the environmental impact statement process for resource … · 2020. 7. 30. · 1.1 site-specific...

38
Guideline Page 1 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 ABN 46 640 294 485 Environmental Protection Act 1994 The environmental impact statement process for resource projects under the Environmental Protection Act 1994 This guideline explains the environmental impact statement (EIS) process for resource projects under chapter 3 of the Environmental Protection Act 1994. Table of contents Introduction ........................................................................................................................................3 PART I: REGULATORY REQUIREMENTS OF THE EIS PROCESS ..................................................4 1 Resource activities that trigger an EIS under the Environmental Protection Act 1994 ..........4 1.1 Site-specific EA applications and major amendments to an existing EA ..................................4 1.2 Voluntary EIS applications ......................................................................................................5 2 Resource activities that also trigger an assessment under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) .............................................................................6 3 EIS process under the EP Act ....................................................................................................7 PART II: EIS ASSESSMENT PROCESS........................................................................................... 11 4 Pre-lodgement discussions ...................................................................................................... 11 5 Lodgement of applications and payment of fees .................................................................... 11 6 Information request and advisory bodies ................................................................................ 12 7 Terms of reference .................................................................................................................... 12 7.1 Preparation and submission of the draft TOR (step 1) ........................................................... 12 7.2 Public notification of the draft TOR (steps 2‒4) ..................................................................... 13 7.3 Comments on the draft TOR (step 5) .................................................................................... 13 7.4 Finalisation and public notification of the final TOR (steps 6‒8)............................................. 13 8 Environmental impact statement ............................................................................................. 14 8.1 Preparation of the EIS ........................................................................................................... 14 8.1.1 Requirements under the EP Act ...................................................................................................14 8.1.2 Requirements under the EPBC Act ..............................................................................................15 8.1.3 New or previously unforeseen matters .......................................................................................16 8.1.4 EIS structure and publishing requirements ................................................................................16 8.1.5 EIS consultation .............................................................................................................................17 8.1.6 EIS amendments ............................................................................................................................17 8.2 Submission and notification of the EIS (steps 9‒18).............................................................. 17 8.2.1 Submission of the EIS (step 9) .....................................................................................................18 8.2.2 Decision on whether the EIS may proceed (steps 10‒11) .........................................................18 8.2.3 Public notification of the EIS (step 12) ........................................................................................18

Upload: others

Post on 25-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Guideline

    Page 1 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 ABN 46 640 294 485

    Environmental Protection Act 1994

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    This guideline explains the environmental impact statement (EIS) process for resource projects under chapter 3 of the

    Environmental Protection Act 1994.

    Table of contents

    Introduction ........................................................................................................................................ 3

    PART I: REGULATORY REQUIREMENTS OF THE EIS PROCESS .................................................. 4

    1 Resource activities that trigger an EIS under the Environmental Protection Act 1994 .......... 4

    1.1 Site-specific EA applications and major amendments to an existing EA .................................. 4

    1.2 Voluntary EIS applications ...................................................................................................... 5

    2 Resource activities that also trigger an assessment under the Environment Protection and

    Biodiversity Conservation Act 1999 (EPBC Act) ............................................................................. 6

    3 EIS process under the EP Act .................................................................................................... 7

    PART II: EIS ASSESSMENT PROCESS........................................................................................... 11

    4 Pre-lodgement discussions ...................................................................................................... 11

    5 Lodgement of applications and payment of fees .................................................................... 11

    6 Information request and advisory bodies ................................................................................ 12

    7 Terms of reference .................................................................................................................... 12

    7.1 Preparation and submission of the draft TOR (step 1) ........................................................... 12

    7.2 Public notification of the draft TOR (steps 2‒4) ..................................................................... 13

    7.3 Comments on the draft TOR (step 5) .................................................................................... 13

    7.4 Finalisation and public notification of the final TOR (steps 6‒8)............................................. 13

    8 Environmental impact statement ............................................................................................. 14

    8.1 Preparation of the EIS ........................................................................................................... 14

    8.1.1 Requirements under the EP Act ................................................................................................... 14

    8.1.2 Requirements under the EPBC Act .............................................................................................. 15

    8.1.3 New or previously unforeseen matters ....................................................................................... 16

    8.1.4 EIS structure and publishing requirements ................................................................................ 16

    8.1.5 EIS consultation ............................................................................................................................. 17

    8.1.6 EIS amendments ............................................................................................................................ 17

    8.2 Submission and notification of the EIS (steps 9‒18) .............................................................. 17

    8.2.1 Submission of the EIS (step 9) ..................................................................................................... 18

    8.2.2 Decision on whether the EIS may proceed (steps 10‒11) ......................................................... 18

    8.2.3 Public notification of the EIS (step 12) ........................................................................................ 18

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 2 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    8.2.4 EIS submission period (step 13) .................................................................................................. 19

    8.2.5 Statutory declaration of compliance with notice requirements (step 14) ................................ 19

    8.2.6 Response to submissions (steps 15‒16) .................................................................................... 19

    8.2.7 Assessment of adequacy of response to submissions and submitted EIS (steps 17‒18) .... 20

    9 EIS assessment report (step 19) .............................................................................................. 20

    10 Completion of process (step 20) ........................................................................................... 21

    11 Failure to take a required step ............................................................................................... 21

    12 Post EIS process .................................................................................................................... 21

    13 Enquiries ................................................................................................................................. 22

    14 References .............................................................................................................................. 22

    Appendix 1: Acronyms and abbreviations ..................................................................................... 24

    Appendix 2: Glossary ...................................................................................................................... 25

    Appendix 3: Description of the project and operational land ....................................................... 31

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 3 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Introduction

    The Department of Environment and Science (the department) is responsible for the administration and

    regulation of resource activities under the Environmental Protection Act 1994 (EP Act). Resource activities

    include mining, petroleum (including coal seam gas; CSG), geothermal, and greenhouse gas storage activities.

    Resource activities that are proposed to be carried out under one or more resource tenures, in any combination,

    as a single integrated operation are known as resource projects.

    A high-impact environmental resource project may be required to be assessed through an environmental impact

    statement (EIS) process under chapter 3, part 1 of the EP Act. This guideline explains the EIS process for

    resource projects under chapter 3 of the EP Act.

    An EIS is a written document for a project that is undergoing the EIS process pursuant to the EP Act. The

    purpose of an EIS and the EIS process, as defined under section 40 of the EP Act, is to:

    assess the potential adverse and beneficial environmental, economic and social impacts of the project

    assess management, monitoring, planning and other measures proposed to minimise any adverse

    environmental impacts of the project

    consider feasible alternative ways to carry out the project

    provide information to the public about the project

    help the administering authority decide an environmental authority (EA) application for which the EIS is

    required

    give information to other Commonwealth and state authorities to help them make informed decisions

    allow the Queensland Government to meet its obligations for a single environmental assessment

    process under a bilateral agreement with the Australian Government.

    While the EIS process is highly structured, timing is primarily driven by the project proponent/applicant

    (proponent). It is the proponent’s responsibility to provide the information required for the EIS process.

    This guideline is subdivided into two parts:

    Part I: Regulatory requirements of the EIS process—summarises the regulatory requirements of the EIS

    process under the EP Act

    Part II: EIS assessment process—explains the stages in the EIS assessment process in more detail.

    This guideline should be read in conjunction with the EP Act (chapter 3) and the Environmental Protection

    Regulation 2008 (EP Regulation).

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 4 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    PART I: REGULATORY REQUIREMENTS OF THE EIS PROCESS

    This part of the guideline summarises the regulatory requirements of the EIS process under the EP Act.

