the challenge - colorado asphalt pavement association · however, in some cases, good performance...

16

Upload: others

Post on 07-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved
Page 2: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

The Challenge:

2

Introduction:

The Strategy:

Hot mix asphalt (HMA) pavement is the pavingmaterial of choice for a majority of Coloradoroadways. The advantages of reduced cost and lessconstruction delay combined with improvedsmoothness and ease of maintenance make asphaltpavement a viable solution for all types of roadways.However, in some cases, good performance ofasphalt pavement at high traffic volume intersectionshas not been achieved.

Some mixes that have a history of good performancemay not perform well in intersections, climbing lanes,truck weigh stations and other slow-speed areas.Special attention should be focused on high trafficvolume intersections to ensure long term pavementperformance.

The key to achieving this desired performance isrecognizing that these pavements may need to betreated differently than conventional roadways.Specifically, the pavement must be designed and

DESIGNING A HIGH PERFORMANCEASPHALT INTERSECTION

Special consideration needs to be given tointersections with heavy truck traffic and high trafficvolumes where 30-year traffic volumes are ≥1-3million ESALs. A standard pavement design is basedon fast moving traffic traveling one direction on longstretches of roadway where drainage is usually easyto handle. With high traffic volume intersections, it’snecessary to design for slower stop and go traffic,which induces much heavier stresses on thepavement section. Design equivalent single axleloads (ESALs) are greater in intersections because ofcompounding traffic direction. Also, drainage isoften compromised within intersections, leading tosaturation of the pavement section and theunderlying subgrade.

To avoid performance problems at high trafficvolume intersections, the following key strategiesshould be followed:

▲ Implementing the correct plan▲ Assessing problems with existing intersections▲ Ensuring structural accuracy▲ Selecting and controlling materials▲ Following proper construction practices

This guideline provides design and project scopinginformation so as to improve the performance ofasphalt pavement for high traffic volumeintersections.

constructed to withstand the more severeconditions. Well-designed, properly constructedHMA intersections provide an economical, long-lasting pavement with minimal disruption.

This document provides design and project scopinginformation so as to improve the performance ofasphalt pavement for high traffic volume intersections.Included is guidance on assessing problems withexisting intersections, ensuring structural adequacy,selecting and controlling materials, and tips on properconstruction practices.

The following guide is intended to help the designengineer with designing high performance, high volumeasphalt intersections utilizing Superpave asphalt mixtechnology. While they can be used, different types ofpavement materials such as Stone Mastic Asphalt (SMA)are beyond the scope of this design guide. The guide isa compilation of the most recent state-of-the-arttechnology related to Superpave and asphalt pavementdesign for high volume intersections.

The traffic analysis procedures are based on currentmethods, which are under review, both nationally andby the Colorado Department of Transportation. Whenthese procedures are modified, they will beincorporated into a futue edition of the guide.

Recognition should be given to the following organizationsfor their contribution to the intersection design guide.▲ The Colorado Department of Transportation (CDOT)▲ The Asphalt Institute▲ National Asphalt Pavement Association (NAPA)▲ Western Colorado Testing, Inc.

Special consideration needs to be given to intersectionswith heavy truck traffic and high traffic volumes where 30-year traffic volumes are ≥1-3 million ESALs.

Page 3: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

rutting

3

Implementing the Correct PlanDetermining whether or not to use a high performanceHMA intersection design vs. a conventional HMA designshould be assessed on a project-by-project basis. Somegeneral rules to consider are:

▲ When 30-year traffic loading is ≥1-3 million ESALswithin an intersection, a high performanceintersection design should be used.

▲ If high traffic volume intersections are within 1/4mile of each other, the entire roadway should bedesigned using a high performance intersectiondesign.

▲ If there are not enough high performanceintersections within a project to warrant a hightraffic volume intersection design throughout, butthe intersections that are within the project arepotentially subject to moderate-to-heavy traffic (≥1-3 million ESAL’s), they should be blocked outand a high traffic volume intersection design used.

▲ Acceleration and deceleration lanes should beincluded as part of the intersection design.

▲ Sharp turns with slow moving traffic should beincluded as part of the intersection design.

▲ When there is two-way traffic, the transitionshould extend at least 300 linear feet on eitherside of the intersection.

