THE EROSION CONTROL BMP MANUAL What are the Major Changes?

Upload: truongdang

Post on 01-May-2018

230 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

THE EROSION CONTROL

BMP MANUAL

What are the Major Changes?

Page 2: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

A GUIDANCE DOCUMENT

►It was published in the PA Bulletin October 17, 2009

►There was a 60 day comment period

Page 3: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

OVERALL LAYOUT

►Current Draft

Introduction

17 Chapters

12 Appendices

List of References

555 + pages (excluding cover & indices)

YOI!

Page 4: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

INTRODUCTION

►Why is erosion & sediment pollution important?

Page 5: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 1: REQUIRED PLAN CONTENT

► Descriptions of the 15 Items listed in Chapter 102 expanded

1. Topographic Features

2. Soil Use Limitations

3. Proposed Alteration

4. Runoff

5. Receiving Surface Waters

6. Perimeter BMPs

7. Sequence (BMP installation & removal) on the plan drawings (not in narrative)

Page 6: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 1: REQUIRED PLAN CONTENT

► Descriptions of the 15 Items listed in Chapter 102 expanded

8. Supporting Calcs

9. Plan Drawings

10.Maintenance Program

11.Recycling & Disposal of Materials

12.Geologic or Soil Conditions that could cause pollution

13.Thermal impacts (in accordance with PCSM plan)

Page 7: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 1: REQUIRED PLAN CONTENT

► Descriptions of the 15 Items listed in Chapter 102 expanded

14.Consistency with PCSM plan

15.Riparian Forest Buffers identified

Page 8: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 2: BMP SEQUENCING

►Expanded to provide better guidance

►3 Standard Notes recommended for detail sheets

►Suggested Outline Provided

Page 9: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Exploration & Surveying►BMPs should be provided for disturbed areas

as well as surface water crossings (streams, wetlands, etc.)

May use the BMPs from Chapter 3

Others may be approved on case-by-case basis if found to be equal to or better than those in Chapter 3

Page 10: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

BMP Ratings for use in Special Protection Watershed

►BMPs with low sediment removal efficiencies are not ABACTS

►BMPs with moderate sediment removal efficiencies are ABACTS for HQ watersheds, but not EV watersheds

►BMPs with high sediment removal efficiencies are ABACTS for HQ & EV watersheds

Page 11: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 3: SITE ACCESS

►Rock Construction Entrance – New detail

Page 12: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Rock Construction Entrance With Wash Rack

►ABACT for HQ & EV watersheds

Page 13: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Temporary & Permanent Access Roads

►Addressed for the 1st time

Page 14: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Temporary & Permanent Access Roads

►Crowned Roadways

Page 15: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Temporary & Permanent Access Roads

►Insloping

Page 16: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Waterbar►Brought out of the Pipeline text

Page 17: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Waterbar

►The detail has been enlarged & clarified

Page 18: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Broad-based Dip

►Broad-based Dips 2 details

Page 19: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

Broad-based Dip

►Spacing Table provided

Road Grade

(Percent)

Spacing Between Dips, Culverts, or Deflectors (feet)

<2 300

3 235

4 200

5 180

6 165

7 155

8 150

9 145

10 140

Page 20: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

OPEN-TOP CULVERTS

►Brought into the manual from the Timber Harvesting packet

Page 21: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

WATER DEFLECTORS►May be used in lieu of

open-top culverts

Page 22: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

ROADSIDE DITCH

►Brought into the manual from the Timber Harvesting packet

Need for lined Protective liners is addressed

Page 23: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

DITCH RELIEF CULVERT►Brought back to the manual

Page 24: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

DITCH RELIEF CULVERTTable 3.3 – Spacing of Temporary Culverts

Road Grade (%)

Culvert Spacing*

(ft)

Length of Upslope Drainage (ft)

< 300 300 –400

400 –500

500 –600

>600

Minimum Culvert Size (in)

2 300 12 15 15 15 18

3 235 12 15 15 15 18

4 200 12 15 15 15 18

5 180 12 12 15 15 15

6 165 12 12 12 15 15

7 155 12 12 12 12 15

8 150 12 12 12 12 15

9 145 12 12 12 12 15

10 140 12 12 12 12 15

12 135 12 12 12 12 15

*Culvert spacing may be adjusted slightly to take advantage of natural drainageways.

