the indian water supply sector has witnessed several ppp ... › files › file... · estimate...
TRANSCRIPT
The Indian water supply sector has witnessed several PPPprojects since the early 1990s. An initiative to address PPP Projectsin water supply has been on-going in the Ministry over severalmonths. A note on strengthening PPPs in urban water supply isenclosed in Annexures. All concerned may please send theirvaluable suggestions and comments for consideration which may beaddressed to Economic Adviser, Ministry of Urban Development,Room No. 219-C Wing, Nirman Bhavan, New Delhi-110 008, thesame may also be [email protected].
Strengthening PPPs in Urban Water Supply
1 Draft_For Feedback Only
Annexure 1: Project Preparation for Water PPP Projects
Reasons for Addressing the Issue
In projects that are executed through the conventional Engineering-Procurement-Construction
(EPC) route, typically a Detailed Project Report (DPR) is prepared by the city / consultant
appointed by the city, detailing, the nature and quantum of works to be undertaken. There is little
room for flexibility in implementation, and (having specified physical infrastructure related
system interventions), the city takes the entire risk of system performance after completion of
works. Often, there is little accountability for performance.
However, in projects executed through PPP, there is a paradigm shift, and service delivery (not
asset construction) is the focus: contract terms explicitly hold the operator responsible for
performance after implementation of works. In such a context, it may be inappropriate for the city
to specify, in too rigid a manner, the nature and quantum of works that the operator is to
undertake, to achieve service delivery improvements, particularly since
(a): adequate data on system characteristics and operations may not be available with the city
(particularly for underground assets – or the distribution network); and whatever is available may
be unreliable.
(b): the consultant appointed by the city to prepare the DPR, typically, may not have operational
experience and thus may not be best placed to advice on how system performance can be
improved or brought about. Also, consultants may not be provided adequate resources and time to
put together the data.
PPP projects in water distribution require a method of preparation that takes cognizance of (a): the
up-front lack of reliable information and (b): the importance of inputs from professionals familiar
with operations (operators)
Current Situation
PPP projects in India tend to prepare detailed project reports, largely relying on incomplete
information, and which include a prescriptive engineering design. In the absence of relevant and
reliable data regarding the existing system, most reports are found to be inadequate once the
operator undertakes his own survey after signing the contract (for eg., Mysore and Khandwa).
From the point of view of project preparation, and given context and capacity limitations, water
operators have suggested that DPRs for water supply PPP projects in India should prioritise
collection of relevant data and information; and allow a degree of flexibility with regards to the
engineering design. They have argued that (a): given their operational expertise, and (b): since
they are held accountable for improved service delivery, they be allowed to finally determine the
interventions necessary to improve system performance; and the associated costs. Moreover, that
they are in a position to do this only after operating the water supply system (for a period of 9 –
Strengthening PPPs in Urban Water Supply
2 Draft_For Feedback Only
12 months) and understanding it’s characteristics. Operators, however, stress the importance of
reliable baseline data, or system information that can help them to gauge a system prior to
operations; or prior to making a price offer for their services, in bidding for a project.
From a public sector perspective also, the requirement is primarily for a project cost estimate
derived through sound processes so that (a): the city may assess financial sustainability, with
regard to resources available to it; and (b): the city may get approval for funding part of the costs
from the Ministry of Urban Development (MoUD), GoI; or through other sources.
The objective or utility of project preparation in a water supply PPP project, from the perspective
of various stakeholders may thus be summarized as:
Providing relevant and reliable data / system information to operators, in order to inform bid
preparation and bid price. The information must cover all aspects relevant to implementation
on a PPP basis
Providing a project cost estimate to the city, in order to assess financial sustainability; and to
serve as a reference for likely price bids. The cost estimate may be based on an engineering
design and estimation of works required, which is amenable to changes by the operator
Providing a project cost estimate to the Ministry for the purposes of project funding. The cost
estimate serves as an envelope for funding purposes, which may vary within pre-established
limits
Proposals
On the basis of the above, the following approach to project preparation for water PPP projects is
proposed. This assumes that cities will make a first level decision on implementation on a PPP
basis – and the nature and objective of the PPP – before starting on project preparation. This has
generally not been the case so far. Many cities prepare the detailed project report and after the
report is ready, take a decision to pursue the PPP.
Project preparation should have much greater focus on providing the required base data /
information, with a reasonable level of reliability. The minimum base level data required to
initiate a water supply PPP will be specified, and the methodology for procuring the
information will be suggested – standard Terms of Reference and scope of work for key
aspects of information will be recommended – so as to enable cities to undertake
information collection at least cost and time, in a reliable manner. MoUD will also support
information collection (surveys, investigations)
The base line data is used to generate a design and investment plan (or DPR) containing (a):
a justification of project needs based on a thorough analysis of gaps in the existing system,
and reasons why it is not performing as originally designed (b): an assessment of the city’s
long term water supply requirements, based on an analysis of growth trends (c): a detailed
Strengthening PPPs in Urban Water Supply
3 Draft_For Feedback Only
assessment of interventions deemed necessary to achieve stated performance objectives (d): a
proposed time frame within which service delivery and performance objectives are proposed
to be met; and (e): a financing plan, based on secured commitments, and demonstration of
the financial sustainability of the proposed project (refer Annexure2 Assessing Project
Financial Sustainability). The DPR will specify non-negotiable parameters such as design
norms for service levels, design horizon for assets, pipe material etc. The DPR will also
indicate aspects of design and cost that are firm; and those that are likely to undergo change,
as they may be based on incomplete information at the time of preparation.
Prior to initiating project preparation, cities will determine the level and nature of private
sector involvement desirable. This may be in the form of (a): a short term contract for
managing the water supply system, and all operations related to service delivery
(management contract), wherein investments are largely made by the city; or (b): a long term
contract also including significant investment from the private operator (concession
contract). Cities opting for a concession contract, must take into account that the Operator
will assume a higher commercial risk. The city will also implicitly protect the rate of return
on the investments of the operator. Therefore, the quality of the baseline data and the design
in the DPR have to be of a greater extent; and assured through adoption of methods
suggested.
The DPR, and the capital investment requirement provided therein (subject to financial
sustainability indicators), along with the proposed project structuring will form the basis on
which the project is bid.
The system related interventions and cost estimate proposed in the DPR will be the basis for
the first level of approval by the Ministry, upon obtaining which the project is assured of
funding. The exact project investment requirement, however, will be finalised only after the
project has been successfully bid out, and the selected operator has prepared a Project
Implementation Plan (refer Annexure 5 Proposed Funding Process). MoUD will finance
its share of cost increase in the Project Implementation Plan up to a maximum of 15% of the
DPR estimate.
Information Requirements
Based on feedback from consultants and water operators the following categories of information
emerge as minimum requirements from the perspective of a DPR for projects implemented on a
PPP basis As mentioned earlier, the methodology for procuring the information will be
suggested, where necessary, in order to ensure a level of reliability. MoUD will provide funding
support for DPR preparation as well as Project Implementation Plan preparation.
I. City level population data
Population data of last 5 decades, population growth rates, No. of households
Strengthening PPPs in Urban Water Supply
4 Draft_For Feedback Only
Ward wise/zone wise distribution of population, No. of households, ward area and
population density as per the last census.
Slum and Urban Poor Profile
- Ward/zone wise distribution of slums, slum population, No. of slum households
- Slum wise data - population, population density, No. of households, No. of BPL
households, legal status (notified/non notified) - as obtained from the consumer survey
undertaken
- Urban poor households living in non-slum locations
II. Other city related information
City Master Plan (latest revision)
Other city specific development plan, if any
Latest GIS maps of city (prepared on the basis of satellite imageries or digitized Google
imagery), with appropriate layers indicating
- Existing municipal and project area boundary, ward boundaries, administrative zone
boundaries, master plan area boundary, urban agglomeration boundary
- Most recent existing land use
- City road network – major and minor
- Contours at 1 meter interval or spot levels of location of source, WTP, Clear Water
Reservoir (CWR), Elevated Storage Reservoir (ESR) all important road junctions within
the city jurisdiction
- Availability and location of vacant government land proposed for water supply
infrastructure
- Information related to water supply infrastructure, as elaborated in section III, sub-section
2.
III. Water supply infrastructure (for city/project area)
1. Water supply system
Raw water capacity
- Details of surface water sources – Name, location, availability of water, allocation, design
capacity of intake well,
- Details of ground water sources – number, location, safe drawl capacity
- Source wise raw water capacity
Water treatment
- Details of Water Treatment Plants (WTP) – number, location, design capacity and
capacity utilization
Water transmission and storage
- Details of Pumping mains - existing pumping machinery and electrical installations at
WTP and booster stations
- Service reservoirs – number, location (ward or zone name) and capacity
- Schematic / Line diagram of the bulk water production and treatment system; transfer to
ESRs indicating capacities of different units, pipe diameters, and water levels (Above
MSL) in different ESRs
Water distribution
Strengthening PPPs in Urban Water Supply
5 Draft_For Feedback Only
- Distribution pipe network details - location, age, pipe diameter, material (as per
methodology suggested)
- Total number of water connections – residential, commercial, industrial, other categories –
as obtained from the consumer survey undertaken
- Details of water connection in respective hydraulic zones – as obtained from the consumer
survey undertaken
- Status of metering – no of metered/unmetered connection, flat rate connections
2. Mapping of infrastructure on digitised city map
Index map showing location of water sources, WTPs, transmission mains, booster stations
Existing water supply distribution network, including location of ESR’s, booster stations,
boundary of different hydraulic distribution zones
Geo-tech details at points where interventions are proposed or along alignment of
proposed pipeline
3. Drawings
Campus plans of all over-ground structures – intake structure, WTP, pumping stations,
reservoirs, electric substations, connecting pipe lines valves etc.
General arrangement drawings of all structures showing piping arrangement, electro-
mechanical installations
IV. Operational data (project area)
Details of raw water production in past three years including raw water produced from
different sources, water quality and raw water transmission losses
Details of treated water production in past 3years including transmission losses
Water transfer to different distribution zones
Supply duration and supply pressure in different distribution zones (zone wise)
Water quality results for chemical and bacteriological analysis, for past one year
Operational efficiency of pumps giving details of existing power supply connections and
power consumption
Availability of power per day during different months
Details of consumables (chemicals, power, fuel) utilized in past 3 years
Details of water supply service delivery to urban poor Hhs and slums under project area
(Based on consumer survey)
Analysis of complaints in past three years in terms of no. of complaints, type of
complaints and time taken for redressal, along with a short description of the complaints
redressal system
Repair history, in past five years (or more, as applicable) of (a): various plant and
machinery (b): transmission and distribution network and (c): leakage repairs
Current status of service delivery against the CPHEEO service level benchmarks
V. Condition Assessment (project area)
Listing of assets under water supply system
Condition assessment including performance assessment of all over ground water supply
infrastructure assets (WTPs, ESRs, pumping stations); and sample condition assessment of
Strengthening PPPs in Urban Water Supply
6 Draft_For Feedback Only
underground network (using recommended methodology), service pipelines, consumer
meters,…etc
VI. Consumer Data (project area)
Registered consumers under different categories along with connection size, type of
connection, status of metering, distribution zone number, etc. derived from data collected
through a consumer survey (as per proposed format).
Consumption estimates based on metering data, if available, or best estimate (ball-park
basis)
VII. On-going works and outsourcing contracts (project area)
Information on on-going works:, extensions to the network, new construction undertaken
in past 5 years.
All outsourcing contract such as for WTP operations, O&M contracts, material supply,
billing and collection, tanker supply, etc
VIII. Operating staff data (city level)
Institutional setup of water supply department of city
Details of O& M staff in terms of number, designation, qualification, experience and
retirement date (for all stages of water supply)
Emoluments and benefits
IX. Financial data (city level)
City Financial data (last 5 years) giving sources of income - own sources, grants;
expenditure; loans and debt servicing
Financial data of water supply operations (last 5 years), including details of operations and
maintenance costs (wages, power, chemicals, repairs/replacements, etc); revenue demand
and collection; No, of bills raised and collected; capital investments made in the system
Water tariff structure in last 5 years for domestic, low income Hhs, commercial,
industrial/other bulk supply connections
X. Other documents
Prevailing water supply rules/bylaws, connection policy including policy for unauthorized
properties
Reports of earlier WSS projects undertaken
Initiatives(including policy adopted) for providing services to urban poor
Master Plans of water supply, etc
Reports on surface water resources and ground water, in the region, if any
Based upon the above information, the city will consider various design options for rehabilitation
and expansion of the system to achieve service level targets; and propose the best suited one. This
will consider a reasonable design horizon of 15 to 30 years for various components, while making
optimum use of the existing assets. Optimization is to be done by striking a balance between
capital expenditure, O&M expenditure and NRW levels.
Strengthening PPPs in Urban Water Supply
7 Draft_For Feedback Only
The city’s DPR will contain the following:
I. Analysis of System Gaps and Shortcomings of Existing System (resulting in non-
performance)
Targeted performance objectives for service delivery and service efficiency against
existing levels (and CPHEEO benchmarks)
Measures proposed to be addressed to achieve continuous supply
II. Design Period – initial stage, intermediate stage and Ultimate stage; and target for
project
III. Population projection (city/project area)
Master Plan horizon
Population growth rate adopted
Demographic method adopted and justification
Population projection – year wise for the project period; and for a longer horizon of 25 to
30 years thereafter.
Ward-wise population projection - initial, intermediate and ultimate stages
Total projected population to be accommodated in existing municipal boundary / project
area
IV. Water demand (city/project area)
Proposed norms for average per capita water supply and upper limit of system losses
Gross water demand and net water demand at initial, intermediate and ultimate stages
Existing water availability and gap for city/project area
V. Design Components as applicable
Intake structure – design period for civil structure and electro mechanical works under the
project
Water treatment plan – Design period, design capacity, shortfall in capacity if any
Tube wells – number of tube wells proposed, yield of each tube well and drawl of water
Details of the proposed DMAs
Pumping main/raising mains and Feeder mains–
- Design period
- Stand by for Pump sets
- Total no. of pumping/rising mains
- Average flow considered in different pumping mains
- Pumping hours considered
- Pumping efficiency considered
- Capacity of pumps proposed for different pumping mains
Service reservoirs (SR)(Details as derived from hydraulic modeling)
- Design period
- SRs to be utilized in the proposed (existing & new) system - number, capacity and height
of SRs
Strengthening PPPs in Urban Water Supply
8 Draft_For Feedback Only
Distribution network
- Design period
- Total length of roads in city
- Total length of roads in project area
- Additional new pipe network proposed – length, diameter, material
- Rehabilitation of existing pipe network proposed – length, diameter, material
- Residual head in distribution network (minimum residual head and range of available
pressure)
- Maximum velocity in distribution network
- Peak flow from the outlet of service reservoirs as per the design (layout wise/DMA
wise/zone wise) and total peak flow from all ESRs
- Proposed number of total water connections – domestic, commercial, industrial
VI. Maps showing the detailed proposed design including marking of land sites for proposed
infrastructure
VII. Land requirements
for WTP, Tube wells, SRs, Pumping stations, Laying pumping mains, distribution mains
and transmission mains
Status of the identified land sites for proposed infrastructure as marked in the land use
plan along with related provisions made in the city master plan
VIII. Bill of Quantities and cost estimates of individual components prepared as per
Schedule of Rates
IX. Financial Projections
Assumptions made for financial projections
Proposed tariff structure (on completion of project)
Provisions made for urban poor in the proposed tariff structure and water connection
policy
Projection of operating subsidies, if envisaged
Projection of revenue and expenditure during rehabilitation period and O&M period,
indicating projected tariff revisions (if any) and related measures to improve recovery of
operational expenditure
Projection of capital investments including for expansions (raw water capacity, bulk water
supply, network expansion, expansion of service area)
Projection of periodic replacements of assets
Financing plan for initial capital investments (including grants, city contribution in the
form of loan and/or grant, operator investments)
Estimate of applicable project viability indicators such as cost recovery, project IRR, debt
service coverage ratio, etc
X. Other related information
Proposed SCADA arrangement
Strengthening PPPs in Urban Water Supply
9 Draft_For Feedback Only
Proposed Management Information System (MIS)
Complaints redressal system
Proposed staffing and plan for deployment of government staff
As mentioned earlier, the designs prepared and interventions proposed by the city shall be flexible to
change by the operator (once appointed), to the extent it follows the design standards/specifications
specified by the city in the DPR. The Project Implementation Plan (PIP) prepared by the operator will
provide the basis for actual implementation.
