWW-V-0515-ZHXA-R

Settling Basin 0501 Sludge Transfer Pump Discharge Valve Fail to Open

LOW NO

FIS-WWW-V-0515-ZLXA-R

Settling Basin 0501 Sludge Transfer Pump Discharge Valve Fail to Close

LOW NO

FIS-WWW-V-0515-ZMXA-R

Settling Basin 0501 Sludge Transfer Pump Discharge Valve Fail to Reach Intermediate Position

LOW NO

FIS-WWW-V-0515-ZXA-R

Settling Basin 0501 Sludge Transfer Pump Discharge Valve Unknown Position

LOW NO

FIS-WWW-P-0500-YA

Settling Basin 0501 Sludge Transfer Pump Not Available

LOW NO

FIS-WWW-P-0500-XA

Settling Basin 0501 Sludge Transfer Pump Fault

LOW NO

FIS-WWW-P-0500-MNXA-R

Settling Basin 0501 Sludge Transfer Pump Fail to Start

LOW NO

FIS-WWW-P- Settling Basin 0501 LOW NO

39

Page 40: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 35 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

0500-MLBXA-R Sludge Transfer Pump Fail to Stop

FIS-WWW-P-0500-MNUXA-R

Settling Basin 0501 Sludge Transfer Pump Uncommanded Start

LOW NO

FIS-WWW-P-0500-MLBUXA-R

Settling Basin 0501 Sludge Transfer Pump Uncommanded Stop

LOW NO

FIS-WWW-P-0500-SIDB-R

Settling Basin 0501 Sludge Transfer Pump Fail to Reach Setpoint

LOW NO

FIS-WWW-P-0500-SAHC-R

Settling Basin 0501 Sludge Transfer Pump Speed Out of Range High

LOW NO

FIS-WWW-P-0500-SALC-R

Settling Basin 0501 Sludge Transfer Pump Speed Out of Range Low

LOW NO

FIS-POL-P-1001-YA

Polymer Pump 1001 Not Available

LOW NO

FIS-POL-P-1001-MNXA-R

Polymer Pump 1001 Fail to Start

LOW NO

FIS-POL-P-1001-MLBXA-R

Polymer Pump 1001 Fail to Stop

LOW NO

FIS-POL-P-1001-MNUXA-R

Polymer Pump 1001 Uncommanded Start

LOW NO

FIS-POL-P-1001-MLBUXA-R

Polymer Pump 1001 Uncommanded Stop

LOW NO

FIS-POL-FE-1001-FAL

Polymer Skid 1000 Dilution Water Low Flow Alarm

LOW NO

FIS-POL-CP-1000-XA

Polymer Skid 1000 General Alarm

LOW NO

FIS-POL-FIT-1002-XAHH-R

Polymer Solution Flow Alarm HI HI

MEDIUM NO

FIS-POL-FIT-1002-XAH-R

Polymer Solution Flow Alarm HI

MEDIUM NO

FIS-POL-FIT-1002-XALL-R

Polymer Solution Flow Alarm LO LO

MEDIUM NO

FIS-POL-FIT-1002-XAL-R

Polymer Solution Flow Alarm LO

MEDIUM NO

FIS-POL-FIT-1002-XAHC-R

Polymer Solution Flow Out of Range HI

MEDIUM NO

FIS-POL-FIT-1002-XALC-R

Polymer Solution Flow Out of Range LO

MEDIUM NO

FIS-POL-UPS- Polymer Skid PLC UPS MEDIUM NO 40

Page 41: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 36 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

1000-EAL Battery Low Voltage FIS-POL-UPS-1000-XA

Polymer Skid PLC UPS Failure

MEDIUM NO

FIS-POL-UPS-1000-EA

Polymer Skid PLC UPS Power Failure

MEDIUM NO

FIS-POL-P-1101-YA

Polymer Pump 1101 Not Available

LOW NO

FIS-POL-P-1101-MNXA-R

Polymer Pump 1101 Fail to Start

LOW NO

FIS-POL-P-1101-MLBXA-R

Polymer Pump 1101 Fail to Stop

LOW NO

FIS-POL-P-1101-MNUXA

Polymer Pump 1101 Uncommanded Start

LOW NO

FIS-POL-P-1101-MLBUXA-R

Polymer Pump 1101 Uncommanded Stop

LOW NO

FIS-POL-FE-1101-FAL

Polymer Skid 1100 Dilution Water Low Flow Alarm

LOW NO

FIS-POL-CP-1100-XA

Polymer Skid 1100 General Alarm

LOW NO

FIS-POL-FIT-1102-XAHH-R

Polymer Solution Flow Alarm HI HI

MEDIUM NO

FIS-POL-FIT-1102-XAH-R

Polymer Solution Flow Alarm HI

MEDIUM NO

FIS-POL-FIT-1102-XALL-R

Polymer Solution Flow Alarm LO LO

MEDIUM NO

FIS-POL-FIT-1102-XAL-R

Polymer Solution Flow Alarm LO

MEDIUM NO

FIS-POL-FIT-1102-XAHC-R

Polymer Solution Flow Out of Range HI

MEDIUM NO

FIS-POL-FIT-1102-XALC-R

Polymer Solution Flow Out of Range LO

MEDIUM NO

FIS-POL-UPS-1100-EAL

Polymer Skid PLC UPS Battery Low Voltage

MEDIUM NO

FIS-POL-UPS-1100-XA

Polymer Skid PLC UPS Failure

MEDIUM NO

FIS-POL-UPS-1100-EA

Polymer Skid PLC UPS Power Failure

MEDIUM NO

FIS-SPC-UPS-1921-EAL

RPU-1921 UPS Battery Voltage Low

MEDIUM NO

FIS-SPC-UPS-1921-XA RPU-1921 UPS Failure

MEDIUM NO

FIS-SPC-UPS-1921-EA

RPU-1921 UPS Power Failure

HIGH YES

FIS-SPC-PS- RPU-1921 24VDC Power MEDIUM NO 41

Page 42: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 37 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

1921C-XA Supply Redundancy Fail FIS-SPC-ASH-1921-XA

RPU-1921 Smoke/Heat Alarm

HIGH YES

FIS-SES-FSH-0001-FAH

Polymer Room Eyewash Shower Flow Alarm High

HIGH YES

FIS-WWW-AIT-0004-XA

Supernatant TSS Transmitter Fault Alarm

MEDIUM NO

FIS-WWW-AIT-0004-XAHH-R

Supernatant TSS Alarm HI HI

LOW NO

FIS-WWW-AIT-0004-XAH-R Supernatant TSS Alarm HI

MEDIUM NO

FIS-WWW-AIT-0004-XALL-R

Supernatant TSS Alarm LO LO

LOW NO

FIS-WWW-AIT-0004-XAL-R

Supernatant TSS Alarm LO

LOW NO

FIS-WWW-AIT-0004-XAHC-R

Supernatant TSS Out of Range Alarm HI

LOW NO

FIS-WWW-AIT-0004-XALC-R

Supernatant TSS Out of Range Alarm LO

LOW NO

FIS-WWW-AIT-0005-XA

Supernatant Chlorine Residual Transmitter Fault Alarm

MEDIUM NO

FIS-WWW-AIT-0005-XAHH-R

Supernatant Chlorine Residual Alarm HI HI

LOW NO

FIS-WWW-AIT-0005-XAH-R

Supernatant Chlorine Residual Alarm HI

HIGH NO

FIS-WWW-AIT-0005-XALL-R

Supernatant Chlorine Residual Alarm LO LO

LOW NO

FIS-WWW-AIT-0005-XAL-R

Supernatant Chlorine Residual Alarm LO

LOW NO

FIS-WWW-AIT-0005-XAHC-R

Supernatant Chlorine Residual Out of Range Alarm HI

LOW NO

FIS-WWW-AIT-0005-XALC-R

Supernatant Chlorine Residual Out of Range Alarm LO

LOW NO

FIS-ACC-TIT-0001-XAHH-R

PLC Room Ambient Temperature Alarm HI HI

MEDIUM NO

FIS-ACC-TIT-0001-XAH-R

PLC Room Ambient Temperature Alarm HI

MEDIUM NO

FIS-ACC-TIT-0001-XALL-R

PLC Room Ambient Temperature Alarm LO LO

MEDIUM NO

FIS-ACC-TIT-0001-XAL-R

PLC Room Ambient Temperature Alarm LO

MEDIUM NO

42

Page 43: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 38 of 42

TAG DESCRIPTION ALARM AREA

ALARM PRIORITY

WIN 911

FIS-ACC-TIT-0001-XAHC-R

PLC Room Ambient Temperature Out of Range HI

MEDIUM NO

FIS-ACC-TIT-0001-XALC-R

PLC Room Ambient Temperature Out of Range LO

MEDIUM NO

FIS-ACC-TIC-0001-XA

Heat Tracing General Alarm (DI)

MEDIUM NO

FIS-ACC-TIC-0002-XA

Heat Tracing General Alarm (DI)

MEDIUM NO

FIS-ACC-TIC-0003-XA

Heat Tracing General Alarm (DI)

MEDIUM NO

Provide alarm conditioning for all alarms allowing for modifications and setting of priorities during Software FAT and SAT.

.7 Associated Ranges and Set Points

EU Default Value Range Tag Name Description

m

FIS-WWW-LIT-0901-LAHH-C Settling Basin 0901 Level Alarm HI HI

m

FIS-WWW-LIT-0901-LAH-C Settling Basin 0901 Level Alarm HI

m

FIS-WWW-LIT-0901-LALL-C Settling Basin 0901 Level Alarm LO LO

m

FIS-WWW-LIT-0901-LAL-C Settling Basin 0901 Level Alarm LO

m

FIS-WWW-LIT-0902-LAHH-C

Settling Basin 0901 Pump Well Level Alarm HI HI

m

FIS-WWW-LIT-0902-LAH-C

Settling Basin 0901 Pump Well Level Alarm HI

m

FIS-WWW-LIT-0902-LALL-C

Settling Basin 0901 Pump Well Level Alarm LO LO

m

FIS-WWW-LIT-0902-LAL-C

Settling Basin 0901 Pump Well Level Alarm LO

m

FIS-WWW-LIT-0701-LAHH-C Settling Basin 0701 Level Alarm HI HI

m

FIS-WWW-LIT-0701-LAH-C Settling Basin 0701 Level Alarm HI

43

Page 44: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 39 of 42

EU Default Value Range Tag Name Description

m

FIS-WWW-LIT-0701-LALL-C Settling Basin 0701 Level Alarm LO LO

m

FIS-WWW-LIT-0701-LAL-C Settling Basin 0701 Level Alarm LO

m

FIS-WWW-LIT-0702-LAHH-C

Settling Basin 0701 Pump Well Level Alarm HI HI

m

FIS-WWW-LIT-0702-LAH-C

Settling Basin 0701 Pump Well Level Alarm HI

m

FIS-WWW-LIT-0702-LALL-C

Settling Basin 0701 Pump Well Level Alarm LO LO

m

FIS-WWW-LIT-0702-LAL-C

Settling Basin 0701 Pump Well Level Alarm LO

m

FIS-WWW-LIT-0501-LAHH-C Settling Basin 0501 Level Alarm HI HI

m

FIS-WWW-LIT-0501-LAH-C Settling Basin 0501 Level Alarm HI

m

FIS-WWW-LIT-0501-LALL-C Settling Basin 0501 Level Alarm LO LO

m

FIS-WWW-LIT-0501-LAL-C Settling Basin 0501 Level Alarm LO

m

FIS-WWW-LIT-0502-LAHH-C

Settling Basin 0501 Pump Well Level Alarm HI HI

m

FIS-WWW-LIT-0502-LAH-C

Settling Basin 0501 Pump Well Level Alarm HI

m

FIS-WWW-LIT-0502-LALL-C

Settling Basin 0501 Pump Well Level Alarm LO LO

m

FIS-WWW-LIT-0502-LAL-C

Settling Basin 0501 Pump Well Level Alarm LO

- 2 1 - 5 Settling Basin Fill Cycles m Settling Basin Maximum Fill Level hrs 24 24 - 72 Stratification Time

