The Bottom Line to Carbon Abatement in Existing Buildings
Michael SkeltonResearch and Knowledge Manager,Australia New Zealand
June 21, 2011
![Page 2: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/2.jpg)
Electricity Price Projections
-5%
0%
5%
10%
15%
20%
-5%
0%
5%
10%
15%
20%
Annual Change
10 Year Average = 6%
Source: Adapted from ABS 6401.0 (Australian Electricity Index)
20 Year Average = 4%
Forecast
![Page 3: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/3.jpg)
Comparative Commercial Sector Sizes
Tenant Drivers Differ Dramatically
Office41%
Shopping Centre
32%
Hotel27%
Total Market Size (m²)
Office 23,574,853 (NLA)
Shopping Centre 18,563,434 (GLAR)
Hotel 15,975,922 (GIFA)
Source: Property Council of Australia, Davis Langdon Research
![Page 4: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/4.jpg)
Australian Property Investment Market
Source: RICS, Davis Langdon Research
Office, $92.00bn
Retail, $87.00bn
Industrial, $52.00bn
![Page 5: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/5.jpg)
Lack of New Office Stock
Source: Construction Forecasting Council
New Office Construction Volumes
![Page 6: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/6.jpg)
Australia’s Ageing Office Stock
![Page 7: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/7.jpg)
Recent Studies
![Page 8: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/8.jpg)
Energy Rating Tools
Currently Available Planned
• Office
• Hotels
• Retail (>15,000sqm Lettable Area)
• Schools
• Hospitals
• Transport
• Industrial
Coming Soon...?
![Page 9: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/9.jpg)
CBD Tower Level 1 Level 2 Level 3
NPV of Investment (10 Years) -$19,000,000 -$15,000,000 $7,000,000
IRR of Investment (10 Years) 4.2% 5.1% 10.0%
Fringe High Rise
NPV of Investment (10 Years) -$11,700,000 -$2,650,000 $4,200,000
IRR of Investment (10 Years) 5.4% 9.2% 11.2%
Suburban Office
NPV of Investment (10 Years) -$1,900,000 -$1,000,000 $200,000
IRR of Investment (10 Years) 3.4% 7.7% 10.9%
Asset Improvement Study
![Page 10: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/10.jpg)
Typical Capital Cost Step Change
$0$100$200$300$400$500$600$700$800$900$1,000
050
100150200250300350400450500
2.0 Star 2.5 Star 3.0 Star 3.5 Star 4.0 Star 4.5 Star 5.0 Star
Cost Range GHG Saving (LHS) Mean Cost (RHS)Source: Davis Langdon Research
BaselinekgCO2/m2 $/m2
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6
Base Building Office – Capital cost and emissions savings
![Page 11: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/11.jpg)
Avoiding Obsolescence
Source: Davis Langdon Research
Vacancy Rate Sensitivity on Net Present Value
![Page 12: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/12.jpg)
New Build – Return on Investment
Source: Davis Langdon Research
Cost Premium to Move from 3.0 to 4.5 Star Design
![Page 13: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/13.jpg)
Heating/Cooling24%
Elec Reheat0%
Heating Gas3%
AHUs25%
Pumps in Plant Room2%
Carpark Fans4%
Carpark Lights5%
Lifts11%
Foyer lighting1%
Toilet, stairs and plant room lighting
5%
Outside Lighting5%
MechExhaust
7%
Tenant condenser water loop and cooling tower fans
2%
Hydraulic Servicing2%
Domestic Hot Water
Distribution of Base Building Energy Use
$
$
$
$
![Page 14: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/14.jpg)
Reducing Base Building Energy Outgoings
![Page 15: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/15.jpg)
However - ‘Typical’ Doesn’t Really Exist
Impact of existing condition – 1.5 to 4.5 Star Upgrade
Low Capex Required – Well Maintained
Building NLA 10,000 sq. m
Building Age 15 years
Base Building (Existing) 1.5 Star NABERS Energy
Base Building (Upgraded) 4.5 Star NABERS Energy