    1 Resource activities that trigger an EIS under the Environmental Protection Act 1994

    Resource activities may only be carried out by a person holding, or operating under, an EA issued under the

    EP Act and a resource tenement granted under relevant resource legislation (e.g. Mineral Resources Act 1989,

    Geothermal Energy Act 2010, Greenhouse Gas Storage Act 2009, Petroleum Act 1923, Petroleum and Gas

    (Production and Safety) Act 2004 and the Petroleum (Submerged Lands) Act 1982).

    The tenements provide the right to access the land and to undertake exploration, resource assessment,

    feasibility studies, prospecting or production. No resource tenement may be granted without an EA being held

    for the relevant resource activity.

    Applications for an EA for resource activities may be standard applications, variation applications or site-specific

    applications. Further information on EA application types can be found on the Queensland Government

    Business Portal website (Queensland Government Business, 2019).

    Only site-specific applications for new resource activities (‘greenfield’ sites) or the amendment of existing EAs

    (‘brownfield’ sites) require a decision whether an EIS is required.

    Potential impacts due to large-scale resource projects usually require site-specific applications that trigger

    assessment by EIS. The scale (i.e. relative magnitude) of an impact is determined by its intensity, duration,

    irreversibility and the risk of environmental harm, as well as social and economic impacts. Section 143 of the EP

    Act describes the circumstances under which a resource activity must, or may be, assessed by EIS.

    There are several ways that an EIS process under the EP Act may be applied to the assessment of a proposed

    resource activity:

    A site-specific application for an EA for a resource activity under the EP Act is made and the

    department decides that assessment will be by the EIS process. This includes site-specific EA

    amendment applications for existing resource activities. Only site-specific applications can trigger the

    EIS process; standard or variation applications do not.

    An amendment application for an existing EA for a resource activity under the EP Act is made and the

    department decides that the proposed amendment is a major amendment.

    The proponent submits an application to voluntarily prepare an EIS and the department decides that

    an EIS is appropriate for the proposed project.

    These matters are explained further in section 1.1 and section 1.2 below.

    An EIS under the EP Act is not required when the resource project is a ‘coordinated project’ declared under the

    State Development and Public Works Organisation Act 1971 (SDPWO Act).

    1.1 Site-specific EA applications and major amendments to an existing EA

    The following four stages apply for a site-specific EA application process (chapter 5 of the EP Act):

    1. Application stage—proponent lodges an application and the department determines if the application

    has been properly made. This includes consideration of the adequacy of information provided in support

    of the application to meet the requirements of the EP Act.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 5 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    2. Information stage—where the information contained in the application is assessed by the department.

    Further information may be requested.

    3. Notification stage—where the application documents are made publicly available by the proponent and

    the department and people have an opportunity to make a submission.

    4. Decision stage—where a decision is made by the department to either approve the application with

    conditions (in the form of a draft EA or draft amended EA) or to refuse it.

    The decision on whether an EIS will be required is made during the information stage of the EA application

    process. If an EA application is found to require an EIS, the EIS process replaces the information and

    notification stages.

    Also, an EA amendment application requires the department to determine if the amendment should be treated

    as a major or minor amendment. Only amendment applications determined to be a major amendment require

    consideration of whether an EIS is required.

    If an EIS has been completed before an EA application is made, the department needs to determine whether

    the environmental risks of the proposed activity(s) requiring an EA have changed since the time an EIS was

    completed. If they have, the proponent may be required to undertake public notification requirements and

    provide information addressing the differences or to submit a new EIS.

    In deciding whether an application requires an EIS, the department will carry out its functions and

    responsibilities in accordance with the EP Act. Consideration is given to the triggers in the departments EIS

    trigger criteria (DEHP, 2014) and the standard criteria. An EIS cannot be required if the application relates to a

    coordinated project under the SDPWO ACT; or an EIS under the EP Act has already been submitted to the

    department.

    In addition, a decision may be made to require an EIS even if no EIS criteria are triggered, if the department

    having regard to the standard criteria determines that the project applied for:

    would involve a significant environmental impact, or a high level of uncertainty about potential impacts,

    or involve a high level of public interest

    is likely to contribute substantially to cumulative impacts. Unacceptable cumulative impacts may occur

    when the environmental impacts of a project are added to environmental impacts of other activities over

    space and time (e.g. impacts to the local airshed, a regional water catchment, or the environmental

    values of aquifers).

    Information on applying for an EA or an EA amendment is available at Queensland Government Business Portal

    website (Queensland Government Business, 2018) and the department’s webpage.

    1.2 Voluntary EIS applications

    Sections 69 to 72 of the EP Act allow a proponent to apply to the department for approval to voluntarily prepare

    an EIS. The department is required to decide whether to accept or reject an application to prepare a voluntary

    EIS. The EIS trigger guideline and the standard criteria are considered by the department when deciding such

    applications.

    An application for a voluntary EIS allows a proponent to commence an EIS process for a project without having

    to submit an EA application. However, the proponent must be able to demonstrate that they have access to the

    project area to enable them to carry out the necessary studies for the EIS.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 6 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    However, an application to voluntarily prepare an EIS cannot be made when: an EIS requirement is already in

    force for an application under the EP Act; or when an EIS must be prepared for the project under another State

    Act and that Act does not allow the EIS to be prepared under the EIS process.

    The voluntary EIS application must be in the approved form and must be supported by sufficient information to

    allow the department to decide whether an EIS would be appropriate for the proposed project. It must also be

    accompanied by the prescribed fee.

    The EIS assessment process that is initiated by the department approval of an application to voluntarily

    undertake an EIS is the same as for an EIS triggered by a site-specific application for an EA and is set out in

    Chapter 3 of the EP Act.

    Once the voluntary EIS process has been completed the proponent may apply for a site-specific EA and

    appropriate tenure to carry out the resource activity.

    The form Application to prepare a voluntary environmental impact statement provides guidance on the

    information (DES 2017b).

    2 Resource activities that also trigger an assessment under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

    The EPBC Act is the Commonwealth’s key piece of environmental legislation and is administered by the

    Australian Government Environment Department (Australian Environment Department). The EPBC Act requires

    that an ‘action’ (refer to glossary for definition) that will have, or is likely to have, a significant impact on a matter

    of national environmental significance (MNES) must be referred to the Australian Environment Minister for a

    decision on whether assessment and approval is required under the EPBC Act.

    Proponents are responsible for referring projects that may impact on MNES to the Australian Environment

    Department for assessment. The Australian Environment Minister (or the Minister’s delegate) decides if the

    proposed action would significantly impact on MNES and if so, it will be declared a controlled action. If a

    proposed action is not controlled, there is no further consideration needed of MNES matters. Substantial

    penalties apply for taking actions that significantly impact on MNES without approval under the EPBC Act.

    If the decision is made that a proposal is a controlled action, one of the five levels of assessment (of which one

    requires an EIS) provided for in EPBC Act are applied, depending on the significance of the project and how

    much information is readily available.

    Under the assessment bilateral agreement between the Australian Government and the State of Queensland,

    proposals that are controlled action and that are required to be assessed by EIS, can be jointly assessed by an

    EIS process under the EP Act (DoEE 2014). This applies whether the Queensland Government environment

    department has determined that the EIS is required or is voluntary. This means that only one EIS is required

    that meets both Commonwealth and State requirements; reducing duplication. The proposed actions will require

    approval by the Australian Environment Minister (or the Minister’s delegate) before the actions can commence.

    The decision by the Australian Environment Minister is made after the EIS process is completed.

    A project cannot be assessed under the bilateral agreement if:

    public notification of the draft terms of reference (TOR) for an EIS for a resource project does not state

    the ‘controlling provisions’ for the project under the EPBC Act; or

    a controlling matter is a nuclear action.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 7 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    For the public notification of the draft TOR to state the controlling provisions for the project, the Australian

    Environment Department must have previously issued a decision notice stating that the proposed action is a

    controlled action, what the controlling provisions are, and that an EIS is necessary.

