the ewz building presentation of the building presentation of the building the design issue the...

22
The EWZ building The EWZ building Presentati Presentati on of the on of the building building The design The design issue issue The The building building concept concept The winter The winter monitoring monitoring The summer The summer monitoring monitoring Major Major findings findings The EWZ The EWZ building building More More informatio informatio n... n... Back to Back to “Select “Select a a building building NatVent

Upload: oswald-conley

Post on 01-Jan-2016

243 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

The EWZ buildingThe EWZ building

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

NatVent

Page 2: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

The EWZ building was completed in 1994.

The building is situated in the northern part of Zurich in an urban area.

It is a five storey triangular shaped building, with two sides facing busy roads in a congested urban area.

It is designed to protect the occupants from noise and air pollution.

The façades provide a noise barrier and four atria are included (two on the north-side and two on the south-side) to provide maximum daylighting and natural ventilation.

Thanks to its massive construction the building has a high thermal mass

The EWZ building was completed in 1994.

The building is situated in the northern part of Zurich in an urban area.

It is a five storey triangular shaped building, with two sides facing busy roads in a congested urban area.

It is designed to protect the occupants from noise and air pollution.

The façades provide a noise barrier and four atria are included (two on the north-side and two on the south-side) to provide maximum daylighting and natural ventilation.

Thanks to its massive construction the building has a high thermal mass

Project presentation Project presentation (1...)(1...)

Page 3: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

It is a five storey triangular shaped building, with two sides facing busy roads in a congested urban area.

It is a five storey triangular shaped building, with two sides facing busy roads in a congested urban area.

Project presentation Project presentation (2...)(2...)

Page 4: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

Mechanically Mechanically ventilated ventilated officesoffices

Mechanically Mechanically ventilated ventilated officesoffices

Naturally ventilated Naturally ventilated officesofficesNaturally ventilated Naturally ventilated officesoffices

Mechanically Mechanically ventilated atriaventilated atriaMechanically Mechanically ventilated atriaventilated atria

Project presentation Project presentation (3|)(3|)

Page 5: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

A two step hybrid ventilation concept was chosen to meet energy and comfort demands: The four atria are mechanically ventilated during the day, but

provide manual window access to the surrounding offices which are naturally ventilated.

At night time the atria and the offices are naturally ventilated.

Decentralised ventilation units are used to reduce ductwork and energy use.

The main target of this project was to design an energy efficient multi-use building, both in construction and in use.

After completion of the building, the aim is to achieve further energy savings during operation together with good indoor environment.

A two step hybrid ventilation concept was chosen to meet energy and comfort demands: The four atria are mechanically ventilated during the day, but

provide manual window access to the surrounding offices which are naturally ventilated.

At night time the atria and the offices are naturally ventilated.

Decentralised ventilation units are used to reduce ductwork and energy use.

The main target of this project was to design an energy efficient multi-use building, both in construction and in use.

After completion of the building, the aim is to achieve further energy savings during operation together with good indoor environment.

The design issue The design issue (1...)(1...)

Page 6: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

The design issue The design issue (2|)(2|)

Page 7: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

The building concept The building concept (1...)(1...) ventilation strategy ventilation strategy during summerduring summer

Off

ices

Off

ices

Atr

ia

… for the Atria: During working hours:

Mechanical ventilation with heat recovery and central cooling.

At night: Natural ventilation by window opening in the atria.

… for the Offices : Natural ventilation by manual

opening the windows facing the atria.

… for the Atria: During working hours:

Mechanical ventilation with heat recovery and central cooling.

At night: Natural ventilation by window opening in the atria.

… for the Offices : Natural ventilation by manual

opening the windows facing the atria.

Page 8: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

The mechanical ventilation system is equipped with a central heat recovery unit to reduce the energy losses during the heating season.

Moreover, the ventilation is turned off outside office hours

The mechanical ventilation system is equipped with a central heat recovery unit to reduce the energy losses during the heating season.

Moreover, the ventilation is turned off outside office hours

Heat Recovery UnitHeat Recovery UnitHeat Recovery UnitHeat Recovery Unit

Exhaust AirExhaust AirExhaust AirExhaust Air

Supply AirSupply AirSupply AirSupply Air

Fresh AirFresh AirFresh AirFresh Air

The building concept The building concept (2...)(2...) low energy use in winter timelow energy use in winter time

Page 9: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

Ice stack is loaded during the night to cool during the day. The atria are then ventilated, with a projected air exchange rate of 5 h-1 (pre-cooled air at 16 to 17°C). To properly mix the air in the atria ventilators are installed.

