“The Build Sequence’ – the art and science behind the consolidation process Simon Ridgway , Peter Davie ASC Shipbuilding [email protected] ; [email protected] INTRODUCTION The AWD Program is executed by the AWD Alliance consisting of the Commonwealth of Australia, and the Industry Participants, namely ASC and Raytheon Australia. The AWD Alliance is empowered and is responsible for the conduct of the AWD Program, including the platform system design. The Commonwealth has engaged Navantia as Platform System Designer (PSD). The AWD is constructed at ASC in Adelaide with blocks being built at sites in Adelaide (ASC), Newcastle (FORGACS), Ferrol (Navantia), and Melbourne (BAES). The existing F104 ship baseline was upgraded to accommodate design modification introduced in the F105 ship which is in construction concurrently with the AWD as well as modifications resulting from obsolescence, Australian legislative compliance, and the introduction of an Australian Combat System. F100 AND AWD BLOCK BREAKDOWN For construction purposes the AWD and F105 retain the same block definition as the first F100 flight. The block breaks correspond naturally to the key structural elements of the ship and are defined to ensure a maximum consolidation weight of 200 tonnes to conform with the crane capacity over Navantia’s Ferrol slipway. The AWD block breakout and construction zone definitions are illustrated in figure 1. Figure 1. AWD Hobart Class Block Definition

Upload: lydien

Post on 17-May-2018

231 views

Category:

Documents


2 download

TRANSCRIPT

“The Build Sequence’ – the art and science behind the

consolidation process

Simon Ridgway, Peter Davie

ASC Shipbuilding

[email protected]; [email protected]

INTRODUCTION The AWD Program is executed by the AWD Alliance consisting of

the Commonwealth of Australia, and the Industry Participants, namely ASC and Raytheon

Australia. The AWD Alliance is empowered and is responsible for the conduct of the

AWD Program, including the platform system design.

The Commonwealth has engaged Navantia as Platform System Designer (PSD). The AWD

is constructed at ASC in Adelaide with blocks being built at sites in Adelaide (ASC),

Newcastle (FORGACS), Ferrol (Navantia), and Melbourne (BAES).

The existing F104 ship baseline was upgraded to accommodate design modification

introduced in the F105 ship which is in construction concurrently with the AWD as well as

modifications resulting from obsolescence, Australian legislative compliance, and the

introduction of an Australian Combat System.

F100 AND AWD BLOCK BREAKDOWN

For construction purposes the AWD and F105 retain the same block definition as the first

F100 flight. The block breaks correspond naturally to the key structural elements of the

ship and are defined to ensure a maximum consolidation weight of 200 tonnes to conform

with the crane capacity over Navantia’s Ferrol slipway. The AWD block breakout and

construction zone definitions are illustrated in figure 1.

Figure 1. AWD Hobart Class Block Definition

The block and zone based design of the ship is driven by Navantia’s “Integrated

Construction Methodology” (ICM) which is an application of the “Product Work

Breakdown Structure” derived from IHI methods of ship construction (ref 1). The ICM

focuses on maximizing fitting of welded outfit items at the sub-assembly or block

assembly stages and the use of modular outfitting assemblies. This approach limits the

amount of work that needs to happen “on-block” and is a key enabler for ASC’s

philosophy of maximizing outsourcing both at the block level and, for in-yard work, at the

sub-assembly level.

Figure 2. Block 413 during Inverted Outfitting Stage

NAVANTIA FACILITY

Navantia has consolidated the five F-100 ships on the inclined slip in its Ferrol Shipyard in

North-Western Spain. Access, stability and clearance considerations dictate the ship

configuration at launch. In the case of the F105 the bow sonar and sonar dome (block 603)

is consolidated following launch whilst the ship is in the dry dock to avoid damage. The A-

Brackets, propeller shafts and propellers are also installed post launch due to the

difficulties of installation on the slipway. The need to achieve hull completion in order to

launch and dry dock the ship is a key driver of Navantia’s consolidation sequence.

Figure 3. Navantia inclined ways

Figure 4 Navantia dry dock

AWD FACILITY

Blocks for the Air Warfare Destroyer program are being constructed in multiple yards

around Australia and some at Navantia’s Ferrol facility. ASC’s role will be the

consolidation and systems integrations of the ship. It will also build the Aegis Tower area

that will be subject to the greatest levels of change to incorporate the “Australianised”

combat system configuration.