% 30% 0 – 100

Supernatant Discharge Valve Intermediate Position

m 0 - 100

Settling Basin Level – Supernatant Valve Fully Open

m Supernatant Disposal Terminated m 0 - Sludge Transfer Pump Start Level m 0 - Sludge Transfer Pump Stop Level % 0 - 100 De-sludge Valve Intermediate Position

m

Pump Well Level- De-sludge Valve Fully Open

min 3-way Valve Sludge Drain Time min B/W FIT Failed-Polymer Feed Stop Delay

44

Page 45: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 40 of 42

EU Default Value Range Tag Name Description

L/sec 2200 1800-2300 Backwash Flow Capped

min

LIT failed-Supernatant Valve Time Delay To Close

0901,0701,0501 0501, 0701, 0901 Settling Basin Duty Feed Sequence

0501, 0701, 0901 Settling Basin In-service/Out-of-Service

1000, 1100 Polymer Skid Duty Sequence

AIT-0001, 0004

Duty Total Suspended Solids Analyzer Sequence

AIT-0002, 0005 Duty Chlorine Residual Analyzer Sequence

Sec 30 0 - 120

Total Suspended Solids High Alarm Time Delay

Sec 30 0 - 120

Total Suspended Solids High-High Alarm Time Delay

Sec 30 0 - 120 Chlorine Residual High Alarm Time Delay

Sec 30 0 - 120

Chlorine Residual High-High Alarm Time Delay

% 0 0 - 100 FIS-WWW-P-0900-HSSP-C

Sludge Transfer Pump Computer Manual Speed Set Point

% 0 0 - 100 FIS-WWW-P-0700-HSSP-C

Sludge Transfer Pump Computer Manual Speed Set Point

% 0 0 - 100 FIS-WWW-P-0500-HSSP-C

Sludge Transfer Pump Computer Manual Speed Set Point

% 0 0 - 100 FIS-WWW-V-0910-HSSP-C

Settling Basin 0901 Supernatant Outlet Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0911-HSSP-C

Settling Basin 0901 De-sludge Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0912-HSSP-C

Settling Basin 0901 De-sludge Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0913-HSSP-C

Settling Basin 0901 De-sludge Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0710-HSSP-C

Settling Basin 0701 Supernatant Outlet Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0711-HSSP-C

Settling Basin 0701 De-sludge Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0712- Settling Basin 0701 De-sludge Valve

45

Page 46: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 41 of 42

EU Default Value Range Tag Name Description

HSSP-C Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0713-HSSP-C

Settling Basin 0701 De-sludge Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0510-HSSP-C

Settling Basin 0501 Supernatant Outlet Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0511-HSSP-C

Settling Basin 0501 De-sludge Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0512-HSSP-C

Settling Basin 0501 De-sludge Valve Computer Manual Position Set Point

% 0 0 - 100 FIS-WWW-V-0513-HSSP-C

Settling Basin 0501 De-sludge Valve Computer Manual Position Set Point

% Polymer Concentration

mg/L Polymer Dosage

FIS-POL-FIT-1002-FAHH-C Polymer Solution Flow Alarm HI HI

FIS-POL-FIT-1002-FAH-C Polymer Solution Flow Alarm HI

FIS-POL-FIT-1002-FALL-C Polymer Solution Flow Alarm LO LO

FIS-POL-FIT-1002-FAL-C Polymer Solution Flow Alarm LO

FIS-POL-FIT-1102-FAHH-C Polymer Solution Flow Alarm HI HI

FIS-POL-FIT-1102-FAH-C Polymer Solution Flow Alarm HI

FIS-POL-FIT-1102-FALL-C Polymer Solution Flow Alarm LO LO

FIS-POL-FIT-1102-FAL-C Polymer Solution Flow Alarm LO

FIS-ACC-TIT-0001-TAHH-C

PLC Room Ambient Temperature Alarm HI HI

FIS-ACC-TIT-0001-TAH-C

PLC Room Ambient Temperature Alarm HI

FIS-ACC-TIT-0001-TALL-C

PLC Room Ambient Temperature Alarm LO LO

FIS-ACC-TIT-0001-TAL-C

PLC Room Ambient Temperature Alarm LO

46

Page 47: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13021B Residuals Management System PROCESS CONTROL NARRATIVE Contract No. 15ECS-MI-01IS / 2013-5598 Page 42 of 42

2 Products

3 Execution

END OF SECTION

47

Page 48: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 1 of 33

1 General

1.1 GENERAL

.1 This section applies to construction of the communication networks at the Toronto Water facility listed below:

.1 Ashbridges Bay Wastewater Treatment Plant

.2 Humber Wastewater Treatment Plant

.3 Highland Creek Wastewater Treatment Plant

.4 North Toronto Wastewater Treatment Plant

.5 R.C Harris Water Treatment Plant

.6 F.J Horgan Water Treatment Plant

.7 R.L Clark Water Treatment Plant

.8 Island Water Treatment Plant

.9 Water Supply and Transmission

.10 Complex Systems

.2 The Toronto Water locations not listed above will use the City of Toronto and Toronto Water Commercial Structured Cabling Standard. The sites include: 60 Tiffield Road, 275 Merton Street, 30 Dee Avenue, 545 Commissioners Street, 505 Richmond Street, and 435 Kipling Avenue.

.3 The horizontal data/voice copper cabling system shall be a Panduit Certified system and backbone fibre optic cabling system shall be a Corning certified system.

.4 The voice cabling system shall be (similar to data cabling) horizontal Category 6 UTP and shall terminate on the copper patch panel like data cables in the Telecom Enclosure (TE) / Cabinets / Racks. There shall be a telephone patch panel in each enclosure having at least 25 pair Cat 3 backbone cable running to the existing or new BIX blocks in the entrance facility.

.5 The data/voice horizontal cabling system shall be based on Category 6 wiring and shall be provided in accordance with this specification.

.6 The Fibre Optic Backbone is defined as the fibre optic segments radiating out from the Network Core to the Access Closets. The fibre optic backbone will be comprised of redundant, full-duplex, 10GBASE-S segments.

.7 The fibre allocation within the fibre optic backbone cable is as follows: Toronto Water LAN - 4 fibres active and Toronto Water LAN - 8 fibres reserved. All 12 fibres of each backbone cable will be terminated and tested.

.8 Horizontal cable segments for the plant floor are defined as the unshielded twisted pair (UTP), category 6 (CAT6) cables that permanently interconnect the patch panel in the Access Closet with a work-area outlet in the Termination Panel.

.9 Horizontal cables on the plant floor will always be collated as a group of four (4) cables. Each group of horizontal cables will be associated with a single 4-port, work-

48

Page 49: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 2 of 33

area outlet in the Termination Panel and a 4-port, snap-in faceplate in the Access Closet, patch panel.

.10 Horizontal cable segments for the office area are defined as the unshielded twisted pair (UTP), category 6 (CAT6) cables that permanently interconnect the patch panel in the Access Closet or Telecommunication Rack with a work-area outlet in the office area.

.11 Horizontal cables in the open office area (cubicle) will always be collated as a group of two (2) cables per work area outlet. Horizontal cables in the closed office area (office room) will always be collated as a group of two (2) cables per work area outlet and two (2) work area outlets per office room. Each group of horizontal cables will be associated with a single 4-port, work-area outlet and a 4-port, snap-in faceplate in the Access Closet, patch panel.

.12 All network components of a single type shall be from the same manufacturer and the same manufacturer's catalogue number.

.13 All network sub-system components shall be from the same manufacturer.

.14 The term "free-issue" refers to equipment supplied by the City for incorporation into the Contract.

.15 All the Network Switching and Routing Equipment will be free issued by the City under existing purchasing agreements. The network equipment will be configured, tested, and installed by Toronto Water ITM Group. Allow six (6) months lead-time for new network equipment.

.16 The standards referenced in this section include:

.1 TIA-568-C series: Telecommunications Cabling Standard All standards referenced within the TIA-568-C, where applicable, constitute standard provisions of this specification. Furthermore, compliance with the Ontario Electrical Safety Code will supersede all other specifications.

.2 Ontario Electrical Safety Code, Section 56 - Optical Fibre Cables.

.3 Ontario Electrical Safety Code, Section 60 - Communication. TIA-569-C: Telecommunications Pathways and Spaces

.4 TIA-606-B : Administration Standard for Telecommunications Infrastructure

.5 TIA-607-B: Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises

.6 TIA-758-B: Customer-Owned Outside Plant Telecommunications Infrastructure Standard

.7 BICSI / TDMM: Telecommunications Distribution Methods Manual (12th Edition or latest)

.8 BICSI Information Technology Systems Installation Methods Manual, 6th Edition or latest

.9 BICSI Network Systems and Commissioning (NSC) reference, 1st Edition or latest

.10 BICSI Outside Plant Design Reference Manual, 5th Edition or latest

.17 Field verify distances before starting work.

49

Page 50: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 3 of 33

.18 Contract Drawing dimensions are approximate and shown as RTS (Reasonably to Scale); field verify the dimensions provided before starting work.

.19 Provide all components and appurtenances necessary to ensure that the network closets are functional and meet the intent of this specification, TW ITM, City and Corporate I&T Standards.

.20 All cabling is to be provided from the manufacturers noted with the following sections. Cabling provided by alternate manufacturers is not acceptable.

.21 The successful System Integrator / Cabling Contractor shall be a BICSI Corporate Member.

.22 The site engineer / supervisor / project manager shall be a minimum BICSI RCDD (Registered Communications Distribution Designer) credential holder in good standing who have demonstrated knowledge in the design, integration and implementation of telecommunications and data communications transport systems and related infrastructure.

.23 The site engineer / supervisor and technician shall hold related manufacturer valid certification on systems and solutions.

.24 The technician shall be Fluke Networks Certified Cabling Test Technician (CCTT) and hands-on experience using DTX cable analyzer for copper and fiberoptics based infrastructures testing.

.25 Sample test template documents will be provided to the contractor for completion comprising the following:

.1 Sample of Cable Acceptance Test

.2 Sample of Factory Acceptance Test (FAT)

.3 Sample of Site Acceptance Test (SAT)

1.2 SUBMITTALS

.1 Comply with the requirements of Section 01300 - Submittals.

.2 Submit proposed cable and enclosure tag labels to the Contract Administrator and TW ITM Technical Representative for approval before proceeding with this work.

.3 Submit the following documentation prior to starting the site acceptance test:

.1 Toronto Water Network - Cable Test Results Manual.

.2 Operations and Maintenance Manual.

.3 Revise and annotate Contract Drawings, in AutoCAD and Microstation V8, to clearly document the as-built network including details related to: location (closets, terminations panels) cabling (size, length, type, routing), tagging (cable ducting, cabling, closets and termination panels).

1.3 TAGGING CONVENTION STANDARD

.1 The requirements of this section will take precedence over other sections.

.2 The labelling of Toronto Water network components, structured cabling and cable routing shall comply with the TIA/EIA-606-B standard.

50

Page 51: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 4 of 33

.3 The codification of network components, cables and cable routing shall follow the identification standards detailed in this specification section.

1.4 IDENTIFICATION AND LABELLING

.1 Closet Identification

.2 Network Closets are defined as any enclosure that contains active network components, including: Core, Server, and Access Closets.