Page 25: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

DITCH RELIEF CULVERTTable 3.4 – Spacing of Permanent Culverts

Road Grade

Soil Type in Ditch

Gravels, Sandy

Gravels, Aggregate Surfacing

Silty Gravels, Clayey Gravels

Plastic and Non-plastic Inorganic

Clays

Inorganic Silts, Silty or

Clayey Sands

Sands, Silty Sands, and

Gravelly Sands

Percent Feet

2 390 315 245 170 95

4 335 275 210 145 85

6 285 230 180 125 75

8 240 195 150 105 65

10 200 160 125 90 55

12 160 130 105 75 45

14 135 110 85 60 35

Page 26: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TURNOUTS

Page 27: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

COMPOST SOCK SEDIMENT TRAP

►Addressed in this chapter to emphasize their usefulness in controlling runoff from access roads

►At entrances or where surface waters are in relatively close proximity to the access road

►An ABACT for HQ & EV watersheds

Page 28: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TEMPORARY STREAM CROSSINGS

►Should be avoided wherever possible

►Must be provided wherever construction equipment (including clearing and grubbing) must cross an existing stream channel

►Appropriate Chapter 105 permits must be obtained from DEP

►Designs must adhere to the conditions of

those permits

Page 29: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TEMPORARY STREAM CROSSINGS

►Ford type crossings may not be used by construction equipment

Page 30: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TEMPORARY STREAM CROSSINGS

►Temporary bridges are the preferred method of crossing

Page 31: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TEMPORARY STREAM CROSSINGS

►Culvert Pipes

Page 32: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TEMPORARY WETLAND CROSSINGS

►Should be avoided wherever possible

►Must be minimized

Page 33: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TEMPORARY WETLAND CROSSINGS

►Figure 3.5

Typical Tire Mat Crossing

►Figure 3.6

Typical Expanded Metal Grating Crossing

►Figure 3.7

Typical Wood Mat Crossing

Page 34: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

EARTHWORK WITHIN STREAM CHANNELS

►Excavations done from the top of banks

►Where it is not possible

Temporary crossing

Causeway

Page 35: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

EARTHWORK WITHIN STREAM CHANNELS

►Figure 3.9 Temporary bypass channel same as old Figure 33

A geotextile protective lining should be provided

Channel designed to pass normal base flows if the crossing will be completed in one to three days

Otherwise, channel must be designed for bank-full flow

Page 36: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

EARTHWORK WITHIN STREAM CHANNELS

►Figure 3.10 Temporary bypass pipe same as old Figure 34

Pipe sized so that the normal flow depth (d) is < ½ the diameter of the pipe (D)

Page 37: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

EARTHWORK WITHIN STREAM CHANNELS

►Figure 3.11 Pumped water bypass system revised to show filter bag for work area

►Also has following note:

“Pump intake shall be

maintained a sufficient

distance from bottom to

prevent sediment from

entering the system”

Page 38: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 3: SITE ACCESS

►Earthwork within stream channels

►Earthwork within lakes or ponds

Turbidity barriers

Page 39: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 3: SITE ACCESS

►Earthwork within stream channels

►Earthwork within lakes or ponds

►Dewatering work areas

New detail for pumped water filter bags

Page 40: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 3: SITE ACCESS

►Earthwork within stream channels

►Earthwork within lakes or ponds

►Dewatering work areas

New detail for pumped water filter bags

Detail provided for sump pits

Page 41: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 3: SITE ACCESS

►Site Housekeeping & Materials Management

Waste Management

Concrete Washouts

Page 42: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Brought back the alignment figure

Page 43: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

►Compost Sock

►ABACT for HQ & EV watersheds

►Can be used in some locations where silt fence cannot

►8” & 9” socks for single lots only

CHAPTER 4: SEDIMENT BARRIERS

Page 44: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

►Max Slope Length Nomograph

CHAPTER 4: SEDIMENT BARRIERS

Page 45: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

►Compost Filter Berm

►ABACT for HQ but not EV

CHAPTER 4: SEDIMENT BARRIERS

Compost Berm

Page 46: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Weighted Sediment Filter Tubes

►ABACT for HQ but not EV

Page 47: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Silt Fence

►Not an ABACT for HQ or EV

►Tolerance for support stakes

►8’ Setback

Page 48: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

►Max Slope Length Nomograph for Silt Fence

CHAPTER 4: SEDIMENT BARRIERS

Page 49: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Minimum Silt Fence Fabric Properties are provided

Page 50: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Super Silt Fence

►Not an ABACT for HQ or EV

►Posts must be installed with a post-hole drill

Page 51: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

►Fiber Logs (wattles)