▲ When there is one-way traffic, the transitionshould be at least 300 linear feet on thedeceleration side and 100 linear feet on theacceleration side of the intersection.

Assessing Problemswith Existing IntersectionsA successful intersection rehabilitation project isdependent on proper project scoping. The keys toproper scoping are the following:▲ Identifying the problem with the existing

intersection,▲ Removing enough of the pavement section to

encompass all of the problem, ▲ Designing and reconstructing with a high

performance hot mix asphalt mix design especiallyformulated for high traffic volume intersections.

PERFORMANCE CHARACTERISTICS

The AASHTO Joint Task Force on Rutting (1987)identified four types of rutting:

▲ Mechanical Deformation (or rutting) is theresult of insufficient structural capacity.“Alligator Cracking” usually accompanies it.(Figure 1)

▲ Plastic Flow can result for various reasons:● High Pavement Temperatures● Materials and Mixture Design

- Rounded aggregate- Too much binder and/or filler- Insufficient or too high of VMA

● Asphalt Production(cont.)

Figure 1: Rutting in the subgrade; a weak subgrade or base will expedite damage in all pavements.

A Guideline for Designing High PerformanceAsphalt Intersections for Colorado Roadways

Page 4: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

plastic flow

consolidation

4

Plastic flow or deformation in theasphalt layer occurs during warmsummer months when pavementtemperatures are high. Atintersections, stopped and slowmoving traffic allows exhaust toelevate asphalt surfacetemperatures even higher.Dripping engine oil and othervehicle fluids are alsoconcentrated at intersections andtend to soften the asphalt. Aproperly designed mixture with astiffer asphalt binder and strongaggregate structure will resistplastic deformation of the hot mixasphalt pavement. (Figure 2)

▲ Consolidation occurs in the wheelpaths because of insufficientcompaction of the pavementsection. A number of factors cancontribute to lack of compaction.(Figure 3)● Insufficient compaction effort

within the lower base layers of the pavement section

● Too few roller passes during paving

● Hot Mix Asphalt Material cooling prior to achieving target density

● High fluid content (asphalt moisture, dust)

● Too low of an asphalt content- lack of cohesion in the mix

● Tender Mix - A gradation problem with the mix can make it hard to compact

▲ Surface wear is the result of chainsand studded tires wearing awaythe road surface in winter.Moisture damage or raveling willoccur if drainage is not adequate.

Figure 2: Rutting in the asphalt layer;good quality control in the design andproduction of asphalt mixtures is crucial.

Figure 3: Consolidation in the wheel paths; proper compaction procedures and techniques will ensure that the target density is achieved.

Page 5: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

Ensuring Structural Adequacy

5

To ensure long life performance, the pavementsection for intersections must have adequatethickness to support the slow moving or stoppedtraffic induced loads. Whether new or existing, thethickness of each component of the section mustprovide structural integrity and be sufficient so that,as a combined unit or pavement section, it will carrythe anticipated loads and higher stresses resultingfrom slower moving traffic.

Key factors to consider when ensuring structuraladequacy:▲ Subgrade strength▲ Frost depth▲ Subbase and base thickness▲ Asphalt thickness▲ Traffic type and loading▲ Drainage

SUBGRADE STRENGTH

For hot mix asphalt pavement in Colorado thesubgrade strength is measured by one of thefollowing methods:

▲ Colorado Procedure CP-L 3101 “ResistanceR-Value and Expansion Pressure of Compacted Soils”

▲ ASTM D 1883 - 94 “Standard Test Method For CBR(California Bearing Ratio) of Laboratory Compacted Soils”

▲ ASTM D 4429 - 93 “Standard Test Method For CBR(California Bearing Ratio) of Soils in Place”

Subgrade strength is a function of soil type, densityand moisture content. A given soil type with varyingdensity and/or moisture content will perform quitedifferently in its ability to support the intendedpavement section and traffic loads. Laboratoryprepared CBR and R-Values are, by standard testprocedure, performed at or near optimum moisturecontents and compacted densities that reflect man-made fills placed under controlled, closelymonitored conditions.

