the detector f.forti, infn and university, pisa pisa, 5 maggio 2007
TRANSCRIPT
The Detector
F.Forti, INFN and University, Pisa
Pisa, 5 maggio 2007
F.Forti - SuperB Project 2May 5, 2007
Outline
Detector requirements and considerations The SuperB Baseline Detector
SVTDCHPIDEMC IFRTrigger/DAQComputing
Budget and Schedule
F.Forti - SuperB Project 3May 5, 2007
Experimental considerations Babar and Belle
designs have proven to be very effective for B-Factory physics Follow the same ideas
for SuperB detector Try to reuse same
components as much as possible
Shifted physics emphasis Rare decays physics Decays involving ’s.
Additional emphasis on: Angular coverage
Improve reconstruction Resolution&efficiency
Tracking & vertexing Energy resolution Particle ID Muon ID Often more relevant for
background rejection than for signal reconstruction
F.Forti - SuperB Project 4May 5, 2007
SuperB Detector Main issues
Machine backgrounds Higher than and different from PEP-II/KEKB
Beam energy asymmetry Smaller: 7+4 GeV =0.28
Strong interaction with machine design Of course, as in Babar and Belle
Impact on Detector segmentation Radius of beam pipe and first sensitive layer Radiation hardness
Aging Several components are not reusable because of
aging, even if the design would be ~OK.
F.Forti - SuperB Project 5May 5, 2007
Detector Layout – Reuse parts of Babar (or Belle)BASELINE
OPTION
F.Forti - SuperB Project 6May 5, 2007
SuperB Layout with dimensions
F.Forti - SuperB Project 7May 5, 2007
Backgrounds More details in Gianni’s talk Dominated by QED cross section
Low currents / high luminosity Beam-gas are not a problem SR fan can be shielded
F.Forti - SuperB Project 8May 5, 2007
Pair production
Huge cross section (7.3 mbarn) Produced particles have low energy and loop in
the magnetic field Most
particles are outside the detector acceptance
F.Forti - SuperB Project 9May 5, 2007
Need serious amount of shielding to prevent the produced shower from reaching the detector.
0.5 11.52
2.533.5
4
4.5 5
5.56 6.5
QD0 QD0
QD0H
QD0HB00LB00H
QF1 QF1
QF1QF1
B0L
B0H
B0H
B0L
SuperB Interaction Region
0
10
20
-10
-200 1 2 3-1-2-3m
cm
M.SullivanNov. 13, 2006SB_IT_ILC_G3_300
2 1.51
0.5
2.53
3.5
QD0 QD0
QD0H
QD0HB00LB00H
QF1 QF1
QF1QF1
B0L
B0H
B0H
B0L
SuperB Interaction Region
0
10
20
-10
-200 1 2 3-1-2-3m
cm
M.SullivanNov. 13, 2006SB_IT_ILC_G3_300
We have an IR design coping with main BKG source
Radiative BhaBha
F.Forti - SuperB Project 10May 5, 2007
Backgrounds SuperB beam currents (2A) are similar to PEP-
II/KEKB Background is not too much larger than what
with have today Except for SVT Layer0 Detailed simulations ongoing, especially for radiative
Bhabhas and Touschek backgrounds Need to design a robust detector with the enough
segmentation and radiation hardness to withstand surprises (x5 safety margin)
IR design is critical Shielding More studies needed
F.Forti - SuperB Project 11May 5, 2007
Beam Pipe Radius and Detector
Separationsignificance Proper time
differenceresolution
7+4GeV
Boost =.28
Instead of 0.56
Small beam pipe radius possible because of small beam size Studied impact of boost on vertex separation
(B) Rest of tracking is Babar Beam pipe needs to be cooled.Study is in progress
to keep total thickness low in the order of % of rad
F.Forti - SuperB Project 12May 5, 2007
Beam pipe
1.0 cm inner radius Be inner wall
≈ 4um inside Au coating 8 water cooled channels
(0.3mm thick) Power ≈ 1kW
Peek outer wall Outer radius ≈ 1.2cm Thermal simulation shows
max T ≈ 55°C Issues
Connection to rest of b.p. Be corrosion
Outer wall may be required to be thermally conductive to cool pixels
F.Forti - SuperB Project 13May 5, 2007
SVT
Baseline: use an SVT similar to the Babar one, complemented by one or two inner layers. Question on whether it would possible/economical to add a layer
between SVT and DCH, or move L5 to larger radius Cannot reuse because of
radiation damage Beam pipe radius is
paramount inner radius: 1.0cm, layer0 radius: 1.2cm, thickness: 0.5% X0
40 cm30 cm
20 cm
Layer0
F.Forti - SuperB Project 14May 5, 2007
SVT Layer 0
Depends critically on background level Striplet solution (baseline)
Basically already available technology but more sensitive to background. OK for 1MHz/cm2
Some margin to improve background sensitivity
Monolithic Active Pixel Solution solution (option)
R&D is still ongoing but giving a big safety margin in terms of performance and occupancy
Cooling and mechanical issues need to be addressed
See talks in the afternoon
V
U1.35 cm
7.7 cm
F.Forti - SuperB Project 15May 5, 2007
Striplets detector concept
F.Forti - SuperB Project 16May 5, 2007
DCH Basic technology adequate. Cannot reuse BaBar DCH because of aging
Faster gas and smaller cell would be beneficial Baseline:
Same gas, same cell shape Some gas improvement possible (order 20%) Reducing cell dimension deteriorates resolution
