the importance of knowing the basics of generator sizing calculations

5
Your Industrial Resource Center Is the generator needed for commercial or residential use? What is the five digit ZIP code for your location? Zip lookup for major cities Generators Home Free Price Quotes Buyer's Guide Related Articles View all categories | Help Compare FREE Price Quotes from the Leading Generator Brands Choose... Continue for Free Quotes Home > Industrial > Generators > Related Articles > Basic Calculations for Sizing Generators and the Impacts of Certain Loads Power Quality and Generators, Part 8: Basic Calculations for Sizing Generators and the Impacts of Certain Loads Knowing the basics of generator sizing calculations will help the system designer understand the impact that certain loads and starting methods have on the ultimate size of the standby generator. Consulting-Specifying Engineer - June 16, 2005 Keith Lane, P.E., RCDD/NTS Specialist, LC, LEED AP Vice President - Engineering SASCO, Seattle Editor's Note: This is the eighth article in a series covering basic engineering and code issues for standby generators and critical systems used in commercial building. This month's column covers the basic calculations for sizing standby generators. Articles in this series Once the starting kVA (sKVA), starting kW (sKW) and the alternator kW requirements are calculated by hand for generator sizing, these values are fed into sizing software to determine a particular manufacturer's recommended generator sizes. Although many generator simulation software programs are available, knowing the basics of generator sizing calculations will help the system designer understand the impact that certain loads and starting methods have on the ultimate size of the standby generator. It is common for a system's sKVA—or its sKW and maximum allowable transient voltage drop—to determine the size of the generator. Motors can draw six times the full-load amps during startup. The motor's NEMA code letter, which identifies the starting kVA/hp, is a representation of the starting inrush current. The example below uses a NEMA “F” motor. Based on this letter code, the motor will draw approximately 5.3 kVA/hp. Using the following calculation for a 150 hp motor with 91% efficiency and 0.91 power factor, the motor will draw approximately 5.9 times the full-load current during motor starting: Calculation #1 150 hp x 5.3 kVA/hp = 795 kVA = 956.6 amps @ 480 volt/3 phase (amps during startup) (150 hp x 0.746 kW/hp) / 0.91 (efficiency) = 123.0 kW (running kW) 123.0 kW / 0.91 (power factor) = 135.1 kVA = 162.5 amps (represent full-load amps) 956.6 amps (during startup) / 162.5 A (full-load amps) = 5.9 (times full-load current) High-efficiency motors can draw ten or more times the full-load current. As a comparison, for a motor with a NEMA “K” rating (8.5 kVA/hp), the inrush current would have been significantly higher (9.4 times full-load current). The following calculation uses a 150-hp motor with 91% efficiency and 0.91 power factor: Calculation #2 Featured Suppliers Supplier Brochures Briggs & Stratton Generators Diesel Service & Supply Generators Jasper Generators Standby Power USA Generators Search by Location We can connect you with generators dealers that serve your specific region. Start a search... Mentioned In... "BuyerZone is the sort of site that the Internet seems designed for... an amazing service." See Also CMMS Software CNC Machines CNC Routers Forklifts For Sale General Steel Order Pickers Pole Barn Steel Building Prices Used CNC Routers Used Forklifts Supplier Program Do you sell Generators or other business products or services? Sign up for our generators lead generation program Search by State Alabama Generators Alaska Generators Arizona Generators Arkansas Generators California Generators Colorado Generators Connecticut Generators D.C. Generators More Link to this article Cat Gas Generator Natural gas gensets, 9 to 6000kW High horsepower, low emissions Siemens answers: Efficient energy supply with Offshore Windparks. Ads by Google 10/24/2010 The importance of knowing the basics… buyerzone.com/…/rbic-power-quality-… 1/5

Upload: mind-of-beauty

Post on 08-Apr-2015

391 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: The Importance of Knowing the Basics of Generator Sizing Calculations

Your Industrial Resource Center

Is the generator needed for commercial

or residential use?