.3 Cubicles or Offices will only contain passive network components for the termination of Horizontal cables in Work Areas. Cubicles or Offices will contain 4-port, work area outlets. Approval for additional ports per cubicle or office must be granted by ITM Technical Representative before proceeding with this work.

.4 Termination Panels will only contain passive network components for the termination of Horizontal cables in Work Areas. Termination Panels will contain up to two 4-port, work area outlets.

.5 Provide a nameplate for each enclosure on the top-left corner of the door.

.6 Use engraved gravoply laminate nameplates having white letters on black background. Minimum nameplate height shall be 50mm. Minimum character height shall be 12mm.

.7 Centre lettering on each line.

.8 Include device identification (tag) number as well as a descriptive name. For example: the tag name: FCL-ITS-COM-0100 followed by the description: PCS CORE CLOSET 01.

.9 All network closet / telecom enclosure tags utilise a four-digit device number (XXYY). The first two numbers (XX) identify the closet and the last two numbers (YY) identify sub-devices. For closets the last two numbers (YY) are always zero (00). For example FCL-ITS-COM-1400 for Access Closet 14.

.10 Core and Server closets in the Computer room are numbered from (01YY) to (10YY).

.11 Termination Panels associated with a Closet on the plant floor should utilise the same first digits as the closet. For example the first Termination Panel associated with Access Closet 14 (FCL-ITS-COM-1400) would be tagged as FCL-ITS-COM-1401.

.12 Termination Panels should only be used on the plant floor and not in the office areas.

.13 Work Areas associated with a Closet in the office areas should utilise the same first digits as the closet. For example the first Work Area Outlet associated with Access Closet 14 (FCL-ITS-COM-1400) would be tagged as 1400-WA01.

.14 Copper and Fibre Patch Panels:

.1 Labels for patch panels shall be laser printed, self-laminating, adhesive, and polyester or polyolefin. Hand-written labels will not be accepted.

.2 Lettering shall be black on a white background. Characters are a minimum of 6 mm high.

.3 Labels shall be applied to patch panels in such a manner as to be readily visible and not obscured by structured cabling or patch cords.

51

Page 52: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 5 of 33

.4 The tagging convention for network closet, patch panels will employ a four (4) character alphanumeric tag. The first two characters will indicate the type of patch panel. The second two characters will be a unique index within each closet starting from the top. The characters "FP" will denote Fibre Patch Panels. For example the second fibre patch panel from the top in Access Closet 14 would be labelled FP02. The copper patch panels in an Access Closet/Telecom Enclosure shall employ one character A, B, C, …, Z. The rack shall be populated with patch panels as necessary and labeled in sequential order from top to bottom. For example, the first copper patch panel in the Access Closet 14 from the top of the rack shall be labeled A, the second shall be B, and so on. The telephone patch panel shall be termed as "TP01" from which 25 pair Cat3 cable shall run to the existing or new BIX blocks or approved equal in the entrance facility.

.15 Copper Patch Panel Termination Point for the Plant Floor or General Office Area

.1 Each 24-port patch panel will have six (6) snap-in faceplates that group four terminations. Each 4-port, snap-in faceplate will be associated with a 4-port, work-area outlet in a Termination Panel or another 4-port, snap-in faceplate.

.2 Labels for each 4-port, snap-in faceplate shall be laser printed, self-laminating, adhesive, polyester or polyolefin. Hand-written labels will not be accepted.

.3 Lettering shall be black on a white background. Characters are a minimum of 4 mm high.

.4 A label shall be applied to the top of each 4-port, snap-in faceplate indicating the destination of the faceplate.

.1 For example: a 4-port, snap-in faceplate whose destination is Termination Panel 1401, Work-Area-Outlet 1 would be tagged as 1401-WA01.

.2 For example: a 4-port, snap-in faceplate whose destination is Cubicle or Office Area 2101, Work-Area-Outlet 1 would be tagged as 2101-WA01.

.16 Apply a two-digit label immediately beneath each data port (RJ) indicating its port number.

.17 Provide colour-coded, snap-in icons (Panduit: CIDXX-C, XX: colour) for each data port (RJ). The following colours will indicate network membership at both copper patch panel and termination outlet:

Colour Membership/Function Colour Membership/Function

Red HMI Blue PLC Green Business Purple Security Orange Video Yellow Maintenance Black Voice White Spare

.18 Fibre Optic Patch Panel Termination Point

.1 Terminate all 12 fibres of each fibre optic cable in either 36/72 Fibre Enclosures (Access Closet) or 72/144 Fibre Enclosures (Core Closet).

52

Page 53: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 6 of 33

.2 The fibre cable for all even-numbered Access Closets/Telecom Enclosures will terminate at Core Closet 02 (COM-0200) while odd-numbered will terminate at Core Closet 01 (COM-0100).

.3 The ordering and colour of individual fibres will be the same for each fibre cable and compliant with TIA/EIA-568-C.

.4 Labels shall be laser printed, self-laminating, adhesive, and polyester or polyolefin. Hand-written labels will not be accepted.

.5 Lettering shall be black on a white background. Characters are a minimum of 4 mm high.

.6 A label shall be applied to the top of the LC duplex adapter modules associated with a single fibre cable indicating the destination of the cable. For example the adapter modules that terminate the fibre cable whose destination is Access Closet 1400 would be labelled as COM-1400.

.19 Work-Area Outlets on the Plant Floor or Office Area

.1 Labels for each 4-port, work area outlet shall be laser printer, self-laminating, adhesive, polyester or polyolefin. Hand-written labels will not be accepted.

.2 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm high.

.3 A label shall be applied to the top of each 4-port, work-area outlet indicating the source of the Horizontal cables. For example: a 4-port, work-area outlet in Termination Panel 1401 connected to the first patch panel in Access Closet 14 would be labelled as 1400-WA01.

.4 Apply a three character label immediately beneath each data port (RJ) indicating the letter of the source patch panel and two-digit port number where it is connected to. The WAO ports will be populated with the data jacks (RJ) in sequential order from left to right and then top to bottom. For example, WAO port 1 connected to patch panel A port 1 would be labelled as 1:A01.WAO port 2 to patch panel A port 2 is labelled 2:A02 and so on.

.5 Provide colour-coded, snap-in icons for each port (RJ). The following colours will indicate network membership:

Colour Membership/Function Colour Membership/FunctionRed HMI Blue PLC

Green Business Purple Security Orange Video Yellow Maintenance Black Voice White Spare

1.5 NETWORK CABLE & PATHWAY IDENTIFICATION

.1 Use durable non-fading sleeve type wire markers to identify all network cables.

.2 Labels for cabling shall be laser printed, self-laminating, adhesive, polyester (indoor/outdoor). Hand-written labels will not be accepted.

.3 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm in height.

.4 Fibre Optic Backbone Cables

53

Page 54: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 7 of 33

As a minimum, all fibre optic backbone cables are to be labelled at both ends of the cable.

.1 In addition, the fibre backbone cables are to be labelled at each transition. A transition is defined as: a change in ducting (e.g. cable tray to conduit), a change in direction of more than 45 degrees, or an entrance and exit of ducting through a wall or floor. Use smart LB where ever required for standardized directional change to respect cables bend radius.

.2 If the fibre cable is run in conduit then the transition labels shall be applied to the conduit.

.3 The tagging convention for identification of fibre optic backbone cables shall indicate the source and destination of the cable separated by a colon. For example a fibre optic backbone cable whose source is Core Closet #2 (COM-0200), Fibre Patch Panel #1 fibre adaptor plate C and terminates in Access Closet 1400 (COM-1400) on the fibre patch panel 01 adaptor plate A would have the following tag:

0200-FP01-C: 1400-FP01-A

.4 The Access Closet fibre optic patch panel must be labelled. For example: Access Closet 1400 with two fibre optic patch panels would be labelled "FP01" and "FP02", where "FP01" is the first patch panel from the top.

.5 Horizontal Cables

.1 As a minimum, all horizontal CA6 cables shall be labelled at both ends of the cable.

.2 The tagging convention for identification of Horizontal cables shall indicate the source and destination of the cable separated by a colon.

.1 Example 1: a horizontal cable whose source is Access Closet #14 (COM-1400), UTP Patch Panel #1 A), Position #10 and whose destination is Position #2, Work-Area Outlet #1, in Termination Panel 1402 would have the following tag: 1400-A-10 : 1402-WA01-02

.2 Example 2: a horizontal cable whose source is Core Closet #1 (COM-0100), UTP Patch Panel #2, Position #8 and whose destination is Position #8, UTP Patch Panel #1, in Server Closet 4 (COM-0400) would have the following tag: 0100-B-08 : COM-0400-A-08

.6 Patch Cords

.1 As a minimum, all Contractor installed CAT6 and fibre optic patch cords shall be labelled at both ends of the cable.

.2 The tagging convention for identification of patch cords shall indicate the source and destination of the cable separated by a colon. The source is the switch port and the destination is the patch panel, termination point.

.7 Voice Backbone Copper Cable

.1 As a minimum, all 25-pair voice backbone cables shall be labeled at both ends of the cable, within every pull box and every 15 metres.

.2 The tagging convention for identification of voice cables between the voice block in the telephone entrance facility/room and the Access Closet patch panel shall

54

Page 55: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 8 of 33

indicate the source and destination of the cable (separated by a colon). For example, voice cable 9 whose source is first floor, Telephone entrance facility room No A and terminates in destination Access Closet 1400 (FIS-ITS-COM-1400) on VOICE/Telephone patch panel 01 would have the following tag: V01A-009:1400-TP01

.8 Cable Routing/Pathway

.1 All ducting (cable tray or conduit) carrying fibre optic/copper backbone cable shall be tagged as "LAN BACKBONE" at frequent intervals as per the standard.

.2 All ducting carrying Horizontal cables shall be tagged as "LAN HORIZONTAL" with the source and destination COM panels at frequent intervals as per the standard.

.3 Cable tray and conduit shall be labeled every 15 metres (50 ft.) on the outer surface as “LAN BACKBONE” or “LAN HORIZONTAL”. There shall be small labels identifying the source and destination of cables in case there are multiple cables carried by the cable tray and conduit.

.4 All ducting shall be labeled at each transition. A transition is defined as a change in ducting (e.g. cable tray to conduit), a change in direction of more than 45 degrees, or an entrance and exit of ducting through a wall or floor.

.5 Use engraved gravoply laminate nameplates using black letters on white background. The laminate nameplates shall have a dimension of 210mm W x 50mm H. Minimum character height shall be 12mm. Character lettering shall be centered on each lne.

2 Products

2.1 FIBRE OPTIC CABLE

.1 Provide all fibre optic cable, connectors and appurtenances that make up the backbone cable segments.

.2 The fibre optic backbone cable segments shall meet the requirements of the TIA/EIA-568-C specification for laser optimized 50 micron, multimode fibre (OM3). When backbone link length is more than 300 metres, singlemode OS2 fiber cable shall be used.

.3 Fibre optic backbone cable shall meet or exceed the following minimum requirements:

.1 12 Fibres per Cable.

.2 Indoor/Outdoor Rating.

.3 Core-locked, Tight-buffered.

.4 50/125 micron Core/Cladding (OM3).

.5 2000 MHz-km Bandwidth (LL-EMB) at 850 nm wavelength.

.6 500 MHz-km Bandwidth (LL-EMB) at 1300 nm wavelength.

.7 Riser-Rated (FT4) inner and outer PVC jackets for risers and Plenum-Rated (FT6) for plenum areas.

55

Page 56: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 9 of 33

.8 The multimode OM3 fibre optic riser cable shall be Corning Optical Cable , model # 012T8F-31180-29. Outer jacket shall be dielectric and color should be Black. Singlemode OS2 riser fibre optic cable: 012E8F-31131-29.