    Further information on EPBC Act requirements and the bilateral agreement are available on the Australian

    Environment Department’s website.

    3 EIS process under the EP Act

    The EIS process consists of the following stages:

    submission and publication of the TOR

    submission and notification of the EIS

    preparation and release of the EIS assessment report.

    The EIS process under chapter 3 of the EP Act is summarised in Figure 1. Each step mentioned in Figure 1 is

    described in Table 1.

    The EIS assessment process is explained in more detail in Part II of this guideline.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 8 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Table 1 The EIS process under chapter 3 of the Environmental Protection Act 1994

    TOR submission and publication

    •SUBMISSION OF DRAFT TOR

    •Proponent submits draft TOR to the department (step 1)

    •PUBLIC NOTIFICATION OF DRAFT TOR

    •The department prepares & publishes TOR notice (steps 2 & 3)

    •Proponent gives TOR notice to interested & affected persons (step 4)

    •Draft TOR comment period (step 5)

    •FINALISATION OF TOR

    •Proponent responds to comments, submits & amends draft TOR for the department's consideration (steps 6 & 7)

    •The department finalises and publishes TOR (step 8)

    EIS submission and notification

    •SUBMISSION OF EIS

    •Proponent submits EIS (step 9)

    •ASSESSMENT OF ADEQUACY

    •The department reviews EIS & decides if EIS can proceed (steps 10 & 11)

    •PUBLIC NOTIFICATION OF EIS

    •Proponent prepares, publishes and provides EIS notice to interested & affected persons (steps 12 & 14)

    •EIS submission period (step 13)

    •RESPONSE TO SUBMISSIONS

    •Proponent responds to submissions and amends EIS (steps 15 & 16) for the departments consideration

    •ASSESSMENT OF AMENDED EIS

    •The department decides if the amended EIS is adequate (steps 17 & 18)

    EIS assessment

    report

    •PREPARATION AND RELEASE OF EIS ASSESSMENT REPORT & COMPLETION OF EIS PROCESS

    •The department prepares and gives EIS assessment report to proponent & publishes report (steps 19 & 20)

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 9 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Step

    no.#Task

    Time allowed

    (business

    days)$

    Section of

    EP Act

    Submission and publication of the TOR

    1 Proponent submits draft TOR.

    The submitted draft TOR must be accompanied by the prescribed

    fee.

    Initiates EIS

    process

    41

    2 The department prepares TOR notice and provides it to the

    proponent.

    15 42

    3 The department publishes TOR notice. 5 43(1)

    4 Proponent gives TOR notice to interested and affected persons. 5 (concurrent

    with step 3)

    43(3)

    5 Comment period for draft TOR. 30 (minimum) 42(3)

    6 The department gives comments to proponent. 10 44

    7 Proponent responds to comments and makes amendments to

    the TOR.

    20* 45

    8 The department considers comments and the proponent’s

    response, publishes the final TOR and gives the proponent a copy

    of the final TOR.

    20* 46

    EIS submission and notification

    9 Proponent submits the EIS to the department within 2 years of

    receiving the final TOR. The submitted EIS must be accompanied

    by the prescribed fee.

    Within 2 years* 47

    10 The department reviews the EIS and determines if it addresses

    the final TOR in an acceptable form and if the EIS can proceed to

    public notification.

    20* 49(1) & (3)

    11 The department provides written notice to proponent if a decision

    (step 10) has been made.

    10 49(6)

    12 Proponent prepares EIS notice.

    Proponent provides EIS notice to interested and affected

    persons, publishes the EIS notice and makes a copy of the

    submitted EIS available on a website.

    20

    52

    51(2)

    13 EIS submission period. 30 (minimum) 49(4)

    14 Proponent provides statutory declaration of compliance with

    notice requirements.

    10

    (concurrent with

    step 13)

    53

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 10 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Step

    no.#Task

    Time allowed

    (business

    days)$

    Section of

    EP Act

    15 The department provides a copy of all submissions to proponent. 10 56(1)

    16 Proponent provides to the department a summary of the

    submissions, a response to submissions and any amendments of

    the EIS.

    This must be accompanied by an EIS amendment notice.

    20* 56(2) & (3)

    66

    17 The department decides if the proponent’s response to

    submissions and submitted EIS are adequate for the EIS process

    to proceed.

    20 56A(2) & (4)

    18 The department provides written notice of the decision. 10 56A(5)

    EIS assessment report and completion of process

    19 The department gives an EIS assessment report to proponent

    and publishes the assessment report.

    30 57

    20 The EIS process under Chapter 3 of the EP Act is completed

    when the proponent is given the EIS assessment report.

    - 60

    #Step numbers are provided in this table to assist explanation of the EIS assessment process in Part II of this guideline.

    *These time periods can be extended (by agreement) usually only once and then only during the initial period. $business days do not include a business day that occurs during the period starting on 20 December in a year and ending on 5 January in the following year.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 11 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    PART II: EIS ASSESSMENT PROCESS

    This part of the guideline explains, in more detail, the stages involved in the EIS assessment process under

    chapter 3 the EP Act.

    4 Pre-lodgement discussions

    It is recommended that the proponent engage with the department through a pre-lodgement meeting to discuss:

    the project activities

    the scale and the feasibility of the project

    if the project is expected to have a medium or high probability of causing serious or material

    environmental harm or a high probability of causing environmental nuisance

    if the project could be considered contentious by the public (e.g. the project has had extensive media

    coverage or there is a public perception of potential environmental harm or nuisance)

    if a decision under the EPBC Act has been made for the project regarding a specific controlling provision

    information and support documents required for the application

    relevant timeframes

    any matters considered important about this project by the administering authority.

    This should occur prior to submitting an EA application or EA amendment application for a project that would

    potentially trigger the EIS process, or prior to submitting a voluntary EIS application.

    Further information on pre-lodgement discussions is available on the department’s website. To request a

    meeting with the department please lodge the Application for pre-lodgement services form (ESR/2015/1664,

    DES, 2016).

    5 Lodgement of applications and payment of fees

    Lodgement of applications (i.e. voluntary EIS application) and EIS documents (i.e. draft TOR and EIS) should

    be organised through the EIS coordinator ([email protected]). EIS application documents cannot be applied

    online through Connect (https://environment.des.qld.gov.au/connect/).

    Fees apply for the following EIS assessment stages:

    an application fee for a voluntary EIS when lodging the application

    fees for the draft TOR and the EIS when submitting the documents

    when the proponent provides a notice of an amendment to an EIS not related to matters raised in

    submissions on the EIS under section 56(2) of the EP Act (DES 2017b).

    The fees are payable by cheque/money order to the Department of Environment and Science and must be paid

    in person on level 3, 400 George Street, Brisbane after making an appointment with the EIS coordinator.

    Fees are subject to an annual Consumer Price Index adjustment. Please call Permit and Licence Management

    on 1300 130 372 (and select option four), email [email protected] or [email protected] to confirm the

    latest fees.

    Further information on EIS related fees is available on the department’s website or Queensland Government

    Business Portal webpage.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 12 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    6 Information request and advisory bodies

    The EP Act (section 62) allows the department to seek relevant advice, comment or information from any

    person or organisation during the EIS assessment process. If the request is made of the proponent, it must be

    written, and must state a reasonable period for the giving of the advice. The request may also be by public

    notice.

    At notification stages (draft TOR and EIS) in the assessment process, the department seeks advice from

    various advisory bodies. For this purpose, an advisory body is an individual or organisation that is requested to

    provide advice to the department within the extent of their areas of responsibility, interest and expertise. As

    such, advisory bodies provide advice to the department and do not have a decision-making role in respect of the

    EIS process. However, they may have a decision-making role in approvals that may be required for the project

    under legislation, which they administer.