In-place, or in-situ, soils are often much less dense andmore saturated. The “true” in-place strength values ofthe subgrade are often much lower than laboratorymeasured strength values. Accordingly, ASTM D 4429-93 “Standard Test Method For CBR (California BearingRatio) of Soils in Place” may be used as a method tomeasure the strength of the in-place subgrade soils. TheColorado Department of Transportation uses Hveemstabilometer equipment to measure strength propertiesof soils and bases. Section 5.4.2.E. of the PavementDesign Manual describes the evaluation of thisprocedure for determining Resilient Modulus.

FROST DEPTH

In Colorado, frost depth needs to be considered whendetermining pavement thickness. Whenever the frostdepth is deeper than the calculated pavement sectionand the subgrade soils are susceptible to frost heave,special consideration should be given to the potentialeffects of the frost.

SUBBASE AND BASE THICKNESS

Thickness of subbase and base should be determinedbased on assigned strength coefficients for eachmaterial. Actual thickness determination should becalculated. Minimum thickness of an individual baselayer should be at least 4 inches but not less than 2 timesthe nominal maximum particle size of the aggregate.

If the underlying subgrade soils are clays and have swellpotential, consideration should be given to removing atleast two feet of the subgrade and placing a pavementsection of subbase, base and hot mix asphalt.

ASPHALT THICKNESS

The asphalt thickness should also be determinedbased on assigned strength coefficients. Theminimum asphalt thickness of an individual lift of hotmix asphalt should be at least three times (3:1 ratio)the maximum nominal particle size of the aggregatein the mix. The only exception to the 3:1 ratiominimum lift thickness would be for surfacetreatments such as various seal coats, which can varybased on the individual application.

A Guideline for Designing High PerformanceAsphalt Intersections for Colorado Roadways

(cont.)

Page 6: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

6

The use of recycled asphalt pavement (RAP) in thepavement section should be considered. As anexample, if it is not convenient to use milled asphaltas RAP in the asphalt mix, it can be incorporated intothe subbase and base layers of the pavementsection. Milled asphalt mixed with base is strongerthan base only. Milled asphalt placed as a layer byitself is even stronger.

TRAFFIC TYPE AND LOADING

Accurate traffic counts of existing traffic and/or realistictraffic projections for future growth and newconstruction are necessary to ensure that thepavement section is designed properly. Cross trafficat intersections needs to be accounted for as part ofthe traffic count projection. The percentage of 18 kipsingle axle trucks also needs to be determined.Vehicle classifications, by type, should be identified inorder to determine 18kip equivalent loads (ESALs).

The impact of construction equipment during earlyphases of a new subdivision or project should beconsidered. Truck traffic hauling building materialsduring the development of a subdivision or projectcan have a greater impact on design than pastconstruction or the “built out” condition.

DRAINAGE

Adequate subsurface and surface drainage isnecessary to assure the structural integrity of hot mixasphalt pavement sections. At intersections, surfacedrainage is often compromised, leading to pondingof water, which results in early surface deteriorationand eventual loss of strength within the pavementsection.

In Colorado, snow removal can be a problem,especially near intersections. If snow is left piled atthe edge of a roadway or street side drainage, curbflow lines, culverts, and cross pans becomeobstructed, forcing runoff to pond on the pavedsurface, or, worse yet, at the pavement interfacewith the curb or edge of the pavement. When thishappens, water infiltrates downward saturating thepavement section causing it to lose strength.Maintaining flow lines in ditches, and into drop inletsand culverts is necessary so that water doesn’tbecome concentrated at intersections.

Irrigation of planters and landscape areas oftencontribute to saturation of the pavement sectionand subgrade. Such areas should not be used orthey should be specially designed with subdrains tokeep water out of the pavement section.

SELECTING AND CONTROLLING MATERIALS

The key elements of a properly designedintersection include various combinations of qualitymaterials.▲ Modified subgrade▲ Geo-synthetic fabrics and mats▲ Aggregate subbase▲ Aggregate base▲ Drainage systems▲ Recycled construction materials▲ Hot Mix Asphalt

MODIFIED SUBGRADE

While not covered in this technical report, subgrademodification techniques to improve the strength ofthe subgrade are often beneficial andrecommended in special cases. Lime, flyash, andcement are types of materials used for stabilization,depending on the subgrade soil type. A qualifiedgeotechnical consultant should be retained to helpwith a potential subgrade modification design.