.9 The multimode OM3 fibre optic plenum cable shall also be Corning Optical Cable, model # 012T8P-31180-29. Outer jacket shall be dielectric and color should be Black. Singlemode OS2 plenum fibre optic cable: 012E8P-31131-29.

.10 In situations where alternate fibre cables for underground, direct buried and ariel installations, it is the contractor/consultant's responsibility to propose an alternative Corning Optical Cable that is appropriate for the installation. Alternate will be submitted to the City for approval. Cable colour shall be black.

2.2 FIBRE OPTIC CONNECTORS AND ADAPTERS

.1 All connectors for the termination of the fibre optic backbone cable shall be duplex LC connectors.

.2 Fibre optic LC connectors shall meet or exceed the following minimum requirements

.1 50 /125 micron (OM3, laser optimized) with a Zirconia ceramic, pre-radiused ferrule.

.2 Insertion loss shall be less than 0.3dB and return loss shall be greater than 40dB multimode.

.3 The connectors shall be used with preloaded adapters configured with 10 Gig FAP loaded 6 LC duplex multimode, adapters fitted with a Zirconia phosphorous bronze split sleeve. Fibre optic adapter shall be Panduit catalogue no. OM3: FAP6WAQDLCZ; OS2: FAP6WBUDLCZ

.4 Field terminable LC connectors shall be Corning catalogue no. OM3: 95-050-99-X; OS2:95-200-99.

.5 All Fibre end-to-end connections are to be performed by a certified Corning Solution Provider.

2.3 OUTSIDE PLANT (OSP) CABLING REQUIREMENTS

.1 OSP cabling shall follow TIA-758-B and BICSI OSP Reference manual (5th edition or latest)

.2 The fibre cable shall be indoor / outdoor cable as specified in this section.

.3 There shall be underground conduit structures / pathways / duct banks used for placing telecommunications cable from the property line and between access points such as MHs, Handholes (HHs) and building entrances.

.4 For underground pathways systems, it is required to thoroughly review the followings:

.1 Right of way

.2 Materials (e.g., Conduit, select backfill etc.)

.3 Subsurface conditions

.4 Restoration of landscape

.5 Roads, railroads, water crossings etc.

.6 Protection from traffic

56

Page 57: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 10 of 33

.7 Type and size of duct/conduit

.5 Lateral / subsidiary conduits are the ones that connect to structures (eg. Buildings, pedestals, cabinets, poles etc.). When planning lateral ducts to distribution points, spare ducts for future use should be provided. As per ANSI standards, installing a minimum of one spare duct is recommended.

.6 The trade size of the duct/conduit shall be at least 78 mm (3”).

.7 The minimum recommended separations between telecommunications conduit systems and outside surfaces of foreign structures shall be:

.1 152 mm (6 in.) when crossing pipes (e.g., gas, water, oil)

.2 305 mm (12 in.) when parallel to pipes (e.g., gas water, oil)

.3 Power or other foreign conduit:

.4 76 mm (3 in.) concrete

.5 101 mm (4 in.) masonry

.6 305 mm (12 in.) of well-tamped earth

.7 Railroads: when crossing 1.27 m (50 in.) below top of rail

.8 Street railways: 914 mm (36 in.) below top of rail

.8 The 50-year frost line should be considered when calculating conduit depth. The top of the conduit should be located at a sufficient depth (normally 610 to 762 mm - 24 to 30 in.) below surface grade so both live and dead loads can be sustained by the conduit structure. A warning tape shall be provided under grade for the buried conduit.

.9 Live or dynamic loads are caused by vehicular traffic and result from the combination of a vehicle's weight and speed. When conduits are located at least 1.83 m (6 ft.) below grade, the load is well dispersed.

.10 Recommended conduit materials must be designed to withstand loads created by a normal traffic flow when there is an adequate amount of fill between the top of the conduit structure and ground surface.

.11 The conduit type is recommended to be High-density polyethylene (HDPE) unless sub-surface condition does not allow. Once built, the conduit system should remain usable for 75 to 100 years and fulfill design specifications.

.12 Installing underground conduit so that a slope exists at all points of the run allow drainage and prevents the accumulation of water. A drain slope towards the MH/HH from the centre of the conduit run or from the building of no less than 10 mm per meter (0.125 inches per foot).

.13 The use of innerduct will enhance conduit capacity and utilization for optical fibre cable placement. Innerduct should be equipped with a pull rope or tape. A tracer wire can be installed in the innerduct to aid in cable locating requirements.

.14 Proper firestopping material shall be used to seal the finished conduits.

.15 Ensure that the conduit has water tight box at the end of the access points / building.

.16 Handholes are manufactured as polyethylene or composite structures. They are used as pull-through points and shall not be used as splice points.

57

Page 58: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 11 of 33

.17 Handholes (HHs) should:

.1 Facilitate cable placement

.2 Have drainage provisions (e.g., drain holes etc.)

.3 Aid cable pulling when the bends exceed either two 90 degree bends or a total of 180 degrees, or the conduit section is over 30 meters (100 ft.).

.4 Meet applicable code requirements.

.18 When planning the location of a HH, the designer should consider:

.1 Ground topography

.2 Soil conditions

.3 Location with respect to surrounding structures

.4 Accessibility for personnel

.19 A finished project documentation should consist of construction plans and specifications showing the:

.1 Location of all existing and proposed conduit

.2 Size and configuration of MHs / HHs.

.3 Total duct / conduit length

.4 Type and size of conduit

.5 Special conduit fittings if required

.6 Conduit (duct bank) formation and depth requirements

.7 Encasement specifications and materials

.8 MH/HH or cable entrances

.9 Locations of any existing substructures

.10 Restoration requirements

.11 Location and depth of other structures

.12 Traffic control plan

.20 A pull cord with 200 lbs pull strength shall be installed and maintained in all conduits before and after cable installation.

2.4 UTP HORIZONTAL CABLE (DATA / VOICE - PLANT & OFFICE FLOOR )

.1 Provide Category 6 (CAT6) unshielded twisted-pair cable, connectors and appurtenances that make up the Horizontal cables segments for data cabling in the administration and office area.

.2 Horizontal CAT6 cable segments shall meet the requirements of the TIA-568-C specification for CAT6 cable.

.3 Horizontal Cable Segments shall meet or exceed the following minimum requirements:

.4 The cable shall be tested up to 250 MHz with a guaranteed performance that meets or exceeds the TIA/EIA-568-C.2 for CAT6.

58

Page 59: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 12 of 33

.5 The cable shall be constructed from 23AWG, bare copper wire insulated. Two insulated conductors twisted together to form a pair and four pairs laid up to form the basic unit.

.1 The cable shall be jacketed in flame-retardant PVC. Cable run in conduit shall meet or exceed FT4 rating. Cable not run in conduit shall meet or exceed FT6 rating.

.2 Horizontal cable run in conduit shall be CMR/FT4 rated, General Cable GenSPEED 6000 part number 7133900 or approved equal.

.3 Horizontal cable not run in conduit shall be CMP/FT6 rated, General Cable GenSPEED 6000 part number 7131900 or approved equal.

2.5 UTP HORIZONTAL CONNECTORS (DATA / VOICE - PLANT & OFFICE FLOOR )

.1 All category 6 (CAT6) connectors shall be unshielded modular jacks and wired for a T586A wire-map.

.2 CAT6 connectors shall meet or exceed the following minimum requirements:

.1 Eight position modular jacks shall meet or exceed the TIA Category 6 standards.

.2 The jack termination to 4 pair 23 AWG unshielded twisted pair cable shall require the use of a punch down tool.

.3 The jack shall limit conductor untwist to less than 23 mm (½").

.4 The jack shall accommodate icons for network identification.

.5 CAT6 unshielded modular jacks shall be Panduit catalogue no. CJ688TGWH or approved equal.

2.6 CATEGORY 3 BACKBONE 25 PAIR TELEPHONE CABLE

.1 All multipair voice cable, connectors and appurtenances that make up the Backbone cable segments shall meet the requirements of the TIA/EIA-568-C specification for Cat3 multipair voice cable.

.2 The multipair cable shall run in conduit/cable tray from telephone patch panel in the telecom enclosure (TE) / access closet to the BIX block in the Entrance Facility.

.3 General Cable catalogue no: Indoor CMR: 2133033; or Indoor CMP: 2131505; Outdoor: 7524648

2.7 GENERAL ENCLOSURE REQUIREMENTS

.1 Unless otherwise specified all indoor enclosures containing network components are to be NEMA 4.

.2 Lockable double hinged doors allows front and rear access to rack-mounted components

.3 All screws, bolts, fasteners etc. are to be corrosion resistant stainless steel.

.4 All wall-mounted panels are to be separated from the wall by stainless steel spacers or galvanised steel struts.

.5 Doors are to have continuous hinges with removable pin and oil resistance cellular neoprene gasket secured by gasket retainers. Front door handles are to be recessed

59

Page 60: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 13 of 33

type (freestanding enclosures) or 3-point external latch (wall mount), complete with key locks. Provide locking mechanism for rear door. All key locks are to be identically keyed. Key number to be provided to Contractor during construction.

.6 Cable bundles are to be neatly laced, run in ducting or approved cable managers and secured to 19" rack or mounting back-panel.

.7 All enclosure doors shall open through 180 degrees without restriction from front and the back.

.8 Enclosure layout and equipment spacing shall be constructed to allow for device removal, calibration and maintenance without disassembly of adjacent devices.

.9 All freestanding, floor-mounted enclosures shall have removable CSA eyebolts to facilitate sling handling of each enclosure. Eyebolt mounting shall be a part of the structural support bracing to distribute stresses and enclosure weight while sling handling enclosures during installation.

.10 All enclosures shall have sufficient structural reinforcements to ensure a limited plane surface vibration and to provide rigidity during shipment, installation and operation without distortion or damage to the enclosure, mounting panel or mounted instruments.

.11 All enclosure seams shall be continuously welded and ground smooth to be undetectable after painting.

.12 Devices shall be installed on the enclosure back-panel or 19" rack.

.13 There shall be no devices installed on the side plates of the enclosure.

2.8 ENCLOSURE WIRING

.1 All enclosure wiring shall run through a cable manager.

.2 Cable managers shall not be filled to more than 50% of their volume upon initial installation.

.3 All wires and cables, including spares, shall be identified at each end and at any connection. Use durable non-fading sleeve type wire markers to identify all network cables as follows:

.1 Labels for cabling shall be laser printed, self-laminating, adhesive, polyester, vinyl (indoor/outdoor).

.2 Hand-written labels will not be accepted.

.3 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm high.

.4 Wire markers are required on each conductor in panel board gutters, and at load connections. The identification shall include branch circuit or feeder number for power and lighting circuits, and control wire numbers for control wiring.

.5 All field wires and cables terminated within enclosures shall be identified at each termination with a marking that corresponds with the drawings and supporting documentation.

60

Page 61: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 14 of 33

.6 Power wiring insulation shall be rated at 600 volts at 90 C and be type RW 90 THHN. Conductors shall be stranded copper. No wire smaller than 12 AWG shall be used for power wiring, unless noted otherwise on the drawings.

2.9 CORE AND SERVER CLOSETS

.1 The enclosures for the Core and Server Closets shall meet or exceed the following minimum requirements:

.1 Overall maximum dimensions of 84"H x 30"W x 42"D.

.2 The enclosures are to be "ganged" together to provide a continuous space for inter-enclosure cable management.

.3 Internal 44 rack-unit, 19" mounting rack.

.4 Plexiglass / lexan / Perforated front door and split rear door with fans.

.5 At Least 2 Movable LED Lights for Enclosure Internal use

.6 Ventilating top with 400 CFM fan.

.7 Lockable front and rear door, identically keyed for all doors.