Carbon fiber endplates instead of Al to reduce thickness Backgrounds simulated, dominated by radiative Bhabhas
Depend critically on shielding About 7% occupancy with current solution, could be reduced to 1.5%
Options/Issues to be studied: Miniaturization and relocation of readout electronics
Critical for backward calorimetric coverage Conical, Carbon fiber endplate Further optimization of cell size/gas
F.Forti - SuperB Project 17May 5, 2007
DCH Gas and Cell Size
F.Forti - SuperB Project 18May 5, 2007
Particle ID Barrel PID essential for
hadron PID above ~0.7GeV. DIRC baseline
Quartz bars are OK and can be reused
Almost irreplaceable PMTs are aging and need to be
replaced Keep mechanical support
Barrel Options Readout options motivated by
reduction of background generated in SOB
SOB: Faster PMTs using the standoff box and water coupling
Smaller SOB: Pixilated MaPMTs and fused silica coupling
No SOB: Focusing readout with pixilated MaPMTs
F.Forti - SuperB Project 19May 5, 2007
Forward/Backward PID option Extending PID coverage to the forward and backward considered Possibly useful, physics case needs to be established quantitatively Serious interference with other systems
Material in front of the EMC Needs space
cause displacement of front face of EMC require miniaturization and displacement of DCH electronics
TOF seems the only viable option
Technologies Aerogel-based focusing RICH
Working device Requires significant space
(>25 cm) Time of flight
Need about 10ps resolution to be competitive with focusing RICH
15-20ps OK. 10ps seems to be achievable, although not easy
F.Forti - SuperB Project 20May 5, 2007
EMC Barrel CsI(Tl) crystals
Still OK and can be reused (the most expensive detector in BaBar)
Baseline is to transport barrel as one device Various other transportation options
Background simulation indicates the need for a careful shielding design
dominated by radiative Bhabha’s Forward Endcap EMC
BaBar crystal are damaged by radiation and need to be replaced Occupancy at low angle makes CsI(Tl) too slow No doubt we need a forward calorimeter
Backward EMC option Because of material in front will have a degraded performance
Maybe just a VETO device for rare channels such as B. Physics impact needs to be quantitatively assessed DIRC bars are necessarily in the middle DCH electronics relocation is critical for the perfomance
F.Forti - SuperB Project 21May 5, 2007
EMC Backgrounds Integrated over 120 crystals in the barrel, 100 in the forward Limit for CsI(Tl) at about 1MeV/us/crystal More detailed studies and optimization are needed
F.Forti - SuperB Project 22May 5, 2007
Forward EMC crystals
Both pure CsI and LSO could be used in the forward EMC
LSO more expensive, but more light, more compact, and more radiation hard Now LSO is available industrially Cost difference still significant, but not overwhelming.
Use LSO as baseline Gives better performance Mechanically easier to assemble Leaves PID option open
CsI option still open in case of cost/availability issues
F.Forti - SuperB Project 23May 5, 2007
Crystal properties
F.Forti - SuperB Project 24May 5, 2007
IFR and steel BaBar configuration has too
little iron for ID > 6.5 I required; 4-5
available in barrel Fine segmentation overdid
KL efficiency optimization Focus on ID : fewer
layers and more iron Is it possible to use the
IFR in KL veto mode ? Baseline:
Fill gaps in Babar IFR with more iron
Leave 7-8 detectionlayers
Need to verify structural issues
Scintillator bars à la MINOS Cost effectiveness of steel reuse needs to be fully
assessed
F.Forti - SuperB Project 25May 5, 2007
IFR Backgrounds
Rates in the range of a few x 100Hz/cm2
F.Forti - SuperB Project 26May 5, 2007
Electronics and Trigger/DAQ L1 Trigger rate of 100-150KHz
Unless a hardware Bhabha rejector is developed
Up from 5KHz current Babar rate Some electronics could be reusable
Especially front-end cards, maybe power supplies
The bulk of the electronics is obsolete and unmaintainable Should be remade with state-of-the-
art technology Clearly a major cost driver
Costed using recent experiments experience (LHC)
F.Forti - SuperB Project 27May 5, 2007
Computing Computing model
extrapolated from Babar Scales with luminosity
Requires distributed computing on the grid
F.Forti - SuperB Project 28May 5, 2007
Cost estimate A full cost estimate of the SuperB project has been done
Based on Babar/PEP-II actual costs Escalated from 1995 to 2007 Bottom-up for almost all elements
Separate new components from reused elements Replacement value of reused components = how much would it
cost today to rebuild those components (extrapolated from Babar/PEP-II costs)
New costs: everything that’s needed today, including refurbishing Transport is not included, but disassembly and reassembly is.