    The option to use advisory bodies is consistent with the department’s aim to ensure the TOR and the EIS are

    comprehensive, and adequately assess impacts on matters relevant to the interests and requirements of all key

    agencies and interested parties. It is important that parties that may need to give approval for the project are

    consulted to ensure that the issues relevant to that approval are adequately addressed in the EIS and

    recommendations about the suitability of the project and recommended conditions of approval can be included

    in the EIS assessment report. Members of the advisory body may be individuals with specific expertise and can

    be selected from the following on a project-by-project basis:

    commonwealth and state government departments

    local governments

    statutory authorities and academic institutions

    private organisations, community groups (including environmental groups) and special interest groups

    (including recognised landowner and Indigenous organisations).

    7 Terms of reference

    The TOR is a statutory document that describes the format, structure and content requirements of the submitted

    EIS. The TOR stage, including statutory timeframes and relevant EP Act sections, is summarised in Table 1

    (steps 1-8).

    The TOR stage has a nominal timeframe of 100 business days; comprising of:

    50 business days for the department to complete its allocated steps

    30 business days (minimum) public comment period for the draft TOR

    20 business days for the proponent to respond to submissions and recommend changes to the draft

    TOR (step 7).

    The steps of the TOR stage are discussed in more detail below.

    7.1 Preparation and submission of the draft TOR (step 1)

    Once a proponent has received written notification from the department stating that an EIS is required, or the

    application for a voluntary EIS has been granted, the proponent can, at any time, provide a draft TOR. Lodging

    a draft TOR initiates the statutory timeframes of the EIS process (step 1).

    The draft TOR must be in the approved form and must contain sufficient information to enable the department to

    finalise the TOR. The ‘Generic TOR template’ for preparing a project specific draft TOR can be downloaded

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 13 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    from the department’s website (DES 2017b). Furthermore, the proponent is required to provide the following

    information in accordance with section 41(3) of the EP Act:

    a description of the project and operational land (often referred to as the initial advice statement—refer

    to Appendix 3: Description of the project and operational land of this guideline)

    a list of names and addresses of all interested and affected persons (as defined in the EP Act).

    a statement explaining how interested persons will be consulted

    EPBC Act requirements if the project is a controlled action

    the prescribed fee (refer to section 5 of this guideline).

    There are no application forms for submitting a draft TOR. However, it is recommended that proponents include

    information on the type of the application (i.e. voluntary EIS application, site-specific EA application or EA

    amendment application) to which the draft TOR relates.

    7.2 Public notification of the draft TOR (steps 2‒4)

    The submitted draft TOR document is reviewed by the department and, if found acceptable, the department will

    prepare the TOR notice and will provide it to the proponent (step 2). The department then publishes the TOR

    notice in the approved form in at least one newspaper circulating throughout Australia or in each State or

    Territory (step 3). Projects that are assessed under the bilateral agreement must be advertised in a nationally

    circulating newspaper, or in newspapers circulating in each state or territory (refer to section 8 of the EP

    Regulation).

    7.3 Comments on the draft TOR (step 5)

    The comment period on the draft TOR is a minimum of 30 business days (step 5). During this comment period,

    the department seeks and considers relevant advice, comment or information from project-specific advisory

    bodies (refer to section 6 of this guideline) to ensure that their interests are addressed in the TOR.

    The department must accept all ‘properly made’ comments, that:

    are written

    are signed by or for each person (‘signatory’) who has made a submission

    state the name and address of each signatory

    are made to the chief executive

    are received on or before the last day of the submission period.

    The department may also decide that a submission that does not meet all these requirements is a properly

    made decision.

    7.4 Finalisation and public notification of the final TOR (steps 6‒8)

    The department provides the comments it receives on the draft TOR to the proponent (step 6). It is a statutory

    requirement that a copy of all comments are forwarded to the proponent.

    The proponent must provide a summary of the comments, a response to the comments and an amended draft

    TOR to the department (step 7) within 20 business days. This period can be extended by agreement.

    The department finalises the TOR, considering all comments and the proponent’s response, and publishes the

    TOR on its website.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 14 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    The proponent has two years to submit an EIS addressing the final TOR.

    8 Environmental impact statement

    8.1 Preparation of the EIS

    8.1.1 Requirements under the EP Act

    The EIS must meet the requirements of the EP Act and EP Regulation, and relevant requirements under the

    EPBC Act if it is also being assessed under the assessment bilateral agreement. It must address relevant

    Commonwealth, state or local government interests in the proposed project and provide information for

    regulatory authorities to assist in future decision-making regarding the project. These matters are set out in the

    TOR as ‘routine’ and ‘critical matters’.

    Key requirements outlined in the EP Act and subordinate legislation, include but are not limited to:

    the requirements of section 40 of the EP Act, which specifies the purpose of an EIS and of the EIS

    process

    the requirements of sections 125, 126126A which set out the general information requirements for

    applications for an EA

    the requirements of chapter 2 and schedule 1 of the EP Regulation, including matters to be addressed

    by assessment under the bilateral agreement between the Australian Government and the State of

    Queensland

    the environmental objectives and performance outcomes specified in schedule 5, part 3, tables 1 and 2

    of the EP Regulation.

    Section 139 of the EP Act states that the information stage of the EA application process does not apply if the

    EIS process is complete, unless there has been a subsequent change to the proposed project. It is therefore

    important that the EIS provide all the information needed to enable the issuing of an EA for the proposed project

    as set out in the TOR in conjunction with the latest version of guidance material published on the department’s

    website (DES 2016).

    The detail in which the EIS deals with all matters relevant to the proposed project should be proportional to the

    scale of the impacts on environmental values. When determining the scale of an impact, the EIS must consider

    the impact’s intensity, duration, cumulative effect, irreversibility, the risk of environmental harm, management

    strategies and offset provisions. The EIS must further identify and assess expected adverse and beneficial

    environmental, social and economic impacts of the project and include suitable planning, mitigation and

    monitoring measures to manage any adverse impacts of the project. Critical matters need to be specifically

    addressed in detail in the EIS either because of the high potential risk of adverse impacts and/or the identified

    values potentially affected. Routine matters would require less detailed consideration.

    Scientific and specialist studies undertaken in response to the TOR must provide details of the methodology,

    reliability, assumptions and scientific conclusions used to predict the potential beneficial and adverse impacts.

    Avoidance, mitigation and management strategies for the protection or enhancement of identified environmental

    values must be proposed following the department’s management hierarchy: (a) to avoid; (b) to minimise or

    mitigate; once (a) and (b) have been applied, (c) if necessary and possible, to offset.

    For any significant residual impact, the EIS must propose offsets that are consistent with the following

    requirements as set out in applicable State and Commonwealth legislation or policies:

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 15 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Where a significant residual impact will occur on a prescribed environmental matter as outlined in the

    Environmental Offsets Regulation 2014, the offset proposal(s) must be consistent with the requirements

    of Queensland’s Environmental Offsets Act 2014 and the latest version of the Queensland

    Environmental Offsets Policy (DES 2018).

    Where Commonwealth offset policy requires an offset for significant residual impacts on a MNES, the

    offset proposal(s) must be consistent with the requirements of the EPBC Act Environmental Offsets

    Policy and Offsets assessment guide and relevant guidelines (Commonwealth of Australia, 2012),

    available at: http://www.environment.gov.au/epbc/publications/epbc-act-environmental-offsets-policy

    Sufficient information for the following persons and organisations must be provided in the EIS:

    The department (administrating authority)—to allow the state to meet its obligations under the bilateral

    agreement and to allow the department to decide EA applications for the project. Given that the EIS

    process replaces the information and notification stages1 for site-specific EA applications, it is essential

    that all the information needed by the department in deciding an EA application is provided in the EIS.

