The Dovre Line:Kleverud-Sørli-Åkersvika

Stine Ilebrekke Undrum Project Director

Bane NOR Tender Conference June 5. 2019

• Safety always has first priority

• Our safety culture shall ensure that we work systematically with safety to avoid human injury and environmental or material damages.− we adhere to the highest safety standards.− we understand and consider risk.− we have zero tolerance for breach of safety

regulations

• The Working Environment Act applies to EVERYONE working in Norway, both Norwegian and foreign nationals.− http://www.arbeidstilsynet.no/working-conditions-in-

norway.html

4

Important HSE principles for Bane NOR

Everybody safely home

Infrastructure Construction Division

5

InfrastrucureConstruction Einar Kilde

New Oslo-tunnelAnne Siri Haugen

FollolinePer David Borenstein

Ringerikeline/ E16Morten

Klokkersveen

West/MidHans-Egil Larsen

VestfoldlineLars A Tangerås

East (Østfoldline & Dovreline)

Stine I Undrum

Project 2020Brede Nermoen

Plan & PortfolioElsebeth A Bakke

Contract & MarketHenning Scheel

Safety & QualityVigdis Bjørlo

Finance & projectcontrol

Birger Steffensen

HRGry Jødestøl

Technique & Concept

Trude Anke

CommunicationCecilie Melland

East – Østfold Line & Dovre Line

6

Project directorStine Ilebrekke

Undrum

Venjar – LangsetRønnaug-Ingeborg

Resset

Kleverud – Sørli –Åkersvika

Geir H Kvillum

PlanprojectsDovreline Lars Eide

Sandbukta – Moss – Såstad

Jarle Rasmussen

PlanprojectsØstfoldline

Elisabeth Nordli

Dep. Project director

Per B Vilnes

ProjectcontrolTor-A Holst Larsen

Contract & strategy

Karin Kaasen

Safety & QualityBente Gamst

Hornnæs

CommunicationTBN

HR Arild Sæthre

7

Construction Projects Dovre Line

8

InterCity-projects on Dovre Line

1:23 (2:14)Oslo-Lillehammer

0:55 (1:23)Oslo-Hamar

0:37 (1:23)Oslo-Hamar

1:00 (1:28)Oslo-Tønsberg

1:30 (2:45)Oslo-Porsgrunn

0:45 (1:08)Oslo-Fredrikstad

1:08 (1:45)Oslo-Halden

• Venjar-Langset 2023

• Kleverud-Sørli 2026

• Sørli-Åkersvika 2026

• Brumunddal-Moelv 2030

• Hamar-Brumunddal 2032

• Moelv-Lillehammer 2034

• Kleverud-Sørli− Preparatory work ongoing− Preparation of invitation to tenders− Start pre-qualification of two first main

contracts autumn 2019− Contract award first Main Contract late 2020

• Sørli-Åkersvika− Zoning plan expected to be approved late 2019− Start pre-qualifications of contracts late 2020− Contract award remaining contract 2021/2022

Project status

9

Hestnes Tunnel(3 km)

Tangenvika Bridge(1 km)

Tangen Railway Station Sørli Timber

TerminalStange

Railway StationÅkersvikaWetland Area

10

Project summary

Oslo S

Eidsvoll

Oslo Airport

Lillestrøm

Tangen

Stange

Hamar

BrumunddalMoelv

Lillehammer

Sørli

JessnesHamar Converter

Sørli-Åkersvika

Kleverud-Sørli

Langset

Kleverud

Venjar

• Facts and numbers− 30 km new double track railway from Kleverud

to Åkersvika− The Hestnes Tunnel 3,1 km− Tangenvika Railway Bridge 1,07 km− Construction of a new railway station at Tangen− Rebuild of existing railway station at Stange− Åkersvika Wetland− 21 other large constructions− Tracks and catenary. Railway technique− Designed for a max speed of 250 km/h

• Planned government funding− Kleverud-Sørli 2020 including Hamar Converter

station− Sørli-Åkersvika 2021

Kleverud – Sørli - Åkersvika

Geir KvillumHead of Project

Bane NOR Tender Conference June 5. 2019

12

InterCity-projects on Dovre Line

1:23 (2:14)Oslo-Lillehammer

0:55 (1:23)Oslo-Hamar

0:37 (1:23)Oslo-Hamar

1:00 (1:28)Oslo-Tønsberg

1:30 (2:45)Oslo-Porsgrunn

0:45 (1:08)Oslo-Fredrikstad

1:08 (1:45)Oslo-Halden

• Venjar-Langset 2023

• Kleverud-Sørli 2026

• Sørli-Åkersvika 2026

• Brumunddal-Moelv 2030

• Hamar-Brumunddal 2032

• Moelv-Lillehammer 2034

Contract structure

15

Procurement plan

16

KS-1 The Hestnes tunnel

17

Contract KS-1 The Hestnes tunnel

18

KS-1 KS-2 KSÅ-3 SÅ-4

Preparatory works at Hamar

Tangen Sørli Stange Åkersvika Hamar

Kleverud

Espa

1200 m open landscape 3100 m rock tunnel no. of large constructions: 3

From Kleverud to Espa

Contract KS-1 The Hestnes tunnel

19

• Civil work - EPC contract

• Contract basis: Norwegian total contract 2015 (NTK 15)

