the project management process - week 9 performance management

94
Project Management Project Management 9. Performance Management 9. Performance Management

Post on 18-Oct-2014

30.888 views

Category:

Business


2 download

DESCRIPTION

How to monitor your project once it's underway. Is it going accoridng to plan?

TRANSCRIPT

Page 1: The Project Management Process - Week 9   Performance Management

Project ManagementProject Management9. Performance Management9. Performance Management

Page 2: The Project Management Process - Week 9   Performance Management

Week 9

Page 3: The Project Management Process - Week 9   Performance Management

Performance management

Page 4: The Project Management Process - Week 9   Performance Management

Once you have selected a project

Page 5: The Project Management Process - Week 9   Performance Management

Once you have selected a project

And planned it

Page 6: The Project Management Process - Week 9   Performance Management

Once you have selected a project

And planned it

And hired the team

Page 7: The Project Management Process - Week 9   Performance Management

Once you have selected a project

And planned it

And hired the team

And started the work

Page 8: The Project Management Process - Week 9   Performance Management

Once you have selected a project

And planned it

And hired the team

And started the work

How do you stay on track?

Page 9: The Project Management Process - Week 9   Performance Management

How do you even know if you are progressing to plan?

Page 10: The Project Management Process - Week 9   Performance Management

Gray & Larson, 2006, Ch 13.

Page 11: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 12: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System?What is a Project Monitoring System?

Page 13: The Project Management Process - Week 9   Performance Management

It involves determining what data to collect, how, when an who will collect the data; analysis of the data; and reporting progress

It involves determining what data to collect, how, when an who will collect the data; analysis of the data; and reporting progress

Monitoring SystemMonitoring System

GatherGather AnalyseAnalyse ReportReport

Page 14: The Project Management Process - Week 9   Performance Management

You need to know what information is needed to satisfy you and your stakeholders.

Page 15: The Project Management Process - Week 9   Performance Management

Think about the Information System Structure

Page 16: The Project Management Process - Week 9   Performance Management

What data are collected?

Page 17: The Project Management Process - Week 9   Performance Management

current status of project (schedule and cost)

current status of project (schedule and cost)

remaining cost to compete project

remaining cost to compete project

date that project will be complete

date that project will be complete

potential problems to be addressed now

potential problems to be addressed now

out-of-control activities requiring intervention

out-of-control activities requiring intervention

Cost and/or schedule overruns & their reasons

Cost and/or schedule overruns & their reasons

Forecasting overruns at time of completion

Forecasting overruns at time of completion

What data are collected?What data are collected?

Page 18: The Project Management Process - Week 9   Performance Management

Collecting data and analysis

who will collect project data?

how will data be collected?

when will the data be collected?

who will compile and analyze the data?

who will receive the reports?

how will the reports be transmitted?

when will the reports be distributed?

Photo by germanium

Page 19: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 20: The Project Management Process - Week 9   Performance Management

Progress Report FormatProgress since last report

Current status of project

ScheduleCostScope

Problems and issues since last report

Actions and resolution of earlier problems

New variances and problems identified

Corrective action planned

Page 21: The Project Management Process - Week 9   Performance Management

How long should a project status report be?

Page 22: The Project Management Process - Week 9   Performance Management

1 page

Page 23: The Project Management Process - Week 9   Performance Management

<example>

Page 24: The Project Management Process - Week 9   Performance Management

office.microsoft.com/en-us/templates/TC011417231033.aspx

http://saulcarliner.home.att.net/idbusiness/statusreport.htm

http://www.projectperfect.com.au/info_status_report.php

More info

www.ic.arizona.edu/~profcomm/writing/samples/stat_samp_s1.htm

www.projectconnections.com/knowhow/subsets/sample-templates/StatusReports.doc

Page 25: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 26: The Project Management Process - Week 9   Performance Management

Project Control Process

Page 27: The Project Management Process - Week 9   Performance Management

The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action

Pensiero

Page 28: The Project Management Process - Week 9   Performance Management

Project Control Steps

Set and baseline a

plan

Measuring progress and performance

Comparing the plan to the facts

Taking Action

Page 29: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 30: The Project Management Process - Week 9   Performance Management

Monitoring Time Performance

Page 31: The Project Management Process - Week 9   Performance Management

Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:

Page 32: The Project Management Process - Week 9   Performance Management

Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:

Tracking and baseline Gantt charts

show expected, actual, and trend data for event duration performance

Page 33: The Project Management Process - Week 9   Performance Management

Figure 13.1 Baseline Gantt Chart(Gray & Larson, 2006, p414)

Time

A Gantt Chart

Page 34: The Project Management Process - Week 9   Performance Management

Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:

Tracking and baseline Gantt charts

show expected, actual, and trend data for event duration performance

Control chartsplot the difference in

scheduled time on the critical path with the actual point on the critical path

Page 35: The Project Management Process - Week 9   Performance Management

Figure 13.2 Project Schedule Control Chart(Gray & Larson, 2006, p415)

A Control Chart

Page 36: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 37: The Project Management Process - Week 9   Performance Management

Monitoring Systems Disparities

Picture by Pensiero

Page 38: The Project Management Process - Week 9   Performance Management

Time-Phase Baseline Plan

Picture by Pensiero

Page 39: The Project Management Process - Week 9   Performance Management

Corrects the failure of most monitoring systems to connect a project’s actual performance to its schedule and forecast budget

Picture by Pensiero

Page 40: The Project Management Process - Week 9   Performance Management

Systems that measure only cost variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule

Picture by Pensiero

Page 41: The Project Management Process - Week 9   Performance Management

Earned Value Cost/Schedule System

An integrated project management system based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs

Picture by airgap

Page 42: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 43: The Project Management Process - Week 9   Performance Management

Earned Value ManagementEarned Value Management

Page 44: The Project Management Process - Week 9   Performance Management

What is Earned Value Management (EVM)?

Page 45: The Project Management Process - Week 9   Performance Management

What is Earned Value Management (EVM)?

A project performance measurement technique that integrates scope, time, and cost data.

Page 46: The Project Management Process - Week 9   Performance Management

What is Earned Value Management (EVM)?

A project performance measurement technique that integrates scope, time, and cost data.

Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals.

You must enter actual information periodically to use EVM.

Page 47: The Project Management Process - Week 9   Performance Management

What is Earned Value Management (EVM)?

A project performance measurement technique that integrates scope, time, and cost data.

Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals.

You must enter actual information periodically to use EVM.

Page 48: The Project Management Process - Week 9   Performance Management

Terms to learn

PV

AC

EV

Planned Value

Actual Cost

Earned Value

CV Cost Variance

SVSchedule Variance

CPICost Performance Indicator

SPISchedule Performance Indicator

Page 49: The Project Management Process - Week 9   Performance Management

(Also called the budget)

This is that portion of the approved total cost estimate planned to be spent on an activity during a given period

PV Planned Value

Page 50: The Project Management Process - Week 9   Performance Management

The total of direct and indirect costs incurred in finishing work on an activity during a given period

AC Actual Cost

Page 51: The Project Management Process - Week 9   Performance Management

An estimate of the value of the physical work actually completedEV Earned Value

Page 52: The Project Management Process - Week 9   Performance Management

Earned value minus the actual cost. Shows the difference between the estimated cost of an activity and the actual cost of that activity

TABLE 13.1

CV Cost Variance

Page 53: The Project Management Process - Week 9   Performance Management

Earned value minus the planned value. Shows the difference between the schedule completion of an activity and the actual completion of that activity

TABLE 13.1

SVSchedule Variance

Page 54: The Project Management Process - Week 9   Performance Management

The ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project.

If the CPI is equal to 1 or 100% then the planned and actual costs are equal, or the costs are as budgeted.

If the CPI is less than 1 or less than 100%, the project is over budget.

If the CPI is greater than 1 or more than 100%, the project is under budget

CPICost Performance Indicator

Page 55: The Project Management Process - Week 9   Performance Management

The ratio of earned value to planned value and can be used to estimate the projected time to complete the project.

Similar to the CPI, an SPI of 1 or 100% means the project is on schedule.

If the SPI is greater than 1 or 100% then the project is ahead of schedule.

If the SPI is less than 1 or 100%, the project is behind schedule

SPISchedule Performance Indicator

Page 56: The Project Management Process - Week 9   Performance Management

TABLE 13.1

Quick EVM quiz

What can we say if CPI > 1

Page 57: The Project Management Process - Week 9   Performance Management

Quick EVM quiz

What can we say if CPI > 1

If the CPI is greater than 1 or more than 100%,

the project is under budget

Page 58: The Project Management Process - Week 9   Performance Management

Quick EVM quiz

What is EV minus AC?

Page 59: The Project Management Process - Week 9   Performance Management

Quick EVM quiz

What is EV minus AC?

EV – AC = SVEarned Value (what was done)

MinusActual Cost (what has been

paid)=

Schedule Variance

Page 60: The Project Management Process - Week 9   Performance Management
Page 61: The Project Management Process - Week 9   Performance Management

Scenario Example

Page 62: The Project Management Process - Week 9   Performance Management

“Purchasing & Installing Web Server”

Duration 1 week,

Budget $10,000.

Scenario Example

Page 63: The Project Management Process - Week 9   Performance Management

“Purchasing & Installing Web Server” Duration 1 week, Budget $10,000.

PV – Planned Value – for that activity for that week = $10,000

AC – Actual Cost – suppose it actually took 2 weeks and cost $20,000. Assume $15,000 were incurred in week 1, and $5,000 in week 2. These costs are the actual costs for that activity each week

EV – Earned Value – earned value after one week is $7,500. (10,000 * 75%)

Example: CP829_Lecture_Week9_EarnedValue.xls

Scenario Example

Page 64: The Project Management Process - Week 9   Performance Management
Page 65: The Project Management Process - Week 9   Performance Management
Page 66: The Project Management Process - Week 9   Performance Management

Earned Value Chart for Project after 5-MonthsEarned Value Chart for Project after 5-Months

Page 67: The Project Management Process - Week 9   Performance Management
Page 68: The Project Management Process - Week 9   Performance Management

Max WidemanMax Wideman

Page 69: The Project Management Process - Week 9   Performance Management

Rules for Earned Value Numbers

Negative numbers for cost and schedule variance indicate problems in those areas

The project is costing more than planned or taking longer than planned

CPI and SPI less than 100% indicate problems

Page 70: The Project Management Process - Week 9   Performance Management

Table 13.3 Interpretation of Indexes(Gray & Larson, 2006, p429)

Page 71: The Project Management Process - Week 9   Performance Management

An alternative

Source: http://www.mountaingoatsoftware.com/release_burndown

Page 72: The Project Management Process - Week 9   Performance Management

Week 2 lecture

Week 2 lecture

Page 73: The Project Management Process - Week 9   Performance Management

So, what do you do when your plan changes?

Page 74: The Project Management Process - Week 9   Performance Management

There are methods used to revise estimates of future project costs

EVM allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate

EVM uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable

Page 75: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 76: The Project Management Process - Week 9   Performance Management

Developing an Integrated Cost/Schedule System

Page 77: The Project Management Process - Week 9   Performance Management

Compute

Calculate

Collect

Schedule

Resource plan

WBS

Budget

Pla

nM

on

itor

Page 78: The Project Management Process - Week 9   Performance Management

Define the work using a WBS

ScopeWork packagesDeliverablesOrganization unitsResourcesBudgets

Develop work and resource schedules

Schedule resource to activities

Time-phase work packages into a network

Photo by shimonkey

Page 79: The Project Management Process - Week 9   Performance Management

Develop a time-phased budget using

work packages

included in an activity.

Accumulate budgets (PV)

At the work package level, collect the actual costs for the work performed (AC)

Multiply percent complete times original budget (EV)

Compute the schedule variance (EV-PV) and the cost variance (EV-AC)

Page 80: The Project Management Process - Week 9   Performance Management

Figure 13.3 Figure 13.3 Project Management Information Systems OverviewProject Management Information Systems Overview(Gray & Larson, 2006, p419)(Gray & Larson, 2006, p419)

Integrated Cost/ Schedul

es

Page 81: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 82: The Project Management Process - Week 9   Performance Management

Project Baselines

Page 83: The Project Management Process - Week 9   Performance Management

Week 4 lecture

Week 4 lecture

Page 84: The Project Management Process - Week 9   Performance Management

a Baseline is an anchor point for measuring performance

Photo by _Robert C_ @

flickr

Page 85: The Project Management Process - Week 9   Performance Management

a planned cost and expected schedule against which actual cost

and schedule are measured

Gold by Куртис Перри

Page 86: The Project Management Process - Week 9   Performance Management

a basis for cash flows and awarding progress payments

Photo by quaziefoto @ flickr

Page 87: The Project Management Process - Week 9   Performance Management

a summation of time-phased budgets (cost accounts as summed work packages) along a project timeline

Picture by Network Osaka @ flickr

Page 88: The Project Management Process - Week 9   Performance Management
Page 89: The Project Management Process - Week 9   Performance Management

What Costs Are Included in Baselines?LaborEquipmentMaterialsProject direct overhead costs (DOC)

Page 90: The Project Management Process - Week 9   Performance Management

Figure 13.14 Scope Changes to a Baseline(Gray & Larson, 2006, p436)

Page 91: The Project Management Process - Week 9   Performance Management

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 92: The Project Management Process - Week 9   Performance Management

ReviewProject monitoring system include; data collection; analysis and reporting.Project control steps include; baseline plan, progress measurement, comparing actual against projected plan, and actions.Performance can be monitored using tools such as; tracking Gantts, control charts, baseline plans and earned value management.Earned value management (EVM) is a technique which incorporated scope, time and cost data to determine the health of the project.Integrated Cost/Schedule systems are developed creating; WBS, work/resource schedules, budget, and EVM.Project baselines are an anchor point for measuring performance.

Page 93: The Project Management Process - Week 9   Performance Management

ReferencesHorodyski, K. (1995). Managing and developing teams. Footscray, Vic.: Open Training Services.Greenberg, J. & Baron, R. (1993). Behavior in organizations (4th ed.). Syd., NSW: Allyn and Bacon. Robbins, S., et al. (1998). Organisational behaviour (2nd ed.). Sydney: Prentice-Hall

Page 94: The Project Management Process - Week 9   Performance Management

BetterProjects.net

Awesome title page picture by Derek Farr ( DetroitDerek )