    Australian Environment Department —to allow the Australian Environment Minister to make an informed

    decision when deciding the project (i.e. approval or refusal and appropriate conditions).

    State and local government and other advisory bodies—to provide a framework for decision makers to

    assess the environmental, social and economic aspects of the proposed project with respect to the

    legislation, policies and standards administered by these bodies; and to assist in making a decision

    whether the project could obtain the necessary approvals, or be refused, and to develop conditions.

    Affected persons—to provide sufficient information to groups and persons with rights or interests in land;

    to understand how the proposed project relates to land of interest; how land would be affected; and how

    impacts on land would be assessed, avoided and mitigated. Queensland Government-owned

    corporations and businesses (i.e. ports, energy, water and transport service providers) should be

    consulted to ensure their assets would meet project demands and that their services are not adversely

    impacted by the proposed project. Privately owned utility and service providers should be consulted in a

    similar manner. More information about Queensland Government-owned corporations is available at the

    Queensland Treasury website.

    Interested persons—to provide sufficient information to persons that may have a financial or non-

    financial interest in the area in which the project would be situated (e.g. unincorporated community or

    environmental bodies).

    The proponent—to understand the potential environmental, social and economic impacts of their

    proposed project to optimise the benefits and minimise adverse impacts and risks, including identifying

    management measures required to avoid, mitigate and offset the adverse and residual environmental

    impacts.

    8.1.2 Requirements under the EPBC Act

    An EIS subject to the bilateral agreement must include a stand-alone assessment report for the MNES included

    in the controlling provisions. The report should provide enough information about the project and relevant

    1 This is provided in the environmental risks of the activity and the way the activity will be carried out have not changed since the EIS has been completed (see section 12 of this guideline for further information).

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 16 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    impacts on MNES to allow the Australian Environment Minister to make an informed decision on the project (i.e.

    approval or refusal) and, if relevant, impose appropriate conditions of approval.

    The information provided in the report must be consistent with other relevant sections of the EIS. Proposed

    mitigation measures for MNES must be consistent with those proposed under Queensland legislation while

    offsets for impacts on MNES must meet Commonwealth requirements.

    For resource projects where water is a controlling provision under the EPBC Act and which are coal seam gas

    or large coalmine developments, the Australian Environment Department, jointly with Queensland Government,

    must make a referral to the Independent Expert Scientific Committee on Coal Seam Gas and Large Coal Mining

    Development (IESC). The IESC provides scientific advice to decision makers on potential impacts from Coal

    Seam Gas (CSG) and large coal mining developments on Australia's water resources.

    8.1.3 New or previously unforeseen matters

    While every attempt is made by the department to ensure the final TOR requires an assessment of all relevant

    matters, the final TOR may not be exhaustive. The EIS should address other matters not covered in the final

    TOR if the following circumstances arise:

    Studies reveal a matter that had not been foreseen when the TOR was finalised.

    An issue not identified previously is considered contentious by the public (e.g., project has had media

    coverage or there is a public perception of potential environmental harm or nuisance).

    The department directs the proponent in writing to address a matter (information request under section

    62 of the EP Act).

    New or amended legislation or policies come into effect after the TOR has been finalised, regardless of

    whether or not the legislation or policies have been listed in the TOR. Transitional arrangements or

    exemptions may apply for individual projects.

    The proponent makes amendments to the project that would result in a change in the nature, timing or

    location of any impacts.

    If the EIS omits the analysis of matters initially considered relevant but subsequently found not to be, the

    reasons for each omission should be sufficiently documented.

    8.1.4 EIS structure and publishing requirements

    To avoid duplication, the findings of each section of the EIS should be cross-referenced to other corresponding

    sections. Matters already covered in a chapter should not be repeated elsewhere. The only exception is for

    projects assessed under the bilateral agreement where the chapter on MNES must be written as a stand-alone

    report and should therefore contain information already stated in other chapters of the EIS.

    The EIS should meet general formatting and publishing requirements and reflect the format, structure and

    content requirements of the final TOR. The EIS is a public document and should be written in plain English so

    that a person without any prior knowledge of the project understands the information presented. Acronyms and

    abbreviations should be included in full in a glossary of terms. Technical terms should be defined or adequately

    explained. Statements used to assess relevant impacts in the main body of the EIS must be supported by

    appendices, technical information and supporting data. To support the generic TOR, the department has

    developed guidance materials to assist with preparing the EIS.

    Maps, diagrams, pictures, artist’s impressions or other illustrative material to assist readers to visualise and

    understand information should be clear and unambiguous. Appropriate scaling and orientation should be

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 17 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    provided. Aerial photography and digital information (e.g. of the project site and adjacent properties) should be

    provided.

    8.1.5 EIS consultation

    The proponent should develop and implement a consultation plan for the persons and organisations identified in section 8.1.1 of this guideline, as well as the general public. The extent to which a proponent consults with relevant persons will be determined by the public interest and significance of the project’s potential environmental, social and economic impacts. Early and sustained consultation is recommended.

    The consultation plan should be consistent with, and complement, the notification activities in the EIS process.

    The proponent’s consultation plan should identify issues of potential concern to relevant persons and

    organisations and address issues from project planning to commencement, project operations, and

    decommissioning. The consultation plan should include:

    the objectives of the consultation process

    timing of consultation

    the number and interests of the persons involved

    methods of consultation and communication

    reporting and feedback methods for consulted persons

    an assessment explaining how the objectives have been met

    an analysis of the issues raised, including:

    – issues raised and by whom

    – how each issue will be addressed in the EIS process

    alterations to the proposed project as a result of feedback received.

    The proponent must also prepare a social impact assessment (SIA) for the proposed project that is consistent

    with the requirements of the Strong and Sustainable Resource Communities Act 2017 (SSRC Act) and the

    Coordinator-General’s SIA guideline (March 2018).

    The SIA is to be developed in consultation with the Coordinated Project Delivery Division in the Office of the

    Coordinator-General, Department of State Development, Manufacturing Infrastructure and Planning. The SIA is

    to describe the potential social impacts (both positive and negative) of the proposed project, and must identify

    relevant and effective impact mitigation and benefit enhancement measures.

    8.1.6 EIS amendments

    The proponent can amend or replace a submitted EIS at any time before the EIS assessment report has been

    given to the proponent, except during the EIS submission period. An EIS amendment, other than an

    amendment in response to submissions on the EIS, incurs a fee. An EIS amendment must be accompanied by

    the department’s Notice – Amendment/replacement of an original of environmental impact statement

    (ESR/2016/2186, DES, 2016).

    8.2 Submission and notification of the EIS (steps 9‒18)

    The submission and notification stages for an EIS, including statutory timeframes and relevant EP Act sections,

    are summarised in Table 1 (steps 9‒18) and explained in more detail below.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 18 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    8.2.1 Submission of the EIS (step 9)

    The proponent has two years from receiving the final TOR to prepare and submit an EIS (hereafter referred to

    as the ‘submitted EIS’) to the department. While it is preferred that the EIS be submitted within this period, the

    proponent may request an extension to the chief executive before the two years ends. In considering whether to

    grant an extension, the department would take into account the length of extension sought, if any major

    changes to the project from that described in the TOR is proposed, whether there has been any major

    legislative or policy changes that would affect the project, and any other matter considered relevant.

    The submitted EIS must be accompanied by the prescribed fee.

    8.2.2 Decision on whether the EIS may proceed (steps 10‒11)

    Within 20 business days of the EIS being submitted, the department must determine if it adequately addresses

    the requirements of the TOR (step 10). To allow the proponent to address any significant errors or omissions in

    the submitted EIS, a longer period for that decision can be agreed between the department and the proponent

    (if agreed within the first 20 business days). The department will seek to determine if any changes are needed

    to the submitted EIS as early in this 20-day review period as possible.

