the alma front end john c. webber national radio astronomy observatory, charlottesville va 22903,...
TRANSCRIPT
The ALMA Front End
John C. Webber
National Radio Astronomy Observatory,
Charlottesville VA 22903, USA
URSI Boulder 2008 2
ALMA Front End Organization
• Work is done by:– The National Radio Astronomy Observatory (NRAO, USA)
– The European Southern Observatory (ESO, Germany)
– The National Astronomical Observatory of Japan (NAOJ, Japan)
– The Herzberg Institute for Astrophysics (HIA, Canada)
– The Institut de Radioastronomie Millimétrique (IRAM, France and Spain)
– The Netherlands Research School For Astronomy (NOVA, The Netherlands)
– Onsala Space Observatory (OSO, Sweden)
– Rutherford Appleton Laboratory (RAL, UK)
– The Centro Astronomico de Yebes (CAY, Spain)
– The University of Cambridge / Astrophysics (CA, UK)
– The Academia Sinica (Taiwan)
URSI Boulder 2008 3
Front End Key Design Goals
• Noise performance as good as the best mm and sub-mm receivers
• Single sideband systems when possible, to minimize noise from the image sideband (all except Bands 9 & 10)
• Beam pointing controlled by mechanical tolerances (except Bands 3 & 4, which have mirrors on top of the cryostat)
• No moving parts except for cryogenics and amplitude calibration loads
• Short-term phase stability good enough for >90% coherence at 950 GHz
• Long-term phase stability good enough to go 30 minutes without instrumental calibration
• Ambient and heated RF loads for amplitude calibration
• WVR for atmospheric phase calibration by radiometry
• Rapid switching between bands for atmospheric phase calibration by position switching on a 10-second time scale
URSI Boulder 2008 4
Front End Key Programmatic Challenges
• Build 70 complete FE assemblies (66 on antennas plus 4 spares) and 3 more sets of spare subassemblies on time and on budget
• Distribute the work to multiple groups around the world and have everything play together when integrated
URSI Boulder 2008 5
Typical results for Bands 3, 6, 7, and 9. Bands 4, 8, and 10 are in development (dashed lines). The horizontal lines are the specification which applies over 80% of the band. Above 600 GHz, mixers are DSB.
URSI Boulder 2008 6
Front End Wiring Diagram
POWER M&C OFFSET LO REF IF OUT OPTICAL LO REF
URSI Boulder 2008 7
3D Model of Front End Assembly
URSI Boulder 2008 8
Front End Assembly Bottom View
URSI Boulder 2008 9
Cryostats
• Cryostat is 1 meter in diameter, mass ~450 kg• Sumitomo 3-stage refrigerator cools below 4K• Internal clamp rings provide thermal contact to cold stages
Cryostat and prototype chassis mounted on tilt table
URSI Boulder 2008 10
Optics
1. Optics design concept completed:• All ALMA Bands 1-10 and WVR pick off
mirror have been designed and incorporated into cartridge designs
• Detailed designs of all windows and IR filters• Widget space containing:
• amplitude calibration device• ¼ wave plate holder for Band 7• Solar filter
2. Design verification:• Complete physical optics calculations made for
bands 3-10• Prototypes tested warm except for bands 5 & 10• Cold tests: done during testing of assembly• Tests on the sky at 5000m elevation to begin
before the end of 2008
URSI Boulder 2008 11
Cartridge 7 Block Diagram
Cold Cartridge Warm Cartridge
URSI Boulder 2008 12
Cold Cartridges
Bands 3 (84-116 GHz), 6 (211-275 GHz), 7 (275-373 GHz), and 9 (602-720 GHz) SIS mixer receivers
URSI Boulder 2008 13
Cold Cartridges
Band 4, 125-169 GHz
(qualification model)
Band 8, 385-500 GHz
(4K stage in test dewar)
URSI Boulder 2008 14
Front End Local Oscillators
• Warm Cartridge Assemblies (WCA)– Contain YIG-Tuned Oscillator, Phase Lock Loop, Active Multiplier Chain, and
output Power Amplifiers
– Locked to output of photomixer driven by photonic signal from Back End
– Phase and amplitude noise meet ALMA specifications
– Band 3 WCA drives SIS mixer directly
– For other bands, WCAs drive cold frequency multipliers mounted in cold cartridge
• Frequency Multipliers– Wideband varistor designs from Virginia Diodes, Inc.
– Designs final for Bands 4, 6, 7, and 9
– Band 8 and 10 prototypes being tested
URSI Boulder 2008 15
183 GHz Water Vapor Radiometer
• Development status
– Two prototype WVRs (Cambridge and Onsala) were completed and fully tested
– Extensive testing was carried out at the SMA
– Final design is a single channel, Dicke-switched radiometer
– First production unit is under test and will be delivered in mid-2008
Dicke switched WVRRF Front End
URSI Boulder 2008 16
Ambient/Hot Load Amplitude Calibration Device
URSI Boulder 2008 17
Integration of Front EndWarm Optics
Band 3 Cartridge
Band 6 Cartridge
Band 9 Cartridge
Band 7 Cartridge
Cryostat
Front end chassis
Front end IF
FE M&C unit
Warm Cartridge Assembly Band 3
(1st LO, Bias, M&C)
Warm Cartridge Assembly Band 6
(1st LO, Bias, M&C)
Warm Cartridge Assembly Band 7
(1st LO, Bias, M&C)
Warm Cartridge Assembly Band 9
(1st LO, Bias, M&C)
FE Assembly
URSI Boulder 2008 18
Assembly and Test
The first FE assembly rear view with side panels removed (minus the LO Photonic Receiver)
URSI Boulder 2008 19
Principal Test Requirements
• Noise temperature• Image rejection• Beam patterns• Amplitude stability• Phase stability• IF output power• Gain flatness• Gain compression• Polarization alignment• Vacuum compatibility• Electromagnetic compatibility
URSI Boulder 2008 20
Schedule
• FE#01– Assembled and tested at the North American integration center
(Charlottesville, Virginia)– Delivered as an “engineering model” without phase stability
measurements (waiting for photonic reference test module)– Installed on a Mitsubishi antenna in November 2008
• FE#02– Assembled and tested at the East Asian integration center (Academica
Sinica, Taiwan)– Delivered as an “engineering model” without phase stability
measurements (waiting for photonic reference test module)• FE#03
– Assembled and under test at the European integration center (Rutherford Appleton Laboratory, England)
– Will be delivered in February 2009 as an “engineering model” without phase stability measurements (waiting for photonic reference test module)
URSI Boulder 2008 21
Schedule
• FE#04-06– One each to be assembled and tested at the three integration centers– Qualification and verification of integration center equipment and
procedures– Delivery as fully qualified units June-August 2009
• FE #07-70– To be delivered over the period October 2009-October 2012– Output rate of each integration center: one every 51 days!