Strengthening PPPs in Urban Water Supply
1 Draft_For Feedback Only
Annexure 2: Assessing Project Financial Sustainability
Reasons for Addressing the Issue
Financial sustainability of WSS service providers 1 specifically refers to the adequacy of
revenues for meeting O&M costs and capital costs during the life cycle of the project.
In conventional city (or other public owned) operations, the availability of finances is a
constraint. To cope with inadequate finances, cities reduced O & M expenditure to match
available finances. Capital investments were deferred and limited to the extent of grants
available. Service levels and asset quality deteriorated as a result. Though the system was not
financially sustainable, cities maintained a low level equilibrium in service quality.
Water PPP projects do not have this option. Operators are responsible for a set of service
delivery parameters and for meeting related costs. Operators need to spend routinely on asset
maintenance and operations. Major refurbishment of assets is also required to maintain service
standards. Some PPP contracts require the operator to undertake new capital expenditure and
also to replace assets whose useful life expires within the contract period. Therefore, the city
needs to assure that it has adequate financial resources to meet (a): initial capital costs (b):
contingencies (c): O & M expenses (d): expansions. Assessing the financial sustainability of
water PPP projects upfront is therefore relevant.
Current Situation
Several water PPP projects have faced financial stress. For eg., while Khandwa and Latur
targeted operational sustainability through user charges, they ignored changes in scope and
future expansions. Nagpur and Aurangabad sought to access private finance partly and improve
the cost recovery situation partly. Mysore focussed neither on operational sustainability nor on
future expansions. Poor financial condition of the cities created a stalemate in Mysore and
Khandwa.
Thus, the PPP projects in the cities focussed only on service delivery improvements; financial
sustainability has not been addressed. Cities such as Mysore, Khandwa and Latur also did not
assess if they would be able to absorb any financial contingencies.
The financial difficulties that water PPPs have encountered are related to the underlying poor
financial status of WSS sector. Operating cost recovery is poor. Tariff is low and is not revised
regularly. Most cities rely on grants from State and national Governments for capital
1 Achieving financial sustainability and recovering costs in bank financed water supply and sanitation and irrigation
projects, Alexander McPhail, Alian R. Locussol, Chris Perry, 2012, Water Partnerships Programme
Strengthening PPPs in Urban Water Supply
2 Draft_For Feedback Only
investments. As a result, when they take up a project, even though it is supported by a grant, they
are not financially capable of meeting increased O & M liabilities of improved and augmented
services; or uncertainties. The grants are limited to a share of approved capital costs and do not
meet cost escalations or change in scope. When a PPP project encounters a financial challenge
(loss of revenue, increase in costs or change in scope), an easy resolution is not possible since the
city is not financially strong and is reluctant to revise tariff to meet costs.
Analysis
Cities have attempted PPP projects in the background of poor operational cost recovery. The
following table summarises how the project design and the PPP contract addressed financial
issues in five projects.
Table 1 – Financial Summary of five PPP Projects
Khandwa Aurangabad Nagpur Latur Mysore
1. Project is concurrent with
tariff revision to improve cost
recovery
Yes Yes Yes Yes No
2. User charges are an integral
part of the revenue model of
the operator
Yes Part user
charges, part
subsidy
Distinct from
user charges Yes Distinct
from user
charges
3. Project eliminates need for
operating cost subsidy from
the city
Yes No, but
subsidy is
capped
No; will
require
operating
subsidy
Yes No
4. Project (pvt. operator)finances
part of initial capital costs
10% 50% 30% of
distribution
network
No No
5. Project design includes a
solution for financing of
change in scope in initial cap-
ex
No No No NA No
6. Project design includes a
solution for financing of
future expansions
No No No No No
Khandwa focussed on achieving long term operational sustainability by linking the operator’s
revenue to user charges. There is no additional subsidy from the city to the Operator.However,
the project remains vulnerable to changes in scope since the city is responsible for financing
change in scope of work and expansions, and did not have the financial strength to meet these
costs.
In Aurangabad, the Operator is compensated partly by user charges (which were fixed prior to
bidding) and partly by a yearly operating subsidy (bidding parameter). The operating subsidy is
25% of the annual revenue of the city. As a result, the project carries significant revenue risks.
Strengthening PPPs in Urban Water Supply
3 Draft_For Feedback Only
Additionally, the city’s ability to finance change in scope or future expansions, which remain it’s
responsibility, is untested
In Nagpur, the operator receives a fixed rate or fee per unit of water billed and collected. This
rate is delinked from the water tariff. The water tariff does not meet the entire water supply costs,
which continues to be dependent on city finances for sustainability. The city is responsible for
any change in scope and for future expansions. Thus the project neither addressed operational
sustainability nor future expansions.
In Latur, the Operator is fully responsible for meeting operating costs through user charges, as in
Khandwa. However, unlike Khandwa, capital investments were not considered in project
preparation. Major capital expenditure was the responsibility of one of the contract counterparts,
the parastatal agency; but the parastatal does not have a revenue base. The second counterpart to
the contract, the city Government, was financially weak and could not support operations or
capital investments. Thus, while the PPP project considered operational sustainability, it ignored
capital investments and future expansions.
In Mysore, the operator is compensated by a fee paid by the city which is higher than current
tariff levels. The gap between the water supply revenue and the operator payments is met from
the general budget of the city. Identified capital investments are fully financed by JNNURM
grants and a small share from the city Government. However, the contract does not clearly assign
responsibility for changes in scope. Further, there is no clear framework for financial
sustainability for the future. Thus the project neither addressed operational sustainability nor
future expansions.
All five projects have attempted to improve their WSS financial situation only partly,
highlighting the need to assess financial sustainability upfront and with regard to all stakeholders
involved.
This requirement is important irrespective of whether the project is initially grant funded or not.
PPP projects should have clear solutions for meeting
a) Capital costs including unforeseen cost escalations or change in scope of work
b) Operational costs whether paid for by the city or by the operator
c) Future capital investments
Corrective Measures
Financial sustainability can be improved only through a carefully planned and phased cost
recovery plan and through committed long term support from cities to WSS sector. The required
measures are well recognised and are part of the municipal and WSS reform agenda. However,
these are long term measures and the current situation will continue to be vulnerable. Therefore
cities that are pursuing PPP projects have to ensure that
Strengthening PPPs in Urban Water Supply
4 Draft_For Feedback Only
a) Financial requirements are carefully assessed
b) The PPP contract assigns clear responsibilities for financing capital expenditure, operating
expenditure, contingencies and expansions
c) The stakeholders understand their respective financial strength relative to their obligations
d) The stakeholders understand the residual financial risks so that they can manage them better.
Proposals
A financial sustainability assessment tool has been developed for this purpose, and is proposed to
be integrated into PPP decision making processes. This tool will be a diagnostic tool which will
assess if the PPP project design ensures availability of finances for sustained service delivery.
Cities would do a self-assessment; appraisal agencies at the state and central level could use this
tool as a part of the appraisal process. The financial sustainability assessment tool is intended to
be used at different stages of the project:
a) At the project concept stage when broad project costs are available. The diagnostic tool will
help the city make a summary assessment of the suitability of the PPP approach, given the
costs, existing tariff and city finances.
b) After the Detailed Project Report (DPR) has been prepared and a financial analysis is
available, a more detailed assessment can be made. At this stage, the ability of the city to
meet the capital and operating subsidies can be assessed. The probability for variations in
project cost can also be assessed based on the quality of preparation underlying the DPR.
c) In the review, appraisal and approval stage, the tool can be used to develop alterative
scenarios to improve project quality. For example, various options related to financing mix
and tariff assumptions can be undertaken. If required, technical preparation can also be
revised to improve project quality.
d) Further assessment can be done after the PPP structure is finalised and a risk sharing
framework is designed. Normally this will occur after the preparation of the Request for
Proposal document for the selection of private operator. This assessment will indicate if the
risk sharing terms are aggravating the financial risks.
e) This assessment can be regularly updated in further stages of the PPP project. For example,
after the Operator prepares a detailed investment plan, the assessment can be updated to
reflect the data gathered by the Operator and the final investment plan.
The tool is not a substitute for financial modelling and instead relies on the outputs of the
financial model and the Detailed Project Report. To illustrate, the financial model will determine
the project returns (say project IRR and equity IRR) given a certain set of assumptions. The
financial assessment tool will indicate whether the assumptions are realistic and what is the
likelihood of the project being vulnerable.
Strengthening PPPs in Urban Water Supply
5 Draft_For Feedback Only
This tool is not intended to asses a) value for money or b) efficiency in investment planning or
c) competitiveness in procurement, which are to be assured separately. Each of these factors may
indirectly impact financial sustainability. For example, if the project intends to replace the entire
distribution network or overprovides for bulk water, the approach may not be efficient in
investment planning. However, it may still be financially sustainable IF the municipal finance or
user charges are adequate to meet these higher costs. The tool will only highlight if the available
finances are adequate.
Financial Sustainability Assessment Tool
Design
The tool assesses financial sustainability with the help of three sets of indicators (Figure 1).
The first set of indicators called Key Indicators, measure the financial impact of the project on the stakeholders and their
ability to bear the impact. These indicators are quantitative. The tool assesses the impact on a) project b) operator, c)
lender, d) consumer and e) city. There are seventeen key indicators (
a) Figure 2). Five of these indicators can be calculated at project concept stage itself, with
minimal information.
b) The second set of indicators measure quality of Risk Allocation in PPP design to assess if all
known costs and revenue risks have been addressed. It assesses how the risk allocation
affects the availability of finances at different stages of the project (development and
construction; revenue; operating cost changes and expansions). This assessment will be
carried out after the project structuring has been completed and risk sharing principles have
been finalised.
c) The third set of indicators measure the quality of Project Preparation to assess the level of
detail underlying cost and revenue estimates and if assumptions are realistic. Eight areas of
project preparation are assessed. This assessment can be carried out on completion of the
DPR and after a financial model is available.
Strengthening PPPs in Urban Water Supply
6 Draft_For Feedback Only
Figure 1 – Summary of the Financial Sustainability Assessment Tool
Overall, through a grading of the indicators, the tool helps assess
a) Which stakeholder is vulnerable to financial impacts?
b) What is the quality of risk allocation and which stages of the project are vulnerable?
c) Which areas of project preparation are weak; and therefore what are the revenue and cost
risks that stakeholders should be conscious of?
The following sections discuss the indicators used and the grading methodology.
Indicators
First Set – Key Indicators
The Key Indicators measure the impact on five key stakeholders. The indicators marked “1” can
be assessed with minimum information, generally at stage of conceptualising the project. The
indicators marked “2” will require additional information, generally available only after Detailed
Project Report, PPP risk sharing principles and financial modelling are available. The two
indicators marked “C” are relevant only for situations where the private operator is financing a
part of the capital investments.
Index TabsProject PreparationRisk AllocationKey IndicatorsSummary
Project Preparation Project SustainabilityInstitutional StrengthInstitutional Strength
Institutional StrengthKey Indicators
Project PreparationProject Preparation
Risk AllocationProject Sustainability
Project SustainabilityProject Preparation
What is the financial impact of the project on key stakeholders?
What is their ability to bear the impact?
How are the key project risks allocated?
How does it impact the availability of finances during various stages of the project?
Covers construction risks, revenue risks, operating costs escalations and expansions
What is the level of detail underlying the cost and revenue estimates?
Are the assumptionsrealistic?
Covers construction, revenue, operating parameters , operating ostsand escalation, expansion and financing
Strengthening PPPs in Urban Water Supply
7 Draft_For Feedback Only
Figure 2 – Key Indicators
Second Set - Risk Allocation
These indicators assess quality of risk allocation in four stages of the project a) development and
construction, b) revenue, c) costs and d) expansions.
Key Indicators
Project
User Charge-----------
Water Supply Costs
Key Indicators related to impact on
Developer Lenders Users ULB
Project IRR post tax
User Charge-----------
Operator Revenue
Equity IRR post tax
% of revenue linked to O & M
performance
% of capexreimbursement
linked to performance
Debt-----------
Revenue Surplus
Minimum DSCR
Average DSCR
Source to customer
responsibility
Average monthly bill for households
Tariff in Rs/KL
Recovery of connection
charges
Own contribution------------------------Revenue Surplus
Municipal Subsidy-------------------------Revenue Surplus
Project Cost-------------------------
Total Revenue
Tariff structure and revision
2
2
1 1 1
1
C
2
2
12
2
C
2
2
2
2
Strengthening PPPs in Urban Water Supply
8 Draft_For Feedback Only
Figure 3 –Indicators – Risk allocation
Third Set - Project Preparation
The third set of indicators assess the key assumptions and level of detail underlying project
preparation - a) development and construction assumptions, b) demand, c) revenue, d) operating
parameters, e) operating costs, f) operating cost escalations, g) provision for expansion and h)
financing. Over fifty indicators related to project preparation are assessed. For example, under
Construction and Development, the following indicators are assessed.
1. Capital costs for bulk and treatment assets
2. Estimates of pipe length
3. Estimates of number of connections
Index Tabs Risk Allocation
Development and
ConstructionRevenue
Operating Cost Changes Expansions
1. % conversion per year
2. Preparatory period3. Operator
implemented capex4. Capex payments
linked to performance
5. Change in pipe length
6. Change in number of connections
7. Change in % of assets replaced
8. Design changes9. Price escalation
1. Estimated connections
2. Consumption per connection
3. Population growth4. Revenue collection
1. Staff cost escalation2. Power costs3. Chemical costs4. Other repairs and
maintenance5. Raw water costs
1. Residual capacity of bulk supply
2. Design period for distribution network
3. Demand increase4. Increase in
connections5. Increase in service
area6. Increase in network
length
Strengthening PPPs in Urban Water Supply
9 Draft_For Feedback Only
4. Percentage of pipes to be replaced
5. Percentage of house service connections to be replaced
6. Percentage of meters to be replaced
7. Escalations
8. Physical contingencies
9. Basis for unit cost estimates
Grading
Each indicator is graded in four categories,
“Weak” indicated by red grade;
“Vulnerable” indicated by yellow grade;
“Acceptable” indicated by blue grade; and
“Sound” indicated by green grade. A template provides guidance on how to grade the
indicator as sound or acceptable or vulnerable or weak.
Though the individual areas are graded in four categories, the tool does not envisage making an
overall grade for a project – since indicators are linked, and a weak grading in one may be
compensated for by a sound grading in another (reflecting city context and priorities). Also, such
a summary grade will divert attention from individual areas that are weak and may affect a
particular stakeholder significantly (or) may affect one aspect of the project strongly. However,
given their critical nature – all of them have the potential to derail a project – the key indicators
for any project must be sound (green grade), or at the very least, acceptable (blue grade).
A grading sheet (refer Financial Sustainability Template attached) provides guidance to grade
each indicator. Some grading criteria are illustrated below:
1. If “Total User Charges” as a proportion of “Total Water Supply Operational Costs” (based on
the projected costs after completion for project) is between 40% to 60%, the project is graded
“Vulnerable” (Yellow grade) since it would rely on significant operational subsidies from the
City Government.
2. If the project viability measures in terms of post tax project IRR is less than 10%, the project
is termed very weak (red grade); commercial borrowing would be difficult under these
circumstances.
3. If estimates of pipe length (proposed) are based only on available surveys of road length
(which may be dated/inaccurate), then it is graded as “vulnerable.” If it is based on a current
survey of road length and also includes ongoing road developments, it is graded as
“acceptable.” If the pipe length estimates are based on covering the entire the service area
based on the master plan road length, it is termed as “sound.”
Strengthening PPPs in Urban Water Supply
10 Draft_For Feedback Only
The grading scale that has been proposed is indicative and is being refined further by
carrying out sample assessments of water supply projects that have been proposed for
funding under JNNURM.
Figure 4 – Illustration of grading
Guidance
Brief remarks on the indicator, source of data and suggested approach for calculation are
included in the template itself. A detailed user manual will be separately provided.