What is the five digit ZIP code for your

location? Zip lookup for major cities

Generators Home Free Price Quotes Buyer's Guide Related Articles

View all categories | Help

Compare FREE Price Quotes from the Leading Generator Brands

Choose...

Continue for Free Quotes

Home > Industrial > Generators > Related Articles > Basic Calculations for Sizing

Generators and the Impacts of Certain Loads

Power Quality and Generators, Part 8: Basic

Calculations for Sizing Generators and the

Impacts of Certain Loads

Knowing the basics of generator sizing calculations will help the system designerunderstand the impact that certain loads and starting methods have on the ultimate size ofthe standby generator.

Consulting-Specifying Engineer - June 16, 2005

Keith Lane, P.E., RCDD/NTS Specialist, LC, LEED APVice President - EngineeringSASCO, Seattle

Editor's Note: This is the eighth article in a series covering

basic engineering and code issues for standby generators and

critical systems used in commercial building. This month's

column covers the basic calculations for sizing standby

generators.

Articles in this series

Once the starting kVA (sKVA), starting kW (sKW) and the alternator kW requirements are

calculated by hand for generator sizing, these values are fed into sizing software to determine a

particular manufacturer's recommended generator sizes. Although many generator simulation

software programs are available, knowing the basics of generator sizing calculations will help the

system designer understand the impact that certain loads and starting methods have on the

ultimate size of the standby generator.

It is common for a system's sKVA—or its sKW and maximum allowable transient voltage drop—to

determine the size of the generator. Motors can draw six times the full-load amps during

startup. The motor's NEMA code letter, which identifies the starting kVA/hp, is a representation

of the starting inrush current. The example below uses a NEMA “F” motor. Based on this letter

code, the motor will draw approximately 5.3 kVA/hp. Using the following calculation for a 150 hp

motor with 91% efficiency and 0.91 power factor, the motor will draw approximately 5.9 times

the full-load current during motor starting:

Calculation #1

150 hp x 5.3 kVA/hp = 795 kVA = 956.6 amps @ 480 volt/3 phase (amps during

startup)

(150 hp x 0.746 kW/hp) / 0.91 (efficiency) = 123.0 kW (running kW)

123.0 kW / 0.91 (power factor) = 135.1 kVA = 162.5 amps (represent full-load amps)

956.6 amps (during startup) / 162.5 A (full-load amps) = 5.9 (times full-load current)

High-efficiency motors can draw ten or more times the full-load current. As a comparison, for a

motor with a NEMA “K” rating (8.5 kVA/hp), the inrush current would have been significantly

higher (9.4 times full-load current). The following calculation uses a 150-hp motor with 91%

efficiency and 0.91 power factor:

Calculation #2

Featured Suppliers

Supplier Brochures

Briggs & StrattonGeneratorsDiesel Service & SupplyGeneratorsJasper GeneratorsStandby Power USAGenerators

Search by Location

We can connect you withgenerators dealers that serveyour specific region.

Start a search...

Mentioned In...

"BuyerZone is the sort of sitethat the Internet seemsdesigned for... an amazingservice."

See Also

CMMS SoftwareCNC MachinesCNC RoutersFork lifts For SaleGeneral SteelOrder PickersPole BarnSteel Building PricesUsed CNC RoutersUsed Forklifts

Supplier Program

Do you sell Generators orother business products orservices?

Sign up for our generatorslead generation program

Search by State

Alabama GeneratorsAlaska GeneratorsArizona GeneratorsArkansas GeneratorsCalifornia GeneratorsColorado GeneratorsConnecticut GeneratorsD.C. Generators

More

Link to this article

Cat Gas GeneratorNatural gas gensets, 9 to 6000kW Highhorsepower, low emissions

Siemens answers:Efficient energy supply with OffshoreWindparks.