.2 Core and Server Closet enclosures shall be Wrightline Paramount Enclosure.

.3 All cable is to enter through the bottom or top of the cabinets. If coring of the floor is required for the passage of cable the Contractor is to X-Ray the floor in accordance with Division 1.

.4 Provide cable tray (12" wide minimum) segregated for Power, Fibre and UTP cables for overhead cabling as shown on the Contract drawings. Cable management is to be provided from the cable tray to the enclosure to ensure that the minimum bend radius for each cable is maintained and the cable is rigidly supported.

.5 Electrical

.1 Contractor is to provide the electrical distribution for each Core and Server Closet as per the related Electrical Distribution drawings and relevant City standards.

.2 Provide each Core and Server Closet with two (2) 20A, 120 VAC, UPS circuits. Terminate each UPS circuit at a 3-wire, duplex receptacle mounted to the rail of the 19" rack.

.3 Bond each 19" rack to ground. A rack mounted grounding bar shall be provided.

.4 The duplex receptacles shall be mounted in such a manner as not to interfere with access to or removal of other equipment within the enclosures.

.5 Power distribution within the enclosure shall be via vertically mounted metered power bars. Power bars shall be Liebert MPH series or approved equal.

.6 Redundant power supplies, within the same device, shall not be connected to the same UPS circuit.

2.10 CORE CLOSET

.1 Provide new network Core Closets as required by contract documents. The Core Closets constitute the central hub of the network and as such are the points of aggregation for all of the fibre optic backbone cables.

61

Page 62: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 15 of 33

.2 The Core Closets will be constructed to support the termination of cables (fibre optic, UTP CAT6, power) in each closet.

.3 Provide minimum one (1) rackmount, 4U fibre optic enclosures for termination of the fibre optic backbone cable within each Core Closet.

.4 The fibre optic enclosure shall meet or exceed the following minimum requirements:

.5 The enclosures shall protect the fibre optic connections for patching or splicing requirements within the premises cabling environment.

.6 Enclosures shall accommodate up to 72 fibres per rack space (per rack unit).

.7 Front and back covers shall be removable for wiring installation.

.8 The enclosure shall include bend radius management for fibre patch cords and backbone cable.

.9 Fibre Optic Patch Panel and Termination

.1 The fibre optic enclosure shall be Panduit catalogue no. FRME4 or approved equal.

.2 Fibre optic backbone cables from even-numbered Access Closets are to terminate in Core Closet 02 (COM-0200) and cables from odd-numbered Access Closets are to terminate in Core Closet 01 (COM-0100).

.3 Terminate all 12 fibres of each backbone cable within the fibre optic enclosures.

.4 Fibre colour and Tx/Rx orientation is to be identical for each termination panel.

.5 All fibres are to be labelled as per the Core Closet Installation - Fibre Patch Panel Termination drawing to be provided during construction

.6 Dark fibres are to be covered to prevent damage.

.7 Blank spaces in the breakout enclosure are to have blank covers installed.

.8 Fibre optic connectors shall be duplex LC style connectors.

.9 Fibre optic termination panels shall be Panduit catalogue no. OM3 multimode: FAP6WAQDLCZ; OS2 singlemode: FAP6WBUDLCZ; Blank panel: FAPB.

.10 Copper Patch Panel and Terminations

.1 Provide four (4) 24-port, patch panels with connectors and appurtenances for termination of unshielded-twisted pair (UTP) cable within each Core Closet.

.2 All snap-in, faceplate modules shall be removable from the front enabling front access to connectors and cable. Each faceplate module will group four (4) UTP connectors.

.3 All 24-port modular patch panels shall be Panduit catalogue no. CPPL24WBLY.

.4 All category 6 (CAT6) connectors shall be unshielded modular jacks and wired for a T586A wire-map.

.5 All CAT6 unshielded modular jacks shall be Panduit catalogue no. CJ688TGBL.

.11 Provide Horizontal UTP CAT6 cables between Core Closet and Server Closet patch panels. Provide two (2) duplex, LC-to-LC, fibre optic patch cords for each fibre optic backbone cable aggregated in the core. The Core Closet fibre optic patch cords shall be 50/125 micron, laser optimized OM3 multimode fibre. Fibre optic patch cables

62

Page 63: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 16 of 33

shall be terminated at one end with a duplex LC style plug and at the other with a LC style plugs. When singlemode OS2 backbone cable is used, singlemode OS2 duplex LC-LC patch cords shall be provided accordingly.

.1 Fibre optic patch cords are to be factory assembled and tested by the manufacturer. Provide written certification from the manufacturer. The Contractor is responsible for determining the length of patch cords.

.2 For each fibre optic cable, terminate one patch cord in COM-0100 and the other in COM-0200.

.12 Provide forty-eight (48) category 6 (CAT6), unshielded twisted pair (UTP), patch cords for each Core Closet.

.13 CAT6 UTP patch cords are to be factory assembled and tested by the manufacturer. Provide written certification from manufacturer. The Contractor is responsible for determining the length of patch cords.

2.11 SERVER CLOSET

.1 Provide the number of Server Closets as noted in the Contract Drawings.

.2 Provide the enclosures, power supplies, and appurtenances to meet the intent of this specification. Refer to the Server Closet (Typical) drawings for detailed design.

.3 Provide one (1) 24-port, patch panel and horizontal cable manager (2U Neat Patch) for termination of unshielded-twisted pair (UTP) cable within each Server Closet.

2.12 ACCESS CLOSETS/TELECOM ENCLOSURE

.1 Provide Access Closets in all locations identified in the Campus Layout drawings and as required by the contract documents. Construct Access Closets to support the termination of cables (fibre optic, CAT6 UTP, power).

.2 Provide all Access Closets per the Access Closet (Typical) and Access Closet Installation drawings and associated schedules.

.3 Access Closet enclosures shall meet or exceed the following minimum requirements

.1 12U enclosure overall dimension of 30"H x 24"W x 24"D

.2 14 gauge steel, smooth continuously welded seams.

.3 Double hinged door allows front and rear access to rack-mounted components. (Enclosure must be able to open and lock from the front and the back both)

.4 Oil resistant gasket.

.5 3-point keyed latch for the front door and locking mechanism for the rear door.

.6 NEMA 4 rating.

.7 LED lighting shall be provided.

.4 Access Closets shall be Hammond NEMA 4 Eclipse Series or TW ITM approved equal.

.5 Access Closets located in corrosive environments shall be constructed from stainless steel. It will be noted on the Access Closet Installation drawings if the environment is corrosive.

63

Page 64: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 17 of 33

.6 Provide a 12U, 19" rack for the mounting of all 19" rack mountable components. The front of the 19" rack is to be recessed 50 mm (2") from the front of the enclosure.

.7 Bond 19" rack to ground.

.8 All rack-mounted components are to be accessible from the front and rear of the enclosure. Components that are not accessible from front must be installed in such a manner as to be easily removed without affecting neighbouring components.

.9 The door handle for the enclosure is to be key-lockable and recessed. All Access Closets are to be identically keyed such that a single master key can lock all closets. Key number will be provided by during construction.

.10 The Access Closet is to be mounted on stainless steel separators or galvanised struts to ensure a minimum 20 mm separation from the wall. The Access Closet shall be levelled against the wall using the separators.

.11 Except where noted on the Tender drawings, all conduits will enter the enclosure from the bottom or sides of the closet. No cable is allowed to enter the enclosure directly without being properly secured in conduit. Cable (fibre backbone and copper horizontal/backbone) can only enter the Access Closet/Telecom Enclosure through the conduit.

.12 Provide the enclosure electrical distribution as per the Access Closet (Typical) - Electrical Distribution drawing and relevant PCS standards.

.1 The Access Closet will be powered by two separate 15 A, 120 VAC supplies (Utility and Network). The Utility Supply is to power non-critical components (enclosure lighting and power bar). The Network Supply (UPS) is to power the critical network components (Ethernet Switch) and environmental controls (ventilating fans). Contractor will provide the Utility Supply from the nearest lighting panel as per the Access Closet Installation drawings. The Network Supply is to be provided by others. However, the Contractor is to provide a 15A Supplementary DIN rail mounted breaker for termination of the Network Supply. In addition, the Contractor shall provide a knockout for the Network Supply conduit as per the Access Closet Installation drawings.

.2 Provide 120 VAC, 3-wire, duplex receptacles, circuit breakers, surge suppressor, wire duct and grounding bar per the Access Closet Layout drawing and associated Component Schedule. The Contractor shall provide rigid-steel conduit and wiring to provide the 15 A, 120 VAC Utility Supply as per the Access Closet Installation drawings. The Utility Supply is to be terminated at a 15 A, DIN rail mounted, circuit breaker and surge suppressor. Distribution of the Utility Supply is as documented in the Access Closet/Telecom Enclosure - Electrical Distribution drawing. Utility supply outlet shall be labeled with source of utility power and circuit breaker number.

.3 Electrical distribution components shall be mounted on the rear inner mounting panel. All cables are to be installed in a fashion that enables the front section of the enclosure to be fully swung open without disconnecting any cables.

.13 A UPS supplied and located in the nearest PLC cabinet will power the Access Closet Network Supply. The Contractor is responsible for the distribution of the Network Supply within the Access Closet and for providing a 15 A supplemental breaker for

64

Page 65: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 18 of 33

termination of the supply by others. UPS supply outlet shall be labeled with source of UPS power and circuit breaker number.

.14 Provide a rack mount, fibre optic enclosure for termination of the fibre optic cable within the Access Closet.

.15 The fibre optic enclosure shall meet or exceed the following minimum requirements:

.1 The fibre optic enclosure shall include a slide-out/tilt-down drawer for front access of the terminations.

.2 The fibre optic enclosure shall include integrated bend-radius managers for patch cords and backbone cable.

.3 The fibre optic enclosure shall support 36 or 72 LC connectors.

.16 The fibre optic enclosure shall be Panduit catalogue no. FRME1U or approved equal.

.17 The Contractor is to ensure that installation of the fibre optic enclosure allows the sliding drawer to be fully extended and lowered without interference from or to other components.

.18 Terminate all 12 fibres in the fibre optic enclosure. Fibre colour and Tx/Rx orientation is to be identical in all Access Closets. All fibres are to be labelled as per the Access Closet - Port Assignment drawing (supplied during construction). Dark fibres (8) are to be covered to prevent damage. Blank spaces in the breakout enclosure are to have blank covers installed. Panduit Fibre Adapter Panel shall be used: For OM3 multimode, use FAP6WAQDLCZ; For OS2 singlemode, use FAP6WBUDLCZ; For Blank panel use FAPB.

.19 TIA/EIA-568-C Fibre Colour Code Chart

Colour Tube No.

Fibre Colour

Colour Tube No.

Fibre Colour

Colour Tube No.

Fibre Colour

Colour Tube No.

Fibre Colour

Colour Tube No.

Fibre Colour

Colour Tube No.

Fibre Colour

1 Blue 3 Green 5 Slate 7 Red 9 Yellow 11 Rose

2 Orange 4 Brown 6 White 8 Black 10 Violet 12 Aqua

.20 Fibre optic connectors shall be LC style connectors. Field terminable fibre connector shall be Corning catalogue no. OM3: 95-050-99-X; OS2: 95-200-99 or approved equal.

.21 Provide Corning fibre optic patch cords, one (1) x 3 metres, one (1) x 2 metres, and two (2) x 1 metres for each Access Closet/Telecom Enclosure. Provide OM3 or OS2 fibre optic patch cords to match the backbone fibre cable accordingly.

.22 Provide two (2) 24-port modular patch panels, connectors and appurtenances for termination of the unshielded twisted pair (UTP) within each 12U Access Closet/Termination Enclosure.