Sample Assessment
This section summarises the financial assessment of an on-going PPP project, wherein the city
engaged a private operator on the basis of a limited period management contract. All investments
in network rehabilitation and construction, as estimated in the DPR, were borne by the city. The
operator is responsible for rehabilitating the network, and achieving performance improvements,
and is remunerated through a fixed management fee, and a performance linked fee. The key
indicators are summarized below.
Category Indicator Sound Acceptable Vulnerable Very Weak
1 Key Indicators
Project
Sustainability through tariff
revenues
User Charge/ Water Supply
Costs > 80% 60% to 80% 40% to 60% < 40%
Project Viability Post tax project IRR >15 % 13% to 15% 10% to 13% <10%
Developer
Dependability of revenue
model
User Charge/ Revenue to
Operator > 80% 60% to 80% 40% to 60% < 40%
Project Viability Post tax equity IRR >20% 15% to 20% 12% to 15% <12%
Revenue risk due to non
performance
% of operator revenue linked
to O & M performance <5% or incentive 5% to 15% 15% to 25% >25%
Capex risk due to non
performance
% of capex reimbursement to
operator linked to
performance <5% or incentive 5% to 10% 10% to 15% >15%
Key for grading
Strengthening PPPs in Urban Water Supply
11 Draft_For Feedback Only
Figure 5 –Key indicators of financial sustainability for a sample city
a) Some key indicators are in the vulnerable category; user charges do not cover operational
costs (column 1). As a result, the city will need to subsidise the operations. However, the
municipal subsidy as a proportion of revenue surplus of the city is at an acceptable level
(column 4).
b) The Developer is vulnerable since a very high proportion of the capital expenditure payments
as well as O & M revenue are linked to performance. The Operator does not have source to
customer responsibility; this increases operational risks.
c) There is no interface with lenders since the project is fully grant funded.
d) Consumers are well placed since tariff levels are low and have not been revised.
Index Tabs Project PreparationRisk AllocationKey IndicatorsSummary
Project
User Charge-----------
Water Supply Costs
Key Indicators related to impact on
Developer Lenders Users ULB
Project IRR post tax
User Charge-----------
Operator Revenue
Equity IRR post tax
% of revenue linked to O & M
performance
% of capexreimbursement
linked to performance
Debt-----------
Revenue Surplus
Minimum DSCR
Average DSCR
Source to customer
responsibility
Average monthly bill for households
Tariff in Rs/KL
Recovery of connection
charges
Own contribution------------------------Revenue Surplus
Project Cost-------------------------
Total Revenue
Municipal Subsidy-------------------------Revenue Surplus
Tariff structure and revision
Grading sheet follows
Strengthening PPPs in Urban Water Supply
12 Draft_For Feedback Only
e) The city too is relatively well placed. Tariff structure is poor and has not been revised.
However, the city is financially in an acceptable position to meet the operating subsidies. Its
share of capital expenditure compared to its revenue surplus is also reasonable.
Strengthening PPPs in Urban Water Supply
13 Draft_For Feedback Only
Poor risk allocation makes the project vulnerable:
a) The development and construction stage risks are poorly allocated. The Operator bears a high
degree of development and construction risk. A very high proportion of capital expenditure
related payments are related to performance.
b) The operator is protected from revenue risks which are borne by the city. Due to the short
term nature of the contract, cost escalation risks are not significant. Future expansions are
clearly not in the scope of the operator, but are capable of being borne by the city.
Figure 6 – Assessment of risk allocation in the PPP structure of a sample city
Index Tabs Risk Allocation
Development and
ConstructionRevenue
Operating Cost Changes Expansions
1. % conversion per year
2. Preparatory period3. Operator
implemented capex4. Capex payments
linked to performance
5. Change in pipe length
6. Change in number of connections
7. Change in % of assets replaced
8. Design changes9. Price escalation
1. Estimated connections
2. Consumption per connection
3. Population growth4. Revenue collection
1. Staff cost escalation2. Power costs3. Chemical costs4. Other repairs and
maintenance5. Raw water costs
1. Residual capacity of bulk supply
2. Design period for distribution network
3. Demand increase4. Increase in
connections5. Increase in service
area6. Increase in network
length
Strengthening PPPs in Urban Water Supply
14 Draft_For Feedback Only
Project preparation is poor which makes the project vulnerable. The assumptions and
methodology related to construction cost estimates, operating cost estimates, operating parameter
specifications are poor and make the project vulnerable. The project is short term in nature and
therefore the assumptions related to demand, revenue, cost escalations and expansion are not
critical. Where applicable, assumptions in these areas are acceptable. The project is fully grant
financed.
Figure 7 – Quality of project preparation in a sample city
Overall, while the city seems to have adequate financial strength to manage the PPP project, the
project has been made vulnerable due to controllable factors – a) poor project preparation, b)
poor risk allocation in construction stage and c) excessive revenue risk to the operator.
Such an assessment, if available at the stage of project approval, would fcailitate the approving
entities to request a rework of risk allocation and a more elaborate project preparation.
Using the Tool
As explained earlier, the assessment can be done at various stages of the project. The tool can
provide inputs to improve project preparation and PPP design. It also is also meant to be used as
an appraisal tool by State and national Government agencies.
Index Tabs Project PreparationRisk AllocationKey IndicatorsSummary
Development and Construction Demand Revenue
Operating Parameters Operating costs Operating cost
escalation
Provision for Expansion Financing
Strengthening PPPs in Urban Water Supply
15 Draft_For Feedback Only
In the project preparation stage, the tool can be used to standardize key assumptions. The
approach for estimating costs and technical preparation can be validated. If the project is termed
weak or vulnerable, the project size can be optimized to reduce the risk.
In the review, appraisal and approval stage, the tool can be used to develop alterative scenarios to
improve project quality. For example various options related to financing mix and tariff
assumption can be undertaken. If required, technical preparation can also be revised to improve
project quality. Approving agencies can also set covenants for grant disbursal, based on
commitments from the city to improve project sustainability.
At the PPP design stage, the tool can help choose the appropriate PPP model so that the risk on
stakeholders is optimized. It can help set appropriate risk sharing. Depending on the strength of
the project, it can help target the right profile of developers. For example, if a project is deemed
vulnerable on operations cost control, developers with strong operations experience may be
preferred. If a project is termed weak on its impact on consumers, developers with a proven track
record of managing civil society (or) with experience in low income countries could be targeted.
Even if the assessment is done after award of the PPP contract, the tool can help identify
vulnerable areas. This can help in strengthening the monitoring and risk mitigation mechanisms.
Review, Appraisal and approval stage
PPP design stage
Post Facto
Project Preparation Stage
• Standardising assumptions
• Validating approach for estimates, technical preparation
• Optimising investments to improve sustainability
• Iterations with various financing mix, tariff assumptions
• Overall assessment of sustainability
• Revising technical preparation
• Setting covenants for disbursal
• Choosing appropriate PPP models and targettingdevelopers matching quality of preparation and financial impact
• Balancing risk allocation and financial impact on stakeholders
• Recognise vulnerabilities
• Design monitoring and risk mitigation mechanisms
Strengthening PPPs in Urban Water Supply
1 Draft_For Feedback Only
Annexure 3, Part I: Performance Targets, Phasing & Linking Performance with
Operator Revenue
Reasons for Addressing the Issue
Cities undertaking water supply PPPs must target significant improvements in service delivery as an
objective and justification for engaging private sector. The private sector partner would be
responsible for delivering on all (pre-determined) performance parameters. Therefore, having clear
performance targets for private partners is imperative to objectively assess the success of the private
partner at the end of any time period of the contract (not only at the end of the contract period). To
enable a regular assessment, time-wise phasing of targets is critical, i.e., what should the private
partner have achieved at the end of the first year or third year of its operations on (for eg.), 24 x 7
supply or on reducing NRW or on any other parameter. Also, if these targets are not realistic, this
discourages bidders and makes enforcement difficult, in either case, a clear recipe for failure of the
PPP. Moreover, once realistic targets are determined and an appropriate phasing is put in place, the
private operator should be incentivised or penalised for the achievement or non-achievement of
these performance targets. This combination of factors results in getting serious operators to be
interested in such projects, and also ensures that the operator brings in its entire expertise to deliver
on the project.
Current Situation
The water supply sector in India has witnessed a limited number of operational PPP projects as yet.
An evaluation of these projects reveals
poor baseline data making the establishment of realistic targets and their phasing difficult
clearly defined performance parameters; but the phasing of the targets either too liberal or too
stringent
Moreover, the performance targets, even for water distribution projects incorporate disproportionate
focus on front ended project construction targets. Further, in terms of incentives and penalties,
linkage of performance to operator revenues is either too weak or too stringent, which resulted in
not too many operators bidding for these projects or disputes during implementation. Very few, if
any, PPP projects has seen a set of balanced performance targets and a clear linkage to operator
revenue, which is significant enough to incentivise operator performance, yet not too stringent.
Analysis
In most Indian cities, improvement of coverage and service delivery entails significant
rehabilitation and augmentation of the network, since existing assets are badly degraded, and / or
inadequate. A large construction component is thus incorporated in to the PPP arrangement. Since a
large investment is proposed ULBs also expect rapid improvement in service standards.
Consequently, while intended to support achievement of service level benchmarks, the construction
component has tended to take centre stage. This has resulted in
Strengthening PPPs in Urban Water Supply
2 Draft_For Feedback Only
Pre-determined construction milestones becoming the first critical benchmark during
implementation
A disregard for the Operator’s expertise and inadequate room for the Operator to suggest
alternative investment approaches which may optimise investments required
It is also evident that a part of the reason for such stringent time frames for construction and
performance delivery is also driven by the need to show significant impact through PPP, to justify
private sector involvement.
Thus, one of the early rehabilitation and O & M PPP projects, Karnataka Urban Water Supply
Improvement Project (KUWASIP), was implemented as a three year contract, in the first 12 months
of which the operator was required to study the system, provide the implementation plan and
complete construction as per the proposed & approved designs. About 30% of the total incentive
available to the operator through the life of the contracts was based on successful completion of this
construction, resulting in providing 24 x 7 water in the 12th
month of the contract. While the
number of connections in each one of the three cities that comprised KUWASIP was not very large,
(a total of 26,045 house service connections across all cities) 100% of the under-ground distribution
pipeline was replaced as part of the system rehabilitation – due, in part, to the poor quality of
existing PE pipes, but also to the stringent time frames to achieve performance standards. Similarly
in the case of Delhi Jal Board’s O & M project in Malviya Nagar (42,000 connections & a
population of 4,00,000), the private operator is given the first 18 months to complete the entire
rehabilitation of the water supply distribution system; and operates the system for a period of eight
years thereafter. In the case of the 25 year concession contract in Aurangabad city in
Maharashtra(about 1,50,000 connections & a population of 12,00,000), the concessionaire is given
barely three years from the date of signing the agreement for completing construction and
rehabilitation of the distribution network for the entire city.
Strengthening PPPs in Urban Water Supply
3 Draft_For Feedback Only
It is evident that cities are focusing disproportionately on rehabilitation and network augmentation,
and front ending these in the initial few years. A shift in focus towards operations and improved
consumer service delivery is required, through ensuring that these are achieved simultaneously with
construction, particularly as these constitute the key justification for engaging in the PPP.
The next significant issue is that of phasing of performance targets. Cities expect private operators
to deliver results (including 24 x 7 water at the requisite pressure; meter, bill and collect over 90%
of water provided for; and establish a redressal system that resolves more than 80% of consumer
complaints within 24 hours, and more) - all virtually immediately upon contract award, and a
limited construction period. As a result, the Operator has little incentive to study the system and
attempt to optimise interventions. He is more likely to over-compensate for performance risk in the
price bid; or seek additional investment for system replacement, in order to meet performance
standards within a short time.
This issue needs to be addressed by first providing relevant and reliable base line data of the project
area, consumers and water supply system, either by (a): bringing in credible, agencies to develop
this on behalf of the cities; or (b): by providing the selected operator an initial period to develop this
baseline data of the system. Once this baseline is credibly established, , PPP contracts need to offer
private operators adequate time to achieve pre-established end objectives. Realistic phasing of
performance targets during rehabilitation is essential, not only for attracting more private operators
to bid for water supply distribution PPPs, but also to ensure that many more PPP projects in the
sector achieve the objectives that are stated to be pursued.
It has been observed that PPP contracts either have very weak linkages between achieving
performance targets and operator revenue; or have very stringent performance targets and related
penalties. Both these extremes are not very conducive to achievement of service delivery objectives.
For eg., in the case of the Nagpur concession, the penalties for not adhering to performance
parameters are capped at 5% of total revenue; moreover, there seems to be virtually guaranteed
revenue for the first five years of the concessionaire’s operations, with very limited service
improvement targets. On the other hand, Mysore provided the operator 12 months to operate and
study the system since accurate baseline data was lacking at the time of bidding. However,
thereafter, the operator was required to meet stringent six-monthly performance targets, and 50% of
the management fees and 70% of the operational costs were liable to be entirely forfeited in case of
non-achievement of targets (i.e., payments were not calibrated to extent of performance).
Neither of the above scenarios is conducive to sustaining well operating PPP projects. In the first
one, the ULB has limited recourse in case of underperformance by operator, whereas in the second
case, disputes are inevitable with adverse impact on consumers.
In contrast to the above, it has been observed that internationally, water supply projects are focussed
on improvement of the consumer service. Given the nature of underground network assets, and poor
data base, utilities have opted to hand over services to the selected private operator, who studies the
existing system over the first year and establishes baseline data on all service parameters. The
operator then evolves an investment plan, based on his experience of operating the system for the
first year; understanding of consumer needs and the utility’s ultimate service delivery objectives;
Strengthening PPPs in Urban Water Supply
4 Draft_For Feedback Only
and within the constraints of resources available to the city. This plan is then implemented over a 3-
4 year period, constantly ensuring that the capital investment is (a) used only if it is imperative and
(b) used in areas where the capital gives the maximum results.
Secondly, while the end-target objective of the service level is established and clear, and since the
operator has established the baseline data, the achievement of these targets are then phased, so as to
provide the private operator adequate time to design and provide the most optimal solutions to
address the gaps in service level.
Table 1 - Phasing of performance standards in an international water PPP contract
Finally, the incentives and penalties are linked to very objective measures/ metrics with respect to
each parameter, and are to a certain extent proportional to achievement of annual targets, i.e., it is
not a situation in which the operator either achieves the target and gets 100% of the incentive or
does not achieve the target and does not get incentive at all (as in the case of the Mysore project). In
fact the incentive works in a manner wherein, if the operator delivers performance above a certain
base level, he is entitled to getting a proportional level of incentive.
Such a structure enables the utility to leverage the expertise and experience of the operator and also
builds in adequate incentives to motivate the operator to deliver on the performance targets.
Suggested Interventions
The interventions proposed seek to strengthen the following key principles:
Greater focus on service delivery performance targets as compared to construction targets
Developing a system that enables objective performance target setting and measurement.
Realistic linkage between operator’s achievement on performance targets with his revenue
Maximising utility of exiting assets, by developing a plan to optimise capital investment,
leveraging private operator’s expertise in water operations, design and engineering
Strengthening PPPs in Urban Water Supply
5 Draft_For Feedback Only
Adequate time for implementation of construction and rehabilitation works to further strengthen
the above objective
It is proposed that MoUD recommend (a) the key performance parameters; (b) the targeted
benchmarks for each one of these performance parameters; (c) the phasing of achievement of these
benchmarks, by the private operator; and finally, (d) the mechanism by which the operator’s
revenue is linked to his performance, for all water PPPs. .
Proposals
It is proposed that cities adopt the MoUD specified service level benchmarks as the
performance targets for all water PPP projects which include water distribution.
Table 2: Proposed Performance Targets for Water Distribution PPPs
Indicator Benchmark
Coverage (percentage of households connected) 100%
Extent of metering (%) 100
Extent of non-revenue water (%) 20%
Continuity of water supply (hours per day)** 24 X 7
Quality of water supplied (%) 100%
Efficiency in addressing customer complaints within 24 hrs
(%)
80%
Efficiency in collection of water supply-related charges (%) 90%
Note 1: ** It is proposed that continuity of supply be measured through availability of minimum pressure (7-
18 m) at pre identified critical points in the distribution system.
