![Page 1: Terminal 18 Dock Rehabilitation - Microsoft · 2017-06-02 · Financial Summary T-18 Dock Rehab Construction 4 26.2 53.7 21.4 18.1 • Total project costs will be capitalized, resulting](https://reader035.vdocuments.net/reader035/viewer/2022070821/5f2291c0a3838f2a9415943b/html5/thumbnails/1.jpg)
Terminal 18 Dock Rehabilitation
6/2/2017 1
Pile and Toe Wall Repairs
Item No.: 5HMeeting: 6/06/17
![Page 2: Terminal 18 Dock Rehabilitation - Microsoft · 2017-06-02 · Financial Summary T-18 Dock Rehab Construction 4 26.2 53.7 21.4 18.1 • Total project costs will be capitalized, resulting](https://reader035.vdocuments.net/reader035/viewer/2022070821/5f2291c0a3838f2a9415943b/html5/thumbnails/2.jpg)
T-18 Dock Rehabilitation
2
26.253.7
21.4
18.1
DEF Pile Repairs
Toe Wall Repairs
DEF = delayed ettringite formation
![Page 3: Terminal 18 Dock Rehabilitation - Microsoft · 2017-06-02 · Financial Summary T-18 Dock Rehab Construction 4 26.2 53.7 21.4 18.1 • Total project costs will be capitalized, resulting](https://reader035.vdocuments.net/reader035/viewer/2022070821/5f2291c0a3838f2a9415943b/html5/thumbnails/3.jpg)
Examples of DEF Damaged Piles
T-18 Dock Rehab Construction
3
26.253.7
21.4
18.1
![Page 4: Terminal 18 Dock Rehabilitation - Microsoft · 2017-06-02 · Financial Summary T-18 Dock Rehab Construction 4 26.2 53.7 21.4 18.1 • Total project costs will be capitalized, resulting](https://reader035.vdocuments.net/reader035/viewer/2022070821/5f2291c0a3838f2a9415943b/html5/thumbnails/4.jpg)
Financial Summary
T-18 Dock Rehab Construction
4
26.253.7
21.4
18.1
• Total project costs will be capitalized, resulting in annual depreciation of $60,000 over a 30-year life once construction is complete.
• No incremental revenue or operating expense is associated with this project. • Depreciation from this capital investment was included in the 2017-2021 NWSA
operating budget starting January 2018. The depreciation will be updated during the 2018-2022 budget to reflect the March 2018 completion date.
This Request
Total Project Cost
Cost To Date
Remaining Cost
Design $0 $350,000 $162,000 $188,000
Construction $1,600,000 $1,600,000 $0 $1,600,000
Total $1,600,000 $1,950,000 $162,000 $1,788,000