• Procurement procedure: Negotiated procedure (konkurranse med forhandling)

• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule− Start prequalification Q4 (December) 2019− Contract award Q4 (December) 2020

KS-1 Civil works

20

• Handling of excavated rock:− 130 000 m3 fillings in lake Mjøsa− Surplus of rock being transported to Sørli

• Bridge over stream Labbelva

• 4 technical buildings• 2 access tunnels, total length 850m

• Drill & blast

• 3,1 km single tube tunnel, cross-section area 125m2

• Excavation volume, 420 000 sm3

− Hard rock, mainly granitic gneiss and amphibolite

• Water & frost-protection; membrane and concrete lining

21

KS-1 Hestnes tunnel

KS-2 Tangenvika railway bridge

22

Contract KS-2 Tangenvika railway bridge

23

KS-1 KS-2 KSÅ-3 SÅ-4

Preparatory works at Hamar

Tangen Sørli Stange Åkersvika Hamar

Kleverud

Espa

1800 m open landscape 1070 m bridge no. of large constructions: 2

From Espa to Furnesbakken

Contract KS-2 Tangenvika railway bridge

24

• Civil work - EPC contract

• Contract basis: Norwegian total contract 2015 (NTK 15)

• Procurement procedure: Competitive dialogue (Konkurransepreget dialog)− With the aim to:

‒ Focus and align project needs and goals in an early phase‒ Make use of competence and technology in the market / Exploit innovative ideas and solutions ‒ Empower efficient project execution through common understanding of technical solutions and allocation of risk

• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule− Start prequalification Q4 (October) 2019− Contract award Q4 (December) 2020

• Tangenvika railway bridge

• Restructuring of local road

• Civil work in open landscape

• Rock cut approx. 250 000 sm3

• Fillings for abutment and embankments

• Temporary quay facilities at northern side of Tangenvika bay

• Wildlife crossing

25

KS-2 Tangenvika railway bridge

KS-2 Tangenvika Railway bridge

• Concrete bridge

• Water depth of up to 50 m with 40 m layer of soils/subsoils above bedrock

• Challenging foundation due to location and depths

• Focus on increased degree of freedom in span-widths and piling method

26

KSÅ-3 Open landscape, incl. 2 stations

27

Contract KSÅ-3 Open landscape, incl. 2 stations

28

KS-1 KS-2 KSÅ-3 SÅ-4

Preparatory works at Hamar

Tangen Sørli Stange Åkersvika Hamar

Kleverud

Espa

13 250 m open landscape 2 stations no. of large constructions: 7

From Furnesbakken to Stange including Stange station

Contract KSÅ-3 Open landscape, incl. 2 stations

29

• Civil work - EPC contract

• Contract basis: Norwegian total contract 2015 (NTK 15)

• Procurement procedure: Negotiated procedure (Konkurranse med forhandling)

• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule− Start prequalification Q4 2020− Contract award Q4 2021

• 13,3 km substructure including civil works at two stations, Tangen and Stange

• Excavation and handling of approx. 1 500 000 sm3 rock and soils− Large capacity landfills close to site

• “Greenfield” areas to Sørli

• Close to existing railway from Sørlitimber- terminal

• Wildlife crossings

30

KSÅ-3

• New 4-track Tangen station, 2 tracks to platform.

• Parking areas

31

KSÅ-3 Tangen station

KSÅ-3 Stange station

• New 3- track station situated at the same place as existing Stange station

• Stange station shall be at full operation during construction.

• Parking, bus and taxi areas

32

SÅ-4 Open landscape

33

Contract SÅ-4 Open landscape

34

KS-1 KS-2 KSÅ-3 SÅ-4

Preparatory works at Hamar

Tangen Sørli Stange Åkersvika Hamar

Kleverud

Espa

9000 m open landscape no. of large constructions: 9

From Stange to Åkersvika

Contract SÅ-4 Open landscape

35

• Civil work - EPC contract

• Contract basis: Norwegian total contract 2015 (NTK 15)

• Procurement procedure: Negotiated procedure (konkurranse med forhandling)

• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule− Start prequalification Q4 2020− Contract award Q4 2021

• 9 km civil works in open landscape

• Excavation and handling of:− approx. 680 000 sm3 rock and soils− 72 000 sm3 of alum shale

• Large landfill at Nesten/Skjerden

• Approved landfill for disposal of alum shale close to site

• 2 large culvert/ concrete tunnels

• Restructuring of roads

36

SÅ-4

SÅ-4

• Two large culverts/concrete tunnels

• Deep cuttings in agricultural landscape

37

SÅ-4 Åkersvika and construction work

38

• Permanent filling above existing track in Åkersvika –Ramsar area

• New operational phase with temporary fillings

• Restrictions in construction work during the breeding period for birds (April-May)