Keep separate categories: EDIA: engineering, design, inspection and administration (man-
months) Labour: technicians (man-months) Materials and Services: 2007 Euros.
All details available in the CDR We have not tried to fully optimize the cost yet. Some reduction
might be possible
F.Forti - SuperB Project 29May 5, 2007
Detector costEDIA Labor M\&S Rep.Val.
WBS Item mm mm kEuro kEuro
1 SuperB detector 3391 1873 40747 464711.0 Interaction region 10 4 210 0
1.1 Tracker (SVT + L0 MAPS) 248 348 5615 01.1.1 SVT 142 317 4380 01.1.2 L0 Striplet option 23 33 324 01.1.3 L0 MAPS option 106 32 1235 01.2 DCH 113 104 2862 0
1.3 PID (DIRC Pixilated PMTs + TOF) 110 222 7953 67281.3.1 DIRC barrel - Pixilated PMTs 78 152 4527 67281.3.1 DIRC barrel - Focusing DIRC 92 179 6959 67281.3.2 Forward TOF 32 70 3426 0
1.4 EMC 136 222 10095 301201.4.1 Barrel EMC 20 5 171 301201.4.2 Forward EMC 73 152 6828 01.4.3 Backward EMC 42 65 3096 01.5 IFR (scintillator) 56 54 1268 01.6 Magnet 87 47 1545 96231.7 Electronics 286 213 5565 01.8 Online computing 1272 34 1624 01.9 Installation and integration 353 624 3830 01.A Project Management 720 0 180 0
Note: options in italics are not summed. We chose to sum the options weconsidered most likely/necessary.
F.Forti - SuperB Project 30May 5, 2007
Computing costs Computing depends
critically on the time scale Moore’s law
Evaluated in two scenarios: startup in 2011 or 2012
Not included in basic detector budget LHC model: distributed computing
resources provided by many partners
The on-site computing center is included in the estimates should probably called out
as a separate entity
F.Forti - SuperB Project 31May 5, 2007
Schedule Overall schedule
dominated by: Site construction PEP-II/Babar
disassembly, transport, and reassembly
We consider possible to reach the commissioning phase after 5 years from T0.
F.Forti - SuperB Project 32May 5, 2007
The Università di Roma Tor Vergata Site Area available Strong interest of University and
INFN Tunnel at about -12m Synergy with approved FEL
(SPARX) Engineering group created Issues: water, power
750m
F.Forti - SuperB Project 33May 5, 2007
Summary and outlook A SuperB detector based on Babar has been
developed It could be based on Belle as well
Technology is available Some areas require focused R&D to be finalized (see
David’s talk) Final technology choices will need to be made
Main goals for the workshop Understand the needed R&D effort Create some structure to move forward
Longer term Arrive to a Technical Design Report in 1-2 years
BACKUP
F.Forti - SuperB Project 35May 5, 2007
Accelerator and site costs
NumberEDIA Labor M\&S Rep.Val.
WBS Item Unitsmm mm kEuro kEuro
1 Accelerator 5429 3497 191166 1263301.1 Project management 2112 96 1800 0
1.2 Magnet and support system 666 1199 28965 25380
1.3 Vacuum system 620 520 27600 14200
1.4 RF system 272 304 22300 60000
1.5 Interaction region 370 478 10950 0
1.6 Controls, Diagnostics, Feedback 963 648 12951 8750
1.7 Injection and transport systems 426 252 86600 18000
NumberEDIA Labor M\&S Rep.Val.
WBS Item Unitsmm mm kEuro kEuro
2.0 Site 1424 1660 105700 02.1 Site Utilities 820 1040 31700 0
2.2 Tunnel and Support Buildings 604 620 74000 0
Note: site cost estimate not as detailed as other estimates.