The Importance of Experience Based Decommissioning Planning
PREDEC 2016 February 16-18, 2016
Arne Larsson, Studsvik Gunnar Hedin, Westinghouse Niklas Bergh, Westinghouse Per Lidar, Studsvik
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 1
![Page 2: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/2.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Agenda
• Introduction and overview
• The Decommissioning Steps
• Experience based Decommissioning Planning
• Conclusions
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 2
![Page 3: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/3.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
The Decommissioning Planning process
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 3
Define - Program
set-up
- Boundary
conditions
- End state
preferences
Implement
the
Program
Planning
for
Implemen-
tation
Generate
Plans
Develop
Strategies
![Page 4: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/4.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
I Initial
Planning
II Defueling
III Inventory
& Charac-
terization
IV Deconta-mination
V Dismant-
ling
VI Waste
Manage-ment
VII Clearance
and Demo-lition
VIII Site
Clearan-ce
Decommissioning overview
Waste
processing
Planning studies
Chemical
decontamination
Material flow
optimization
On-site
dismantling
Waste acceptance
Characterization
Clearance
measurements
Waste treatment
systems
Segmentation
Inventory
calculations
Survey
measurements
Fuel Leakage
Detection
Detailed planning &
Licensing support
Decontamination
systems
Waste
transportation
4 PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING
![Page 5: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/5.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Decommissioning success factors
• Defined end-state criteria
• Early decision on self performance or contracting
• Clear and well communicated objectives
• Staff management (transition, replacement and redundancy)
• Active knowledge management
• Focus on structure and logistics, do things in the right order
• Effective and robust waste management processes
• Good relations to stakeholders
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 5
![Page 6: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/6.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Decommissioning is interface management
6 PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING
Participation in 250 decommissioning projects the last 10 years
![Page 7: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/7.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
The Decommissioning Steps
I – Initial planning
• Decommissioning strategy
• Dismantling and Waste Management Strategies
including disposition routes
• Licensing documentation
• Material flow optimization
• Detailed planning
II – Defueling
• Fuel leakage detection
• Management of intact and failed fuel
• PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 7
![Page 8: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/8.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
III – Inventory and characterisation
• Inventory assessment – theoretical
calculations verified by in-situ
measurements
• Radiological characterisation of systems,
installations, structures and site
• Waste and material categorisation based on
risk for contamination
• Building and site categorisation based on
risk for contamination
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 8
Decommissioning Steps
![Page 9: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/9.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
IV – Decontamination
• Selection of decontamination techniques
• Chemical decontamination of systems
and components
• Mechanical decontamination of materials
and structures
V – Dismantling
• Segmentation of internals and reactor pressure
vessel
• Dismantling of systems and installations in a
waste led process
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 9
Decommissioning Steps
![Page 10: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/10.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
VI – Waste management
• Development of a Waste Management Plan
implementing the Waste Management Strategy
• Establish the required in-situ Waste Treatment
and Material Clearance Systems
• Implement waste transportation and off-site
treatment routes
• Implement waste conditioning for disposal in
accordance with WMP
• Implement the waste documentation systems
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 10
Decommissioning Steps
![Page 11: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/11.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
VII – Clearance and demolition of structures
• Characterisation and categorisation of structures
upon completion of dismantling
• Decontamination and demolition of contaminated
structures, as necessary
• Clearance measurements and documentation
• Demolition of remaining structures after clearance
VIII – Site clearance
• Site characterisation (surface/sub-surface)
• Site remediation
• Site clearance
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 11
Decommissioning Steps
![Page 12: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/12.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning for Implementation
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 12
I Initial
Planning
II Defueling
III Inventory & Charac-terization
IV Deconta-mination
V Dismant-
ling
VI Waste
Manage-ment
VII Demo-lition
VIII Site
Clearan-ce
Define
preferred
End-State
and
requirements
Select and
optimize
waste
management
and clearance
Plan
dismantling
procedures
Apply
deconta-
mination
measures
Characterize
according to
defined DQO
Develop
Strategies,
Plans and
detailed
planning
![Page 13: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/13.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning for Implementation
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 13
Define end state and disposition routes
Key objectives:
• Clearance criteria for materials, buildings and site
• Secure disposal routes
• Evaluate costs and economical risks for different options
• Evaluate repository requirements (WAC) and availability
Do not underestimate consequences of intermediate storage –
try to reach end-state as soon as possible
![Page 14: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/14.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning for Implementation
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 14
Select and optimize waste management and clearance
Key objectives:
• Select the material and waste management processes to
meet selected end-states
• Define and optimize the different waste streams
• Define what should/could be done inside the facility, at other
locations on the site and off-site.
• Start planning for validation and acceptance of methods
(statistical methods for clearance evaluation etc.)
![Page 15: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/15.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning for Implementation
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 15
Plan the dismantling procedures
Key objectives:
• Safety is always No 1
• Secure robust and proven technologies
• Apply ALARA
• Focus on material and waste management.
Do not forget the logistics
![Page 16: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/16.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning for Implementation
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 16
Implement decontamination measures
Key objectives:
• ALARA (keep dose rates low)
• Transfer waste to another category (for example LLW -> VLLW)
• Open up for expanded possibilities for clearance
Watch up:
Residues from chemical decontamination from chemical
decontamination can be a Waste Management challenge
![Page 17: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/17.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning for Implementation
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 17
Define the Characterization and categorisation efforts required
Key activities:
• Definition of objectives in general and especially DQO
Define plant status and perform initial categorisation
• Careful planning
• Proper implementation
• Data assessment and draw conclusions
A proper information management system should be taken into
operation as early as possible
![Page 18: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/18.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning for Implementation
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 18
Optimisation and finalisation
• Perform modelling to identify and mitigate potential bottle necks
Revisit and optimise previous steps, as necessary
• Secure Quality Assurance
• Communicate to build stakeholder confidence
• Identify and secure competence and resources for the different
phases. Plan for transition- and redundancy programs, recruitments
and contractor support
Press the button:
Ready to Go
![Page 19: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/19.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Planning in practice
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 19
Decommissioning planning is an iterative process
![Page 20: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/20.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Summary and conclusions
• Decommissioning projects are complex.
Planned and performed by people
• Do not underestimate the staff
management in planning activities
• Experience, competence and
understanding is crucial in planning
• Structure, logistics and robust
processes is vital for success
• Focus planning on reaching end-state
conditions as early as possible
PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING 20
Safe
Fast
Cost Efficient
Motivated staff building their career performs better
![Page 21: The Importance of Experience Based Decommissioning Planning · This document contains proprietary information owned by the ndcon companies. All rights reserved. The Importance of](https://reader033.vdocuments.net/reader033/viewer/2022041612/5e38a40a3b7b143c656bb405/html5/thumbnails/21.jpg)
This document contains proprietary information owned by the ndcon companies. All rights reserved.
Thank you for your attention
21 PARTNERSHIP FOR DECOMMISSIONING & DISMANTLING