Fig 5. Block Allocations to Subcontractors (Ship 1)

Consolidation of AWD Blocks will occur on the South Australian Government Techport

Common User Facility (CUF) commencing in October 2012. This newly constructed

facility offers the benefit of a level construction site coupled with a side-transfer facility

and a Syncrolift® shiplift with a capacity in excess of 9,400 tons and 160m in length. This

system allows the option to dock and undock a fully outfitted AWD if required

underpinning a build philosophy and schedule designed to maximise outfit levels prior to

launch in preference to driving to a relatively earlier launch with significant work requiring

completion in the dry-dock.

Fig 6. South Australian Government Techport Common User Facility and ASC

shipyard

In addition to the land-level site, ASC has invested in a 900 tonne crane with a 102m boom

crane capacity to enable the lifting of larger more heavily outfitted consolidation units and

four 200 tonne mobile transporters providing the ability to drive machinery blocks onto the

CUF with major equipments (reduction gears, gas turbines and propulsion diesel engines)

incorporated rather than waiting to include these items on the building berth.

Figure 7. ASC Self Propelled Modular Transporters

A final feature of the ASC facility designed to further exploit the efficiencies available

from level construction is the placement of two “outfit support towers” (OST) beside the

ships in construction. These towers allow for a permanent facility including tool cribs,

workshops and amenities available to workers in the ships avoiding the need to leave the

work site for extended periods during the day. By placing suitable access cuts in the hull it

is possible to significantly improve the time spent “on the job” and alleviate some of the

significant movement penalties associated with working in a completed ship. A schematic

of the AWD personnel access plan and the outfit support towers in figure 8.

Figure 8. Use of side access cuts and OSTs to support efficient on-board work

COST OF DELAYING WORK

It is generally accepted that there are significant cost penalties for executing work later in

the production cycle. Whilst the quantum of the relation is a product of many factors one

generally accepted metric is the 1:3:5 ratio for hours in pre-outfit: hours on-board: hours in

the water (ref 2). As ASC is still only in the pre-outfit stage the actual ratio for the yard

Shell Access Cut

Interior Bulkhead Cut

Passageways

OST

Inclined Ladders

Vertical Ladders

Shell Access Cut

Interior Bulkhead Cut

Passageways

OST

Inclined Ladders

Vertical Ladders

isn’t known, but as the 1:3:5 reflects a mature shipbuilding operation it is probably

conservative for a new yard providing a strong impetus to drive work early.

INCREASING PRE-OUTFIT COMPLETION

The focus of Navantia’s ICM is to exploit the efficiencies inherent in maximizing pre-

outfit levels. In ASC’s case further efficiencies should be possible due to the facility

differences described above as larger and more complete units can be consolidated.

One method of increasing the total outfit executed at the pre-outfit stage is to increase the

size of the consolidation units through combining multiple units into “grand blocks”. This

approach maximizes enables the completion of the scope of work across block breaks as

well as allowing the alignment and joining of blocks in the outfitting hall reducing the

overall consolidation duration.

For the AWD build ASC has taken advantage of the facility capability to plan joining of

the machinery spaces along the keel into two grand-blocks, as well as grand-blocking the

blocks containing the key combat systems spaces. Additional grand blocks covering the

accommodation spaces in zones 4 and 5 are also under investigation as current plans do not

use all the “grand blocks” identified by Navantia for the F105 build and the land-level

facility also allows for “driving out” rather than lifting keel-line units into place.

719

715

717

713

GB02 GB01

GB03

1 2

3

46

5

7

8

9

Figure 9 Proposed grand blocks for AWD 1 consolidation

BALANCING PRE-OUTFIT AND ON-BOARD CRITICAL PATHS

The consolidation sequence of the ship is a key attribute in the planning and control of the

overall program schedule. Defining the consolidation sequence sets the demand profile for

the blocks, which in turn allows the “back scheduling” of work through the pre-outfit

facilities to support that plan. The order and placement of the blocks during consolidation

also dictates how early the key work-fronts needed to integrate the ship system can be

opened up.