    Once the department has decided whether the submitted EIS is suitable to proceed to public notification (step

    10), a written notice of the decision is given to the proponent (step 11). Where the decision is to proceed, the

    notice will state the length of the submission period (minimum 30 business days) and a template for preparing

    the EIS notice for public notification.

    If the submitted EIS does not sufficiently meet the requirements of the TOR, the department can refuse to allow

    the submitted EIS to proceed under section 49(6) of the EP Act. If the submitted EIS has been refused, the

    proponent can apply to the Queensland Government Environment Minister (Queensland Environment Minister)

    to review the decision under section 50 of the EP Act. Under sections 49A(3-4) the proponent may resubmit,

    with changes, the EIS once within three months after the day notice of the decision is given to the proponent or

    within an agreed period if agreed to by the department and the proponent.

    8.2.3 Public notification of the EIS (step 12)

    The EIS notice and its contents must be prepared in accordance with section 52 of the EP Act and the department’s guideline Requirements for an environmental impact statement notice (ESR/2016/2172, DES, 2018). The EIS notice must include information on the project and operational land, where the submitted EIS may be inspected (e.g. a local library, the department and/or proponent’s office) or where copies, or extracts, from the submitted EIS may be obtained.

    Under section 51 of the EP Act (step 13), the proponent must:

    provide the EIS notice to all interested and affected persons, and any other person decided by the

    department, before the submitted EIS is made public

    provide the EIS notice to the department for publishing on its website

    publish an EIS notice in the approved form in at least one newspaper circulating throughout Australia or

    in each State or Territory and make a copy of the submitted EIS available on a website.

    The submitted EIS must remain publicly available on the internet for a minimum period of 12 months after the

    department has issued the EIS assessment report. The submitted EIS must also be published on the

    department’s website (or a link to another website) as the ‘application documents’ if the EIS is for an

    environmental authority or amendment of an environmental authority.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 19 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Electronic and/or printed copies of the submitted EIS should be provided to each advisory body a few days

    before the submission period commences.

    8.2.4 EIS submission period (step 13)

    The public submission period for an EIS is a minimum of 30 business days unless there are special

    circumstances that warrant a longer period (step 13—concurrent with step 14). During this period, submissions

    on the submitted EIS are accepted by the department. Submissions, which meet the EP Act requirements for a

    properly made submission, have to be accepted. The department can also accept any other submissions if it is

    considered appropriate to do so.

    As well as receiving submissions from the public and interested persons and organisations, the department

    seeks and considers relevant advice, comment or information about a range of matters in the EIS from advisory

    bodies (see section 6 of this guideline). The department has to consider all properly made submissions when

    deciding on the adequacy of the EIS.

    For resource projects where impacts on water resources is a controlling provision under the EPBC Act, the

    department, jointly with the Australian Environment Department, must make a referral to the IESC.

    The IESC provides scientific advice to decision makers (and proponents) on potential impacts from CSG and

    large coal mining developments on Australia’s water resources. Information about the IESC can be found on the

    IESC webpage. A referral to the IESC does not affect the statutory EIS assessment timelines.

    8.2.5 Statutory declaration of compliance with notice requirements (step 14)

    Within 10 business days after the EIS notice has been published, the proponent must provide a statutory

    declaration to the department (step 14—concurrent with step 13) consisting of the following:

    a statement of compliance under the EP Act

    the names and addresses of each person to whom the EIS notice was given

    a copy of the EIS notice that was given.

    Use the department form Requirements for an environmental impact statement notice (Environmental

    Impact Statement) (ESR/2016/2194, DES, 2018)

    8.2.6 Response to submissions (steps 15‒16)

    All submissions on the submitted EIS are forwarded to the proponent within 10 business days after the

    submission period has ended (step 15).

    The proponent then has 20 business days to provide the department with:

    a summary of the submissions

    a statement of the proponent's response to submissions

    any amendments to the submitted EIS as a result of the submissions.

    This response is often referred to as the ‘supplementary EIS stage’, although it is not a recognised term under

    the EP Act. A longer period to make that response may be agreed in writing, within the 20 business days, at the

    proponent’s request (step 16).

    If changes have been made to the submitted EIS because of the submissions, the proponent must provide an

    EIS amendment notice (under section 66 of the EP Act). Use the department form ‘Amendment or replacement

    of an original environmental impact statement’ (EM562).

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 20 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    8.2.7 Assessment of adequacy of response to submissions and submitted EIS (steps 17‒18)

    It is essential that the response to submissions and any amendments made to the submitted EIS (often referred

    to as the ‘supplementary EIS’) contains sufficient information on potential impacts and proposed avoidance and

    mitigation measures for the department to be able to prepare the EIS assessment report including

    recommendations for conditions.

    Under section 56A of the EP Act, the department must assess and consider:

    the submitted EIS

    a summary of the submissions

    a statement of the proponent’s response to the submissions

    any amendments of the submitted EIS because of the submissions (step 17).

    The department has 20 business days after receiving the response to submissions to decide whether to allow

    the EIS to proceed and must only allow the EIS to proceed if:

    the proponent’s response to the submissions is adequate

    the proponent has made all the appropriate amendments to the submitted EIS because of the

    submissions.

    The period may be extended if, at any time before the decision is made, the proponent has agreed in writing to

    the extension. Within 10 business days after the decision to proceed or not has been made, the department

    must provide written notice of the decision to the proponent (step 18).

    If the decision is to refuse to allow the submitted EIS to proceed, the notice must also state:

    the reasons for the decision

    that the proponent may, under section 56B, apply to the Queensland Environment Minister to review the

    decision

    how to apply for a review.

    If the chief executive decides, under section 56A, to refuse to allow the EIS to proceed, the proponent can apply

    to the Queensland Environment Minister to review the decision under section 56B of the EP Act. The proponent

    may resubmit under sections 56AA(2-4), with changes, the submitted EIS and the proponent’s response to the

    submissions once. This needs to occur within 20 business days after the notice of decision is given to the

    proponent under 56A(5), or within an agreed period if agreed to by the department and the proponent. A

    resubmitted EIS must be accompanied by the prescribed fee and the form Notice – Amendment/replacement of

    an original of environmental impact statement (ESR/2016/2186, DES, 2016) (refer to section 8.1.6 of this

    guideline).

    9 EIS assessment report (step 19)

    Once the department has issued the proponent with a decision notice allowing the EIS to proceed to the next

    stage, the department must prepare an EIS assessment report and gives it to the proponent within 30 business

    days (step 19).

    The EIS assessment report must:

    address the adequacy of the submitted EIS (including any amendments made to the submitted EIS) in

    addressing the final TOR

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 21 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    address all properly made submissions and any other submissions accepted by the chief executive

    address the adequacy of any environmental management plan for the project

    include recommendations about the suitability of the project

    include any recommended conditions for required approvals

    address the standard criteria

    address other matters prescribed under a regulation (e.g. an assessment of the adequacy of the

    submitted EIS in addressing MNES under the EPBC Act).

    If the EIS is conducted under the bilateral agreement, a copy of the report must be given to the Australian

    Environment Minister. The EIS assessment report is also made available on the department’s website.

    10 Completion of process (step 20)

    The EIS process under Chapter 3 of the EP Act is completed when the proponent is given the EIS assessment

    report (step 20).

    11 Failure to take a required step

    If the proponent does not complete or comply with a required step under the EP Act for the EIS process, the EIS

    process will be suspended until the step has been taken. The proponent’s draft TOR or submitted EIS will lapse

    on the first anniversary of the suspension or a later day if agreed to by the department and the proponent before

    the first anniversary.

    If under sections 49 (step 10) and 56A (step 17) the department decides to refuse to allow the EIS process to

    proceed, the proponent may, by written notice, apply to the Queensland Environment Minister to review the

    decision.