Note 2: The operator will not be held accountable for supply less than 135 lpcd if the demand is on lower
side even with 24x7 pressurised supply. However, overall system planning and capacity will be for 135 lpcd.
At the bidding stage, it is proposed that cities establish a) the requisite baseline data1 on all the
service parameters, b) the overall time frame allowed for rehabilitation / augmentation and c)
the intermediate targets within the rehabilitation period.
The private operator validates this baseline data in the initial 9-12 months of the contract. The
validated baseline data is used to revise the intermediate targets, if required.
Subsequent to this, it is proposed that 4-6 years be provided for construction, rehabilitation and
conversion of the entire project area (depending on the size of the project, completion time for
1 for the year immediately preceding the year in which they propose to bid out the PPP project
Strengthening PPPs in Urban Water Supply
6 Draft_For Feedback Only
bulk water facilities, complexity of rehabilitation etc). Providing adequate time for rehabilitation
is necessary to avoid undue focus on rapid construction.
Performance targets may be measured differently during the rehabilitation period as illustrated
below. This difference is necessary till the time the entire service area is converted to
continuous supply.
Table 3: Proposed Performance Targets during Construction / Rehabilitation Period
Indicator Benchmark Performance targets
during rehabilitation
period
Performance targets
during O & M period
(after conversion)
Coverage (percentage of
households connected)
100% Minimum percentage of
connections to be covered
at the end of each year
100% in each year
Extent of metering (%) 100 As above 100% for each year
Extent of non-revenue water (%) 20% Not linked to operator
revenue
Internalised within
operator revenue
Continuity of water supply (hours
per day)**
24 X 7 Percentage of connections
to be covered with
continuous pressurised
supply at the end of each
year
24 X 7 for all
connection in all years
Quality of water supplied (%) 100% 100% of samples 100% of samples
Efficiency in addressing customer
complaints within 24 hrs (%)
80% 80% of complaints related
to surface leaks and billing
errors
80% of all complaints to
be addressed within 24
hours
Efficiency in collection of water
supply-related charges (%)
90% At the current level Internalised within
operator revenue
Since the construction would be phased, it is envisaged that after 18 months or so of the start of
construction, the Operator may convert about 20% of the total number of connections to
continuous supply (24 x 7) connections. This conversion would be the key performance
parameter of the Operator in the rehabilitation period. In a management contract the Operator’s
fees during this period would be linked to progress in conversion2.
2 Please note that the Operator will not directly or through any of its associates, undertake construction; but would
be responsible for tendering and supervising the construction through third part construction contractors procured through a transparent competitive bidding process, as outlined by the respective state Governments. This is detailed further in the Note on Optimising Capital Investments.
Strengthening PPPs in Urban Water Supply
7 Draft_For Feedback Only
The following time-line graphically depicts the preparatory and construction / rehabilitation
periods, in number of months. Please note that the time line presented hereunder is indicative
and each project’s time lines may vary depending on the preparatory period and/or the number
of connections. The ULB would determine at the bid stage the number of months within which
the Operator has to complete the construction / rehabilitation of the entire water supply system.
Preparatory period of 1 year Conversion of 20%
connections to 24x7
0 9 12 16 30 36 42 48 54
Signing of 40% 60% 80% 100%
Contract connections connections
Proposed Fee Structure for a Management Contract: As mentioned (refer Framework Note), in
most cities, Operators will be compensated through a fee arrangement, unrelated to prevailing tariff
/ user charges, since the tariff may not be at cost recovery levels at start of project.
In a management contract, it is proposed that during the Construction / rehabilitation period, the
Operator be paid a Fixed Management Fee and a fee per kilo-litre of water pumped into the
distribution system, (as measured at the Water Treatment Plant(s)). These fees would be as finalised
through the bid process and detailed in the Management Contract.
It is proposed that from a predetermined milestone (say the 30th month onwards in the illustration
above), the Operator would only be paid 90% of his Management Fee, and the balance 10% of his
Management Fee would be based on the actual percentage of user connections that have been
converted to 24 x 7, against the targeted percentage of connections in the same time period. From
the 36th month, this variable component of the Management Fee would increase to 20%; further to
30% from the 42nd month and so on, such that in the last 6 months of rehabilitation / construction
period, a maximum of 50% of the Management Fee is based on performance against the target. The
other component of the fee (per KL of water pumped into the network) would remain the same.
After completion of the rehabilitation / construction period, the Management Contract enters the
operations period, during which the Operator is remunerated based on a Fixed Management Fee and
a fee per kilo-litre of water billed and collected from users. In this fee structure the operator will
bear all the actual costs of raw water, water treatment, including chemicals, energy costs etc. This
fee structure is effective and appropriately balanced, and also ensures that the private operator’s
interests are aligned to that of the ULB. To illustrate, if the NRW is high, the Operator
automatically bears the cost of increased raw water consumption, since he is remunerated only for
the water that is billed and collected.
Linkage between performance and Operator revenue: During the Operations period, up to 50%
of the fixed management fee would be linked to performance targets. The revenue adjustment is
Strengthening PPPs in Urban Water Supply
8 Draft_For Feedback Only
proposed to be calculated based on a weighted average performance on each one of the performance
parameters, against its annual target. The performance parameters and their proposed weightages
are as follows:
Table 4: Illustrative weightages of Performance Parameters during Operations Period
Performance Parameter Weightage
Customer Coverage 25%
Continuous Supply 30%
Water Pressure 30%
Customer complaint redressal 15%
Extent of NRW (%) Revenue adjustment is in-built in the operator remuneration
mechanism
Billing & Collection Revenue adjustment is in-built in the operator remuneration
mechanism
Water Quality Performance below 100% compliance to CPHEEO norms, on
more than “x” occasions, would result in start of termination
process
Based on the achievement, or the lack of it, the operator would be allotted a score between 1 and 5,
where he would be scored 1 if the operator has achieved the target for that parameter, a score of 2 if
the operator has under-achieved the target by, say, 2% and so on, as depicted in the table hereunder.
So a score of 1 is “Excellent”, 2 is “Very good”, 3 is “Good”, 4 is “Fair” and 5 is “Poor”.
Table 5: Operations Period: Rating of Performance
Strengthening PPPs in Urban Water Supply
9 Draft_For Feedback Only
The operator’s annual revenue adjustment would be calculated based on the following formula:
Annual revenue adjustment= Weighted average Composite score - 2 x (Max. Annual revenue adjustment)
3
The revenue adjustment would be to the extent of non-performance, but with a cap of about 50% of
the operator’s Fixed Management Fee.
In the case of a concession, the performance parameters during the Operations Period would be the
same as those outlined above for a Management Contract. The manner of evaluating performance,
the weightage attributed to the performance parameters and rating performance would also remain
the same as in the case of a Management Contract.
However, the concessionaire’s annual revenue adjustment would be calculated as follows:
Annual revenue adjustment = 3-Weighted average Composite score x10% of concessionaire revenue
2
This variance in the mechanism of linking Concessionaire revenue to operating performance,
compared to that in Management Contract is due to the fact that the revenue of the Concessionaire
would be entirely based on a fee per kilo litre of water billed and collected.
Strengthening PPPs in Urban Water Supply
10 Draft_For Feedback Only
Annexure 3, Part II: Optimising Capital Investments
Reasons for Addressing the Issue
Most water PPP contracts in India to date, have been structured as construction and operations &
management contracts, wherein the private sector operator is incentivised to deliver targeted service
levels and operational efficiency. But, none of the performance parameters seem to have included
optimising capital investments. This has resulted in most operators tending to recommend complete
replacement of the under-ground distribution system.
Evidently, on a national scale such complete replacement of networks is neither feasible nor
desirable. Refurbishment of the under-ground distribution network to the extent required to deliver
on the targeted performance parameters is what is sustainable, as well as desirable. This section
addresses this issue in the case of management contracts.
Current Situation
Most water PPP contracts in India, to date, have been accompanied with significant capital
investments to improve water supply assets.3. Given the current status of water supply
infrastructure, it is expected that such large scale investment would be required by almost all cities.
In a context of unreliable data on existing assets and pressure to show results, private operators
have, more often than not, tended to recommend that cities undertake complete replacement of the
water distribution infrastructure to ensure that they can deliver on the performance targets. Thus,
while cities would want to maximise performance with the least capital investment, private
operators are focussed only on achieving the performance targets on each of the parameters,
irrespective of the capital investment required. For a successful PPP to operate, it is imperative to
align the interests of both the parties in such contracts.
Analysis
In most PPPs, (eg.: Mysore, Aurangabad, Khandwa, Patna and others) the Detailed Project Report
(DPR) developed by consultants is not oriented towards PPP. Often, inadequate time and resources
preclude undertaking requisite in-depth surveys to bridge information gaps. Notwithstanding this,
interventions required are identified, and costs estimated on this basis, in order to secure funding.
Projects are bid out based on these DPRs. Given the nature of PPP agreements, once an operator has
won a bid, it then becomes very difficult subsequently to alter the DPR or the associated project
cost. As a result, recommended designs /interventions do not leverage the operator’s expertise
towards optimising capital investments. The current process for procuring MoUD funding, which
requires up-front statement of project costs thus limits the city’s ability to maximize the potential of
the PPP arrangement.
This process also very often results in projects being stalled, as operators indicate the funding
procured to be inadequate to achieve stated performance targets – as, for eg, in Mysore and
3 including, clear water reservoirs, elevated service reservoirs, pumping stations, pipeline network, house service
connections and water meters
Strengthening PPPs in Urban Water Supply
11 Draft_For Feedback Only
Khandwa, where operators have recommended almost 100% replacement of the under-ground
distribution network4. KUWASIP also had a complete replacement of under-ground distribution
network, though the contract had a built-in an incentive to the private operator for reducing the
investment. DJB’s Malviya Nagar contract provides for replacement of 50% of the under-ground
distribution network, though the details of assets to be replaced would be decided by the private
operator in the initial six months when the private operator is responsible for operating the system.
Such a tendency has encouraged private operators to focus on delivering on performance targets and
not on reducing capital investment through painstakingly refurbishing underground assets, rather
than take the easier option of replacing all under-ground assets. Other than the KUWASIP project,
virtually none of the projects has any incentive to the private operator to reduce capital investment.
To a certain extent, the easy availability of grant funds has also made cities insensitive to the issue
of cost optimisation in delivering improved services. Further, in many of the PPP projects, even the
ULB’s contribution towards the project has been sought from the private operator, thereby not
exerting any capital financial burden for the project on the ULB. For eg., in the case of Khandwa,
the city had a UIDSSMT grant approval for about Rs.90 crores and bid out the concession based on
providing this fund to the project and the balance amount to complete the project was to be funded
by the private concessionaire. Therefore, the financial pressure on the ULB to try and reduce capital
investment was also vitiated.
There is thus a strong case for designing PPP processes and structures that enable cities to
effectively leverage private operator expertise to maximise system efficiency while striking an
optimum project cost. Allowing adequate time for implementation is critical to this. As noted
briefly in the earlier section, a practice of phased implementation is observed in international water
projects, wherein
Phase 1 is a preparatory period, typically 9-12 months (depending on the number of
connections or the size of the distribution network) in which the private operator takes over
the water distribution system and validates information regarding gaps in performance of the
distribution assets; consumption patterns; consumer metering and billing systems;
consumer’s paying habits, etc. This is used to develop a project implementation plan for
construction and rehabilitation to deliver on the targeted performance objectives. This plan
is submitted to the city for concurrence and approval.
Phase 2 is an implementation period, again depending on the number of connections under
the contract, wherein the operator implements the agreed project implementation plan and
also begins to deliver on the target performance parameters. This is a relatively longer
period, which enables the operator to maximise refurbishment of the existing system, i.e.,
minimise capital investment. This is usually incentivised by the city.
Phase 3 is the operations phase, where the operator delivers on the city’s and consumer’s
expectations across all aspects of operations. This phase is usually 3-5 years, in order that
sustained improvements may be demonstrated
4 This is also related to unrealistic phasing of performance targets, such that operators are unable to meet them in
the absence of complete system replacement.
Strengthening PPPs in Urban Water Supply
12 Draft_For Feedback Only
Similarly, a study of probably the only private sector water management company in India, JUSCO,
in Jamshedpur, when it was corporatized, shows that JUSCO did not undertake its entire capital
investment program within 12 or 24 months, but did so over a period of 5 years, gradually studying
and replacing or refurbishing the network to deliver the desired results. This resulted both in adding
to the total number of connections, and also, over time, in reducing water tariffs and improving the
operating ratios.
Thus, if a poorly-informed, pre-determined capital investment plan is not forced through in the first
12-24 months of signing the PPP contract, a PPP contract could be structured to achieve capital
optimisation, while achieving the performance targets.
Suggested Areas of Intervention
The process of project preparation and selection of water operator, (refer Note on RfQ for Water
Distribution Projects) are proposed to be revised to address the following issues:
a) MoUD’s evaluation and approval process for PPP projects; and the manner in which the
financial support is disbursed.
b) PPP contracts that enable ULBs to draw upon the private operator’s expertise and build in an
incentive for the private operators to minimise the capital investment required to deliver on the
service level benchmarks.
Proposals
Project preparation: Please refer the Note on Project Preparation, for elaboration of proposals
regarding this aspect.
Strengthening PPPs in Urban Water Supply
13 Draft_For Feedback Only
MoUD funding approval process: It is evident that in the foreseeable future water supply
distribution projects will require grant fund support. Therefore, a distinct approval process for
JnNURM / UIDSSMT funding support for PPP projects is proposed. This approval process will
provide for a 9-12 month period to the private operator to propose his final Project
Implementation Plan, in which interventions identified may differ from those in the DPR
(Please refer the Note on Proposed Process for Funding Water PPP Projects for further
elaboration of proposals under this aspect). This addresses the current reluctance of cities to
modify the approved DPR, and enables the Operator to optimise investments.
Moreover, the Ministry is considering the option of offering the same absolute quantum of grant
for a project (as per initial city DPR project cost), in case the PIP project cost is lower than the
initial city DPR project cost. The city would effectively receive a higher percentage of project
cost as MoUD’s contribution.
Project Implementation & incentive for capital optimisation: The contract should encourage
operators to prioritise focus on performance with construction activities being undertaken to
support this. To optimise investments it is also necessary that the operator (or any direct
associate) does not directly benefit from increased construction scope. Therefore, it is proposed
that the selected private operator should develop the project implementation and investment
plan, but implement it through third party contractors. The Operator would remain responsible
for the design, engineering, project management and construction supervision, but would follow
the ULB’s or the state’s competitive bidding process to procure services of third party
construction contractors to undertake construction activities. The construction cost would be
met by the ULB. The private operator will also be offered a financial incentive to reduce the
project cost from the initial city DPR cost. This could be in the range of up to15% of the saving
that they can bring about, where saving is determined as the difference between the
implemented capital cost and the initial city DPR cost.
It is believed that the combination of the initial city DPR cost; the non-negotiable
specification of key design parameters in the city DPR; third party construction and the
financial incentive for capital cost optimisation should result in optimising capital costs.
Finally, the project implementation should be permitted to be made over a period of 4-6 years,
to ensure that the capital is invested in the most efficient manner, with respect to performance.
Strengthening PPPs in Urban Water Supply
1
Draft_For Feedback Only
Annexure 4: Developing a Request for Proposal (RfQ) for Water Supply
Distribution Projects
Reasons for Addressing the Issue
High bidder interest is one of the indicators of a well-structured and transparent PPP bidding
process. Three key indicators of bidder interest are
1. Number of Expressions of Interest/ Request for Qualification received and shortlisted
2. Number of financial proposals received
3. Diversity of bidder profile consisting of domestic and international bidders
A project that receives adequate number of diverse bids, at the initial stage as well as the
financial proposal stage, indicates that the project profile is attractive, the PPP contract is well
designed and the procurement is on a level playing field.
A bidding process that excludes a certain class of bidders or favours a certain class of bidders
sends a signal of cartelization, especially if the criteria is not consistent with best practices.
