THE COLONNADE BUILDING 5 & 6(VILLAS 3 & 4)
COFFEE WITH THE CONTRACTOR
THE WEITZ COMPANY June 5th,
2015
BUILDING 6 (VILLA #4)JUNE 5TH, 2015
BUILDING 6 (VILLA #4)JUNE 5TH, 2015
Framing Layout Marks
BUILDING 6 (VILLA #4)JUNE 5TH, 2015
First coat of insulation, a total of two coats will be applied.
BUILDING 6 (VILLA #4)JUNE 5TH, 2015
BUILDING 6 (VILLA #4)JUNE 5TH, 2015
Spray Insulation Machine
BUILDING 5 (VILLA #3)JUNE 5TH, 2015
BUILDING 5 (VILLA #3)JUNE 5TH, 2015
First Floor- Walls & Joist were completed
in 10 days. (13,500 Livable Sqft)
BUILDING 5 (VILLA #3) FUN FACT FIRST FLOOR VERTICAL LUMBER
What is the length in miles if you lay each vertical stud end to end on the ground?
-Each stud is approximately 10 feet long.
BUILDING 5 (VILLA #3)FUN FACT ANSWER
- 4,200 total 10ft pieces- 7.95 Miles in length
That is the approximant length from the Colonnade Campus to the Loop
101 Freeway
BUILDING 5 (VILLA #3)JUNE 5TH, 2015
Plumbing Rough-In @ Bathroom
BUILDING 5 (VILLA #3)JUNE 5TH, 2015
Overhead Plumbing Manifold Location
BUILDING 5 (VILLA #3)JUNE 5TH, 2015
Electrical Rough-In (Can Lights) @ Kitchen Area
BUILDING 5 (VILLA #3)JUNE 5TH, 2015
Garage
APS ELECTRICAL CONDUITJUNE 5TH, 2015