.23 All 24-port modular patch panels shall be Panduit catalogue no. CPPL24WBLY or approved equal.

65

Page 66: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 19 of 33

.24 Faceplate modules are to be removable enabling front access to connectors and cable. Each faceplate module will group four (4) UTP connectors and will be associated with a single 4-port, work-area outlet.

.25 All category 6 (CAT6) data / voice connectors for the plant and office floor shall be unshielded modular jacks and wired for a T586A wire-map. All CAT6 unshielded modular jacks shall be Panduit catalogue no. CJ688TGBL or approved equal.

.26 Provide Panduit Cat6 patch cord (UTPSP0.5MGYY) for each installed Copper patch panel jack port.

2.13 WORK AREA OUTLETS FOR OFFICE AREA

.1 Provide one 4-port, single-gang, work area outlets in each work area for termination of the horizontal CAT6 cables as required by the contract documents. Faceplates or decora module frames shall be either Panduit catalogue no. CFPL4IWY or approved equal.

.2 One 4-port, work-area outlet will be associated with one 4-port, snap-in faceplate installed in the patch panel of the Access Closet.

.3 In the majority of cases the 4-port, work-area outlets will be installed within the cubical partitions. In some situations the work-area outlet will be installed directly on the wall in the office areas.

.4 All category 6 (CAT6) connectors in the office area shall be unshielded modular jacks and wired for a T586A wire-map.

.5 All CAT6 unshielded modular jacks shall be Panduit catalogue no. CJ688TGWH or approved equal

.6 UTP Patch Cables

.7 Supply two (2) 5-meter, Panduit UTPSP5MGYY CAT6 UTP patch cables for each work area outlet.

.8 The Contractor is responsible for certifying that the supplied patch cables meet or exceed the requirements for CAT6 UTP patch cords as described in the TIA-568-C standard. The cabling distance from the work area outlet to the network node must be less than 10 metres.

2.14 TERMINATION PANELS FOR THE PLANT FLOOR

.1 Provide Termination Panels per the Termination Panel (Typical), Enclosure Layout drawing and schedule in all locations identified in the Access Closet Installation drawings as outlined in the contract documents

.2 A Termination Panel is a secure and environmentally protected work area outlet (4 or 8 port). Each Termination Panel will contain one or two 4-port, work-area outlets for termination of the horizontal UTP cable runs. Termination Panels will contain passive network components only.

.3 Termination Panel enclosures shall be Hammond NEMA 4 Eclipse Series wall-mounted enclosures with dimensions of 30mm (12") H x 30mm (12") W x 15mm (6")

66

Page 67: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 20 of 33

D with standard key lock or approved equal. The Hammond lock catalogue no. EJWKL

.4 Provide a back-panel with the enclosure for mounting one or two 4-port, work-area outlet boxes.

.5 Provide knockouts for the installation of 27 mm (1") conduit to carry CAT6 UTP patch cords.

.6 A minimum of four (4) and maximum of eight (8) horizontal CAT6 UTP cables will be consolidated at each Termination Panel.

.7 Work Area Outlets

.1 Provide one or two 4-port, single-gang, metal work-area outlets, connectors and appurtenances in each Termination Panel for termination of the horizontal CAT6 UTP cables. If eight (8) CAT6 UTP cables are consolidated at the Termination Panel then two 4-port work-area outlets are required.

.2 Each 4-port, work-area outlet will be associated with a 4-port, snap-in faceplate installed in the Access Closet patch panel. For PLC Nodes the typical assignment for work-area outlets will be 1-PLC, 2-PLC, 3-SPARE, 4-HMI. For HMI nodes the typical assignment for wall outlets will be 1-HMI, 2-HMI, 3-SPARE, 4-PLC. For SECURITY nodes the typical assignment for wall outlets will be 1-SEC, 2-SEC, 3-SEC, 4-SPR.

.3 Termination Panels with two (2) 4-port work-area outlets must reserve three (3) ports allocated as HMI, PLC and SPR. The remaining five (5) ports can be allocated to any combination of PLC and/or HMI.

.4 All category 6 (CAT6) connectors on the plant floor shall be unshielded modular jacks and wired for a T586A wire-map.

.5 All CAT6 unshielded modular jacks shall be Panduit catalogue no. CJ688TGBL or approved equal.

.6 Outlet faceplates shall be stainless steel. Faceplates shall be Panduit catalogue no. CFP4SY or approved equal.

.7 UTP Patch Cords

Supply four (4) 1 and 2 meter, Panduit CAT6 UTP patch cords for each Termination Panel. Hand over to the City, the Termination Panel patch cables. The Contractor will supply the Termination Panel patch cords to the City for free-issue to others for installation.

Certify in writing that the patch cords supplied under this Contract meet or exceed the requirements for CAT6 UTP patch cords as described in the TIA-568-C standard.

2.15 GROUNDING AND BONDING

.1 The facility shall be equipped with a Telecommunications Bonding Backbone (TBB). This backbone shall be used to ground all telecommunications cable shields, equipment, racks, cabinets, raceways, and other associated hardware that has the potential to act as a current carrying conductor. The TBB shall be installed independent of the building's electrical and building ground and shall be designed in

67

Page 68: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 21 of 33

accordance with the recommendations contained in the ANSI/TIA-607-B Telecommunications Bonding and Grounding Standard.

.2 The main entrance facility/equipment room in each building shall be equipped with a telecommunications main grounding bus bar (TMGB). Each telecommunications room shall be provided with a telecommunications ground bus bar (TGB). The TMGB shall be connected to the building electrical entrance grounding facility. The intent of this system is to provide a grounding system that is equal in potential to the building electrical ground system. Therefore, ground loop current potential is minimized between telecommunications equipment and the electrical system to which it is attached.

.3 All racks, metallic backboards, cable sheaths, metallic strength members, splice cases, cable trays, etc. entering or residing in the TR or ER shall be grounded to the respective TGB or TMGB using a minimum #6 AWG stranded copper bonding conductor and compression connectors.

.4 All wires used for telecommunications grounding purposes shall be identified with a green or with a wrap of green tape insulation. Non-insulated wires shall be identified at each termination point with a wrap of green tape. All cables and busbars shall be identified and labeled in accordance with the System Documentation Section of this specification.

2.16 FIRESTOPPING

.1 A firestop system is comprised of the item or items penetrating the fire rated structure, the opening in the structure and the materials and assembly of the materials used to seal the penetrated structure. Firestop systems comprise an effective block for fire, smoke, heat, vapor and pressurized water stream.

.2 All penetrations through fire-rated building structures (walls and floors) shall be sealed with an appropriate firestop system (EZ-PATH). This requirement applies to through penetrations (complete penetration) and membrane penetrations (through one side of a hollow fire rated structure). Any penetrating item i.e., riser slots and sleeves, cables, conduit, cable tray, and raceways, etc. shall be properly firestopped with EZ-PATH.

.3 All systems shall be UL Classified to ASTM E814 (UL 1479) and shall be approved by a qualified Professional Engineer (PE), licensed (actual or reciprocal) in the state where the work is to be performed. A drawing showing the proposed firestop system, stamped/embossed by the PE shall be provided to the Owner's Technical Representative prior to installing the firestop system(s).

3 Execution

3.1 GENERAL

.1 Install network enclosures in all locations identified in the Contract Drawings. Field verify and obtain written approval from the Contract Administrator of all final locations of the enclosure prior to commencing this work. All costs required to relocate enclosures in unapproved locations will be at no additional cost to the City.

68

Page 69: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 22 of 33

.2 Provide all components and appurtenances necessary to ensure that the network closets are functional and meet the intent of this specification and City Process Control System (PCS) Standards.

.3 Locate Termination Panels such that the length of the horizontal cable runs from the Access Closet interconnect to the Termination Panel work-area outlet shall be less than 90 metres. For Termination Panels where this proves impossible the Contract Administrator will authorize in writing an exception if the link still meets the performance requirements of this specification.

.4 Mount the Termination Panel on stainless steel separators or galvanised steel struts to ensure a minimum of 20 mm separation from the wall.

.5 The Contract Administrator reserves the right to relocate Access Closets and Termination Panels within 3 m of the locations identified in the Contract Drawings at no additional cost to the City.

.6 It is the Contractor's responsibility to size all power supply cables to meet the requirements of the Ontario Hydro Safety Code based on field verified length of cable run and power supply load.

.7 Cable and Conduit

.1 Provide four (4) or eight (8) CAT6, UTP horizontal cables to each Termination Panel from an Access Closet in a single 35 mm (1 ¼") conduit. Where eight (8) cables are required it will be noted on the Access Closet Installation drawing, otherwise, four (4) cables are required. This applies for installations of Termination Panels on the plant floor.

.2 Conduit carrying horizontal cables shall enter the Termination Panel through the side.

.3 Conduit for patch cords shall enter the Termination Panel through the bottom and shall be installed by others.

.4 Conduit shall be galvanized rigid steel unless the environment is corrosive. Corrosive environments will be noted on the Access Closet Installation drawings. Conduit running through corrosive environments shall be Rigid PVC coated or Aluminum conduit. See Section 16130. All metal conduits shall be reamed and bushed at both ends and bonded to the distribution system. All fittings, connectors, and couplings shall be of the same material as the conduit used on site.

3.2 FIBRE OPTIC CABLE INSTALLATION

.1 Installation of the fibre optic backbone cable shall comply with Section 56 (Optical Fibre Cables) of the Ontario Electric Safety Code and the EIA/TIA-568-C Telecommunications Building Standard.

.2 Each fibre backbone segment shall be a continuous run from the Network Core Closet to the target Access Closet. Splices are not permitted.

.3 The fibre optic backbone cable shall be installed in new 305 mm (12") W x 150 mm (6") H cable tray provided under this contract. The cable tray shall be segmented into a 50 mm (4") wide section reserved for network cables only using dividers.

.4 Cable tray shall be constructed of galvanised steel or aluminum.

69

Page 70: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 23 of 33

.5 Cable tray is to be labelled per the TIA/EIA-606-B standard.

.6 If not integral to the installed cable tray, bend radius managers shall be provided where the cable tray changes direction by more than 45 degrees or when cable leaves the tray.

.7 Where more than one fibre optic backbone cable resides in the cable tray, the cables are to be bundled together using straps or cable guides. Do not use PVC cable ties. The number of fibre cables bundled shall not exceed four (4). Labels shall be applied to the cables in a manner that ensures they are readable without unbundling the cable. As a minimum, cable bundles shall be strapped together and to the cable tray structure every 20 metres and at every transition.

.8 Galvanised, rigid-steel conduit shall be utilized to bridge gaps between sections of cable tray.

.9 The fibre optic backbone cable shall be installed in 27 mm (1") galvanised, rigid-steel conduit for the full length of the vertical run from the network closet to cable tray. The conduit is to make a smooth transition from cable tray to ensure that the fibre optic cable bend radius shall not be less than the manufacturer's recommended minimum bend radius.

.10 As a minimum, a one (1) metre loop shall be left at the end of each fibre optic backbone cable and housed in the network closet. Additional loops shall be provided for every 100 metres of cable length. Loops not located at the end of the cable shall be wrapped around bend radius managers provided within the cable tray.

.11 The bend radius for fibre optic backbone cable shall not be less than the manufacturer's recommended minimum bend radius.

.12 The tensile load for fibre optic backbone cable shall not exceed the manufacturer's recommended maximum tensile load.

.13 To prevent micro-bends the Contractor shall not use nylon cable-ties. Instead the Contractor shall use straps to secure or collate fibre optic backbone cable.