Projects that shortlist too few bidders create a perception of lack of transparency and level
playing field. Projects that receive few financial bids send a signal of poor project
preparation.
Repeated instances of such poor bidder participation lead to an impression that Water Sector
PPPs in India are unattractive. This in turn reduces bidder interest to invest in the Indian
market and undertake business development efforts. Civil society opposition also grows as a
perception of cartelization is created.
Therefore, ensuring a wide bidder participation is a key success factor for individual projects
as well as for the Indian water sector as a whole.
Current Situation
The Indian water sector PPPs have shown a mixed record on this indicator. The number of
financial bids has been low in most of the projects (average of 2.58 in 12 projects studied).
Four of these projects adopted a two stage process (an initial Request for Qualification or
shortlisting stage followed by a detailed technical and financial proposal stage). In three of
them, there was adequate interest initially (6 to 9 shortlisted bidders). However, only a few of
the shortlisted bidders eventually submitted a financial proposal. In the fourth project that
adopted a two stage process only a limited number of bidders (3) were shortlisted leading to
limited competition in the financial proposal stage.
Strengthening PPPs in Urban Water Supply
2
Draft_For Feedback Only
City Financial Bids Shortlisted Bidders
KUWASIP 2003-04 4 7
Latur 2006-07 3 6
Mysore 2008 3 NA1
Khandwa 2008 3 NA
Shivpuri 2008 1 NA
Nagpur Full City 2009 2 3
Aurangabad 2009-10 2 9
Malviya Nagar 2012-13 2 NA
Vasant Vihar 2012-13 3 NA
Raipur 2012-13 4 NA
Shimla 2012-13 2 NA
Nangloi 2012-13 2 NA
In 2003-04, the perception regarding Indian water PPPs was poor, as a result of a few failed
PPP projects in the late 1990s (Bangalore, Hyderabad, Pune). In spite of this, the KUWASIP
project in 2004 attracted international bidders and shortlisted seven bidders each of which
was led by an international firm. As compared to this, in three of the recently awarded Delhi
Jal Board projects (2012), two projects received only two bids and the third received three
bids. In Aurangabad (2009-10), nine bidders were shortlisted with a mix of domestic and
international firms. Only two bids were finally received.
Analysis
An analysis of bid documents of water PPP projects indicates the following issues.
1. A few water PPP projects were considered unattractive due to their location/ size of
the city. As a result, these projects received limited bidder interest.
2. Some projects received considerable bidder attention. However, due to poor process
(constant changes in bid documents) and poor design (poor contractual terms), these projects
received only a limited number of financial bids; this is inspite of high initial bidder interest
and atleast in one case, shortlisting of several bidders.
3. Some projects had broad qualification criteria which permitted both contractors with
construction experience and operators with O & M experience to bid. In such cases, the
number of interested bidders, especially domestic bidders was high. However, this
discouraged international operators who felt that their operating experience was not valued;
the international operators also felt that they would not be able to compete with domestic
firms which have a higher risk appetite and who are therefore aggressive in pricing their bids.
1 NA – Refers to single stage bid process.
Strengthening PPPs in Urban Water Supply
3
Draft_For Feedback Only
4. Where projects required the bidders to have O & M experience, the number of bids
was low. Possible reasons are as follows;
a. Domestic firms do not have water sector operating experience. Therefore, they
had to tie up with international firms. The project documents required that the
partners in a consortium should have a minimum equity stake in the project to be
considered for evaluation. This may have discouraged some international firms
that were keen on the project as an operating partner, but were reluctant to invest
and expose themselves to financial as well as legal risks of the project.
b. The experience criteria were specific to each project. For example one project
required the bidders to have experience in constructing a certain size of river
intake, although the asset was only a small fraction of the overall investment. In
another project, the criteria required bidders to have operated a system with very
low Non Revenue Water levels – below 20% to be eligible to apply and
effectively below 15% in order to be shortlisted. In still another project, the
criteria also had subjective elements and required bidders to demonstrate
experience similar in ―complexity and characteristics‖ to the project being bid.
5. Projects also included criteria that are non standard PPP practices. For example, one
project did not consider project experience if the project had been implemented by an
associate company or a subsidiary. PPP projects are normally implemented through Special
Purpose Vehicles. This criteria did not permit the parent company to claim the project
experience. Some projects specified a threshold eligibility. All bidders crossing the threshold
in all evaluation areas would be shortlisted. Some projects specified a minimum combined
score in order to be shortlisted. One project specified that upto seven bidders would be
shortlisted.
In summary, the reasons for poor bidder interest in submitting financial bids can be attributed
to the following reasons:
1. Restrictive and inconsistent criteria
2. Requirement to invest in SPV that discourages some international bidders
3. Poor project structure or project potential
4. Rushed procurement process
Each of these factors successively reduce bidder interest, leading to limited competition. This
of course affects the project but it has a larger impact on the water PPP potential.
International bidders are unable to develop an India strategy since the pre-qualification
criteria are inconsistent. This also affects domestic bidders who are unable to enter into long
term partnerships with experienced international operators. Depending on the criteria for a
particular project, they pursue partnership dialogues within the limited time provided for
bidding. These factors build up a perception that the selection process is inconsistent and non
-transparent; this reduces bidder interest further in the Indian water PPP market.
Strengthening PPPs in Urban Water Supply
4
Draft_For Feedback Only
Observations from Other Infrastructure Sectors
Highway sector
The highway sector in India has seen a large number of projects. The level of participation of
domestic as well as international firms is high. Over the years, the bidding process for
highway projects has been streamlined. A few salient features of national highway bidding
are summarized below:
1. There is a model concession agreement for highway projects. This document was
evolved taking into consideration feedback from bidders and financiers. The revenue model
in the highway sector is also formalized. There is a legally notified toll policy. Projects that
are not viable are provided ―Viability Gap‖ assistance. Together, the toll policy, the viability
gap fund and the model concession agreement reduced commercial risks in a project.
2. The eligibility criteria is standardised across projects. This was initially done through
a standard RFQ document. Since the criteria is uniform across projects, interested domestic
and international bidders were able to develop a business strategy for the Indian highway
sector as a whole. Many bidders also formed medium term partnerships to pursue projects
together.
3. In the recent years, the process has also been more standardised with the introduction
of annual scoring of applicants. Under this process, bidders are evaluated on an annual basis
and are assigned a score. This score is in turn related to the value of the project. A bidder
receiving a particular score is deemed eligible to bid for projects upto a corresponding
threshold size (in terms of Rs crores). When a project is bid out, bidders need to only submit
their score (with other limited documentation). This simplified the qualification process
further.
Electricity distribution
The electricity distribution sector has several parallels with water distribution. In the recent
past, the concept of distribution franchisee2 has gained ground in India. In these projects, the
bidders undertake responsibilities which can be compared to a PPP water distribution project.
The eligibility criteria in the distribution franchisee projects have the following
characteristics:
1. The criteria is broad and is not restrictive. For example, bidders who have experience
in any aspect of the electricity sector value chain (in generation, distribution or transmission)
are eligible.
2 An arrangement under which an electricity distribution company can appoint a franchisee in a specific area, to
carryout electricity distribution on its behalf. While project arrangements vary, generally the franchisee buys
bulk electricity from the distribution company, supplies it to retail customers in the area, bills and collects
revenue. Many contracts include asset rehabilitation also in the responsibility.
Strengthening PPPs in Urban Water Supply
5
Draft_For Feedback Only
2. Additionally, the projects seek experience in handling a large customer base in retail
supply / service delivery, power, gas, water or telecommunication sector.
3. The projects also seek experience in handling a large employee base commensurate
with the proposed project.
Thus, the criteria in the electricity distribution franchisee projects are broad and encourage
both domestic and international bidders.
International Experience in Water Projects
In the year 2009, a study of the PPP experience in water projects in developing countries3 was
published by the World Bank. Among other factors, the study also reviewed the experience of
domestic operators in PPPs. The findings were
1. Local private operators have developed considerably in recent years, serving more
than 40 percent of the market by 2007, and several have performed well.
2. Many of the PPPs classified as broadly successful were implemented with local
private investors that had little or no previous experience in operating water utilities.
3. In Eastern Manila (the Philippines) and Salta (Argentina), partnerships with
experienced operators to transfer operational know-how allowed local operators to bridge the
initial expertise gap over a few years. In other cases, investors with previous experience
in the water sector through the construction, engineering, or consulting businesses proved able
to operate water utilities satisfactorily (as in Brazil, Colombia, and Malaysia). Usually,
those new operators just hired managers and engineers who previously worked for
public utilities in order to have the necessary technical capability (as international operators do
when they enter a new country).
4. This suggests that the need for investors to have strong previous experience in
operating water utilities has probably been overestimated. The benefits from an improved
commercial orientation can be achieved equally through international and local investors—and
the latter have the advantage of knowing more about local needs and culture.
5. Operational and technical experience is important, but it can be obtained through
many means. What counts is not so much whether the local investors have been involved with
operating water utilities before, but whether they can credibly ensure that they have
experienced people in their team to run the utility.
These findings also have relevance to the Indian water PPPs. There are many experienced
domestic construction contractors in the water industry. Some of them also have PPP
3 Marin, Philippe, Public-Private Partnerships for Urban Water Utilities: A Review of Experiences in
Developing Countries. World Bank, 2009
Strengthening PPPs in Urban Water Supply
6
Draft_For Feedback Only
experience in other sectors, such as electricity and highways. Water sector PPPs in India need
to encourage international operator participation (since domestic experience in 24 X 7 is
unavailable at this point in private sector too) and at the same time consider developing the
domestic operator base (which can cater to the diverse size and shape of Indian cities).
Corrective Measures Proposed
Based on the analysis of the current situation, experience from other infrastructure sectors in
India and international water PPP experience, the following corrective measures are
proposed;
1. The criteria for shortlisting bidders may be standardised; critically, it should
emphasise O & M experience in the water sector.
2. Pure operating partnerships between interested bidders and international water
operators, without the necessity of equity investment from water operators, should be
permitted. This will encourage international water operators to participate in Indian water
PPP projects.
3. The bidders should be required to commit staff members with relevant experience (in
continuous water supply operation and in customer management) in water utility operations,
as a part of their proposed project team.
4. Standardised annual scoring of water operators, on the lines of the scoring carried out
for highway PPP projects by the National Highways Authority of India should be explored.
Together, these measures will standardize the criteria and emphasise water utility operating
experience; they will also provide adequate avenues for both domestic bidders and
international operators to participate. Most importantly, standardization of the shortlisting
process will also help interested bidders to gain confidence in the potential of water PPPs in
India and encourage them to develop an India business plan.
These corrective measures are also in line with the principles of the Model RFQ document
proposed by the Government of India.4
1. The model RFQ document specifies standardised criteria applicable across
infrastructure sectors. The Technical Capacity (project experience) and financial capacity
(networth) are examined. Experience in the relevant sector in PPP projects is provided the
maximum weightage. Construction experience in related infrastructure sectors is provided the
least weightage. Construction experience in the relevant sector and PPP experience in related
infrastructure sectors are provided intermediate weightages. The indicative weightages are
provided below.
4 Guidelines of the Ministry of Finance, File No 24(1)/PF-II/2006, Department of Expenditure, dated May 18,
2009
Strengthening PPPs in Urban Water Supply
7
Draft_For Feedback Only
Nature of experience Factor
PPP Experience in water sector 1.25
Construction experience in water sector 1.00
PPP experience in other sectors 1.00
Construction experience in other sectors 0.50
2. The model RFQ document also specifies that O & M experience be evaluated. The O
& M experience may be brought in by one of the equity partners or through a specific O &
M arrangement with an experienced entity; and in case of less complex sectors, through
experienced staff. The stress on O & M experience is relevant for the water sector and the
Model RFQ also provides for a non equity arrangement with the O & M partner.
Proposals
1) A model RFQ recommended by the Government of India may be adopted for the
water sector, with the required sector specific modifications in line with suggestions in the
already existing model RFQ document itself. The proposed adaptations are as below:
i) The Technical capacity will be evaluated with reference to the water sector.
Experience in water sector PPP projects will be given the maximum weightage.
Construction experience in other related infrastructure sectors will be given the
least weightage. Construction experience in water sector and PPP experience in
other related infrastructure sectors will receive intermediate weightage. The
Harmonized List of Infrastructure Sectors notified by Government of India5 will
be used to define related infrastructure sectors.
ii) The project team will be required to have experienced staff members to head
Technical (distribution and leak reduction) and Commercial functions (billing &
collection and customer management).
iii) O & M experience in water sector will be emphasized. The O & M experience
will be measured as experience in operating a continuously pressurised water
distribution system catering to a specified number of connections (to be linked to
the size of the specific project).
iv) The O & M experience may be brought in by the lead member of the consortium.
On the lines of the RFQ document, two further options are proposed to encourage
international and domestic bidders respectively;
5 Harmonized Masterlist of Infrastructure Sub-Sectors as published in Government of India Gazette Serial
Number No. 59, dated April 5, 2013
Strengthening PPPs in Urban Water Supply
8
Draft_For Feedback Only
(1) The O & M experience may be brought in by an O & M partner, who need not
take an equity stake in the project. In this case, a) the O & M partner will be
required to commit key staff with relevant water utility operating experience
as a part of the project team in the Request for Proposal stage and b) the size
of O & M experience will be made higher by a specific factor.
(2) A provision will also be made for the lead member to meet the O & M
experience by inducting experienced staff in the project team. In such a case,
a) the staff members will have to be committed in the RFQ stage itself and b)
the size of prior O & M experience will be made still higher by an additional
factor.
v) Since water sector PPPs are likely to be pure operating contracts without private
investment, setting up a Special Purpose Vehicle for the project need not be
mandatory, but would be based on bidder preference.
vi) All bidders who meet technical capacity, financial capacity and O & M experience
will be shortlisted and will be issued the Request for Proposal document. There
will be no ranking of bidders.
A proposed RfQ, based on the existing model RfQ document (GoI) is attached (refer
Proposed Water RfQ attached. Changes proposed to adopt this to water sector requirements
are highlighted, for easy reference)
2) MoUD will conduct an annual scoring exercise similar to the exercise conducted by the
National Highways Authority of India. Interested bidders will be evaluated based on the
standardised scoring framework and will be assigned scores in technical capacity,
financial capacity and O & M experience. A project proponent will be able to use these
scores directly, in case the bidder is interested to bid for the project.
a) Bidders who are not part of the annual scoring exercise will also be permitted to bid
for a specific project opportunity in order to encourage open competition. In such a
case the project proponent will use the evaluation framework in the Model RFQ for
water sector to evaluate the bidder.
b) Bidders forming a consortium for a specific project may also apply. In such a case
also, the project proponent will use the evaluation framework in the Model RFQ for
water sector to evaluate the consortium.
3) MoUD will create an electronic PPP market place to promote transparency and
information sharing. The annual standardised scoring process will be conducted through
the electronic market place. In addition, the market place will also share information
related to forthcoming PPP projects. MoUD may also create an e-tendering facility for the
use of interested project proponents. The PPP market place will also contain an update of
Strengthening PPPs in Urban Water Supply
9
Draft_For Feedback Only
ongoing PPP projects. It will also provide updates on blacklisted/sanctioned bidders,
similar to that of National Highways Authority of India.
Strengthening PPPs in Urban Water Supply
1
Draft_For Feedback Only
Annexure 5: Proposed Process for Funding of Water PPP Projects
Reason for Addressing the Issue
In most Indian cities, improvement of water supply coverage and service delivery entails
significant investment, since existing assets are badly degraded, and / or inadequate. Cities have
been able to take up such investments only with the help of funding programs such as JNNURM,
or externally aided projects. Under JNNURM / UIDSSMT this funding is only available after
cities prepare a Detailed Project Report (DPR). Cities typically prepare the DPR with the help of
consultants who may not have exposure to designing rehabilitation projects in water distribution
or exposure to operations. Cities also lack reliable baseline data regarding under-ground
distribution assets; and inadequate time and resources are made available consultants, which
preclude undertaking adequate and in-depth surveys to bridge information gaps. As a result,
recommended interventions and derived project costs reflected in the DPR are liable to wide
variations. These, however, form the basis of JnNURM / UIDSSMT approval for project
funding, which cities currently procure in a single stage, prior to selecting an operator.