Ads by Google

10/24/2010 The importance of knowing the basics…

buyerzone.com/…/rbic-power-quality-… 1/5

Page 2: The Importance of Knowing the Basics of Generator Sizing Calculations

150 hp x 8.5 kVA/hp = 1,275 kVA = 1,534 amps @ 480 volt/3 phase (amps during

startup)

(150 hp x 0.746 kW/hp) / 0.91 (Efficiency) = 123.0 kW (running kW)

123.0 kW / 0.91 (power factor) = 135.1 kVA = 162.5 amps (represent full-load amps)

1,534 amps (amps during starting) / 162.5 amps (full-load amps) = 9.4 (times full-load

current)

This illustrates that the starting of motors can dramatically affect the inrush current and

associated sKVA and the sKW required and may exceed the maximum sKVA or the sKW of a

generator set that would otherwise be large enough to serve the steady state load. This could

require an oversized generator set based solely on the motor starting requirements of the

electrical system.

To clarify this issue, I will use an example with the same load profile but with two different

methods of motor starting. These simple examples will include lighting and miscellaneous loads

as well as motor starting with an across the line starter in one example and a solid-state starter

in another example.

Example #1: Motor with an across the line starter

Motor Load: 150-hp motor, NEMA “F” with a 0.28 starting power factor

Running power factor of 0.91 and an efficiency of 0.91.

NEMA Code Letter “F” = 5.3 kVA/hp

sKVA = 150 hp x 5.3 kVA/hp = 795 kVA

sKW = 795 kVA x 0.28 (starting power factor) = 222.6 kW

Running kVA = 123.0 kW / 0.91 (power factor) = 135.1 kVA

Running kW = (150 hp x 0.746 kW/hp) / 0.91 (Efficiency) = 123.0 kW

Lighting Load: 75 kVA at 0.9 power factor

sKVA = 75 kVA

sKW = 75 kVA x 0.9 power factor = 67.5 kW

Running kVA = 75 kVA

Running kW = 75 kVA x 0.9 power factor = 67.5 kW

Miscellaneous Load: 50 kVA at 0.9 power factor

sKVA = 50 kVA

sKW = 50 kVA x 0.9 power factor = 45 kW

Running kVA = 50 kVA

Running kW = 50 kVA x 0.9 power factor = 45 kW

System Totals:

sKVA = 795 + 75 + 50 = 920 kVA

sKW = 222.6 + 67.5 + 45 = 335.1 kW

Running kVA = 135.1 + 75 + 50 = 260.1 kW

Running kW = 123 + 67.5 + 45 = 235.5 kW

Alternator kW = 123 + 67.5 + 45 = 235.5 kW

Using one manufacturer's sizing software, the recommended generator set size is 350 kW. This

is based on about a 20% transient voltage dip followed by a sustained recovery of 90% of rated

voltage during starting. The generator would run at about 67% of capacity (Running kW = 236,

Generator Capacity = 350 kW, 236 / 350 = 67.4%).

Large motors that are started with across-the-line starters fed by generators to allow for very

low transient voltage drop during starting can require a greatly oversized generator set. In

these cases the running capacity of the generator can be significantly lower than the rating of

the generator set. It is critical to ensure that the running load represents at least 30% of the

rated size of the generator set or wet stacking or carboning can occur. See Part 7 for

definitions and a discussion of these terms.

Example #2: Motor with a solid-state starter with bypass contactor:

Motor Load: 150-hp, NEMA “F” motor with a 0.28 starting power factor

Running power factor of 0.91 and an efficiency of 0.91.

Soft Start set at a 300% full load ampere current limit. The current limiting range is

typically between 150% and 600%. A 300% current limit reduces the starting kVA and

starting kW by almost 50%.

sKVA, = (150 hp x 0.746 kW/hp) / 0.91 (efficiency) = 123.0 kW

10/24/2010 The importance of knowing the basics…

buyerzone.com/…/rbic-power-quality-… 2/5

Page 3: The Importance of Knowing the Basics of Generator Sizing Calculations

123.0 kW / 0.91 (power factor) = 135.1 kVA = 162 amps @ 480-volt/

3 phase.