• Permission from county governor granted before construction starts

Kleverud – Sørli - Åkersvika

Niklas MarcussenEngineering manager

Bane NOR Tender Conference June 5. 2019

KSÅ-6 & KSÅ-7 – Railway technique

40

41

Contract KSÅ-6 and KSÅ-7 Railway technique

KS-1 KS-2 KSÅ-3 SÅ-4

Preparatory works at Hamar

Tangen Sørli Stange Åkersvika Hamar

Kleverud

Espa

KSÅ-6 Tracks and OCL KSÅ-7 Power supply and TelecomFrom Kleverud to Åkersvika

30 000 m railway no. of technical buildings: 19

Contract KSÅ-6/ KSÅ-7 Railway technique

42

• Railway technique - Construction contract

• Engineering – Integrated team with Bane NOR employees and consulting engineers

• Contract basis construction contract: NS 8405

• Procurement procedure: Negotiated procedure

• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule Construction contract− Start prequalification Q3 or Q4 2021− Contract award Q3 or Q4 2022

• Power systems and installations:− 19 technical buildings− Two stations− All subsystems and components

• Installation of emergency systems in the Hestnes tunnel

• High voltage cables, 22kV

• Public information systems and video surveillance

43

KSÅ-6 Railway technique electrical power/telecom

Track works• Ballasted tracks• Installation of company provided items:

− 65 000 m of tracks− 100 000 Sleepers− 36 turnouts

• 300 000 m3 ballast

Overhead contact line• Standard Bane NOR S25 overhead contact

line system• Autotransformers

44

KSÅ-7 Railway technique Tracks/OCL

KSÅ-5 - Engineering contract

• Engineering consultancy contract− Engineering of railway systems− Project support civil works− Manpower support to integrated team, Railway technique− Interface coordination

45

Ground conditions - site investigations

46

• Geotechnical site investigations with more than 500 holes drilled along the planned track

• Kleverud-Sørli- Good ground conditions for construction

purposes. Visible rock or thin layers of topsoil

• Sørli-Åkersvika- Hard moraine of varying

depth above a soft type of rock. Stable soils for civil works

• Focus on analysis – soil and rock

• Comprehensive geotechnical site investigation program with 90 drilling points performed 2015/2016

• Stable barge ensure correct data

• Use of "down-the hole” technology to verify bedrock in addition to geophysical investigation

• Soil consist mud and hard moraine

47

Ground conditions – Tangenvika

• There is a large difference between the regulated water levels in summer and winter in Lake Mjøsa.

• Highest regulated water level HRV = 122.94 m

• Lowest regulated water level LRV = 119.33 m

• Discharge permit granted

48

Special conditions – Lake Mjøsa

Åkersvika wetland

• Åkersvika is Norways first Ramsar site (1974)-one of the largest (4300 ha) and best-developed freshwater deltas in Norway.

• Application for exemption from RAMSAR-regulations-Hedmark county – in good progress

• Building new railway will have a footprint of 29 daa, of which 19 daa is permanent.

49

• Main principles for allocation of risk in the contract will be: - The risk shall be carried by the party most familiar with the risk and best able to control it- Risk allocation in the contract shall be fair (balanced) and well-defined- Compensation format will be compiled to reflect the above

• Risk mitigation is also applied by:- Reduced uncertainty through thorough geological and geophysical surveys - Test pile driving in Mjøsa by contractor, to be considered - Use of competitive dialogue for Tangenvika railway bridge- Environmental regulations; Several permits for environmental emissions in good progress

• The compensation format will aim for neutral liquidity

50

What do we think about risk

Kleverud-Sørli-Åkersvika. Contract Summary

51

EPC contractKS-1

Tunnel

Prequal. Q4.2019

EPC contractKS-2

Bridge

Prequal. Q4.2019

EPC contractSÅ-4

Open landscape

Prequal. 2020

EPC contractKSÅ-3

Open landscape Incl. 2 stations

Prequal. 2020Civil

Railway systems

Prequal. 2021

Construction contractKSÅ-6 Tracks and OCL

Construction contract KSÅ-7 Electro and Tele

Tangen

Stange

Hamar

Tangen

Stange

Hamar

Eidsvoll

Kleverud-Sørli-ÅkersvikaDovre Line – a part of InterCity

• Reduced travel time

• Increased capacity• 2 new stations• Project estimated to 12 billion NOK• Opening scheduled for 2026

• For project information, please see Bane NOR’s home page:− www.banenor.no

• Project home page:− www.banenor.no/Prosjekter/prosjekter/klev

erud-sorli/− www.banenor.no/Prosjekter/prosjekter/dovr

ebanen/sorli-akersvika/

• Supplier contact:− [email protected]

53

Kleverud-Sørli-Åkersvika

54