Given the nature of PPP agreements, once an operator has been selected, it then becomes very
difficult subsequently to alter the approved DPR and the associated project cost. This is despite
the recognition that a competent operator, after running a water supply system, may be better
placed to grasp and recommend interventions necessary to ensure improvements in service
delivery – and the associated capital investment required. The current process for procuring
JnNURM / UIDSSMT grant funding support, which requires up-front statement of project costs
prior to selecting an operator, thereby
limits the ability to leverage the private operator’s expertise;
very often results in projects being stalled, as the funding procured is shown by the
private Operator to be inadequate to achieve stated performance targets.
Suggested Interventions and Proposals
This issue may partly be addressed by designing a process for funding water PPP projects that
(a): enables the ULB to leverage the operator’s design and operation capabilities to arrive at
credible interventions and realistic costs for achieving project objectives1; and also (b):
simultaneously offers a certain extent of flexibility on DPR and project cost.
The broad stages of such a funding process are outlined below.
1 It is simultaneously recognized that checks and balances are required to ensure that the operator’s implementation
plan is in line with the ULB’s objectives. These may be established through specifying non-negotiable system
parameters (regarding pipe material; type of pumps deployed…etc) that may be included in the DPR.
Strengthening PPPs in Urban Water Supply
2
Draft_For Feedback Only
S.No. Process Components Comments
1 Selection of Detailed Project Report (DPR) Consultant
Cities may use standard ToR and scope of work as per MoUD guidelines. MoUD will fund DPR preparation as per guidelines.
2. Submission of DPR by Consultant to ULB ULB passes a resolution to implement on a PPP basis and obtains state govt. concurrence for the same, if required.
3. Submission of DPR to CPHEEO and MoUD. DPR includes (a): justification of project need (b): information required as per revised information checklist (c): Design norms for the project that would not be amenable to change (d): cost estimate and assessment of financial sustainability (f): proposed project structuring for implementation through PPP
Submitted through SLNA, as per applicable JNNURM process
4. CPHEEO and MoUD review the DPR and provide a first approval. Subsequently, ULB will:
Adopt the MoUD recommended RfQ for bidding
Adopt and build upon the MoUD recommended contract formats, making project specific changes as required
Provide the selected private Operator the opportunity to review and amend the DPR (subject to design norms) and prepare a Project Implementation Plan (PIP)
Approval
Approval is based on (a) ULB prepared DPR, as per revised information check-list (b): satisfaction on financial sustainability; an initial sum is released on approval.
5. Selection of Operator by ULB, adopting MoUD recommended model RfQ document
Contract based on MoUD recommended model contract formats
6. Operator operates the water supply system, and prepares the PIP (within 9 – 12 months of signing the contract) which includes:
Review of existing water supply system and operations and confirmation of baseline conditions
investment plan – capex, opex phased project implementation plan
MoUD will provide funding for operation preparation activities (PIP preparation) undertaken by the Operator (including undertaking additional surveys), as per guidelines. The ULB may be required to submit periodic operational reports to MoUD.
Cost savings are being encouraged since a) the Operator will undertake construction through third party contractors and b) there is an explicit financial incentive under the contract to reduce costs from approved DPR figure.
Strengthening PPPs in Urban Water Supply
3
Draft_For Feedback Only
7. ULB submits the PIP with final investment plan and project construction / rehabilitation plan to MoUD.
Submitted through SLNA
The operator will provide revised phased implementation plan, indicating the performance improvement that will be achieved in each time frame.
8. CPHEEO and MoUD review and approve the final PIP and the associated construction / rehabilitation investment plan and fund disbursement plan
MoUD will bear its proportionate share of project cost subject to an increase of 15% from DPR estimates.
An extended time frame for implementation of the investment plan would be more amenable to deliver cost efficient improvements. Subject to guidelines, MoUD will permit such disbursements.
9. Invitation of bids and award of contract to third party contractors based on documents prepared by Operator, in line with procurement guidelines
10. Operator to supervise the construction work and ensure quality and timely completion of contract. Operator will have responsibility for quality and performance.
MoUD will maintain GoI grant share in Rs cr, even if the Operator is able to reduce implemented costs further. This will further incentivize the ULB and Operator to achieve cost savings.
11. Operator to maintain the water supply system and achieve phased performance targets (SLB Benchmarks). Operator revenue is linked to achievement of performance targets.
Strengthening PPPs in Urban Water Supply
1 Draft_For Discussion Only
Annexure 4
Assessing Project Financial Sustainability
Reason for addressing the issue
Financial sustainability of WSS service providers1 specifically refers to the adequacy of revenues
for meeting O&M costs and capital costs.
In conventional operations, the availability of finances is a constraint. To cope with inadequate
finances, cities reduced O & M expenditure to match available finances. Capital investments
were deferred and limited to the extent of grants made available. Service levels and asset quality
deteriorated as a result. Though the system was not financially sustainable, cities maintained a
low level equilibrium in service quality.
Water PPP projects do not have this option. Operators are almost always responsible for a set of
service delivery parameters and to meet the related costs. Operators routinely need to spend on
asset maintenance and operations. Major refurbishment of assets is also required to maintain
service standards. Some PPP contracts require the operator to undertake new capital expenditure
and also to replace assets at the end of their useful life.
Assessing the financial sustainability of water PPP projects is therefore relevant.
Current situation
Out of the five water PPPs studied in detail, atleast three projects have faced financial stress. In
Khandwa and in Mysore, the scope of work for the private operators increased as a result of
detailed surveys undertaken by the operator after the contract was signed. The Khandwa
Municipal Corporation was unable to bear the increase in costs. In Mysore, the increased in
scope of work triggered a dispute regarding whose responsibility it is to undertake the additional
work.
In Latur, the project was based on the premise that the Operator would recover his operating
costs through a newly introduced metering and volumetric tariff. The consumers were unwilling
to pay increased tariff, in the absence of improved services, which the operator found difficult to
provide. The two counterparts to the contract (parastatal and the city) were not financially
capable of absorbing the loss of revenue, if the old tariff were to continue. This and other factors
led to a suspension of the contract.
1 Achieving financial sustainability and recovering costs in bank financed water supply and sanitation projects,
Alexander McPhail, Alian R. Locussol, Chris Perry, 2012, Water Partnerships Programme
Strengthening PPPs in Urban Water Supply
2 Draft_For Discussion Only
In Nagpur and in Aurangabad, the cities have committed to provide an operational subsidy to the
Operator. The cities will also be responsible for future capital investments. Thus, the PPP
projects in the cities focussed only on service delivery improvements; financial sustainability has
not been addressed.
Underlying these issues is the poor financial status of WSS sector. Operating cost recovery is
poor. Tariff is low and is not revised regularly. Most cities rely on grants from State and national
Governments for capital investments. As a result, when they take up a project, even though it is
supported by a grant, they are not financially capable of meeting increased O & M liabilities of
improved and augmented services; or uncertainties. The grants are limited to a share of approved
capital costs and do not meet cost escalations or change in scope. When a PPP project encounters
a situation (loss of revenue, increase in costs or change in scope), an easy resolution is not
possible since the city is not financially strong and is reluctant to revise tariff to meet costs.
Analysis
Availability of adequate finances is therefore a critical requirement in WSS projects. PPP
projects should have clear solutions for meeting
a) Unforeseen cost escalation or change in scope of work
b) Operational costs
c) Future capital investments
All five cities that were studied, attempted PPP projects in the background of poor operational
cost recovery. The following table summarises how the case study projects fared in improving
the financial situation and how the PPP contracts were designed.
Financial Summary of the Five Case Studies
Khandwa Aurangabad Nagpur Latur Mysore
1. Project is concurrent with
tariff revision to improve cost
recovery
Yes Yes Yes Yes No
2. User charges are an integral
part of the revenue model of
the operator
Yes Part user
charges, part
subsidy
Distinct from
user charges Yes Distinct
from user
charges
3. Project eliminates need for
operating cost subsidy from
the city
Yes No, but
subsidy is
capped
No; will
require
operating
subsidy
Yes No
4. Project (pvt. operator)finances
part of initial capital costs 10% 50% 30% of
distribution
network
No No
5. Project design includes a
solution for financing of
change in scope in initial cap-
ex
No No No NA No
Strengthening PPPs in Urban Water Supply
3 Draft_For Discussion Only
6. Project design includes a
solution for financing of
future expansions
No No No No No
Khandwa focussed on achieving long term operational sustainability. The operator’s revenue is
linked to user charges. The Operator was selected based on its tariff requirements to recover
operating costs and privately financed capital costs (10% of project costs). There is no additional
subsidy from the city to the Operator. The project was vulnerable to changes in scope since the
city did not have the financial strength to meet these costs. Future expansions are also
unaddressed.
In Aurangabad, the Operator is compensated partly by user charges (while the tariff continues to
be determined by the ULB) and partly by a predetermined yearly operating subsidy. The
operating subsidy is 25% of the revenue income of the city. As a result, the project carries
significant revenue risks. In addition, as per the contract, the liability for all changes in scope or
for future expansions rests with the city (since the Operator’s revenue is capped) and its ability to
finance these is untested.
In Nagpur, the operator receives a fixed rate or fee per unit of water billed and collected. This
rate is delinked from the water tariff. The water tariff does not meet the entire water supply
costs. The water supply function will continue to be dependent on city finances for sustainability.
The initial capital investments are partly grant financed (70%) and partly operator financed
(30%). The operator recovers its capital investments through the fee. The city is responsible for
any change in scope and for future expansions. Thus the project neither addressed operational
sustainability nor future expansions.
In Latur, the Operator is fully responsible for meeting operating costs through user charges, like
in Khandwa. However, unlike Khandwa, capital investments were not considered in project
preparation. Major capital expenditure was the responsibility of one of the contract counterparts,
the parastatal agency; but the parastatal does not have a revenue base. The second counterpart to
the contract, the city Government, was financially weak and could not support operations or
capital investments. Thus, while the PPP project considered operational sustainability, it ignored
capital investments and future expansions.
In Mysore, the operator is compensated by a fee paid by the city which is higher than current
tariff levels. The gap between the water supply revenue and the operator payments is met from
the general budget of the city. Identified capital investments are fully financed by grants and a
small share from the city Government. However, the contract does not clearly assign
responsibility for changes in scope. This has led to disputes when surveys doubled the length of
distribution network that needed replacement. Further, there is no clear framework for financial
sustainability for the future. The PPP arrangement expects to improve commercial practices, but
after the PPP project, the water supply function will continue to rely on city finances for meeting
Strengthening PPPs in Urban Water Supply
4 Draft_For Discussion Only
deficits in recurring costs as well as to finance future expansions. Thus the project neither
addressed operational sustainability nor future expansions.
All five studied have attempted to improve their WSS financial situation in one way or the other.
While Khandwa and Latur targeted operational sustainability through user charges, they ignored
changes in scope and future expansions. Nagpur and Aurangabad sought to access private
finance partly and improve the cost recovery situation partly. Mysore focussed neither on
operational sustainability nor on future expansions. In addition, poor contract clauses triggered
disputes in Mysore and poor financial condition of the cities created a stalemate in Mysore and
Khandwa.
Corrective Measures
Financial sustainability can be improved only through a carefully planned cost recovery plan (or)
through committed long term support from cities to WSS sector. The required measures are well
known and are part of the municipal and WSS reform agenda. However, these are long term
measures and the current situation will continue to be vulnerable. The best possible solution at
present is to
a) assess whether the financial risks are compatible with a PPP approach,
b) integrate to the extent possible, financial sustainability into PPP design and
c) make stakeholders aware of residual risks so that they can manage them better.
A financial sustainability assessment tool is intended to be developed for this purpose. This tool
will be a diagnostic tool which will assess if the PPP project design ensures availability of
finances for sustained service delivery.
Proposals
The financial sustainability assessment tool is intended to be used at different stages of design:
a) At the pre-feasibility level, when broad project costs are available. The diagnostic tool will
help make a summary assessment of the suitability of the PPP approach, given the costs,
existing tariff and city finances.
b) After a Project Feasibility Report (PFR) has been prepared and financial analysis is available,
a more detailed assessment can be made. At this stage, the ability of the city to meet the
capital and operating subsidies can be assessed. The likely variations in project cost can also
be assessed based on the quality of preparation underlying the feasibility report.
c) The third assessment can be after the PPP structure is finalised and a risk sharing framework
is designed. Normally this will occur after the preparation of the Request for Proposal
document for the selection of private operator. This assessment will indicate if the risk
sharing terms are aggravating the financial risks.
Strengthening PPPs in Urban Water Supply
5 Draft_For Discussion Only
d) This assessment can be regularly updated. For example, after the Operator prepares a detailed
investment plan, the assessment can be updated to reflect the data gathered by the Operator
and the final investment plan.
This tool builds on the financial model that will be prepared as a part of the feasibility report. It
is not a substitute for financial modelling. To illustrate, the financial model will focus on
determining the project returns given a certain set of assumptions. The financial assessment tool
will indicate whether the assumptions are realistic and what is the likelihood of the project being
vulnerable. This tool is not intended as to asses if a) the project is delivering value for money or
b) efficiency in investment planning or c) competitiveness in procurement. Each of these factors
may indirectly impact financial sustainability. But the focus of the tool is on availability of
finances.
Design
The tool will assess financial sustainability with the help of three sets of indicators (Each
indicator will be elaborated in 1 – 2 lines, for easy comprehension).
a) The first set of indicators called Key Indicators, which are quantitative, measure the impact
of the project on the stakeholders and their ability to bear the impact. The tool will assess the
impact on a) project company, b) Operator, c) lender, d) consumer and e) city. There are
seventeen key indicators. Six of these indicators can be calculated at pre-feasibility stage
itself or even earlier, with minimal information. This assessment can be used by the project
proponent as well as funding agencies (like JNNURM).
b) The second set of indicators measure quality of Risk Allocation in PPP design to assess if all
known costs and revenue risks have been addressed. It will assess how the risk allocation
affects the availability of finances at different stages of the project (development and
construction; operations – revenue; operating costs changes and expansions). This
assessment can be carried out after the project structuring has been completed and a draft
Request for Proposal document has been prepared. This assessment can be used by the
project proponent as well as the State Government agencies that may be approving the PPP
approach.
c) The third set of indicators measure the quality of Project Preparation to assess the level of
detail underlying cost and revenue estimates and if assumptions are realistic. Eight areas of
project preparation are assessed. This assessment can be carried out on completion of the
feasibility report and after a financial model is available. This assessment can be used by the
project proponent as well as agencies approving the project report (State Government
agencies, JNNURM).
Each indicator is graded in a four-way colour scheme. Red indicates Weak; Yellow indicates
Vulnerable; blue indicates Acceptable and green indicates Sound; A template provides guidance
on how to grade the indicator as sound or acceptable or vulnerable or weak.
Strengthening PPPs in Urban Water Supply
6 Draft_For Discussion Only
Overall, the tool helps assess
a) Which stakeholder is vulnerable to financial impacts?
b) What is the quality of risk allocation and which stages of the project are vulnerable?
c) Which areas of project preparation are weak; and therefore what are the revenue and cost
risks that stakeholders should be conscious of?
Next steps
1. A grading template has been developed alongwith the tool. While indicative grading has been
provided, it would be useful to test the tool with a set of projects that are currently being
considered for approval. This would help calibrate the grading template. More importantly it
could also highlight additional indicators that may be relevant for financial sustainability
assessment.
2. The financial sustainability tool also needs to be web enabled for easy access and data
aggregation. This step would be taken up once the tool is tested and calibrated with a set of
projects.
Financial Sustainability Assessment Tool
As discussed earlier, the tool has three areas of assessment, a) Key indicators, b) Risk allocation
and c) Project preparation.
Index TabsProject PreparationRisk AllocationKey IndicatorsSummary
Project Preparation Project SustainabilityInstitutional StrengthInstitutional Strength
Institutional StrengthKey Indicators
Project PreparationProject Preparation
Risk AllocationProject Sustainability
Project SustainabilityProject Preparation
What is the financial impact of the project on key stakeholders?
What is their ability to bear the impact?
How are the key project risks allocated?