Green Power Included Yes (1 Star)
Total Capex $1,111,320
GHG Savings (Actual) 1,012 tonnesCO2/year
Equivalent Passenger Vehicles
166
Building Class B-Grade
0
200
400
600
800
1,000
1,200
0.0
20.0
40.0
60.0
80.0
100.0
120.0
1.5 to 4.5 StarGreen PowerEnergy Efficiency
tonnesCO2kgCO2/m²
Per Year High Capex Required – Poorly Maintained
Building NLA 10,000 sq. m
Building Age 15 years
Base Building (Existing) 1.5 Star NABERS Energy
Base Building (Upgraded) 4.5 Star NABERS Energy
Green Power Included Yes (1 Star)
Total Capex $4,358,400
GHG Savings (Actual) 1,012 tonnesCO2/year
Equivalent Passenger Vehicles
166
Building Class B-Grade
![Page 16: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/16.jpg)
Energy Efficiency Drivers in the Office Market
![Page 17: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/17.jpg)
Government Leased Area
0
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
NLA
Other
State and Territory (Leased)
Commonwealth Government (Leased)
26% Government Leased
Source: Government Property Group, Davis Langdon Research
![Page 18: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/18.jpg)
What can we achieve? Existing Buildings are the Key!
Source: Adapted from AGO 1999 & DEWHA 2009, Davis Langdon Research
0
5
10
15
20
25
Emissons (Mt of CO2-e per annum)
Total GHG from Office Sub-Sector
Estimated Trajectory if 20% of Existing Buildings <2.5 Star upgraded to 4.5 Star
Forecast
![Page 19: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/19.jpg)
Where are Incentives Required
1
4
65
Larger Incentives RequiredHigh CO2 AbatementHigh Cost of AbatementLow Level of Industry Investment without Grants/Green Depreciation(Investment and Awareness of Cost to Industry should be Focussed Here)
Minimal Incentives RequiredLow CO2 AbatementNegative Cost of AbatementHigher Levels of Industry Investment(Government and Industry Commentators Focus Too Much on These Figures)
-$100
-$50
$0
$50
$100
$150
$200
$250
$300
-$100
-$50
$0
$50
$100
$150
$200
$250
$300
Width Indicates Size of Abatement(Tonnes CO2 Over Time Horizon)
2 3
78
10
9
11
12
Cost
of A
bate
men
t
Cost
of A
bate
men
t
Value for Money from Grants/Accelerated Depreciation/etc
Maximised by Targeting These Initiatives
![Page 20: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/20.jpg)
Human Resources
the Biggest Driver!
![Page 21: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/21.jpg)
Employee Remuneration and Benefits
63%
Training 2%
Other Expenses10%
IT Equipment1%
Depreciation and Amortisation Expense
1% Telephone and Data1%
Travel and Motor Vehicle3%
Fees13%
Rent/Outogings/Fitout(Ex Electricity)
6%
Electricity0.2%
Business Expenses - Tenants
Tenant’s Focus ???
Source: Davis Langdon Research
![Page 22: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/22.jpg)
Staff Response when asked “What Provides Improved...”
Source: CABE & BCO
Job Satisfaction
Effect of Workspace
Effect of:•Technology•Pay Incentives•Advancement Opportunities•Work-Life Balance
![Page 23: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/23.jpg)
People Performance – Physical or Mental Environment?
IEQ
Improved Physical Surroundings
Impacton
Performance?
Workspace Design
Improved Mental Surroundings
VSImpact
onPerformance?
![Page 24: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/24.jpg)
Embodied Carbon
![Page 25: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/25.jpg)
Embodied Carbon Metric
Source: Davis Langdon
![Page 26: The Bottom Line to Carbon Abatement in Existing Buildings](https://reader030.vdocuments.net/reader030/viewer/2022012602/6198b9fb3f9ceb1eeb1de927/html5/thumbnails/26.jpg)
Embodied CarbonCase Study – Educational Facility and Hospital Building
Source: Davis Langdon