.14 Individual fibre backbone segment lengths are shown in the Campus Layout - Cable Routing Schedule. Segment lengths are estimates calculated from the Campus Layout for each plant. The Campus Layouts provided with this tender document are Reasonably-To-Scale (RTS). Contractor is to field verify cable lengths. The recommended fibre route to the Access closets is provided in the Campus Layout - Cable Routing Schedule.

.15 Labelling

.1 Use durable non-fading sleeve type wire markers to identify all network cables.

.2 Apply the tagging convention described in this specification for all Fibre Optic cables.

.3 As a minimum, label both ends of the fibre optic backbone cable.

.4 In addition, label the fibre optic cable every 20 metres from the Network Core and at all major transitions. Major transitions are defined as: the entrance and exit of a wall or floor, a change in method of ducting, or a change in direction of more than 45 degrees.

70

Page 71: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 24 of 33

3.3 HORIZONTAL CABLE INSTALLATION

.1 Run horizontal cables connecting Access Closets to Termination Panels on plant floor in 35 mm (1 ¼") galvanised, rigid steel conduit.

Cable fill capacities of conduit shall not be greater than 40%. The inside radius of a bend in a conduit shall be not less than six times the internal diameter when the conduit is less than 50mm in diameter and ten times the internal diameter when conduit is 50 mm or larger.

A pull box shall be placed in conduit runs where the sum of the bends exceeds 180 degrees, where the overall length of the conduit run is more than 30m, or if there is a revers bend in the run. Pull boxes shall be constructed and sized in accordance with Canadian electrical Code, TIA and BICSI standards of code gauge steel and shall have a rust resistant finish.

The use of LB, LL, LR, C, and T type fittings is not permitted. Only LBs designed and manufactured for communications systems are allowed where applicable.

A pull cord shall be installed in all conduits of 200 lbs pull strength. The pull cord shall be installed and maintained in the conduit before and after the cable installation.

There shall be no attachment of pull boxes or any type of panel/enclosure onto the surface of Telecom Enclosure/Termination Panel/Cabinet/Rack.

.2 Run horizontal cables connecting Access Closets to work area outlets in office area in overhead cable tray (preferred), or conduit, or J-hook (not preferred but applicable in a no choice situation) separated every 20 metres.

.3 Run either four (4) or eight (8) Horizontal cables in a conduit to the Termination Panel as noted on the Installation drawings.

.4 The bend radius for Horizontal cable shall not be less than the manufacturer's recommended minimum bend radius.

.5 Horizontal cables within the network core may be run in cable tray or through the plinth but must be segregated from power distribution cable.

.6 Labelling

.1 Use durable non-fading sleeve type wire markers to identify all network cables.

.2 Apply the tagging convention described in this specification for all Horizontal cables.

.3 As a minimum, label both ends of the Horizontal cable.

3.4 FIRESTOPPING SYSTEM

.1 All firestop systems shall be installed in accordance with the manufacturer's recommendations and shall be completely installed and available for inspection by the local inspection authorities prior to cable system acceptance.

3.5 GROUNDING SYSTEM

.1 The TBB shall be designed and/or approved by a qualified P. Eng, licensed in the province that the work is to be performed. The TBB shall adhere to the

71

Page 72: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 25 of 33

recommendations of the ANSI/TIA-607-B standard, and shall be installed in accordance with best industry practice.

.2 A licensed electrical contractor shall perform installation and termination of the main bonding conductor to the building service entrance ground.

3.6 CABLE ACCEPTANCE TESTING - GENERAL

.1 This section specifies the inspection, test, and acceptance requirements for the structured cabling of the Plant Local Area network.

.1 Comply with the provisions of Section 01650 - Start-Up, Testing and Commissioning.

.2 Supply all of the test equipment required to conduct acceptance tests.

.2 Submit acceptance documentation as defined in this section.

.3 All of the installed cabling must be tested and successfully pass all test criteria.

.4 Standards referenced in this section include:

.1 TIA/EIA-568-C: Telecommunications Cabling Standard. All standards referenced within the TIA/EIA-568-C, where applicable, constitute standard provisions of this specification.

.2 TIA/EIA-526-14-B: Optical Power Loss Measurement, Multimode

.3 TIA-526-7-B: Optical power loss measurement, Singlemode

.4 TIA-1152: Requirements for field test instruments and measurements for balances of twisted-pair cabling.

.5 PCS 13932: Field Installation Testing.

.5 Visually inspect all cables, cable reels, and shipping cartons to detect possible cable damage incurred during shipping and transport. Visibly damaged goods are to be returned to the supplier and replaced at no additional cost to the City.

.6 The City reserves the right to conduct, using Contractor equipment and labour, a random re-test any of the cables to confirm documented results. Any failed cabling shall be re-tested and restored to a passing condition. In the event more than two (2) percent of the cable plant fails during re-test, the entire cable plant shall be re-tested and restored to a passing condition at no additional cost to the Owner. All full re-test of all cabling at the discretion of the Owner may be performed with no additional cost.

.7 Acceptance shall be subject to completion of all work, successful post-installation testing which yields 100% PASS rating, and receipt of full documentation as specified.

.8 The City may agree to allow certain cable runs to exceed acceptable standardized performance criteria. If required these cable runs will be exempt from meeting the specified standards. However, the Contractor will still be required to test these cable runs to validate component and installation performance.

.9 Backbone Fibre Optic Testing

72

Page 73: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 26 of 33

.1 Backbone fibre optic cable shall meet or exceed the permanent link, performance requirements specified in TIA -568-C.3 for 50/125, laser optimized multimode and singlemode fibre.

.2 For multimode fibre test link attenuation in accordance with TIA/EIA-526-14B, Annex A – one cord reference method. Measure optical loss on each fibre at 850 nm and 1300 nm. Measure loss on each fibre from each direction (bi-directionally).

For singlemode fibre, make reference measurements in accordance with TIA-526-7-B, - One cord reference method. Measure optical loss on each fibre at 1310 and 1550 nm. Measure loss on each fibre from each direction (bi-directionally).

.3 Measure link length optically or calculate using cable sheath length markings.

.4 Mutimode backbone fibre optic cabling shall meet the following loss and length criteria:

.1 Attenuation @ 850 nm shall be less than or equal to: fibre length (km) x 3.5 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB.

.2 Attenuation @ 1300 nm shall be less than or equal to: fibre length (km) x 1.50 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB.

.3 Length shall be less than or equal to 300 metres. If the length is required to be increase than singlemode cabling shall be preferred.

.4 VCSEL driver shall be used for testing as the SFP active modules on the switch runs with VCSEL drivers up to 10Gbps. However, testing with encircled flux module (EFM2) using LED driver is also acceptable.

.5 Singlemode backbone fibre optic cabling shall meet the following loss and length criteria:

.1 Attenuation @ 1310 nm shall be less than or equal to: fibre length (km) x 0.5 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB.

.2 Attenuation @ 1550 nm shall be less than or equal to: fibre length (km) x 0.5 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB.

.3 Length more than 300 metres and shall be less than or equal to 10000 metres.

.10 Fibre Optic Test Equipment

.11 All test equipment of a given type shall be recently (within 1 year) calibrated from the same manufacturer, and have compatible electronic results output with up to date test limits and version limits. Acceptable test equipment manufacturer is Fluke Networks DTX 1800 Cable Analyzer.

.12 Fibre optic test equipment shall meet the following minimum criteria:

.1 Test equipment shall be capable of measuring relative or absolute optical power in accordance with TIA/EIA-526-14B, TIA/EIA-526-7-B, TIA-568-C and latest edition of BICSI TDMM.

.2 Test equipment shall not include the loss or length of the test jumpers in the cable plant measurements.

73

Page 74: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 27 of 33

.3 Multimode test equipment shall incorporate both 850 nm and 1300 nm sources. The coupled output power into multimode fibre shall be >= -20 dBm at each wavelength. Detectors shall have a dynamic range of at least +3 dB to -55 dB.

.4 Sources and meters shall automatically synchronize wavelengths to prevent calibration-related errors.

.5 Test equipment shall employ a serial port to facilitate uploading of saved information from tester to PC.

.6 The time-of-flight methodology shall be employed when optically measuring fibre length.

.7 Test equipment capable of measuring a Tx/Rx fibre pair simultaneously is recommended to enhance productivity.

.8 Singlemode test equipment shall incorporate both 1310 nm and 1550 nm laser sources.

.9 Backbone multimode fibre cabling shall be tested at both 850 nm and 1300 nm bi-directional using VCSEL light source and GFM2 Fluke Fibre Module. However, testing with encircled flux module (EFM2) using LED driver is also acceptable.

.10 Test report shall only be accepted upon TW ITM satisfaction.

.13 Cable Test Results Manual

.1 Submit test reports in both a hardcopy and electronic format. Hand-written test reports are not acceptable. Submit electronic files on a CD format disk in a LINKWARE and PDF format.

.2 Fibre optic backbone cable and horizontal CAT6 copper cable test results shall be incorporated in the Toronto Water Network - Cable Test Results manual. Submit five (5) copies of the Cable Test Results manual for each plant. The manual consists of hardcopy test result reports placed into lockable 'D' ring binders with a cover and spine that clearly indicates the title of the manual. Put a CD with the electronic copies of test reports in a pocket in the Cable Test Results manual.

.14 Both the Contractor and Contract Administrator must sign hardcopy reports.

.15 Fibre Optic Documentation. As a minimum, test reports shall include the following information for each fibre optic cabling element (fibre) tested:

.1 Actual measured attenuation, maximum allowable attenuation (loss) and the attenuation margin at the specified wavelengths. An individual test that fails the link criteria shall be marked as FAIL.

.2 Reference method.

.3 Number of mated connectors.

.4 Actual length and maximum allowable length. Any individual test that fails the link length criteria shall be marked as FAIL.

.5 Group refractive index (GRI) for the type of fibre tested, if length was optically measured.

.6 Tester manufacturer, model, serial number and software version.

.7 Circuit ID number (Cable Tag Id) and facility (Plant).

.8 Link criteria used.

74

Page 75: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 28 of 33

.9 Overall pass/fail indication.

.10 Date and time of test.

.16 Horizontal twisted pair cable shall meet or exceed the permanent link, performance requirements specified in TIA-568-C.2 for Category 6, Unshielded Twisted Pair (UTP).

.17 Category 6 Test Equipment. Category 6 test equipment shall meet the following minimum criteria:

.1 All test equipment of a given type shall be recently (within 1 year) calibrated from the same manufacturer, and have compatible electronic results output with up to date test limits and version limits. Acceptable test equipment manufacturer is Fluke Networks DTX 1800 Cable Analyzer, DSX5000, JDSU NGC-4500.

.2 Permanent link test adapters must be approved by the manufacturer of the test equipment. Adapters from other sources are not acceptable.

.3 Horizontal cable testing shall only be Permanent Link configuration. Channel testing configuration is not acceptable.

.4 All twisted-pair copper cable links shall be tested for continuity, pair reversals, shorts, opens and performance as indicated below. Additional testing is required to verify Category performance.

.5 Baseline accuracy of the test equipment must meet or exceed TIA Level III, as indicated by independent laboratory testing.

.6 Test equipment must be capable of certifying Category 6 to TIA-568-C.2 standards.

.7 Test equipment must have a dynamic range of at least 100 dB to minimize measurement uncertainty.

.8 Test equipment must be capable of storing full frequency sweep data for all tests.

.9 Test equipment must include S-Band time domain diagnostics for NEXT and return loss (TDNXT and TDRL) for accurate and efficient troubleshooting.

.10 Test equipment must be capable of running individual NEXT, return loss, etc., measurements in addition to auto tests. Individual tests increase productivity when diagnosing faults.

.11 Test equipment must make swept frequency measurements in compliance with TIA/EIA-568-C standards.