300 % current limit = 162 amps x 3 (3 x FLA) = 487 amps = 405 kVA

sKW = 405 kVA x 0.28 (starting power factor) = 113.4 kW

Running kVA = 123.0 kW / 0.91 (power factor) = 135.1 kVA

Running kW = (150 hp x 0.746 kW/hp) / 0.91 (Efficiency) = 123.0 kW

Lighting Load:75 kVA at 0.9 power factor

Starting kVA = 75 kVA

Starting kW = 75 kVA x 0.9 power factor = 67.5 kW

Running kVA = 75 kVA

Running kW = 75 kVA x 0.9 power factor = 67.5 kW

Miscellaneous Load: 50 kVA at 0.9 power factor

Starting kVA = 50 kVA

Starting kW = 50 kVA x 0.9 power factor = 45 kW

Running kVA = 50 kVA

Running kW = 50 kVA x 0.9 power factor = 45 kW

System Totals:

sKVA = 405+ 75 + 50 = 530 kVA

sKW = 113.4 + 67.5 + 45 = 225.9 kW

Running kVA = 135.1 + 75 + 50 = 260.1 kW

Running kW = 123 + 67.5 + 45 = 235.5 kW

Alternator kW = 123 + 67.5 + 45 = 235.5 kW

Using one manufacturer's sizing software, the recommended generator set size for this example

is 275 kW. This is based on about a 20% transient voltage dip followed by a sustained recovery

of 90% of rated voltage during starting.The generator would run at about 86% of capacity

(Running kW = 236, Generator Capacity = 275 kW, 236 / 275 = 85.8%).

At this threshold, the engineer may want to specify the next larger generator set to allow for

some future additional loads. It is clear from this example that reducing the sKW requirements of

the motor with the use of current limiting starters can reduce the size of the required generator

set.

The solid-state starter will cause voltage distortion across the alternator of the generator. This

distortion is cause by the nonlinear way the silicon-controlled rectifiers (SCRs) in the solid-state

starter draw current. The generators alternator may have to be oversized to compensate for

this voltage distortion. This issue can be avoided, as in the example above, by specifying a

bypass contactor with the sold state starter. The bypass contactor closes after startup and

the SCRs are only operating during the starting of the motor. If the solid-state starter does not

have a bypass contactor, a rule of thumb is to add again the motor running kW to the running

kW of the system. This calculation will estimate the total alternator kW. See calculation below:

Alternator kW with a bypass contactor: 235 kW

Alternator kW without a bypass contactor: 235 kW + 123 kW = 358 kW

If the soft starter does not have a bypass contactor, the engineer must determine if a larger

alternator is required. In our example above, the same 275-kW generator can handle either case

(with and without a bypass contactor), but a larger alternator is required to handle the

additional alternator kW if no bypass contactor is specified.

In our example above, in the across-the-line starter situation, the sKW drove the requirement

for the larger generator set. Below is a breakdown of some of the critical parameters for the

different starting methods as well as the two generator set sizes noted above. Three total

generator set configurations have been noted below, one for 350 kW and two for 275 kW. The

275-kW generator set has been split into a smaller and a larger alternator. The parameters

(sKVA, sKW and alternator kW) noted under the three generator set configurations are the

maximum the generator set can provide. The parameters noted under the form of motor starting

are the requirements for the different system examples noted above with their associated form

of motor starting configuration.

Chart 1

sKVA sKW Alternator kW

275 kW Genset w/ Small Alternator 1028 291 300

275 kW Genset w/ Larger Alternator 1372 293 380

350 kW Genset 1896 518 515

Solid-State Start with no Bypass 530 226 358**

Solid-State Start with Bypass 530 226 235

10/24/2010 The importance of knowing the basics…

buyerzone.com/…/rbic-power-quality-… 3/5

Page 4: The Importance of Knowing the Basics of Generator Sizing Calculations

Across the Line Starter 920 335* 235

* The across-the-line starter exceeded the sKW (starting kW) capacity of the 275-kW

generator. Therefore, a 350 kW generator set is required.

** The solid state starter without a bypass contactor exceeded the alternator kW of the

smaller alternator. Therefore, a 275-kW generator set with a larger alternator is required

for this starting configuration.