    12 Post EIS process

    Upon completion of the EIS process under Chapter 3 of the EP Act, any current application process suspended

    by the EIS process resumes pursuant to their respective law.

    For resource projects, the EA application resumes to chapter 5 of the EP Act, namely the decision stage—

    where a decision is made either to approve the EA application with conditions or to refuse it. Specifically:

    For site-specific applications and major amendments to an EA, the draft EA is issued in the decision

    stage after the EIS process is completed, and may involve the hearing of objections in the Land Court.

    Under section 172 of the EP Act, the department must then decide if the EA application for a site-

    specific application is approved subject to conditions or is refused (refer to section 1.1 of this

    guideline).For voluntary EIS projects, the proponent may now apply for a site-specific EA and for tenure

    under relevant resource legislation (refer to section 1.2 of this guideline). If the environmental risks of the

    activity or way the activity will be carried, have changed between the time when the voluntary EIS was

    completed under the EP Act and when the EA application was made, the proponent will not be exempt

    from the information request and public notification requirements under the EP Act.

    For projects assessed under the bilateral agreement, the Australian Environment Minister makes a separate

    decision under the EPBC Act, subsequent to completion of the EIS process.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 22 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    13 Enquiries

    The EIS process under the EP Act is administered by the department’s Environmental Impact Assessment

    team. Any EIS queries can be directed to this unit, which can be contacted via email: [email protected] or on

    telephone 13 74 68 (13 QGOV) during business hours, 8:30am–5:00pm on business days.

    14 References

    Commonwealth of Australia 2012, Environment Protection and Biodiversity Conservation Act 1999Environmental Offsets Policy accessed January 2019.

    Commonwealth of Australia 2014, Queensland Bilateral Agreement Information accessed January 2019.

    Business Queensland 2018, Types of applications for a new environmental authority accessed January 2019.

    Business Queensland 2018, Applying for an environmental authority accessed March 2019.

    Department of Environment and Heritage Protection 2014, Triggers for environmental impacts statements under the Environmental Protection Act 1994 for mining and petroleum activities accessed March 2019.

    Department of Environment and Science 2016, Application for pre-lodgement services form (ESR/2015/1664) accessed March 2019.

    Department of Environment and Science 2016, Amendment/replacement of an original of environmental impact

    statement (ESR/2016/2186) .

    Department of Environment and Science 2016 (ESR/2016/2172), Requirements for an environmental impact statement notice accessed March 2019.

    Department of Environment and Science 2016, Information guideline for an environmental impact statement accessed March 2019.

    Department of Environment and Science 2017a, Environmental Impact Statement (EIS) process

    accessed March 2019.

    Department of Environment and Science 2017b, Environmental impact statement guidelines <

    https://www.qld.gov.au/environment/pollution/management/eis-process/about-the-eis-process/terms-of-

    reference> accessed March 2019.

    Department of Environment and Science 2018, About the EIS process accessed January 2019.

    Department of Environment and Science 2018, Queensland Environmental Offsets Policy Version 1.6 accessed January 2019.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 23 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Department of Environment and Science 2018, Forms and applications accessed January 2019.

    Department of State Development 2017, Economic impact assessment guideline accessed March 2019.

    While this document has been prepared with care, it contains general information and does not profess to offer legal,

    professional or commercial advice. The Queensland Government accepts no liability for any external decisions or actions

    taken on the basis of this document. Persons external to the Department of Environment and Science should satisfy

    themselves independently and by consulting their own professional advisors before embarking on any proposed course of

    action.

    Approved:

    signed 23/04/2019

    Signature Date

    Philip Rowland Operational Support Delegate of the Administering Authority Environmental Protection Act 1994

    Enquiries:Operational Support Regulatory Support Branch Ph. 13 74 68 (13 QGOV)

    Version history

    Version Effective date Description of changes

    1.00 03/06/2015 Publication of guideline EM1375 (replacing guidelines EM584 and EM596)

    1.01 26/11/2015 Guideline updated to reflect legislative changes

    1.01 15/03/2016 Guideline renamed to ESR/2016/2171

    2.00 23/04/2019 Guideline updated to reflect legislative and departmental changes

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 24 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Appendix 1: Acronyms and abbreviations

    Acronym/abbreviation Meaning

    Australian Environment

    Department Australian Government Department of the Environment and Energy

    Australian Environment Minister The Australian Government Minister whom administers the EPBC Act

    Commonwealth Commonwealth of Australia

    CSG coal seam gas

    EA environmental authority

    the department Queensland Government Department of Environment and Science

    EIS environmental impact statement

    EP Act Environmental Protection Act 1994

    EPBC Act Environment Protection and Biodiversity Conservation Act 1999

    (Commonwealth)

    EP Regulation Environmental Protection Regulation 2008

    IESC Independent Expert Scientific Committee on Coal Seam Gas and Large

    Coal Mining Development (Commonwealth)

    MNES matters of national environmental significance

    MSES matters of national environmental significance

    NUMA Non Use Management Area

    Queensland Environment

    Department The Queensland Government Department of Environment and Science

    Queensland Environment

    Minister The Queensland Government Minister whom administers the EP Act

    TOR terms of reference

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 25 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Appendix 2: Glossary

    Term Definition

    Actions under the Environment

    Protection and Biodiversity

    Conservation Act 1999 (EPBC

    Act)

    The glossary of terms under the EPBC Act states that “an action

    is defined broadly in the EPBC Act and includes: a project, a

    development, an undertaking, an activity or a series of activities,

    or an alteration of any of these things. A lawful continuation of an

    existing use is not an action. A decision by a government body to

    grant an authorisation (for example, a permit or licence) or to

    provide funding is not an action.

    Actions include, but are not limited to: construction, expansion,

    alteration or demolition of buildings, structures, infrastructure or

    facilities; storage or transport of hazardous materials; waste

    disposal; earthworks; impoundment, extraction and diversion of

    water; research activities; vegetation clearance; military exercises

    and use of military equipment; and sale or lease of land.”

    Advisory bodies Individuals or organisations invited by the department to provide

    advice or information during the EIS process.

    Affected person for a project An affected person for a project is defined under section 38 of the

    EP Act. It includes a person for the operational land or any land

    joining it; such as: local governments; Native title holder

    bodies/claimants or representative Aboriginal/Torres Strait

    Islander bodies; landowners/landholders; mining leases; state

    land (state forests; state controlled roads; national parks;

    conservation parks). The full list can be found in the EP Act.

    Bilateral agreement The environmental impact statement process under the EP Act

    has been accredited under ‘An agreement between the

    Commonwealth and the State of Queensland under section 45 of

    the EPBC Act relating to environmental assessment’ (the bilateral

    agreement).

    The bilateral agreement can be applied to projects that are:

    controlled actions requiring assessment under part 8 of

    the EPBC Act, and

    are subject to the EIS process under the EP Act.

    Chief executive The chief executive is the person in charge of managerial matters

    for a government department. Chief executives (or their delegate)

    make decisions under legislation they are responsible for

    administering.

    Controlling provision It is a requirement under the EPBC Act that actions must not be

    carried out without prior approval under this Act if they have, or

    are likely to have, a significant impact on matters of national

    environmental significance. The Australian Environment

    Department determines whether or not an action is, or is likely to,

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 26 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Term Definition

    have a significant impact on a matter/s of national environmental

    significance. If so, these matters are the ‘controlling provisions’ for

    that action.

    Coordinated project A project may be declared to be a coordinated project under the

    SDPWO Act if a proponent applies to the Coordinator-General,

    and if the Coordinator-General accepts the application. In making

    that decision, the Coordinator-General may consider the following

    matters:

    complex approval requirements involving local,

    Queensland and the Australian Governments

    significant environmental effects

    strategic significance to the locality, region or state,

    including infrastructure, economic and social benefits,

    capital investment or employment opportunities

    significant infrastructure requirements.

