the pentagon by qwynton b. evans jef benigno steven brooks

11
The Pentagon By Qwynton B. Evans Jef Benigno Steven Brooks

Upload: douglas-gervais-martin

Post on 29-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

The Pentagon

ByQwynton B. Evans

Jef BenignoSteven Brooks

History of the Pentagon

• The Pentagon is the headquarters of the United States Department of Defense. It was dedicated on January 15, 1943 and it is the world's largest office building.

• It was built from 680,000 tons of sand and gravel dredged from the nearby Potomac River that were processed into 435,000 cubic yards (330,000 m³) of concrete and molded into the pentagon shape. Very little steel was used in its design due to the needs of the war effort.

• At five acres (20,000 m²), the central plaza in the Pentagon is the largest "no-salute, no-cover" area (where hats need not be worn and salutes are not required) in the world. The open space in the center is informally known as ground zero, a nickname originating during the Cold War when it was thought of as the most likely target of a nuclear missile. At the center of the plaza is the "Ground Zero Cafe," a snack bar. One 'legend' states that due to the heavy traffic into this cafe (evidenced by satellite imagery), Soviet intelligence concluded it was a center for highly secret research.

Graph of Participation

90

90

80

85

100

95

94

92

100

91

90

90

team grade

power point

participate

Reading

Mike

Jeff

Steven

Qwynton

Facts and Figures of Pentagon

• Prime contract awarded 11 August 1941 • Mechanical engineering contract awarded 3 September

1941 • Construction began 11 September 1941 • Grading contract awarded 24 September 1941 • First occupants move in 29 April 1942 • Construction completed 15 January 1943 • Total Land Area (acres) 583 • Government Owned (acres) 296 • Purchased or condemned (acres) 287 • Cost $2,245,000 • Area covered by Pentagon bldg (acres) 29

Fact and Figures of “The Pentagon

• Area of center court (acres) 5 • Area of heating and refrigeration plant (acres) 1 • Area of sewage structures (acres) 1 • Access highways built (miles) 30 • Overpasses and bridges built 21 • Parking space (acres) 67 • Capacity (vehicles) 8,770 • Cost of building $49,600,000 • Total cost of project (including outside facilities) $83,000,000 • Gross floor area (sq. ft.) 6,636,360 • Net space for offices, concessions and storage (sq. ft.) 3,705,793 • Cubic contents (cu. ft.) 77,015,000

Bibliography

• “Pentagon Encyclopedia” 2 May 2005 http://searchlocolcolorart.com/search/encyclopedia/the_pentagon

• “HOUSDOD The Pentagon” 3 May 2005 http://defenselink.mil/pubs/pentagon

Graph Of ParticipationName Team

Score

Math

Report

Score

Speech

Score

Overall

Score

Qwynton 100% 100% 100% 100%

Steven 85% 90% 80% 90%

Mike 100% 90% 90% 90%

Jeff B 100% 90% 92% 94%

TEAM PAGE Team Number: __

Role Student Task

ReaderOverview and

Content of the Presentation

HistorianHistory of the

Building

AnalystGeometric Analysis of the

Building

BibliographerBibliography of the Project

Introduction

Task

Process

Resources

Evaluation

Conclusion

Web Quest

Contact Info

Mathematical Report Rubric

Beginning Average Good ExcellentPossible

Point

Self

Assessment

Teacher

Assessment

IntroductionNot focused

Focused but irrelevant

Focused

too long

Presents a concise

lead-in

info

4

ResearchDoes not

present

With inadequacy

With adequacy

Presents

main theme

with excellence

4

ProcedureNot

sequentialSome steps

Most

stepsunderstandable

Presents

easy to

follow sequence

4

Results Little SomeMostly complete

Data and figure

complete4

Conclusion Little Some Mostly

Presents

main theme

4

Introduction

Task

Process

Resources

Evaluation

Conclusion

Web Quest

Contact Info

Oral Presentation Rubric

Beginning Average Good ExcellentPossible

Point

Self

Assessment

Teacher

Assessment

Content Little Some Mostly

Speech is clear &

focused4

Organization Little Some Mostly

Effective beginn, main, end

4

Language Little Some Mostly

Words are specific &

accurate

4

Delivery Little Some Mostly

Good eye contact,

speed,

volume

4

Introduction

Task

Process

Resources

Evaluation

Conclusion

Web Quest

Contact Info

Project Scoring System

NameTeam Score

Math Report Score

Speech Score

Overall Score

Qwynton 99 99 90 96Steven 99 99 90 96

Mike 99 99 90 96

Jeff B 99 99 90 96

Introduction

Task

Process

Resources

Evaluation

Conclusion

Web Quest

Contact Info