In addition night cooling is applied by automatically opening the top windows in the atria.

To reduce solar impact there are motorised shading devices (external screens) on the side walls and atria roofs.

There is no active cooling in the offices !

(Schematic - see next slide…)

Ice stack is loaded during the night to cool during the day. The atria are then ventilated, with a projected air exchange rate of 5 h-1 (pre-cooled air at 16 to 17°C). To properly mix the air in the atria ventilators are installed.

In addition night cooling is applied by automatically opening the top windows in the atria.

To reduce solar impact there are motorised shading devices (external screens) on the side walls and atria roofs.

There is no active cooling in the offices !

(Schematic - see next slide…)

The building concept The building concept (3...)(3...) overall strategy for summer comfortoverall strategy for summer comfort

Page 10: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

External External screensscreensExternal External screensscreens

NightNightNightNight DayDayDayDay

Ice stack Ice stack loadload

Ice stack Ice stack loadload

Night Night CoolingCoolingNight Night

CoolingCoolingMixing Mixing FansFans

Mixing Mixing FansFans Cooled AirCooled Air

(Outside air is (Outside air is pre-cooled by pre-cooled by the Ice stack the Ice stack load: 16 to load: 16 to

17°C)17°C)

Cooled AirCooled Air

(Outside air is (Outside air is pre-cooled by pre-cooled by the Ice stack the Ice stack load: 16 to load: 16 to

17°C)17°C)

The building concept The building concept (4...)(4...) overall strategy for summer comfortoverall strategy for summer comfort

Page 11: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

The ventilation concept was chosen to meet comfort demands.

Concept: The atria is mechanically ventilated and provides manual window access to the surrounding offices which are naturally ventilated.

Control: The air change rate in the office is chosen by the users as they wish.

The ventilation concept was chosen to meet comfort demands.

Concept: The atria is mechanically ventilated and provides manual window access to the surrounding offices which are naturally ventilated.

Control: The air change rate in the office is chosen by the users as they wish.

NatVent

Off

ices

Off

ices

Atr

iaA

tria

The building concept The building concept (5|)(5|) indoor air quality during office hoursindoor air quality during office hours

Page 12: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

Monitoring set-upMonitoring set-up Continuous measurements of carbon dioxide (CO2 ) / ventilation rate /

temperature / humidity / indoor air velocity (in the offices)

were made over one week periods during February 1997, July 1997,

in atrium 2 (right side of the south façade of the building) three cellular offices on the first, second fourth floor of the atrium 2 (fully

monitored) atrium 1 (left side of the south façade of the building) three cellular offices on the first, second fourth floor of the atrium 2 (only

temperature)

The following offices were considered as representative: for winter: a cellular office on the second floor surrounding atrium 2 for summer: a cellular office on the first floor surrounding atrium 2

. The monitoring results of these offices are shown in the following charts

Continuous measurements of carbon dioxide (CO2 ) / ventilation rate / temperature / humidity / indoor air velocity (in the offices)

were made over one week periods during February 1997, July 1997,

in atrium 2 (right side of the south façade of the building) three cellular offices on the first, second fourth floor of the atrium 2 (fully

monitored) atrium 1 (left side of the south façade of the building) three cellular offices on the first, second fourth floor of the atrium 2 (only

temperature)

The following offices were considered as representative: for winter: a cellular office on the second floor surrounding atrium 2 for summer: a cellular office on the first floor surrounding atrium 2

. The monitoring results of these offices are shown in the following charts

Page 13: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

-5

0

5

10

15

20

25

30

35

40

12 15 18 21 00 03 06 09 12 15 18 21 00 03 06 09 12 15 18 21 00

07-09.02.1997

Ind

oo

r a

nd

ou

tsid

e t

em

pa

ir c

ha

ng

e r

ate

0

200

400

600

800

1000

1200

Ca

rbo

n d

iox

ide

Indoor Temp.- office [°C] Air Change - office [1/h] Outside Temp. [°C]

Atrium Temp. [°C] Carbon Dioxide [ppm]

Winter monitoring Winter monitoring (1...)(1...) typical winter day - monitoring resultstypical winter day - monitoring results

Slight overheating in offices due to problems with automatic control of the shading devices