How does it impact the availability of finances during various stages of the project?
Covers construction risks, revenue risks, operating costs escalations and expansions
What is the level of detail underlying the cost and revenue estimates?
Are the assumptionsrealistic?
Covers construction, revenue, operating parameters , operating ostsand escalation, expansion and financing
Strengthening PPPs in Urban Water Supply
7 Draft_For Discussion Only
Key Indicators
The Key Indicators are organised into five columns each of which measure the impact on a
specific stakeholder. These are in turn divided into three categories. The six indicators marked
“1” are summary indicators and can be calculated at even with minimum information. The four
indicators marked “2” will require additional information, generally available only after a Project
Feasibility Report (PFR) / study and financial modelling have been undertaken. The seven
indicators marked “3” are supplementary indicators. Some of the seven indicators will require
additional information related to risk sharing. This information is available after a Request for
Proposal document has been prepared.
If, for example, Own Contribution/ Revenue Surplus is graded “Vulnerable”, it indicates that the
project is too large to be financed by the city. Thus, at an early stage itself, the city can focus on
optimising the investments or seeking additional source of finance. Alternatively, it can pursue
private investment, if it is confident of reforming tariff framework to ensure cost recovery.
A grading sheet provides guidance to grade each indicator. For example, if “Total User
Charges” as a proportion of “Total Water Supply Operational Costs” (based on the projected
costs after completion for project) is between 40% to 60%, the project is graded “Vulnerable”
since it would rely on operational subsidies from the City Government. Similarly if the project
viability measures in terms of post tax project IRR is less than 10%, the project is termed very
weak; commercial borrowing would be difficult under these circumstances.
Index Tabs Key Indicators
Project
User Charge-----------
Water Supply Costs
Key Indicators related to impact on
Developer Lenders Users ULB
Project IRR post tax
User Charge-----------
Operator Revenue
Equity IRR post tax
% of revenue linked to O & M
performance
% of capexreimbursement
linked to performance
Debt-----------
Revenue Surplus
Minimum DSCR
Average DSCR
Source to customer
responsibility
Average monthly bill for households
Tariff in Rs/KL
Recovery of connection
charges
Own contribution------------------------Revenue Surplus
Project Cost-------------------------
Total Revenue
Municipal Subsidy-------------------------Revenue Surplus
Tariff structure and revision
Grading sheet follows
1 1
1
1 1
12
2
2
23
3
3
3
3
3
3
Strengthening PPPs in Urban Water Supply
8 Draft_For Discussion Only
Risk allocation
Risk allocation in four stages of the project a) development and construction, c) operations
related to revenue, c) operations related to costs and d) expansions is assessed. Indicators are
provided to assess quality of risk allocation pertaining to each stage.
Sound Acceptable Vulnerable Very Weak
1 Key Indicators
Project
Sustainability through
tariff revenues
User Charge/ Water
Supply Costs > 80% 60% to 80% 40% to 60% < 40%
Project Viability Post tax project IRR >15 % 13% to 15% 10% to 13% <10%
Key for grading
Index Tabs Risk Allocation
Development and
ConstructionRevenue
Operating Cost Changes Expansions
1. % conversion per year
2. Preparatory period3. Operator
implemented capex4. Capex payments
linked to performance
5. Change in pipe length
6. Change in number of connections
7. Change in % of assets replaced
8. Design changes9. Price escalation
1. Estimated connections
2. Consumption per connection
3. Population growth4. Revenue collection
1. Staff cost escalation2. Power costs3. Chemical costs4. Other repairs and
maintenance5. Raw water costs
1. Residual capacity of bulk supply
2. Design period for distribution network
3. Demand increase4. Increase in
connections5. Increase in service
area6. Increase in network
length
Strengthening PPPs in Urban Water Supply
9 Draft_For Discussion Only
The grading is qualitative for most parameters; the grading template provides guidance.
Project Preparation
The key assumptions and level of detail underlying project preparation are assessed. Eight areas
of project preparation are assessed. These are a) development and construction assumptions, b)
demand, c) revenue, d) operating parameters, e) operating costs, f) operating cost escalations, g)
provision for expansion and h)financing. A total of fifty seven key indicators related to project
preparation are assessed. For example, under Construction and Development, the following
indicators are assessed.
1. Bulk and treatment assets
2. Estimates of pipe length
3. Estimate of number of connections
4. Percentage of pipes to be replaced
5. Percentage of house service connections to be replaced
6. Percentage of meters to be replaced
7. Escalations
8. Physical contingencies
9. Basis for unit cost estimates
To illustrate, if estimates of pipe length are based only on available surveys (which may be
dated/inaccurate) of road length, then it is graded as vulnerable. If it is based on a detailed
assessment of road length and also includes ongoing road developments, it is graded as
Sound Acceptable Vulnerable Very Weak
2 Risk Allocation
Development and
Construction
Change in scope Change in pipe length
ULB to
compensate
additional costs
Project area
reduced to fit
budget
Not operator
liability, but no
clear solution
Operator
responsibility
Change in number of
connections
ULB to
compensate for
connection
subsidy
Operator to
recover costs
from consumers
Not operator
liability, but no
clear solution
Operator
responsibility
Change in % of
assets replaced
ULB to absorb
validated costs
Operator to
mobilise
finance,
compensated by
deferred
payment
Not operator
liability, but no
clear solution
Operator
responsibility
Key for grading
Strengthening PPPs in Urban Water Supply
10 Draft_For Discussion Only
acceptable. If the pipe length estimates are based on covering the entire the service area based on
the master plan road length, it is termed as sound.
Sound Acceptable Vulnerable Very Weak
3
Project Preparation -
Estimates and
Assumptions
Construction and
Development
Bulk and treatment
assets
Detailed design
available
Feasibility level
estimates
Estimates of pipe
length
Coverage of
entire service
area
Coverage of
entire road
network existing
and ongoing
developments
Based on
available surveys
of road length
Based on
estimated road
length without
physical surveys
Estimate of number
of connections
Based on
physical survey
of households;
allowance for
growth
Based on
physical survey
of households
Based on
current data on
connections; no
physical survey
Key for grading
Strengthening PPPs in Urban Water Supply
11 Draft_For Discussion Only
Sample assessment
This section summarises the financial assessment of one of the case studies. The key indicators
are summarized below.
a) The project is somewhat vulnerable; user charges do not cover operational costs (column 1).
As a result, the city will need to subsidise the operations. However, the municipal subsidy as
a proportion of revenue surplus of the city is at an acceptable level (column 4).
b) The Developer is vulnerable since a very high proportion of the capital expenditure payments
as well as O & M revenue are linked to performance. The Operator does not have source to
customer responsibility; this increases operational risks.
c) There is no interface with lenders since the project is fully grant funded.
d) Consumers are well placed since tariff levels are low and have not been revised.
e) The city too is relatively well placed. Tariff structure is poor and has not been revised.
However, the city is financially in an acceptable position to meet the operating subsidies. Its
share of capital expenditure compared to its revenue surplus is also reasonable.
Going a step further, if we assess the quality of risk allocation, the following conclusions
emerge:
a) The development and construction stage risks are poorly allocated.
b) Due to the short term nature of the contract, risks in other stages are not relevant. Future
expansions are clearly not in the scope of the operator.
Index Tabs Project PreparationRisk AllocationKey IndicatorsSummary
Project
User Charge-----------
Water Supply Costs
Key Indicators related to impact on
Developer Lenders Users ULB
Project IRR post tax
User Charge-----------
Operator Revenue
Equity IRR post tax
% of revenue linked to O & M
performance
% of capexreimbursement
linked to performance
Debt-----------
Revenue Surplus
Minimum DSCR
Average DSCR
Source to customer
responsibility
Average monthly bill for households
Tariff in Rs/KL
Recovery of connection
charges
Own contribution------------------------Revenue Surplus
Project Cost-------------------------
Total Revenue
Municipal Subsidy-------------------------Revenue Surplus
Tariff structure and revision
Grading sheet follows
Strengthening PPPs in Urban Water Supply
12 Draft_For Discussion Only
The project is vulnerable due to poor preparation. The assumptions and methodology related to
construction cost estimates, operating cost estimates, operating parameter specifications are poor
and make the project vulnerable. The project is short term in nature and therefore the
assumptions related to demand, revenue, cost escalations and expansion are not critical. Where
applicable, assumptions in these areas are acceptable. The project is fully grant financed.
Index Tabs Risk Allocation
Development and
ConstructionRevenue
Operating Cost Changes Expansions
1. % conversion per year
2. Preparatory period3. Operator
implemented capex4. Capex payments
linked to performance
5. Change in pipe length
6. Change in number of connections
7. Change in % of assets replaced
8. Design changes9. Price escalation
1. Estimated connections
2. Consumption per connection
3. Population growth4. Revenue collection
1. Staff cost escalation2. Power costs3. Chemical costs4. Other repairs and
maintenance5. Raw water costs
1. Residual capacity of bulk supply
2. Design period for distribution network
3. Demand increase4. Increase in
connections5. Increase in service
area6. Increase in network
length
Index Tabs Project PreparationRisk AllocationKey IndicatorsSummary
Development and Construction Demand Revenue
Operating Parameters Operating costs Operating cost
escalation
Provision for Expansion Financing
Strengthening PPPs in Urban Water Supply
13 Draft_For Discussion Only
Overall, while the city seems to have adequate financial strength to manage the PPP project, the
project has been made vulnerable due to controllable factors – a) poor project preparation, b)
poor risk allocation in construction stage and c) excessive revenue risk to the operator.
If such an assessment were available at the stage of project approval, the approving entities could
have been in a position to request a rework of risk allocation and a more elaborate project
preparation.
Using the tool
As explained earlier, the assessment can be done at various stages of the project. The tool can
provide inputs to improve project preparation and PPP design. It can also be used as an appraisal
tool by State and national Government agencies.
In the project preparation stage, the tool can be used to standardize key assumptions. The
approach for estimating costs and technical preparation can be validated. If the project is termed
weak or vulnerable, the project size can be optimized to reduce the risk.
In the review, appraisal and approval stage, the tool can be used to develop alterative scenarios to
improve project quality. For example various options related to financing mix and tariff
assumption can be undertaken. If required, technical preparation can also be revised to improve
project quality. Approving agencies can also set covenants for grant disbursal, based on
commitments from the city to improve project sustainability.
At the PPP design stage, the tool can help choose the appropriate PPP model so that the risk on
stakeholders is optimized. It can help set appropriate risk sharing. Depending on the strength of
the project, it can help target the right profile of developers. For example, if a project is deemed
vulnerable on operations cost control, developers with strong operations experience may be
preferred. If a project is termed weak on its impact on consumers, developers with a proven track
record of managing civil society (or) with experience in low income countries could be targeted.
Strengthening PPPs in Urban Water Supply
14 Draft_For Discussion Only
Even if the assessment is done after award of the PPP contract, the tool can help identify
vulnerable areas. This can help in strengthening the monitoring and risk mitigation mechanisms.
Review, Appraisal and approval stage
PPP design stage
Post Facto
Project Preparation Stage
• Standardising assumptions
• Validating approach for estimates, technical preparation
• Optimising investments to improve sustainability
• Iterations with various financing mix, tariff assumptions
• Overall assessment of sustainability
• Revising technical preparation
• Setting covenants for disbursal
• Choosing appropriate PPP models and targettingdevelopers matching quality of preparation and financial impact
• Balancing risk allocation and financial impact on stakeholders
• Recognise vulnerabilities
• Design monitoring and risk mitigation mechanisms
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K1 Key Indicators
Project
Due to lack of
project viability
assessment
Sustainability through
tariff revenues
User Charge/ Water
Supply Costs Financial model
Average of atleast five years after
completion of rehabilitation.
Water supply costs will include
the total cost of service delivery
including costs borne by the ULB
directly. > 80% 60% to 80% 40% to 60% < 40% 50% 100%
Project Viability Post tax project IRR Financial model
To include, at the least the entire
debt service period >15 % 13% to 15% 10% to 13% <10% NA Not assessed
Developer
Weakness partly
mitigated by low
financial exposure
Due to lack of
project viability
assessment
Dependability of revenue
model
User Charge/
Revenue to Operator Financial model
Average of atleast five years after
completion of rehabilitation. In
case operator revenue is entirely
through user charges, this ratio
will be 1. > 80% 60% to 80% 40% to 60% < 40% >80% 100%
Project Viability Post tax equity IRR Financial model
To match with the period over
which post tax project IRR is
calculated >20% 15% to 20% 12% to 15% <12% NA Not assessed
Revenue risk due to non
performance
% of operator
revenue linked to O
& M performance
PPP contract or Risk
sharing principles
Percentage of revenue operator
would lose if performance
standards are not met <5% or incentive 5% to 15% 15% to 25% >25%
About 60% of the
fee is performance
linked and
therefore revenue
risk is very high
Operator only loses
concession period;
Small penalties for
non performance
Capex risk due to non
performance
% of capex
reimbursement to
operator linked to
performance
PPP contract or Risk
sharing principles
Percentage of capital cost
expenditure that operator would
not be able to recover if
performance standards are not
met (relevant where ULB finances
capital expenditure partly or fully) <5% or incentive 5% to 10% 10% to 15% >15%
Several guarantees,
securities and
liability, combining
to exceed 15% <5%
Unity of command
Source to consumer
responsibility Project concept
Does the operator have
responsibility over the entire
value chain of water supply? Is
the operator responsible for the
entire city?
Source to consumer
responsibility
Treatment to
consumer
responsibility
Responsibility starts
ex treatment
Multiple
operators;
Limited
responsibility
Responsibility is ex
treatment;
Fragmented
institutional
structure at city
River intake to
customer service
Lenders Not applicable Not assessed
Size of borrowing
Debt/ ULB Revenue
Surplus
ULB's financial
statements
Relevant when ULB is financing
capital expenditure through
borrowings. To consider
outstanding debt as well as
incremental borrowing for
project. < 2.5 times 2.5 to 7 times 7 to 10 times > 10 times
Key for grading
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
Ability to service debt Min DSCR
Financial model or
projections of ULB
finances
Calculated from ULB's projected
finances if ULB is the borrower.
Calculated from project's
projected finances if the
borrowing is through the project
company > 1.25 1.1 to 1.25 1 to 1.1 <1
Ability to service debt Average DSCR
Financial model or
projections of ULB
finances
Calculated from ULB's projected
finances if ULB is the borrower.
