The Greek Muon Chambers (BIS) The three Greek Laboratories: 112 (90 BIS30 +22 BIS36) chambers ALL CHAMBERS @CERN since Sept 04 University of Athens (UoA) Tube wiring/assembly (30,000 tubes finished Dec.2003) National Technical University of Athens(NTUA) Quality Assurance/Quality Control of tubes (30,000 tubes finished Mar.2004) University of Thessaloniki (AUTh) Chamber assembly (112 chambers finished April 2004)

Post on 21-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

The Greek Muon Chambers (BIS)

The three Greek Laboratories:

112 (90 BIS30 +22 BIS36) chambers

ALL CHAMBERS @CERN since Sept 04• University of Athens (UoA) Tube wiring/assembly (30,000 tubes finished Dec.2003)

• National Technical University of Athens(NTUA) Quality Assurance/Quality Control of tubes (30,000 tubes finished

Mar.2004)

• University of Thessaloniki (AUTh) Chamber assembly (112 chambers finished April 2004)

The Greek ATLAS Muon Collaborating institutes

UoA• C. Kourkoumelis• P. Ioannou• D. Fassouliotis• I. Hatziantonaki• K. Nikolopoulos• D. Pappas

NTUA• M. Dris• A. Filippas• E. Gazis• T. Alexopoulos• E. Katsoufis• T. Papadopoulou• E. Fokitis• Y. Tsipolitis • S. Maltezos• A. Tzamarioudaki• P. Savva

AUTh• Ch. Petridou• T. Liolios• M. Manolopoulou  • S. Dedousis• M. Chardalas• D. Sampsonidis• T. Lagouri• K. Ypsilantis   • A. Krepouri• C. Lamboudis• K. Economou • K. Filippousis  

…providing the servicesthe procedure

Preparation activities home(gas bars, cables +29 chambers at Thessaloniki) FINISHED summer 2004

Stage 1 (Blg 184 :equip with gas bars, FC’s, HH’s+MECCA test

78 chambers at CERN, test for gas leak OK)STARTED March 2004 - FINISHED Sept 2004 (but 7 chambers)

Stage 2 NOW HALF_FINISHED Electronic Noise test NOW

Cosmic Ray test NOW

Database NOW

Blg 283 (ALL 112 CHAMBERS) Test facilities shared with BIL team

Stage 2 (Bldg:283 started Oct 2004 after gas leak test)

Equip chambers with:

gas supply brass tubes, plugs, valves etcMezzanines boards +FC coversalignment platforms + cables + measure themHV and readout cables (stiff cables/support!!)B field platforms +cablesT sensor cablesProtective covers

A team of 2 technicians working on them since Oct Since Dec. 3 technicians + ½ physicist (since Jan.)

FINISHED 56 C

HAMBERS

RATE IS : 4 min to 5 max chambers/week Expect to fin

ish by

Easter

(Gre

ek)

…providing the servicesStage II-Blg 283 (ALL CHAMBERS)

Noise test/ Cosmic Ray Test (10 chambers before Xmas+restarted last week)

Data base

A team of 1 physicist –S.Vlachos (since Jan.) +½ physicist (Ph.D.student) (from March)

Leak test/certification

CONCLUSIONS …providing the services+commissioning the

chambers

Stage I- Blg 184 Finished 6 months ago

(but 7 chambers are still bare)Stage II-Blg 283 (ALL CHAMBERS)

Half are fully equipped, rest by May Integration has just restarted MAIN EFFORT NOW Expect to finish by July