test project electrical installation junior · • install the equipment in accordance with the...
TRANSCRIPT
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 2 of 12
INTRODUCTION TO TEST PROJECT DOCUMENTATION
The following is a list of sections or information that must be included in all
Test Project proposals that are submitted to World Skills Asia 2018
• Contents including list of all documents, drawings and photographs that
make up the Test Project
• Introduction/overview
• Short description of project and tasks
• Instructions to the Competitor
• Equipment, machinery, installations and materials required to complete the
Test Project
• Marking scheme (incl. assessment criteria)
• Other
INTRODUCTION
This should be a brief introduction or overview to the design concept or
background to the proposal.
Electrical work is a special type of construction work, during which the
specialist is engaged in the electrification of residential commercial and
industrial buildings.
An electrician can work as an individual entrepreneur and as an employee of
a construction company,
When working as an electrician, you must be able to:
• Correctly organize a work place
• Observe safety rules
• Be able to organize communication with the customer and with the
partner
• To show ingenuity when assembling an electrical circuit
• Install the equipment in accordance with the wiring diagram
• Correctly prepare the wires, following the rules of electromagnetism
• Connect the equipment in accordance with the schematic diagram
• To start the electric circuit
• Find faults in the wiring diagram and fix them or indicate on the circuit
diagram.
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 3 of 12
Adolescents aged 14-16 years can assemble the electrical circuit using
standard technical documentation and conventional electro technical
equipment.
At work of children at the age of 14-16 years it is necessary to observe safety
precautions. Especially - safety electro technical and at work with the
metalwork tool.
DESCRIPTION OF PROJECT AND TASKS
This should provide a description of the overall project and tasks broken
down into the smaller milestones or modules. It may also include a summary
of the assessment for each project or task.
General requirements
• Test project must be coincide with the principles of WSI Test project of
competition Electrical Installation with limitation of working with children.
At first: work only in a network with a voltage not exceeding 240 volts
AC.
• Test Project to be designed by experts, safety specialists and industry
partners;
• All technical terms and descriptions used in the Test Project must be in
accordance with internationally recognized standards;
• Cable and conduit measurements are to the centre of the cable/conduit;
• Duct and equipment measurements are to the centre or edge of the
duct/equipment;
• All dimensions must be from specific reference lines (datum/centre
lines);
• Using only installation wire with cross section 1.5 ,2.5 mm;
• At least three different cable support systems must be used. For
example:
✓ Plastic cable tray,
✓ Plastic corrugated tube,
✓ Rigid smooth plastic tube,
✓ Metal trays are forbidden.
The Test Project will consist of the following modules
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 4 of 12
Module one – Domestic and Commercial installation module
• 11 hours maximum including commissioning and equipment setup;
• Working time 4 hours a day
• The Competition Organizer must supply materials for the competition
only;
• Module one to begin on day C1;
• Measurement marks will be measured progressively each day as
indicated by the Test Project;
• Before start of Module 1 experts must to draw the axial lines
• Axial lines must not be erased to the end of mark
• Module one must be completely finished and marked by the end of
C3;
• Module one will be installed on one or two walls and the ceiling of
the Competitors cubicle;
• Drawings to be circulated at least two months prior to the
Competition.
• Installation testing board to be built by Competition Organizer;
• Competitors perform the task of module three in turn during days c1-c3
• Module three and marking to be completed by day C3;
• A circuit diagram will be released with the Test Project and all Experts
are required to bring this with a list of five or ten faults (depends on the
complexity of the wiring diagram) and any equipment that may be
needed to create them;
• One set of faults will be selected at random for use.
• Faults can be made only by independent expert (for suppose, expert from the WSI competition area)
General instructions for all modules
• The Test Projects must reflect the standards from across the world and not one specific continent.
• Once all the Test Projects have been completed they must reflect aspects of electrical installations throughout the world.