Cross traffic at intersections needs to beaccounted for as part of the traffic countprojection.

Page 7: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

7

GEO-SYNTHETIC FABRICS AND MATS

Geo-synthetic fabrics and mats can be used asreinforcement in a variety of ways within and belowthe pavement section. Any time poor or marginallyacceptable in-situ soils are encountered, geo-synthetic fabrics and mats should be considered.Technical representatives for individual brandmaterials are available to help in the selection of themost appropriate product.

Separation fabrics used to separate fine grain siltsand clays from open-graded drainage mats andsubbase/base materials are an especially valuableand cost effective application. Without them, a softsubgrade could inundate the more open voidspaces of drainage mats and base courses, thereby,decreasing their strength and ability to drain.

AGGREGATE SUBBASE

Aggregate Subbase courses should conform toSection 304 “Aggregate Base Course” and Section703.03 “Aggregate For Bases” Class 1 or 2 of theColorado Department of Transportation StandardSpecifications for Road and Bridge Construction,1999 Edition.

AGGREGATE BASE

Aggregate Base Course should conform to Section 304“Aggregate Base Course” and Section 703.03“Aggregate for Bases” Class 6 of the ColoradoDepartment of Transportation Standard Specificationsfor Road and Bridge Construction, latest revisionthereof.

DRAINAGE SYSTEMS

A well drained pavement section is required tomaintain the strength coefficients assigned to individualcomponents of a hot mix asphalt pavement section.Edge drains, cross drains, and drainage layers all musttie into a collection system or some means to carrycollected water away from intersections and thepavement section. Installing drainage systems thatcollect and impound water rather than diverting it awayfrom the pavement section should never be allowed.

RECYCLED CONSTRUCTION MATERIALS

During rehabilitation of intersections, it is often acost savings to utilize certain construction materialsthat have been removed by placing these materialsback into the pavement section. Such things aspulverized concrete, milled asphalt, and existingbases can sometimes be re-incorporated intosubbase and base layers with or without additionalenhancement. Doing so can result in a cost savingsto the project without sacrificing the structuralintegrity of the pavement section. Any suchinclusion of these materials should be based onassigning appropriate strength coefficients for theirindividual use.

The Colorado Department of Transportation allowsthe use of reclaimed asphalt pavement. Reclaimedasphalt pavement (RAP) is allowed in hot mix asphalt(HMA)* up to a maximum of 25% provided allspecifications for HMA are met. The use of RAP inintersection design should be permitted in a similarmanner.

*with the exception of the top 4” of new or reconstructed pavements

A Guideline for Designing High PerformanceAsphalt Intersections for Colorado Roadways

Page 8: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

HOT MIX ASPHALT (HMA)

HMA is composed of aggregates with anasphalt binder and, when required, certainanti-stripping additives. As a result of theStrategic Highway Research Program (SHRP),now commonly referred to as “Superpave”,asphalt binders are now classified based ontheir performance at both hot and coldtemperatures. By carefully selectingquality aggregates and the correctSuperpave Performance Graded (PG)asphalt binder, it is possible to producehigh quality hot mix asphalt for a widevariety of climactic conditions inColorado.

Performance Graded (PG) Binders have twonumbers in their designation such as PG 58-34. Bothnumbers describe the pavement temperatures inCelsius at which the pavement must perform. Thefirst number (58 in the example) is the hightemperature standard grade for the pavement, andthe second number (minus 34 in the example) is thelow temperature standard grade.

PG graded asphalt binders available in Colorado canbe compared to previous graded binders asillustrated in the cart on upper right.

The CDOT grade bumping procedure for “slowmoving traffic” should be used on State projects asdescribed in the Pavement Design Manual, Table A-8.In determining the use of polymer modified bindersat an intersection, minimum quantities need to beexamined.

For high traffic volume intersections, the asphaltbinder industry in Colorado recommends PG 76-28binder be used for all lifts of intersection pavingthroughout all climactic regions of Colorado.