►Not an ABACT

►12” Logs may use Standard Silt Fence slope lengths

►18” Logs may use Reinforced Silt Fence slope lengths

CHAPTER 4: SEDIMENT BARRIERS

Page 52: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Wood Chip Berms

►ABACT for HQ, but not EV

Page 53: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Straw Bale Barriers

►Not an ABACT

►Disallowed for projects lasting more than 3 months

Page 54: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: SEDIMENT BARRIERS

►Vegetative Filter Strips

►ABACT for HQ (when used in conjunction with another BMP) but not EV

►Minimum width table provided

Page 55: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: INLET PROTECTION

►Inlet filter bags

►ABACT for HQ, not EV

Page 56: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: INLET PROTECTION

►Stone Inlet Protection

►Not an ABACT unless compost layer provided (HQ, not EV)

Page 57: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: INLET PROTECTION

►Alternate details for stone & mesh at grade

Page 58: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 4: INLET PROTECTION

►Alternate details for stone & mesh not at grade

Page 59: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 5: RUNOFF CALCS

►Designers referred to NOAA’s website for up-to-date rainfall data

►Runoff coefficient table expanded to give more options

►New equations for calculating intensity

Page 60: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 5: RUNOFF CALCS

►Penn DOT’s updated tables, charts, & maps provided as an alternative method

Page 61: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►New standard detail provided for vegetated channels

Page 62: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►Equation provided to calculate Manning’s “n” for vegetated channels (Retardance C)

(n = 0.047 -0.4)

Page 63: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►Tables provided for trapezoidal vegetated channel “n” values (Retardance C)

Page 64: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►Standard detail provided for sodded channels

Page 65: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►New standard detail provided for riprap channels

Page 66: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►Guidance provided for design of riprap channels using shear stress

Page 67: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►Nomograph for permissible flow depth of riprap channels (acceptable alternative to shear stress analysis)

Page 68: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHANNELS

►Table for reno mattress & gabions revised

Page 69: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TOP-OF-SLOPE BERMS

►New standard detail provided for Top-of-slope Berms

Page 70: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

TOP-OF-SLOPE BERMS

►Figure provided for maintaining Top-of-slope Berms as fills are built upward

Page 71: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Additional Design Criteria (Now 26)

Forebays and/or turbidity barriers may be substituted for 2:1 flow length:width ratio

Routing of peak flow from 25 yr/24 hr storm may be substituted for 2 cfs discharge capacity

Principal spillway must have capacity for 10 yr/24 hr storm

Some outlet barrels to be set in concrete cradle

PVC outlet barrels disallowed

Page 72: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Additional Design Criteria

Guidance provided for discharge analyses

Limitations put on soils acceptable for use as embankment material (GC, GM, SC, SM, CL or ML )

Page 73: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►New skimmer detail provided

Page 74: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Detail for skimmer attached to permanent riser provided

Page 75: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Detail for stone landing for a skimmer provided

Page 76: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Design chart for skimmer orifice revised

Page 77: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Tables provided for outlet barrel capacity

Page 78: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Standard cross-section has been revised

Page 79: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Table provided for sizing concrete bases of risers

Page 80: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Tables provided for sizing emergency spillway

Page 81: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Figure provided to illustrate forebay

Page 82: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Confusing chart for sizing anti-seep collars replaced with step-by-step guidance for calculating size & spacing of collars

►Typical details provided

Page 83: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Figure provided to illustrate filter diaphragm

Page 84: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 7: SEDIMENT BASINS

►Figure provided to illustrate concrete cradle

Page 85: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 8: SEDIMENT TRAPS

►Additional Design Criteria (Now 14)

Minimum surface area to be provided

Permanent facilities to meet standards of Stormwater BMP Manual

4:1 Flow length:width ratio for traps in special protection watersheds

Discharge requirements added

Page 86: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 8: SEDIMENT TRAPS

►Embankment Spillway Detail revised

Page 87: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 8: SEDIMENT TRAPS

►Table provided for sizing barrel/riser spillways

Page 88: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 8: SEDIMENT TRAPS

►Type M Inlet Trap Detail revised

Page 89: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 8: SEDIMENT TRAPS

►Detail provided for permanent riser with temporary holes

Page 90: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

STEEP GRADIENT PIPES

►Slopes > 0.05 ft/ft

►Manning’s equation must be used

►For pipe with high anticipated velocities (>17.0 FPS), drop structures or other energy reducing structures to reduce velocity prior to discharge

Page 91: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

MANNING’S EQUATION

SD

nV

3

2

4

486.1

where: V = Velocity in fps

D = Pipe diameter in feet

S = Pipe slope in ft/ft

Page 92: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

MAX & MIN TAILWATER

►Disallowed for box culverts

Page 93: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

GROUTING

► Grouting of riprap is not recommended for most installations

► Where riprap is grouted, the following applies:

1. Precautions must be taken to prevent uncured concrete from coming into contact with any surface waters

2. Grout must be placed in a layer with thickness equivalent to the d50 stone size over the entire extent of the apron prior to rock placement

3. After stone placement, void spaces shall be filled with grout

Page 94: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 9: OUTLET PROTECTION

►Detail provided for outfall without wingwalls

Page 95: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 9: OUTLET PROTECTION

►Detail provided for discharge to existing channel

Page 96: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 9: OUTLET PROTECTION

►Detail provided for transition flow mat

Page 97: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 9: OUTLET PROTECTION

►Figure provided to illustrate drop inlet structure

Page 98: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 10: ON-LOT CONTROLS

► 3 Standard Details provided

Page 99: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 11: STABILIZATION

► Surface roughening techniques should be applied to slopes 3:1 and greater unless it can be shown that no potential for sediment pollution to surface waters

► Slopes within 50 feet of surface water should be blanketed if seeding is proposed as the means to achieving permanent stabilization

► Spray-on type blankets should be applied to roughened surfaces

Page 100: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 11: STABILIZATION

►Table provided for various depths of topsoil application

Page 101: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 11: STABILIZATION

►Table provided for application rates of soil amendments

Page 102: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 11: STABILIZATION

►Guidance provided for Bonded Fiber Matrices and Flexible Growth Media

►Guidance provided for use of PAMs

►Guidance provided for sodding

Page 103: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 11: STABILIZATION

►Guidance provided cellular confinement systems

Page 104: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

CHAPTER 12: NEW PRODUCTS & PROCEDURES

►One requirement added:

Applicants should submit their request for approval (along with all pertinent drawings, details, supporting calculations, manufacturer’s recommendations, etc.) to the local Conservation District, the appropriate Regional DEP Office (Watershed Management), AND the Area Engineer responsible for the part of the state in which the project is located

Page 105: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

ADDITIONAL CHAPTERS

►17 – Areas of Special Concern

Sinkhole Repair

Page 106: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

ADDITIONAL CHAPTERS

►17 – Areas of Special Concern

Sinkhole Repair

Contaminated Sites

Page 107: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

ADDITIONAL CHAPTERS

►17 – Areas of Special Concern

Sinkhole Repair

Contaminated Sites

Special Protection Watersheds

Page 108: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

ADDITIONAL CHAPTERS

►17 – Areas of Special Concern

Sinkhole Repair

Contaminated Sites

Special Protection Watersheds

Slope Failures

Page 109: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

ADDITIONAL CHAPTERS

►17 – Areas of Special Concern

Sinkhole Repair

Contaminated Sites

Special Protection Watersheds

Slope Failures

Geothermal Wells

Page 110: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►A – Checklists

Complete Plan Checklist

Revised Technical Review Checklist

Expanded Technical Review Checklist

Page 111: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►A – Checklists

►B – Standard Worksheets

Page 112: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►A – Checklists

►B – Standard Worksheets

►C - Standard Plan Notes

Standard Notes placed on Plan Drawings

Optional Notes placed on drawings where appropriate

Page 113: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►A – Checklists

►B – Standard Worksheets

►C - Standard Plan Notes

►D – Standards for Maps & Drawings

Page 114: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►A – Checklists

►B – Standard Worksheets

►C - Standard Plan Notes

►D – Standards for Maps & Drawings

►E – Soil Use Limitations

If an X appears, go to the NRCS website for more info

Page 115: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►A – Checklists

►B – Standard Worksheets

►C - Standard Plan Notes

►D – Standards for Maps & Drawings

►E – Soil Use Limitations

►F – Energy Dissipaters

Page 116: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►A – Checklists

►B – Standard Worksheets

►C - Standard Plan Notes

►D – Standards for Maps & Drawings

►E – Soil Use Limitations

►F – Energy Dissipaters

►G- Structural Level Spreaders

Page 117: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►H – Dust Control

Page 118: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►H – Dust Control

►I – Guide to Preserving Trees

Page 119: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►H – Dust Control

►I – Guide to Preserving Trees

►J – Tree Planting

Page 120: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►H – Dust Control

►I – Guide to Preserving Trees

►J – Tree Planting

►K – Water Well Drilling Fact Sheet

Page 121: THE EROSION CONTROL BMP MANUALwcdpa.com/documents/THEDRAFTEROSIONCONTROLBMPMANUAL... · THE EROSION CONTROL BMP MANUAL ... Figure 3.10 Temporary bypass pipe same as old Figure 34

APPENDICES

►H – Dust Control

►I – Guide to Preserving Trees

►J – Tree Planting

►K – Water Well Drilling Fact Sheet

►L – Glossary

►References