Several factors should be evaluated prior to determining the type of starting for motors within

an electrical distribution system. These factors include, but are not limited to the following:

Electrical system effects from not providing some form of reduced voltage starting. How

will the large inrush current affect the components in the electrical distribution system?

A cost analysis of providing alternative forms of starting should be performed. It may be

more cost effective to provide a solid state starter, or other form of reduced voltage

starter, with a smaller generator set than to provide an across the line starter with a

larger generator set.

All applicable utility or jurisdictional requirements have to be evaluated during the design

process of the generator standby system.

In addition, the system designer must be familiar with local codes and the serving electrical

utility requirements. Many electrical utilities specify the largest system voltage drop during

motor starting or specify the largest motor size that can be started with an across the line

start.

For example, one of our local electrical utilities, Seattle City Light, indicates that “reduced

starting current shall be required on all motors exceeding 15 hp nameplate rating, unless

otherwise agreed to by the utility.” Another serving utility in our area, Puget Sound Energy,

indicates, “If the voltage dip exceeds 2%, the transformer size must be increased to reduce the

dip to 2%. The customer is responsible for the difference in cost of the larger transformer.”

When only the maximum allowable voltage dip is indicated as a requirement, the largest allowed

motor without some form of reduced voltage starting will be based on the size and impedance of

the serving utility transformer.

Another form of reduced-voltage starting is the variable-frequency drive. VFDs can reduce both

sKVA and sKW. They draw load in a nonlinear fashion, similar to the solid-state starter, and will

continue to draw loads in a nonlinear manner, as the frequency of the motor can be altered by

control devices through the entire operation of the motor. The size of a generator set feeding a

system with a VFD may have to be increased or may have to be fitted with an oversized

alternator similar to that of a system feeding a soft start without a bypass contactor. The use

of 12-pulse IGBTs (Insulated Gate Bipolar Transistor), (PWM) pulse width modulated drives and

harmonic filtering can make the VFD more generator-friendly.

In addition, stepping the sequence of the loads within the requirements of the National Electric

Code, Section 700 can greatly reduce the sizing of the generator set. Since larger generators

are often required because of the peak kW or kVA on the system, stepping the loads long

enough for the inrush of motors not to be simultaneous can reduce the ultimate size of the

generator set required to feed the critical loads.

Articles in This Series

Part 1: Sizing and Code Issues

Part 2: The Effects of Harmonics

Part 3: Complying with the Codes and Controlling Noise

Part 4: Fuel Configurations for Standby Gensets

Part 5: Paralleling Generators in Critical Applications

Part 6: Generator Sizing and UPS

Part 7: Commissioning, Training and Long-Term O&M Programs

Part 8: Basic Calculations for Sizing Generators and the Impacts of Certain Loads

Part 9: Design Criteria for Grounding

Part 10: Generators and the 2005 NEC

Ready to find a generator dealer for your business?

Consulting-Specifying Engineer is a practical, application-oriented

magazine that chronicles the changes sweeping across the

construction industry.

RelatedTerms

Diesel Generator, Commercial Generators, Emergency Generator, Equipment Leasing, Gas Generators,Generator Manufacturers, Generator Prices, Metal Buildings For Sale, Portable Generators, Used Generators,

Gas Turbine SalesAvon / Olympus - Alba Power TurbineExcellence - Scotland, UK

Renewable Energy InfoFind Out About Eco Energy Sources &How To Be Green. Get A Free Report!

Ads by Google

10/24/2010 The importance of knowing the basics…

buyerzone.com/…/rbic-power-quality-… 4/5

Page 5: The Importance of Knowing the Basics of Generator Sizing Calculations

Forklift Telescopic, Telehandlers, Generator Buyer Comments

Corporate About Us - Help - Privacy Policy - Top Cats - Site Map - B2B Sales Leads - Affiliate Marketing Programs -Lead Generation Blog - Subscribe

Customer Care: 1-888-393-5000

© 1997-2010, BuyerZone.com, LLC, A Division of

blank

10/24/2010 The importance of knowing the basics…

buyerzone.com/…/rbic-power-quality-… 5/5