The asphalt mix design or job mix formula should bebased on Superpave technology. The compactioneffort, or number of gyrations of compaction atDesign ( NDesign), for the Superpave compactor isvaried to allow for different levels of compaction for

8

different traffic loading (ESALs) and for differentenvironmental categories. The various designgyrations used for Superpave are similar to differentblow counts for the Marshall Method of Mix Designs.The highest 7-day average maximum air temperatureis used to find the high temperature category. Thiscategory is used with the total 18k ESALs to findNDesign. The new recommended NDesign Table forSuperpave shows the number of gyrations requiredfor the Superpave compactor for different ESALs andenvironmental categories.

It is recommended that for high traffic volumeintersections the NDesign should be selected basedon a traffic level one level higher than would beselected for normal roadway or street design. Thecompaction effort (number of gyrations)corresponding to the higher level of ESALs should beused for the mix design. Example: Traffic level isdetermined to be <0.3 million ESALs. Go to 0.3-3million ESALs (one traffic level higher) in the tableand select 75 gyrations NDesign for the mix designcompaction effort.

To assure high quality and long term performance, itis recommended that a laboratory performance testbe conducted on the final mix design. The HamburgRut Tester or the Asphalt Pavement Analyzer couldbe used for this test.

Non-Modified Binders Modified Binders

Previous Grade PG Grade Previous Grade PG Grade

AC-5 – – PG 58-34

AC-10 PG 58-28 AC-20R PG 64-28

AC-20 PG 64-22 – –

– – – PG 76-28

For high traffic volume intersections, the asphalt binderindustry in Colorado recommends PG 76-28 binder beused for all lifts of intersection paving throughout allclimactic regions of Colorado.

Page 9: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

High performance hot mixasphalt for intersections requirethat the aggregate selected forthe mix be of high quality. TheAggregate Properties Tableprovides specificationrequirements necessary toassure that the hot mix asphaltwill perform properly.

9

(cont.)

A Guideline for Designing High PerformanceAsphalt Intersections for Colorado Roadways

Aggregate Properties

Aggregate Test Property Coarse - Retained on #4 Fine - Passing #4

Fine Aggregate Angularity CP 5113 Method A –– 45% Minimum

Two Fractured Faces 80% minimum ––

L.A. Abrasion AASHTO T96 40% maximum ––

Flat & Elongated Pieces (Ratio 3:1) AASHTO M283 10% maximum ––

Sodium Sulfate Soundness AASHTO T104 12% maximum – Combined Course/Fine

Adherent Coating (Dry Sieving) ASTM D5711 0.5% 45% minimum

Plasticity Index AASHTO T89, T90 –– N.P.

Recommended Superpave Gyratory Design Revolution (NDesign)

Total 18k High Temperature CategoryESALs Very Cool Cool Moderate Hot

<105 50 50 50 50

105 to 3x105 50 75 75 75

3x105 to 106 75 75 75 75

106 to 3x106 75 75 75 100

3x106 to 107 75 75 100 100

107 to 3x107 – – 100 –

>3x107 – – 125 –

It is recommended that for high traffic volume intersections theNDesign should be selected based on a traffic level one level higherthan would be selected for normal roadway or street design.

Additionally, the aggregates representing the minus #4 sieve fraction (fines) should have no flat and/or elongatedrock slivers (arrowhead shaped). They should be composed entirely of angular, coarse textured, cube shapedparticles. Absorptive aggregates (>2% water absorption) should be avoided.

Page 10: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

10

Voids in the Mineral Aggregate (VMA) requirements.

Minimum VMA RequirementsNominal Maximum Size1 mm (in.) Design Air Voids2

3.5% 4.0% 4.5%

37.5 (1-1/2) 11.2 11.7 12.2

25.0 (1) 12.2 12.7 13.2

19.0 (3/4) 13.2 13.7 14.2

12.5 (1/2) 14.2 14.7 15.2

9.5 (3/8) 15.2 15.7 16.21 The Nominal Maximum size is defined as one size larger than the first sieve to retain more than 10%.

2 Interpolate specified VMA values for design air voids between those listed

The volumetric properties of the mix design should be as follows:

Air Voids - design air voids of 3.5% to 4.5% with a target of four percent.