    Environmental authority (EA) In Queensland, before undertaking an environmentally relevant

    activity, approval, in the form of an EA, is needed.

    Environmentally relevant activities are industrial, resource or

    intensive agricultural activities with the potential to release

    contaminants into the environment and are defined in the EP Act

    and regulations. They include a wide range of activities such as

    aquaculture, sewage treatment, cattle feed lotting, mining and

    other resource activities such as petroleum (which includes coal

    seam gas), geothermal and greenhouse gas storage activities.

    Environmental nuisance The EP Act defines environmental nuisance as unreasonable

    interference or likely interference with an environmental value

    caused by:

    aerosols, fumes, light, noise, odour, particles or smoke

    or an unhealthy, offensive or unsightly condition because

    of contamination

    another way prescribed by regulation.

    Environmental Protection Act

    1994 (EP Act)

    The EP Act is administered by the Department of Environment

    and Science. The object of this Act is to protect Queensland’s

    environment while allowing for development that improves the

    total quality of life, both now and in the future, in a way that

    maintains the ecological processes on which life depends

    (ecologically sustainable development).

    Environment Protection and

    Biodiversity Conservation Act

    1999 (EPBC Act)

    The EPBC Act is administered by the Australian Government

    Department of the Environment and Energy. The Act provides a

    legal framework to protect and manage nationally and

    internationally important flora, fauna, ecological communities and

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 27 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Term Definition

    heritage places, defined in the Act as matters of national

    environmental significance.

    Independent Expert Scientific

    Committee on Coal Seam Gas

    and Large Coal Mining

    Development (IESC)

    The committee is a statutory committee established by the

    Australian Government under the EPBC Act.

    Description of the project and

    operational land (commonly

    referred to as the ‘initial advice

    statement’)

    The description of the project and operational land (commonly

    referred to as the ‘initial advice statement’) is a document that

    should be submitted with a draft terms of reference application or

    with a voluntary environmental impact statement application to

    meet requirements under the EP Act. The project description

    should be in accordance with Appendix 3 land of this guideline.

    Interested person Interested person means an interested person proposed by the

    proponent under section 41(3)(b) of the EP Act; such as an

    unincorporated community or environmental body with a financial

    or non-financial interest in the local government area that the

    operational land is in.

    Material environmental harm The EP Act defines material environmental harm (other than

    environmental nuisance) as environmental harm:

    that is not trivial or negligible in nature, extent or context

    or that causes actual or potential loss or damage to

    property of an amount of, or amounts totalling, more than

    the threshold amount but less than the maximum amount

    that results in costs of more than the threshold amount but

    less than the maximum amount being incurred in taking

    appropriate action to prevent or minimise the harm and to

    rehabilitate or restore the environment to its condition

    before the harm.

    The threshold amount is $5000, or, if a greater amount is

    prescribed by regulation, the greater amount.

    Mining activity A mining activity is:

    an activity that is an authorised activity for a mining

    tenement under the MR Act

    or another activity that is authorised under an approval

    under the MR Act that grants rights over land.

    No use management area

    (NUMA)

    An area of land the subject of a PRC plan that cannot be

    rehabilitated to a stable condition after all relevant activities for the

    PRC plan carried out on the land have ended (section 112 of the

    EP Act).

    Offsets An activity undertaken (either voluntarily or imposed) to

    counterbalance significant residual impacts of activities on

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 28 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Term Definition

    particular matters of national, state or local environmental

    significance. Relevant legislation include the Queensland

    Environmental Offsets Act 2014 and/or the Commonwealth’s

    EPBC Act.

    Operational land Operational land means the land on which the project is to be

    carried out.

    Person Person includes a body of persons, whether incorporated or

    unincorporated.

    Petroleum activity A petroleum activity is:

    an activity that, under the Petroleum Act 1923, is an

    authorised activity for a petroleum tenure under Petroleum

    Act 1923

    or an activity that, under the Petroleum and Gas

    (Production and Safety) Act 2004, is an authorised activity

    for a petroleum authority under that Act

    or exploring for, exploiting or conveying petroleum

    resources under a licence, permit, pipeline licence,

    secondary licence or special prospecting authority granted

    under the Petroleum (Submerged Lands) Act 1982.

    Project A project includes a development, a proposed development, an

    action, a proposed action, a plan or policy.

    Proponent Proponent means the person who proposes the project to which

    the EIS process applies.

    Proposed action A proposed action is an activity or activities proposed under a

    project that has to be assessed under the EPBC Act because it

    would or has the potential to impact on matters of environmental

    significance.

    Resource activities Resource activities include mining, petroleum (including coal

    seam gas), geothermal and greenhouse gas storage activities.

    The Department of Environment and Science is responsible for

    the administration and regulation of resource activities under the

    EP Act.

    Resource projects Resource activities that are proposed to be carried out under one

    or more resource tenures, in any combination, as a single

    integrated operation are known as resource projects.

    Serious environmental harm The EP Act defines serious environmental harm as environmental

    harm (other than environmental nuisance) as:

    irreversible, of a high impact or widespread

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 29 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Term Definition

    or caused to an area of high conservation value or special

    significance

    or that causes actual or potential loss or damage to

    property of an amount of, or amounts totalling, more than

    the threshold amount

    or that results in costs of more than the threshold amount

    being incurred in taking appropriate action to prevent or

    minimise the harm and to rehabilitate or restore the

    environment to its condition before the harm.

    The threshold amount is $50,000, or, if a greater amount is

    prescribed by regulation, the greater amount.

    Significant impact (under the

    EPBC Act)

    A significant impact is defined under the EPBC Actas an impact

    which is important, notable, or of consequence, having regard to

    its context or intensity. Whether or not an action is likely to have a

    significant impact depends upon the sensitivity, value, and quality

    of the environment which is impacted, and upon the intensity,

    duration, magnitude and geographic extent of the impacts. All of

    these factors should be considered when determining whether an

    action is likely to have a significant impact on the environment.

    Refer to Commonwealth significant impact guidelines

    Significant impact on water

    resources

    Significant impact on water resources is caused by a single action

    or the cumulative impact of multiple actions which would directly

    or indirectly:

    result in a substantial change in the quantity, quality or

    availability of surface or ground water

    substantially alter ground water pressure and/ or water

    table levels

    alter the ecological character of a wetland that is State

    significant or a Ramsar wetland

    divert or impound rivers or creeks or substantially alter

    drainage patterns

    reduce biological diversity or change species composition

    alter coastal processes, including sediment movement or

    accretion, or water circulation patterns

    result in persistent organic chemicals, heavy metals, or

    other potentially harmful chemicals accumulating in the

    environment such that biodiversity, ecological integrity,

    human health or other community and economic use may

    be adversely affected

    substantially increase demand for, or reduce the

    availability of water for human consumption.

    Refer to Commonwealth significant impact guidelines.

  • Guideline

    The environmental impact statement process for resource projects under the Environmental Protection Act 1994

    Page 30 of 38 • ESR/2016/2171 • Version 2.00 • Last reviewed: 23 APR 2019 Department of Environment and Science

    Term Definition

    Site-specific application A site-specific application is an application for an environmental

    authority for ineligible Environmentally Relevant Activities under

    the EP Act, i.e. for activities that are:

    not able to comply with the eligibility criteria

    have no set eligibility criteria

    or are carried out as part of a coordinated project.

    Standard criteria The standard criteria are defined in schedule 4 of the EP Act.

    Voluntary EIS Sections 69 to 72 of the EP Act allow a proponent to apply for

    approval to voluntarily prepare an EIS. An application for a

    voluntary EIS allows a proponent to commence an EIS process

    for a project without having to submit an environmental authority

    application.

  • Guideline

    The environmental impact statement process for resource projects un