.12 The measurement reference plane of the test equipment shall start immediately at the output of the test equipment interface connector. There shall not be a time domain dead zone of any distance that excludes any part of the link from the measurement.

.18 Category 6 (UTP) Documentation: As a minimum, test reports shall include the following information for each UTP CAT6 cabling element tested:

.1 Wiremap results that indicate the cabling has no shorts, opens, mis-wires, split, reversed, or crossed pairs, and end-to-end connectivity is achieved.

.2 Attenuation, NEXT, PSNEXT, Return Loss, ACR, ACR-F, and PSACR-F data that indicate the worst case result, the frequency at which it occurs, the limit at that point, and the margin. These tests shall be performed in a swept frequency manner

75

Page 76: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 29 of 33

from 1 MHz to highest relevant frequency, using a swept frequency interval that is consistent with TIA requirements. Information shall be provided for all pairs or pair combinations and in both directions when required by the appropriate standards.

.3 Length (in metres), propagation delay, and delay skew relative to the relevant limit.

.4 Any individual test that fails the relevant performance specification shall be marked as a FAIL.

.5 Cable manufacturer, cable model number/type, and NVP.

.6 Tester, manufacturer, model, serial number, hardware version, and software version.

.7 Circuit ID number (Cable Tag Id) and Facility (Plant).

.8 Test criteria used.

.9 Overall pass/fail indication.

.10 Date and Time of test.

.11 Submit test reports in both a hardcopy and electronic format. Hand-written test reports are not acceptable. Submit electronic files on a CD format disk in a LINKWARE and PDF format.

.19 All field terminated twisted-pair copper patch cord from Termination Panel (TP) to end device shall be tested for continuity, pair reversals, shorts, opens, and performance to Category 6. Patch cord shall be tested using a minimum level III test unit for Category 6 patch cords performance compliance and appropriate patch cord adapters. Use channel test adapter and channel test limit tested patch cords test result is not acceptable.

.20 Multipair Cat3 copper backbone cable shall be tested for voice application using DTX-1800 or approved equivalent. The testing shall be conducted from the voice patch panel in the Telecom Enclosure (TE) to the termination blocks at the Entrance Facility.

3.7 FACTORY ACCEPTANCE TEST (FAT) - ACCESS CLOSET & TERMINATION PANEL

.1 The Factory Acceptance Test (FAT) will be performed at the location where the panels are manufactured and/or assembled.

.2 The system components that will be Factory Acceptance Tested are the Access Closets and Termination Panels. The FAT will evaluate workmanship and verify construction and components against the Layout drawings and associated Component Schedules submitted to and reviewed by the Contract Administrator and consultant.

.3 Provide Record and Shop Drawings to the Contract Administrator three weeks prior to the test for review.

.4 Prepare a checklist or test sheet and submit to the Contract Administrator, three weeks prior to the commencement of the test, for review. The Contractor shall conduct the test when directed by the Contract Administrator. As a minimum, the Contract Administrator/project manager, consultant, and City shall witness the test.

76

Page 77: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 30 of 33

.5 The FAT will be completed when all items in the checklist have been witnessed and initialed by the Contract Administrator as being in conformance with the design as specified.

.6 The remaining Termination Panels and Access Closets will not undergo a witnessed Factory Acceptance Test. However, the Contractor will certify that: each enclosure has been constructed in the same manner as the equivalent witnessed and accepted enclosure, each enclosure has undergone a QA/QC test by the Contractor, and the manufacturer and catalogue number of components utilized are identical to those of the equivalent witnessed and accepted enclosure. Termination Panels and Access Closets that do not comply with above will be made compliant at no expense to the City.

3.8 SITE ACCEPTANCE TEST (SAT)

.1 A Site Acceptance Test (SAT) will NOT test functionality of the system or its components. Site Acceptance Tests will evaluate the workmanship and verify installation against the Installation and Layout drawings.

.2 Provide Record and Shop Drawings to the Contract Administrator three weeks prior to the test for review.

.3 Prepare a checklist or test sheet and submit to the Contract Administrator, three weeks prior to the commencement of the test, for review. The Contractor shall conduct the test when directed by the Contract Administrator. As a minimum, the Contract Administrator, Consultant, and City shall witness the test.

.4 The SAT will be completed when all items in the checklist have been witnessed and initialed by the Contract Administrator as being in conformance with the design as specified. Prior to SAT, the Consultant shall review and approve all copper and fibre optic cabling testing, bonding, bonding and grounding inspections, and any other criteria as may be described in the project tender.

.5 Computer Room SAT:

.1 Each plant will have one or more computer rooms, which house the Server and network Core Closets. Each computer room will undergo a witnessed SAT.

.2 The Contractor is responsible for the Computer Room UPS, Lighting Panel and any Computer Room modifications noted in the tender drawings and specifications. The extent of Computer Room modifications varies for each plant.

.3 In addition to the above, the Computer Room SAT will include the evaluation of the Server and Core Closet Installation, power supplies to each closet and external cable management (e.g. cable tray). For the purpose of the Computer Room SAT the Server and Core Closets will be empty except for the installation of duplex receptacles to receive the UPS.

.6 Access Closet SAT

.1 At each plant, the Contractor will provide one complete Access Closet, associated Termination Panels and Horizontal Cable for the Access Closet SAT. Following acceptance, the Contractor will be directed to proceed with the installation of the remaining Access Closets, Termination Panels and Horizontal Cabling. The

77

Page 78: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 31 of 33

Contractor is to note that the fibre optic backbone cable installation will be included in the Core Closet SAT.

.2 As a minimum, the complete Access Closet for the SAT will include the installation of copper patch panels, fibre patch panel, power supplies, horizontal cable terminations, cable management and patch cords.

.3 The remaining Access Closets will not undergo a witnessed Site Acceptance Test. However, the Contractor will certify that each Access Closet has been provided in the same manner as the witnessed and accepted Access Closet. The City reserves the right to do a random inspection of the remaining Access Closets and those that do not comply with the above will be made compliant at no expense to the City.

3.9 FIELD SUPPORT

.1 Provide 160 hours of on-site support for each plant beginning immediately after successful site acceptance test at that plant for a period of 24 months following Substantial Performance.

.2 Respond within 24 hours to a request for on-site support.

.3 The minimum site time per call will be four (4) hours.

.4 Travel time will not be included in the on-site time.

.5 The cost for the on-site field support will be paid based on the rates quoted in the Schedule of Prices.

3.10 FINAL ACCEPTANCE

.1 Once all work has been completed and all documentation has been submitted, and the City is satisfied that all work is in accordance with contract documents, the City shall notify Contractor in writing of formal acceptance of the system.

.2 Contractor must warrant in writing that 100% of the installation meets the requirements specified.

.3 The Owner reserves the right to conduct, using Contractor equipment and labour, a random re-test of up to five (5) percent of the cable plant to confirm documented results. Any failing cabling shall be re-tested and restored to a passing condition. In the event more than two (2) percent of the cable plant fails during re-test, the entire cable plant shall be re-tested and restored to a passing condition at no additional cost to the Owner.

.4 Acceptance shall be subject to completion of all work, successful post-installation testing which yields 100% PASS rating, and receipt of full documentation as specified.

.5 The City may agree to allow certain cable runs to exceed acceptable standardized performance criteria. If required these cable runs will be exempt from meeting the specified standards. However, the Contractor will still be required to test these cable runs to validate component and installation performance.

.6 Documentation: The Contractor shall submit the following documentation for final acceptance:

78

Page 79: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 32 of 33

.1 Toronto Water Network - Cable Test Results Manual.

.2 Operations and Maintenance Manual.

.3 As-Built drawings.

3.11 MAINTENANCE PERIOD

.1 This sub-section is supplemental to Schedule "A", Information For Tender's, Maintenance Period.

.2 For a period of twelve (12) months following Final Acceptance the Contractor will provide a qualified technician/electrician to assist in the resolution of network related problems. The Contractor will be given twenty-four (24) hours’ notice as to their requirement on-site.

.3 The Contractor will be compensated at the per diem rate quoted by the Contractor in the Form of Tender. However, if the source of the problem is discovered to be a result of work or components supplied by the Contractor, the Contractor will not be compensated.

3.12 WARRANTY

.1 The manufacturer shall warrant the project for twenty five (25) years against application assurance and extended product manufacturing defects.

.2 The Contractor shall warrant installation against all product installation defects, and that all approved cabling components meet or exceed the specified requirements for a period of twenty five (25) years following acceptance.

.3 The Contractor shall warrant that all permanent fibre optic links meet or exceed the performance requirements of TIA-568-C.3 for 50/125 micron OM3 fibre.

.4 The Contractor shall warrant that all permanent twisted pair links meet or exceed the performance requirement of TIA/EIA-568-C.2 for Category 6, shielded twisted pair and unshielded twisted pair.

.5 Contractor must provide complete end to end mapping of all connectivity at the end in both hard and softcopy formats. This includes but not limited to horizontal data / voice cable number, copper and fibre backbone cable and active equipment ports.

.6 Contractor should provide a manufacturer written certificate and warranty that the structured cabling platform is installed and fully operating in accordance with this standard and manufacturers specification.

.7 The Warranty must guarantee that the design or installation negligence on the part of the Cabling Contractor will not negate or void any portion of the certified system. The manufacturer must guarantee that all material, components and labour are covered in this circumstance for the full certification period of twenty five (25) years. It must also guarantee that in the event a Cabling Contractor is no longer able to service the Warranty, the full certification remains valid and is responsibility of the manufacturer.

.8 If a Warranty issue arises for the cabling the Warrantor must make arrangements to undertake the repair or replacement of Warranty issues within 24 hours of notification. This may require the repair/replace of cabling components outside regular working hours at no additional cost.

79

Page 80: Tender 278 -2015 Addendum No. 4 › inter › pmmd › callawards.nsf... · CLOSING DATE: OCTOBER 23, 2015, 12:00 PM (LOCAL TORONTO TIME) Please refer to the above Request for Tender

City of Toronto - Island Water Treatment Plant 13510 Residuals Management Facility Phase 1 Upgrades PCS LOCAL AREA NETWORK Contract No. 15ECS-MI-01IS / 2013-5598 Page 33 of 33

.9 The Warranty for the Cabling must be such that the cable meets or exceeds the requirements of TIA-568-C 'Transmission Performance Specifications for 100 Ohm 4-pair Category 6 Cabling" including all Standards stated in this Contract.

.10 The Cabling Contractor shall forward the Structured Cabling Platform certification request form(s) to the proper authority and ensure that a Plaque and Certificate is issued to the Customer / Project Site along with the Structured Cabling Platform user manual. The successful bidder will provide a certification number within two weeks of award of this project. Please note that the Plaque/Certificate must have the Customer name / Project name on the Plaque/Certificate.

.11 The Cabling Contractor will provide letter(s) of Certification within two weeks of substantial completion of the project to the Customer. This document will include the following: verification of the performance of the installed system, identification of the installation by location and project number and a copy of the Warranty.

.12 Upon request and at no additional cost to the Customer the Cabling Contractor must provide a manufacturer's technical representative to conduct an on-site visit to ensure complete technical compliance.

.13 The Cabling Contractor must supply a copy of an unexecuted Warranty statement (at the time of bidding) including all related terms and conditions. This copy will be the Standard to which the Warranty will be held. No changes will be accepted unless it is deemed to benefit the Customer. Any proposed changes to the Warranty must be submitted in writing to the Customer/their representative for review. The changes will then be accepted or declined by the Customer at their discretion. This is to remain valid for the entire Warranty period.

.14 All cable Cabling Contractor technicians on site must be trained by the manufacturer of the Structured Cabling Platform being installed.

.15 Any defective or improperly installed products shall be replaced, or correctly reinstalled at no cost to the Customer.

END OF SECTION

80