Page 14: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

-5

0

5

10

15

20

25

30

35

40

12 15 18 21 00 03 06 09 12 15 18 21 00 03 06 09 12 15 18 21 00

07-09.02.1997

Ind

oo

r a

nd

ou

tsid

e t

em

pa

ir c

ha

ng

e r

ate

0

200

400

600

800

1000

1200

Ca

rbo

n d

iox

ide

Indoor Temp.- office [°C] Air Change - office [1/h] Outside Temp. [°C]

Atrium Temp. [°C] Carbon Dioxide [ppm]

Winter monitoring Winter monitoring (2...)(2...) typical winter day - monitoring resultstypical winter day - monitoring results

Good IAQ: low CO2 concentration during office hours (far below 1200 ppm)

Page 15: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

-5

0

5

10

15

20

25

30

35

40

12 15 18 21 00 03 06 09 12 15 18 21 00 03 06 09 12 15 18 21 00

07-09.02.1997

Ind

oo

r a

nd

ou

tsid

e t

em

pa

ir c

ha

ng

e r

ate

0

200

400

600

800

1000

1200

Ca

rbo

n d

iox

ide

Indoor Temp.- office [°C] Air Change - office [1/h] Outside Temp. [°C]

Atrium Temp. [°C] Carbon Dioxide [ppm]

Winter monitoring Winter monitoring (3|)(3|) typical winter day - monitoring resultstypical winter day - monitoring results

Low air change rate is sufficient: good air quality

Page 16: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

Summer monitoring Summer monitoring (1...)(1...) typical summer day - monitoring resultstypical summer day - monitoring results

0

5

10

15

20

25

30

35

40

12 15 18 21 00 03 06 09 12 15 18 21 00 03 06 09 12 15 18 21 00

23-25.07.1997

Ind

oo

r a

nd

ou

tsid

e t

em

p a

ir c

ha

ng

e r

ate

Indoor Temp. [°C] Outside Temp. [°C] Atrium Temp. [°C]

Good thermal comfort in office: Tint = 23°C while Text goes to 33°C:

Remark: This results is partially the result of active cooling in the atrium

Page 17: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

-5

0

5

10

15

20

25

30

35

40

12 15 18 21 00 03 06 09 12 15 18 21 00 03 06 09 12 15 18 21 00

23-25.07.1997

Ind

oo

r a

nd

ou

tsid

e t

em

p a

ir c

ha

ng

e r

ate

0

200

400

600

800

1000

1200

Ca

rbo

n d

iox

ide

Indoor Temp.- office [°C] Air Change - office [1/h] Outside Temp. [°C]

Atrium Temp. [°C] Carbon Dioxide [ppm]

Summer monitoring Summer monitoring (2...)(2...) typical summer day - monitoring resultstypical summer day - monitoring results

Good IAQ: low CO2 concentration during office hours (far below 1200 ppm)

Page 18: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

-5

0

5

10

15

20

25

30

35

40

12 15 18 21 00 03 06 09 12 15 18 21 00 03 06 09 12 15 18 21 00

23-25.07.1997

Ind

oo

r a

nd

ou

tsid

e t

em

p a

ir c

ha

ng

e r

ate

0

200

400

600

800

1000

1200

Ca

rbo

n d

iox

ide

Indoor Temp.- office [°C] Air Change - office [1/h] Outside Temp. [°C]

Atrium Temp. [°C] Carbon Dioxide [ppm]

Summer monitoring Summer monitoring (3|)(3|) typical summer day - monitoring resultstypical summer day - monitoring results

Air change rates are sufficient good IAQ

However no ventilation during the night to cool the office: window is closed

Page 19: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

Night Cooling of the atria: Thanks to the architecture the stack effect in the atria can be considered to

provide a sufficiently strong force for natural ventilation; On the other hand a re-evaluation of the dimensions of the openings could

increase night ventilation resulting in a better natural night cooling.

Night Cooling of the offices - Barriers Night cooling in the atria only takes place if atria windows are open. The atria

windows are in this case automatically open if outside temperature is three degrees lower than the air temperature in the atria (this a typical strategy for mechanical night cooling). For natural night cooling the atria windows should automatically open if outside temperature is lower than the air temperature in the atria

Night cooling in the offices only takes place if the office windows have been left open after the end of the working days. Closed office windows and doors form a large obstruction for the natural night cooling. The best night cooling efficiency is achieved by cross ventilation through window and door.