In the case of an AEGIS ship, there are two key critical paths defining the duration

between the initial keel laying and the final completion of the ship. The primary

consideration is the commencement of the cable pulling and compartment load-outs

necessary to support the combat system integration and set to work. The next critical path

is the completion of the machinery installation and alignment. Unlike a slipway

construction, the final completion of the hull to allow launching is not critical. The

selection of the launch point is driven primarily by the scope of work that cannot be

completed on the land level. In the case of the first Hobart Class ship, this work includes

the need to perform final alignments prior to both main engine and combat system light-

offs.

SETTING THE CONSOLIDATION SEQUENCE

As the pivot point for the ship construction schedule, the consolidation schedule provides a

critical tool for managing changes to the ship program. The setting of the sequence is a

simple “stacking” exercise. It is controlled by a number of heuristics including, ensuring

all necessary supporting blocks are in place; avoiding the creation of “key-holes” in the

sequence; and avoiding the consolidation of the blocks “closed ends” in a manner that

requires staging to complete joints. The complexity arises when this conceptually simple

exercise needs to accommodate situational factors, such as construction delays in critical

blocks and design restrictions that affect block support requirements and outfitting access

due to temporary bracing.

EVOLUTION OF THE AWD CONSOLIDATION SEQUENCE

When the initial consolidation sequence was developed following the award of the AWD

contract, it was planned to use an optimal consolidation sequence driving up the combat

tower to support main cable pulls with a secondary emphasis on building the stern to

support machinery alignment in order to maximize the value from the ASC land-level

facility (figure 10). This also allowed the establishment of a repeating work stations to

sequentially outfit grand blocks 1 and 2 at a constant pace throughout the program

maximizing learning.

Figure 10 Ideal CUF consolidation sequence optimizing cable pull as the primary critical

path

This philosophy has been challenged in a number of ways as the program has progressed,

knowledge of the ship design has increased and real world events have intervened.

One example of the types of factors that may drive a change in the consolidation sequence

can be seen as the result of difficulties in the construction of the ship 1 machinery blocks.

The resolution of these issues has significantly reduced the value of the repeating work

station concept for follow ships and lead to an erosion of the time available for serial outfit

of the ship 1 machinery spaces. To minimize the impact on the program, the consolidation

sequence has been adjusted from the “ideal” to a more stern focused approach shown in

figure 11. This revised sequence allows earlier completion of the keel line to support

machinery alignment whilst maintaining the relative completion dates of the combat

systems tower to the initial keel laying.

Figure 11 Revised consolidation sequence to accommodate keel and machinery issues but

maintaining relative starts for cable pulls

FUTURE CHALLENGES

With the keel laying for HOBART less than 12 months away the most immediate

challenge around the consolidation sequence will be achieving the necessary rate of hull

consolidation to support the plan. With a unit consolidation pace of one every two to three

weeks in a new shipyard, it will be necessary to operate the consolidation operations over

multiple shifts to ensure completion of the makeup activity of early blocks prior to

commencing consolidation of the blocks abutting them. Achieving the required rate will

also demand high accuracy in the blocks presented for consolidation to prevent rework.

ASC is investing heavily in total station technology and the training of a significant

Accuracy Control team in order to minimize the cost and time associated with the scribing

and cutting necessary to support final fit of the blocks.

The short overlap (12 months) between the delivery dates for the Hobart class ships

presents a challenge in the incorporation of lessons learned from ship to ship. In particular,

the ability to change the consolidation sequence as a result of learning may be challenging

as the keel laying of the follow ships occurs shortly before the completion of the preceding

hull integration. Given the lead-times through pre-outfit, adjusting the consolidation

sequence of Ship 2 will prove difficult but with the knowledge gained from both the ship 1

launch and consolidation of ship 1 and most of ship 2, opportunities to gain improvements

through the consolidation of ship 3 are expected to be substantial.

The AWD project remains on a tight schedule, with many significant challenges to

overcome. However, the AWD Alliance is committed to seeking further improvements in

productivity. As more experience is gained with the consolidation and set-to-work of the

ships, opportunities to challenge accepted practice and safely increase productivity will be

applied at every opportunity in order to deliver the capability promised by the AWDs.

REFERENCES

1. Y Okayama, (1980) “Product Work Breakdown Structure”, i

2. Kvaerner Masa Marine Inc, (1996) “Shipyard Cost Model Using Activity-Based

Costing Methods,