the road to harbor bridge · september 13, 2016 us 181 harbor bridge project 3 constructed...
TRANSCRIPT
September 13, 2016
THE ROAD TO HARBOR BRIDGE:Achieving Environmental Clearance on
a Major Project for the State of Texas
October 11, 2016
September 13, 2016
Richard O’Connell
Associate General Counsel
Christopher Amy,
Environmental Specialist
September 13, 2016
US 181 Harbor Bridge Project
3
Constructed 1956-1959
Replacing the existing US 181
Harbor Bridge and
approaches over the Corpus
Christi Ship Channel.
2005-2007 Project Scoping
2010 FHWA determined EIS
developed under SAFETEA-LU
Procedures
2011 Published NOI to
prepare EIS
FHWA the lead Federal agency
with TxDOT as the joint lead
agency for the project
EPA, HUD & USCG were
Cooperating AgenciesCourtesy of Corpus Christi Caller Times
September 13, 2016
US 181 Harbor Bridge Project
4
September 13, 2016
Harbor Bridge Public Involvement
5
Public Hearing Store Front Meetings
September 13, 2016
Developing Harbor Bridge Mitigation
6
September 13, 2016
Developing Harbor Bridge Mitigation
7
TxDOT and FHWA Commitments to
the Neighborhood
Implement Recreational
Enhancements
– Implement park mitigation
– Construct hike & bike trails
Noise Mitigation
Host Job Fairs
Provide Information on Workforce
Support
Develop Northside Neighborhood
Livability Plan
– Develop Historical Record of
neighborhoods
– Identify neighborhood needs and ideas
September 13, 2016
The FEIS was published in November 2014
In March of 2015, FHWA received a complaint under Title VI of the Civil Rights Act
US 181 Harbor Bridge FEIS
September 13, 2016
US 181 Harbor Bridge FEIS
September 13, 2016
ROD signed January 8, 2016
Record of Decision
September 13, 2016
Voluntary Resolution Agreement
11
September 13, 2016
Voluntary Resolution Agreement
12
September 13, 2016
Community Advisory Board (CAB)
Meetings Monthly
• Where: (Oveal Williams Senior Center)
• First Meeting was held May 12th
Meetings will be professionally facilitated;
Open to the public;
• Citizens provide input during the public comment period
TxDOT responsibilities
– Collaborate with CAC on implementation of Agreements:
• Voluntary Acquisition
• Relocation Benefits
• Voluntary Restrictive Covenant
• Tenant relocation at D.N. Leathers
• 4(f) mitigation for T.C. Ayers and H.J. Williams Parks
– Document Meetings with CAB for update to FHWA
13
September 13, 2016
Lessons Learned
14