Night Cooling of the atria: Thanks to the architecture the stack effect in the atria can be considered to

provide a sufficiently strong force for natural ventilation; On the other hand a re-evaluation of the dimensions of the openings could

increase night ventilation resulting in a better natural night cooling.

Night Cooling of the offices - Barriers Night cooling in the atria only takes place if atria windows are open. The atria

windows are in this case automatically open if outside temperature is three degrees lower than the air temperature in the atria (this a typical strategy for mechanical night cooling). For natural night cooling the atria windows should automatically open if outside temperature is lower than the air temperature in the atria

Night cooling in the offices only takes place if the office windows have been left open after the end of the working days. Closed office windows and doors form a large obstruction for the natural night cooling. The best night cooling efficiency is achieved by cross ventilation through window and door.

Major findings Major findings (1...)(1...)

Page 20: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

Shading devices: In the winter, the shading devices , which close automatically, did

not close at the right time. Therefore offices are sometimes lightly overheated and illuminated with too much direct sun light.

The automatically shading devices in summer achieved the expected aims. The thermal comfort in summertime is optimal (remark: in summer active cooling is used in the atria).

The Indoor Air Quality is always acceptable

Occupant Reactions: The occupants are very satisfied with the building.One of the

main reasons is that they appreciate being able to open the windows.

Shading devices: In the winter, the shading devices , which close automatically, did

not close at the right time. Therefore offices are sometimes lightly overheated and illuminated with too much direct sun light.

The automatically shading devices in summer achieved the expected aims. The thermal comfort in summertime is optimal (remark: in summer active cooling is used in the atria).

The Indoor Air Quality is always acceptable

Occupant Reactions: The occupants are very satisfied with the building.One of the

main reasons is that they appreciate being able to open the windows.

Major findings Major findings (2...)(2...)

Page 21: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

In General: The EWZ building is a good example of a pragmatic approach.

The hybrid concept combines active cooling and passive elements like night cooling and shading devices. The concept provides high quality indoor comfort at any external condition.

Energy consumption: The EWZ building can be considered as a building with a rather

low energy consumption. A further reduction of the energy consumption can be achieved by an optimisation of the heating level in winter and the electricity consumption for the cooling and for the mechanical ventilation.

In General: The EWZ building is a good example of a pragmatic approach.

The hybrid concept combines active cooling and passive elements like night cooling and shading devices. The concept provides high quality indoor comfort at any external condition.

Energy consumption: The EWZ building can be considered as a building with a rather

low energy consumption. A further reduction of the energy consumption can be achieved by an optimisation of the heating level in winter and the electricity consumption for the cooling and for the mechanical ventilation.

Major findings Major findings (3|)(3|)

Page 22: The EWZ building Presentation of the building Presentation of the building The design issue The design issue The building concept The building concept

More information...More information...

NatVent

Presentation Presentation of the buildingof the building

The design The design issueissue

The building The building conceptconcept

The winter The winter monitoringmonitoring

The summer The summer monitoringmonitoring

Major Major findingsfindings

The EWZ The EWZ buildingbuilding

More More information...information...

Back to Back to “Select a “Select a building”building”

Find more information on the PROBE building in the following documents:

\Reports \Monitoring Reports \Summary Reports\ch2summ.pdf global presentation of the buildings (4p./building) contents: building description - ventilation strategy and technology -

winter and summer monitoring results - conclusions

\Reports \Monitoring Reports \Detailed Reports\ch2det.pdf detailed reports of all 19 monitoring campaigns (20p./campaign) contents: monitoring set up - analysis of results - conclusions

Find more information on the PROBE building in the following documents:

\Reports \Monitoring Reports \Summary Reports\ch2summ.pdf global presentation of the buildings (4p./building) contents: building description - ventilation strategy and technology -

winter and summer monitoring results - conclusions

\Reports \Monitoring Reports \Detailed Reports\ch2det.pdf detailed reports of all 19 monitoring campaigns (20p./campaign) contents: monitoring set up - analysis of results - conclusions

You can read and print pdf-files with the Acrobat® Reader ®3.0. Program. This program is free.

Download it from the Acrobat web site: www.adobe.com OR run the installation file ar32e301(1).exe in the directory \Installation

You can read and print pdf-files with the Acrobat® Reader ®3.0. Program. This program is free.

Download it from the Acrobat web site: www.adobe.com OR run the installation file ar32e301(1).exe in the directory \Installation