Calculated from project's
projected finances if the
borrowing is through the project
company >1.5 1.25 to 1.5 1.1 to 1.25 < 1.1
UsersOn the borderline of
vulnerability
Affordability
Average monthly bill
for households
Tariff schedule,
Consumption
assumptions
To consider bill for domestic
customers <150 per month
150 to 250 per
month
250 to 350 per
month > 350 per monthRoughly 150 per
month
Entry costs Connection Charges Tariff structure
To consider recovery mechanism
for providing connections to
domestic customers
Recovered in
installments
Capitalised or
subsidised
Recovered upfront,
with subsidies for
poor
Full cost
recovered
upfront
To recheck. There
was no special
connection cost
design
Affordability Tariff/ KL Tariff structure To consider domestic customers <7.5 7.5 to 12.5 12.5 to 17.5 >17.5 6.81
ULB/ Government
Agency
Tariff structure
introduces a degree
of vulnerability
Project is large, but
mitigated by ring
fenced model
Size of project - Capex
Own Contribution/
Revenue surplus ULB finances
Ratio of ULB contribution to
capital expenditure (if any) to
current revenue surplus of the
ULB < 1.5 1.5 to 2.5 2.5 to 4 >4 0.69 Estimate
Size of project
Project Cost/ Total
Revenue ULB finances < 1.5 1.5 to 2.5 2.5 to 4 >4 1.82 Estimate
Sustainability of O & M
Municipal Subsidy/
Revenue Surplus
ULB finances, Financial
model
Annual operating subsidies if any,
by the ULB to the project. The
subsidy would also include costs
that are being borne directly by
the ULB. To be calculated as an
average of first five years of
operations after rehabilitation. < 0.25 0.25 to 0.5 0.5 to 0.75 > 0.75
Pre Project status;
would improve
with private sector
billing
Municipality only
pays for bad debt
remaining
uncollected
Sustainability of O & M Tariff model Tariff structure
Increasing block
volumetric tariff,
automatically adjusted
for power, salary cost
and WPI changes; Reset
periodically to reflect
allowed costs
Increasing block
volumetric tariff
automatically
adjusted for power
and WPI
Volumetric tariff,
with predetermined
escalation rates
Non volumetric
tariff or tariff
structure
without any
specified
adjustments
Tariff revisions are
not periodic,
though later on the
State Government
introduced such a
framework
Periodic WPI linked
revision + power
cost adjustment
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
2 Risk Allocation
Development and
Construction
Risks in implementation
% Conversion of
connections to 24 X 7
each year
Detailed Project
Report, Contract <25% 25% to 33% 33% to 40% >40%
Preparatory period
Detailed Project
Report, Contract
Consider the time the Operator
has after signing of the contract
till start of rehabilitation activities >1 year 9 months to 1 year 6 to 9 months < 6 months
Operator
implemented capex/
Total capex
Detailed Project
Report, Contract
Consider all parallel investments
in the water supply system for the
entire city > 90% 75% to 90% 50% to 75% < 50%
% capex
reimbursement
linked to
performance
Detailed Project
Report, Contract
Percentage of capital cost
expenditure that operator would
not be able to recover if
performance standards are not
met (relevant where ULB finances
capital expenditure partly or fully) <5% 5% to 10% 10% to 15% >15%
Change in scope
Change in pipe
length Contract
Assess the methodology in the
contract for accommodating
changes in distribution network
length
ULB to compensate
additional costs
Project area
reduced to fit
budget
Not operator
liability, but no clear
solution
Operator
responsibility
Change in number of
connections Contract
Assess the methodology in the
contract for accommodating cost
increase due to increase in
number of connections
ULB to compensate for
connection subsidy
Operator to recover
costs from
consumers
Not operator
liability, but no clear
solution
Operator
responsibility
Change in % of
assets replaced Contract
If there is an increase in the
percentage of assets that require
replacement, how does the
contract allocate responsibility?
ULB to absorb validated
costs
Operator to
mobilise finance,
compensated by
deferred payment
Not operator
liability, but no clear
solution
Operator
responsibility
Design changes Contract
ULB responsibility if due
to external factors
Operator
responsibility
Price Changes Price escalation Contract
Componentwise
adjustment of capital
cost items
Adjustment linked
to a few large
components of
capital costs
General WPI linked
adjustment
Operator
responsibility
Revenue Not applicable
Number of
connections Contract
Is the operator compensation
adjusted to reflect change in the
number of connections?
Operator compensation
is adjusted Operator bears risk Not applicable
Consumption per
month per
connection Contract
Impact of variation in
consumption assumptions
Two part revenue
model for operator that
protects fixed costs Operator bears risk Not applicable
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
Population growth Contract
Impact of variation in population
growth as compared to
assumptions
Two part revenue
model for operator that
protects fixed costs Operator bears risk Not applicable
Revenue collection/
disconnection
procedures Contract
Do the disconnection procedures
protect operator revenue?
Operator bears risk of
collection; ULB agrees
to disconnect defaulting
customers or
compensate Operator
Operator bears risk;
authorised to
disconnect
defaulting
customers
Operator bears the
risk, disconnection
procedures are not
enforceable or are
prolonged
Operator bears
the risk; no clear
disconnection
procedure
There is a marginal
risk. Operator
revenue is not
directly affected by
poor collections. A
part of the fee is
linked to improved
revenue
Operating Cost changes Not applicable
Staff cost escalation Contract
How is the operator revenue
adjusted to reflect change in staff
costs during the contract
duration?
Costs are adjusted
to reflect consumer
price index
Part of overall cost
adjustment
formulae
No mechanism
for adjusting
costs related to
staffNot applicable;
Short term contract
Power costs Contract
How is the operator revenue
adjsuted to reflect changes in
power tariff?
Costs are adjusted
to reflect actual
power tariff
Costs are adjusted
based on overall
formulae
Operator bears
the riskNot applicable;
Costs borne by ULB
Chemical Costs Contract
How is the operator revenue
adjsuted to reflect changes in
chemical costs?
Costs are linked to
specific indices
Costs are adjusted
based on overall
formulae
Operator bears
the riskNot applicable;
Costs borne by ULB
Other repairs and
maintenance Contract
How is the operator revenue
adjsuted to reflect other price
changes?
Costs are linked to
wholesale price
index or other
appropriate indices
Costs are adjusted
based on overall
formulae
Operator bears
the risk
Short term
contract; Low level
of risk
Raw water costs Contract
How is the operator revenue
adjsuted to reflect chages in cost
of raw water?
Costs are linked to
actual raw water
tariff
No specific
adjustments
Operator bears
the risk Not applicable
ExpansionsNot applicable;
short term contract
Residual capacity for
bulk supply and bulk
supply assets
Detailed Project
Report
Do the existing and planned bulk
water production assets (offtake,
transmission lines, treatment
plants etc) have sufficient
capacity to outlast the contract
duration?
> 1.25 times contract
duration
Matches contract
duration
Less than contract
duration
Less than debt
tenure
Short term
contract; Bulk
supply addition is
parallelly in
progress
Design period for
distribution network
Detailed Project
Report, Contract
Is the distribution network being
planned to cover existing and
future requirements?
Coverage of entire
service area
Coverage of entire
existing road
network and
ongoing land
developments
Based on available
surveys of road
length
Based on
estimated road
length without
physical surveysNot applicable;
short term contract
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
Demand increase Contract
If the consumption levels increase
beyond assumptions, does the
contract enable additional
investments in bulk water supply?
ULB responsible for
incremental
investments
Financing in line
with initial
formulae for capex
financing
Operator's
responsibility
exceeds initial
capex financing
formulae
No clear
mechanism for
financingNot applicable;
short term contract
Increase in
connections Contract
How does the contract deal with
change an increase in the number
of connections?
ULB responsible for
incremental
investments
Financing in line
with initial
formulae for capex
financing
Operator's
responsibility
exceeds initial
capex financing
formulae
No clear
mechanism for
financingNot applicable;
short term contract
Increase in service
area Contract
How does the contract deal with
expansion in service area during
the term of the contract?
ULB responsible for
incremental
investments
Financing in line
with initial
formulae for capex
financing
Operator's
responsibility
exceeds initial
capex financing
formulae
No clear
mechanism for
financingNot applicable;
short term contract
Increase in network
length Contract
How does the contract provide
for expanding network within the
initial service area?
ULB responsible for
incremental
investments
Financing in line
with initial
formulae for capex
financing
Operator's
responsibility
exceeds initial
capex financing
formulae
No clear
mechanism for
financingNot applicable;
short term contract
3
Estimates and
Assumptions
Construction and
Development
Bulk and treatment
assets
Detailed Project
Report
Basis for calculation of capital
costs for bulk water assets
Detailed design
available
Feasibility level
estimates Not applicable
Estimates of pipe
length
Detailed Project
Report
Basis for estimating the length of
distribution network
Coverage of entire
service area
Coverage of entire
road network
existing and
ongoing
developments
Based on available
surveys of road
length
Based on
estimated road
length without
physical surveys
Estimate of number
of connections
Detailed Project
Report
Basis for estimating the number
of household connections
Based on physical
survey of households;
allowance for growth
Based on physical
survey of
households
Based on current
data on
connections; no
physical survey
% of pipes to be
replaced
Detailed Project
Report
Basis for identifying the
percentage of pipes that are
proposed to be replaced
Conservative estimate
based on sample
physical assessment of
condition
Estimate based on
sample physical
assessment; no
allowance for
contingencies
Assessment based
on age and material
No basis for
estimates
% of household
service connections
to be replaced
Detailed Project
Report
Basis for estimating the
percentage of connections that
need replacement
Conservative estimate
based on physical
assessment of condition
Estimate based on
physical
assessment; no
allowance for
contingencies
No basis for
estimates
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
% new meters
Detailed Project
Report Proposal for replacing meters
Conservative estimate
based on physical
assessment of condition
and age
Estimate based on
physical condition
and age; no
allowance for
contingencies
Estimate based on
meter reading
records; no
allowance for
contingencies
No basis for
estimates
Price escalations
Detailed Project
Report/ Financial
model
Estimated based on
historical trends
No strong basis
for estimatesNo data available
to assess
Physical
contingencies
Detailed Project
Report
Specific assumption
relecting each asset
category and the
methodology of
detailed project report
Past experience in
contracts
General assumption
cutting across asset
categoriesNo data available
to assess
Basis for unit cost
estimates
Detailed Project
Report
Do the unit cost estimates reflect
market situation?
Schedule of Rates
adjusted for market
situation
Schedule of rates
with key items
adjusted for market
situation
Schedule of Rates
with general
inflation applied
Outdated
Schedule of
RatesNo data available
to assess
Demand
Population estimates
Detailed Project
Report
Are the Estimates of population
realistic?
Based on census data;
adjusted with a recent
physical consumer
survey
Based on census
data; adjusted with
annual growth
rates
Outdated census
data
Estimated
connections
Detailed Project
Report
Are the estimates of number of
connections based on verified
data?
Based on physical
survey of households;
allowance for growth
Based on physical
survey of
households
Based on current
data on
connections; no
physical survey
People per
connection
Detailed Project
Report
Based on consumer
survey.
Based on census
data, verified with
sample consumer
survey.
Assumptions - 4 to 6
per connection
Assumption - <
4 per
connection
Consumption per
person
Detailed Project
Report
< 100 lpcd for revenue
purposes or based on
reliable metering data
100 to 120 lpcd for
revenue purposes
or based on sample
household survey
120 to 150 lpcd for
revenue purposes
> 150 lpcd for
revenue
purposes
Consumption per
month per
connection
Detailed Project
Report
< 15 m3 or based on
reliable metering data
15-20 m3 or based
on sample
household survey 20-25 m3 >25 m3
Population growth
Detailed Project
Report
What is the basis for assumptions
underlying population
projections?
Conservative as
compared to past
trends for revenue
purposes
In line with past
trends
Not in line with past
trends
Revenue
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
Tariff Structure Tariff Structure
Does the existing tariff structure
progressive and protect the
revenue concern of the project.
Increasing block
volumetric tariff
Simple volumetirc
tariff
Non volumetric
tariff or tariff
structure
without any
specified
adjustments
Average tariff/ KL
Is the tariff structure likely to
generate citizen opposition? <7.5 7.5 to 12.5 12.5 to 17.5 >17.5
Average monthly
bill/house Tariff Structure
Is the average monthly bill likely
to generate citizen opposition? <150 per month
150 to 250 per
month
250 to 350 per
month > 350 per month
Connection Charge/
Connection Tariff Structure
Are there adequate mechanisms
to ensure that connection costs
don’t discourage citizens from
taking formal connections?
Recovered in
installments
Capitalised or
subsidised
Recovered upfront,
with subsidies for
poor
Full cost
recovered
upfront
Tariff holiday on
conversion Contract
Does the existing tariff structure
progressive and protect the
revenue concern of the project. > 6 Months 3 to 6 months 1 to 3 months None
Collection efficiency Contract
Are the collection efficiency
assumptions realistic? <90% 90% to 95% 95% to 98% >98%
Tariff escalation
method Tariff Structure
Does the tariff revision
mechanism provide adequate
protection against cost increases?
Automatically adjusted
for power, salary cost
and WPI changes; Reset
periodically to reflect
allowed costs
Automatically
adjusted for power
and WPI
Predetermined
escalation rates
No specified
adjustments
% Revenue from bulk
users Financial model
Is the project too dependent on
revenues from bulk users?
% below poverty line
connections
Detailed Project
Report
Does the service area have a
disproportionate number of
households below poverty line,
requiring special tariff and supply
arrangements?
Operating Parameters
Pumping efficiency
Detailed Project
Report, Financial
model
Are the pumping efficiencies
assumed pratically achievable?
As per manufacturer
specs; allowance for
non optimal utilisation
As per
manufacturer
specs; no allowance
for non optimal
utilisation
Unrealistic
efficiency
assumptions
Change in pumping
efficiency Contract
Do the operating cost projections
provide for normal decrease in
pumping efficiency over the life of
the contract?
Decreasing in line with
age as per manufacture
specs
Decreasing, but
better than
manufacturer specs
Contant
efficiency
assumption
Real Losses
Detailed Project
Report, Financial
model, Contract
Does the contractual target for
real losses increase financial risk
on the project? >25% 20% to 25% 15% to 20% <15%
To be determined after sample assessments
To be determined after sample assessments
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
Apparent Losses
Detailed Project
Report, Financial
model, Contract
Does the contractual target for
apparent losses increase financial
risk on the project? >10% 5% to 10% 3% to 5% <3%
Staff/ Connection Financial model
Does the contract make realistic
projections of the number of staff
required for operations >6 / connection
4 to 6 per
connection
3 to 4 per
connection
< 3 per
connection
% of municipal staff
moved to the project Contract
Does the contract expect that PPP
operations will be carried out by
existing ULB staff? <10 % 10% to 30% 30% to 70% > 70%
Operating Costs
Specific power
consumption
Specific chemical
consumption
Detailed Project
Report
Calculated based
on raw water
characteristics No clear calculation
Total staff
Detailed Project
Report
Does the Detailed Project Report
have an accetable manning
shcedule?
Calculated based
on asset profile,
service
requirements and a
detailed manning
shcedule
Based on staff/
connection
thumb rules
Average staff salary
Detailed Project
Report
Are the salary projections
realistic?
Based on market
conditions
Based on thumb
rules
Repairs and
maintenance costs
Detailed Project
Report
Do the operating cost projections
provide for adequate repairs and
maintenance?
Based on asset
profile and asset
specific
requirements
Based on generally
accepted
percentages
Periodic replacement Contract
Does the contract envisage
investmets to replace assets at
the end of their useful life?
Based on
manufacturer
recommendations No clear proposals
Raw water costs
Detailed Project
Report
Have raw water costs been
correctly estimated?
Based on unit rates
and estimated
requirements
Based on existing
payment records
Cost of international
staff in the
rehabilitation period Financial model
Does the financial model provide
for costs of intenational water
utility staff who may be required
to be deployed during the
rehabilitation period?
Calculated based
on a clear manning
estimate for expat
staff No clear provisions
Cost of third party
auditors Financial model
Does the financial model provide
for costs of independent third
party monitoring agencies/
auditors? Provided Not provided
Covered in pumping efficiency as above
Source of data
Remarks/ Suggested calculation
methodology Sound Acceptable Vulnerable Very Weak Sample M Sample K
Key for grading
Office space and
administration Financial model
Does the financial model reflect
the costs of setting up new office
space? Provided Not provided
Software and
licenses Financial model
Does the financial model include
the costs of procuring utility
systems, software and licenses? Provided Not provided
Operating cost
escalation
Staff cost escalation >10% 8% to 10% 6% to 8% <6%
Power costs >4% 4% to 6% 2% to 4% <2%
Chemical Costs
Other repairs and
maintenance
Raw water costs Higher than trends
Based on historical
trends
General inflation >7% 5% to 7% 3% to 5% <3%
Provision for expansion
Demand increase
Detailed Project
Report
Assumes a
normative increase
in consumption per
capita over time
No clear
assumptions
Increase in
connections
Detailed Project
Report
In line with
population growth
No clear
assumptions
Increase in serviced
area
Detailed Project
Report
In line with land
use density
No clear
assumptions
Increase in network
length
Detailed Project
Report
In line with service
area
No clear
assumptions
Financing
Debt:Equity Ratio Financial model < 1:1 Debt 40% to 60% Debt 60% to 70% Debt > 70%
Interest Rate Financial model
Higher than 3% of base
rate
Within 2% to 3% of
base rate
Within 2% of base
rate
At or below
base rate
Term of the loan Financial model < 9 years 9 to 12 years 12 to 15 years > 15 years
Tax assumptions Financial model
MAT and IT at
existing rates
MAT not
considered
Depreciation
assumptions Financial model
Asset specific
allowance as per IT
and Companies Act
General
depreciation
rate
Working capital
allowance Financial model Considered Not considered
Financial model
Are the cost escalation
assumptions made in the financial
model realistic?
Are the financing assumptions
realistic?