The composite gradation for the aggregate should be in compliance with Table 703-3 “Master Range Table forHot Bituminous Pavement (Hot Mix Asphalt) of the Colorado Department of Transportation StandardSpecifications for Road and Bridge Construction, 1999 Edition:

TABLE 703Master Range Table for Hot Mix Asphalt Pavement

Percent by Weight Passing Square Mesh Sieve

Sieve Size Grading SX (1/2") Grading S (3/4") Grading SG (1") Job Mix Tolerances

37.5mm (11/2") 100 –

25.0mm (1") – 100 90-100 +_6

19.0mm (3/4") 100 90-100 +_6

12.5mm (1/2") 90-100 * * +_6

9.5mm (3/8") * * * +_6

4.75mm (#4) * * * +_5

2.36mm (#8) 28-58 23-49 19-45 +_5

1.18mm (#16) –

600µm (#30) * * * +_4

300µm (#50) –

150µm (#100) –

75µm (#200) 2-10 2-8 1-7 +_2

*These additional Form 43 Screens will initially be established for the Contractor’s Quality Control Testing usingvalues from the AS Used Gradation shown on the Design Mix.

Page 11: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

11A Guideline for Designing High PerformanceAsphalt Intersections for Colorado Roadways

COMPLIANCE WITH PROJECT SPECIFICATIONS

Materials delivered to the intersection constructionproject should be sampled and tested beforeplacement to make sure they are of high quality andin compliance with project specifications.Additional sampling and testing should beperformed again during placement and uponcompletion of each phase to ensure that they arestill in compliance and have been placed or installedproperly. Special attention should be given tocontrolling grade for each portion of the pavementsection. Target densities should be met for all of thevarious materials provided.

UTILITIES

Whether it be intersection rehabilitation or newconstruction, a utility study should be performed todetermine if utilities being proposed, or that arealready installed, are adequate in size to handle theprojected growth within their service area. It shouldbe verified that they are adequately sized and thatthey have been installed properly, and that utilitytrenches have been backfilled and compactedproperly.

Voids Filled with Asphalt (VFA) at 4% air voids, based on traffic level.

VFA Criteria

ESALs (millions) Design VFA, %

<0.3 70-80

0.3-3 65-80

3-30 65-75

>30 65-75

Construction Practices

A final and very important strategy to consider whenrehabilitating or constructing a high performanceintersection is following proper constructionpractices. The quality of a completed project is notonly dependent on proper design and good qualitymaterials, but also on using quality workmanship.Here are several issues to address to ensure qualityworkmanship.

▲ Process Control Plan▲ Compliance with Project Specifications▲ Utilities▲ Production and Placement

PROCESS CONTROL PLAN

When rehabilitating intersections or constructingnew intersections, special consideration should begiven to details and to practicing properconstruction techniques. The contractor shouldsubmit a “Process Control Plan” containing QualityControl, Quality Acceptance and IndependentAssurance Testing schedules. All details ofconstruction, including control of materials and theirtransportation and placement, need to be covered.A complete schedule of construction activitiesshould be included. Quality Control, QualityAcceptance, and Independent Assurance Testingshould be defined and coordinated so that allparties work together for the benefit of the project.

Page 12: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

12

PRODUCTION AND PLACEMENT

At the start of paving, the volumetric properties of theplant produced material should be re-evaluated.Adjustments should be made to the plant producedmaterial as necessary, so that all of the volumetriccriteria remain within the specification limits requiredfor the Job Mix Formula (Mix Design). If “fine tuning”of the plant produced mix does not allow for therequired volumetric properties, a new Job MixFormula should be required.

During Hot Mix Asphalt paving, it is vital that thecontractor practice proper construction techniquesand pay attention to details.

▲ Achieve target density. (Most Important)▲ Avoid the use of diesel fuel in truckbeds.▲ Do not overheat the mixture.▲ Thoroughly clean milled areas.▲ Avoid segregation during production,

transportation and placement.▲ Proper joint construction is important to prevent

the entrance of water.

CONSTRUCTABLILTY REVIEW

In order to have a successful intersection project, theconstruction sequencing needs to be addressed. It isrecommended that a constructability review be heldfor complex or high performance intersections. Thisshould include the owner and industryrepresentatives so that a wide variety of options onthe most effective phasing can be obtained.