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 5 of 12
Requirements for module one – Domestic and Commercial installation
• This module must include lighting circuits, power outlet circuits;
• This module must include a design task for the Competitor;
• Installation of distribution boards and protection equipment must be included;
Requirements for module three – Installation testing
• Installation testing must be without with power
• The test circuit designs must include the following circuits: o A lighting circuit; o A socket outlet circuit; o A power circuit (such as a motor leading system);
• A total of 5/10 faults must be installed;
• Installation testing faults must include as a minimum: o One incorrect polarity fault; o One incorrect visual fault. o One short circuit faults; o One open circuit faults; o One interconnection faults
• Competitors are required to bring their own test instruments to the Competition in order to be able to carry out the requirements of this module. They must meet the Host Country’s/Region’s health and safety requirements;
• Under the terms of the module, the competitor does not correct the scheme, but only notes the errors on the principal scheme
• At the completion of C4 the Competitors will see the installed faults.
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 7 of 12
General scheme 2. Lighting
The competitors must :
• Take measures on the board to build the circuit
• Builds the circuit properly as the diagram.
• Design a proper standard circuit
• testing to the circuit using standard test equipment,
• Fault finding
Test Project marking scheme: -
Each Test Project must be accompanied by a marking scheme proposal based on
the assessment criteria defined
The marking scheme proposal is developed by the person(s) developing the Test
Project. The detailed and final marking scheme is developed and agreed by all
Experts at the Competition.
Test Project validation Experts will validate the Test Project together at the
Competition.
The test
Follow the standard instruction in building the circuit :-
- The DB height 160 cm from the reference point
- The switches height 130 cm from the reference point and 40 cm from
the right side
- The sockets height 50 cm from reference point
- The emergency switch height 100 cm from reference point
- Loads to be set at the 160
- PIR
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 9 of 12
MARKING SCHEME
Every Test Project must be accompanied by an associated marking scheme
matching the assessment criteria as given in the Technical Description
(Marking Summary). For each of these criteria a detailed list of aspects to be
assessed must be defined (this would be a draft proposal that is discussed
and finalised during preparation time at the Competition).
Criteria Mark
A Safety (electrical and personal) 10,00
B Size 12,00
C Marking of elements 3,00
D Circuit start 35,00
E Installation, cutting of the ends of wires and cables 30,00
F Fault findings 10,00
OTHER
Some minor changing may occur through the competition (about 30%)
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 10 of 12
The marking scheme as follow :
( more detail for each category upon the points needed )
Health and safety (20 marks)
Aspect
ID Max
Aspect sub criterion
description result
Mark
awarded
F1 2 Manual test of function - P1
2 Manual test of function - EMR
2 L1 is controlled by S1
Safety practice
Total
Total
Commissioning (16 marks)
Aspect
ID Max Aspect sub criterion description result
Mark
awarded
C1
Safe to power ON
First attempt (10 points)
Second attempt (5 points)
More than two attempt (2
points)
C2
Correct CB connected to
P1,P2,P3
C3
Correct CB connected to L1 and
L2
C4
Correct CB connected to L3
Total
Total
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 11 of 12
Function (20 marks)
Aspect
ID Max
Aspect sub criterion
description result
Mark
awarded
F1
Manual test of function - P1
Manual test of function -
EMR
L1 is controlled by S1
L3 is controlled by S4
Total
Total
Measurements ( level ,distance ,height….) (20 marks)
Aspect
ID Max Aspect sub criterion description Result
Mark
awarded
M1 1 E1 level
M2
E9 is ( top of MDB)
M
E10 (bottom of MDB )
M
DB level
Distance between points
Total
Total
WSAAD2018_TPJ_ Electrical Installation Version: 1.0
Date: 17.09.18 12 of 12
Installation and termination ( Fitting ,termination ,saddels,….)( 24
marks)
Aspect
ID Max Aspect sub criterion description result
Mark
awarded
IT
Correct fitting used in
IT
correctly terminated into
IT
Correctly DB fitting
IT10
saddled
IT11
All Junction box are covered (1,2 or 3)
IT13
Terminations (at CBs and MCB) must have No
copper visible
( deduct one mark for each mistake)
Total marks 100