The use of Competitive Dialogue for major projects in the UKPhD findings
19 October 2011
Susie Smith, Bevan Brittan LLP
Richard Craven, University of Nottingham
7038881
![Page 2: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/2.jpg)
2
Setting the scene
• Aims of the PhD
• Approach used•Legal analysis•58 interviews (January 2010 – March 2011)
• 14 Procurement officers and in-house lawyers• 41 External legal advisors• 3 Policymakers
• Structure of the PhD – follows the planning and
procurement process
• Publication date
![Page 3: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/3.jpg)
Five areas of interest
• Choosing CD
• Confidentiality and the dialogue phase
• Phased dialogue and the use of award criteria
• How final are final tenders?
• Perceptions of risk of challenge and impact on decision
making
3
![Page 4: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/4.jpg)
Choosing CD
• Grounds for use of CD•Is this considered•Views on the conditions to be satisfied
• Is CD a standard procedure?
• Commoditised procurements
• Other factors influencing choice of CD or choice not to
use CD
4
![Page 5: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/5.jpg)
Confidentiality and the dialogue process
• High level of concern pre 2006 and general finding•Single solution or multiple solutions•Respect for confidential information• Amicable resolution of concerns
5
![Page 6: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/6.jpg)
Phased dialogue and the use of award criteria
• Reduction of solutions or bidders?
• Is a formal bidding process required?
• Same criteria for all stages or different criteria?•Particular issue with pricing at early stages
• Scope for variation of award criteria or weightings
during the CD process
• Uncertainty as to use of award criteria is a major
concern
6
![Page 7: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/7.jpg)
How final are final tenders?
• Theory and practice
7
![Page 8: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/8.jpg)
Perceptions of risk of challenge and impact on decision making
• Legal risk – central role in decision making
• Sources of challenge – Commission and the market
• Rise in bidder queries
• Impact on behaviour
8
![Page 9: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/9.jpg)
Next steps……
9
![Page 10: The use of Competitive Dialogue for major projects in the UK PhD findings 19 October 2011 Susie Smith, Bevan Brittan LLP Richard Craven, University of](https://reader035.vdocuments.net/reader035/viewer/2022070413/5697bfc11a28abf838ca470e/html5/thumbnails/10.jpg)
10
Contact details
Susie Smith 0870 194 [email protected]