As the owner/agency nears the point where theproject plans are nearing completion, it is beneficialfor several paving contractors from the area to meetand discuss the project logistics in an open, roundtable discussion. Issues that can be discussed includeavailability and delivery of materials planned for themix design; construction schedule, sequencing, orphasing; coordination with local residents orbusinesses; environmental concerns; and other issuesof mutual interest to the owner and contractor. Quiteoften these constructability reviews will result inchanges that will benefit everyone involved, avoidsurprises at the bid letting stage, and frequently resultin better bid prices.

REHABILITATION OF EXISTING INTERSECTIONS

Thus far, this guideline provided design informationas it pertains to new or the reconstruction of existingintersections. Often, funding is not available forreconstruction of the complete pavement sectionand a top-down rehabilitation is planned. This isalso the case when the underlying pavementsections are performing satisfactorily and are not inneed of reconstruction.

Under these circumstances, a good engineering studyof the existing intersection pavement structure isnecessary to determine the type and extent ofrehabilitation needed. An investigation of theintersection site is necessary which includes visualobservations of the existing surface distress. However,most importantly, a transverse slab or cores should betaken of the pavement layers for observation in thelaboratory and testing to determine material propertiesincluding void content, stripping, and others. Thesecores should be taken strategically throughout theintersection including within and outside thewheelpaths. Surface material should be milled to adepth where the pavement has 3-5% air voids.

It is important to note the distressed sections on thecores so that that thickness, from the top of thepavement surface, is milled and replaced as part ofthe pavement rehabilitation process. This isespecially the case when the air void content in theupper asphalt pavement surface is less than 3percent. Structural requirements should then becalculated using the properties of the remainingpavement layers the projected traffic levels (in bothdirections) and other design perimeters as identifiedpreviously in this intersection design guide.

CONCLUSIONS

Even with ever increasing truck traffic and trafficlevels, tools now exist to gain top performance fromHMA intersections. Well-designed, properlyconstructed HMA intersections provide aneconomical, long lasting pavement with minimaldisruption. Implementation of an intersectionstrategy as outlined in this document will result in adramatic increase in the performance life of thepavement - reducing life-cycle costs.

Page 13: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

13A Guideline for Designing High PerformanceAsphalt Intersections for Colorado Roadways

Grand JunctionSuccesses using good design procedures have been observed on several intersections in Colorado. The designof rehabilitation for intersections at 1st Street and Grand Avenue (I-70 Business Route) in Grand Junction isanother example and was used as a reference in the development of the Design Guideline. Rehabilitated in1997, the intersection carries a large number of heavy trucks and cars. Not only is there a significant amount ofstopping and starting but heavy traffic from eastbound I-70 turns at this intersection to go south on US 50.

The intersection was blocked out and constructed at the same time as several other intersections in GrandJunction. A pavement design was developed using a 1/2” nominal mix conforming to Superpave requirements. Themix consists of 30% crushed fines, 5% washed sand, 99% of the course aggregate having two or more crushedfaces, and a fine aggregate angularity of 74. The L.A. abrasion of the aggregate yielded 17.2% loss. The asphaltbinder used in the mix was a PG 76-28 with an AC content of 5.4% and 3.11% voids (VMA 14.5, FVA 78.5). Therepair strategy consisted of a 2” mill and overlay.

Recent performance observations show no signs of cracking from the extreme temperature variations in theGrand Junction area and the high quality mix has withstood the heavy truck turning movements. Thisintersection provides a good indication ofwhat can be expected when innovativepavement design is matched with Superpavemix design technology for high qualityperformance aggregates and asphalt binder.It is expected that this intersection willprovide quite a few years of maintenancefree service.

First and Grand Ave. in GrandJunction. This intersection carriesheavy traffic including large trucksfrom I-70 to US 50. Performance isexcellent after six years.

CASE STUDIES OF GOOD INTERSECTION DESIGN PRACTICES

Ft. CollinsSeveral intersections in the City of Ft. Collins have been designed and constructed using the concepts identified in theGuideline. These intersections include Prospect/Lemay, Mulberry/Timberline, Shields/Horsetooth, Drake/Shields, andShields/Prospect. The first of these was constructed in 1995. Traffic volumes (ADT) range from 42,000 to 55,000including the heavy truck traffic observed on the Mulberry St. (SH 14) route. These intersections included a 4” mill andfill design as well as others that consisted of full depth rehabilitation. Each intersection is performing well.

