the ilc ir john amann ilc mechanical engineering 09/12/06
TRANSCRIPT
The ILC IR
John Amann
ILC Mechanical Engineering
09/12/06
IR Requirements Comparison Table
Item BCD from VC
Surf. Asm.
CCR
SiD LDC GLD
IR Shaft Crane 1kt x 2 2kt x 2 600t 120t ?(1.2kt)
Surface Assembly Crane
80t x 2 400t ?(400t) 2kt 400t
IR Hall Crane 20t x 4 400t x 2 ?(400t) 80t 400t
Largest Piece for Surf. Asm.
600t 490t ~350t
IR Hall Size
(w x l x h)
32x72x42m 30x100x35m 30x48x28m 30x82x?m
30x45x?m
32x72x?m
IR Shaft Size 15m 15m 9m may work 15m (14x8) 20m Full Surface
16m Hybrid
Surface Assembly Building Size
30x100m TBD TBD TBD
Other Shafts 9m service
cavern
Amann – 09/12/06
About Cranes
• Cranes >100t are custom engineered = $$$.• Cranes <100t are off the shelf standard = $.• Cranes have a duty rating = +/- $.• Crane support structure cost scales with capacity.• A 400t crane will require a support structure and
foundation on the scale of a steel mill = $$$.
Amann – 09/12/06
SLC Collider Hall 100 ton Bridge Crane
Hook Height = Runway Height
5-10m Additional Clearance Needed Above Runway
Amann – 09/12/06
SLC Collider Hall 100 ton Bridge CraneBridge Crane has an Effective Area Due to Size of Trolley and Cross Beam
100 ton > Effective Area > 400 ton
Amann – 09/12/06
PEPII IR2 50 ton Bridge Crane
Amann – 09/12/06
About Curtain Walls
• It has been proposed to use a single collider hall separated into two detector regions by a removable 3m concrete wall.
• In order to accomplish this, a combination of stacked concrete blocks topped with a retractable curtain wall will be required.
Amann – 09/12/06
PEPII IR2 Curtain WallCurtain Wall Fully Retracted Into IR Hall
Amann – 09/12/06
PEPII IR2 Curtain Wall• Curtain walls need a runway.
• Runway rail is embedded into concrete support.
• To maintain small gap between curtain wall and the IR hall surfaces the bridge crane runway should be embedded and not a freestanding steel structure.
• The above will require a IR hall with a robust concrete structure.
• In general, a curtain wall will require a smooth finished IR cavern to maintain a small gap between the curtain wall and the IR hall walls and ceiling.
Amann – 09/12/06
PEPII IR2 Curtain WallClose-up of Runway Support Structure
Amann – 09/12/06
IR Hall and Surface Assembly BuildingCutaway View of IR Hall/Surface Assembly Building
Amann – 09/12/06
IR Hall and Surface Assembly BuildingRight Side View
Amann – 09/12/06
Other IR Hall Needs• Compressed Air - need required PSI, CFM, moisture content, locations
• H2O supply – potable, non-potable
• AC Power Distribution – welding sockets 500 amp, other 480/240V sockets.
• Machine Shop, Welding Area, and Tool Crib
• VESDA and Fire Suppression
• IR Hall Lighting
• O2 Deficiency Monitors
• Clean Room – how big, what class?
• Materials Storage Area
Amann – 09/12/06
Questions to Think About
• IR Hall - rectangular box or curved cavern?
• Surface assembly building - size and orientation?
• BDS tunnel height above IR Hall floor – what constrains this?
• Curtain Wall – required thickness?
Amann – 09/12/06