The design, construction, and performance ofthese intersections is a indication of the successagencies can have using the guidelines along withgood engineering and construction practices.

View of Shields/Horsetooth Ave.intersection in Ft. Collins using Superpavedesign as outlined in the Guidelines. Thisclean, well-designed intersection providesgood contrast pavement markings for safetraffic control. The city has used thisprocedure to obtain excellent performance.

Page 14: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

the problem...

the solution . . . asphalt.

the problem...

the solution . . . asphalt.

With ever increasing congestion at urban intersections;heavy busses and trucks starting and stopping; merchantswanting continuous access to their businesses; andtraffic/pedestrian safety concerns; local agencies arechallenged to build, rebuild or reconstruct intersections thatare cost-effective, long lasting, and with minimalconstruction impact.

Lower CostWith rising prices and intense labor costsfor concrete pavement construction, thecost of an asphalt intersection is often halfthe cost of a concrete intersection,sometimes as low as 30%! Don’t forget thatmore than 90% of the paved road mileagein Colorado is asphalt. The reason is simple– asphalt is less costly to build and maintainthan concrete pavement. Asphalt isenvironmentally acceptable since it isrecyclable. It is the life cycle cost solution.

Less DelayA great advantage of using hot mix asphalt isthat it takes significantly less time toconstruct than concrete. Intersections canbe open to traffic within minutes afterconstruction. This results in much less delayand impact on motorists and businesses. Inaddition, asphalt paving can be completedat night, further lessening the impact ofconstruction on the motoring public andbusinesses.

Long Service LifeThrough the use of improved materials andmixture designs developed by theSuperpave System (see illustration), mixescan now be designed for very high trafficlevel intersections. These new designs andpremium mixes can withstand the loadingsand conditions that have resulted in rutting,shoving and cracking in the past.

New Superpave technology with rutresistant coarse crushed stone. Notestone on stone matrix.

Intermediate mix designs gave marginal results.

outdated mix with high percent offines and AC tended to rut and shove.

Page 15: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

the solution . . . asphalt.the solution . . . asphalt.Ease ofMaintenanceAsphalt street cutsfor undergroundutilities are easier,quicker, and lesscostly to make –resulting in quickerrepairs and lesstraffic delays thanare necessary forconcrete inter-sections. Streetcuts often damageelectronic traffic detour loops – which are morequickly re-installed in asphalt, lessening traffic flowdisruptions.

SaferAsphalt provides superior driver visibility forpavement markings, especially at night and duringwet pavement conditions. This enhances safetyfor drivers, bicyclists, and pedestrians. White andyellow stripes show up best against smooth blacksurfaces – helping drivers to be more aware ofcrosswalks, stop bars, turn lanes, and off-set linestripes at intersections. Also, asphalt providessuperior skid resistance without special grooving.

SmootherThere aren’t joints, saw cuts, or grooving requiredin asphalt pavements, so asphaltintersections can be built smootherthan concrete and much quieter.Asphalt is a flexible pavement thatcan be made to easily conform tothe grade changes which occur atintersections. Asphalt pavementscan be economically maintained topreserve superior ride quality overlong periods of time – and smoothroads keep the traveling publichappy.

Consider the many advantages of hot mix asphalt.

Page 16: The Challenge - Colorado Asphalt Pavement Association · However, in some cases, good performance of asphalt pavement at high traffic volume intersections has not been achieved

Centennial, Colorado • (303) 741-6150 • Fax: (303) 741-6146e-mail – [email protected] • www.co-asphalt.com

Proper design, combined with qualitymaterials and construction workmanship canmake hot mix asphalt a long termconstruction solution for even the mostheavily trafficked intersections in Colorado.

Considered with its many benefits –reduced cost, ease of maintenance,reduced delay and construction impact –asphalt pavement is the right choice forColorado intersections.

hot mix asphalt . . .is the right choice.hot mix asphalt . . .is the right choice.

hmaHMA ▲ Costs Less

▲ Causes Less Delay

▲ Rides Smoother

▲ Allows Easy Maintenance

▲ Safer

To find out more about the advantages of

asphalt pavement at intersections or for

technical support, call your local CAPA

asphalt producer or: