the value of building commissioning study · 2020. 5. 18. · learning objectives 1. present the...

50
BCxA| 2016 1 Tom Poeling, PE, CEM, CCP BCxA Immediate Past President Project Support Director – U.S. Engineering Construction Working Together. Building Excellence. The Value of Building Commissioning Study

Upload: others

Post on 21-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

BCxA| 20161

Tom Poeling, PE, CEM, CCPBCxA Immediate Past President

Project Support Director – U.S. Engineering Construction

Working Together. Building Excellence.

The Value of Building

Commissioning Study

Page 2: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Learning Objectives

1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning.

2. Provide data that can be used by commissioning stakeholders to promote the industry.

3. Understand market opportunities to improve the commissioning industry.

4. Understand Cx scope of work improvements to improve delivery process.

2

Page 3: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

3

Prior LBNL Studies – Cost Effectiveness of

Commercial Building Commissioning

(2004)

(2009)

Page 4: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

• Refresh the LBNL 2009 survey

• Maintain consistency in the dataset

• Reflect changes to the industry due to maturity

• Define effects of changes to Cx approach (such as Ongoing Cx)

• Include economics for Cx of new and additional systems

• Expand database for different building types, markets

• Establish new baseline for Cx metrics

• Identify appropriate level of data to gather

• Create an iterative process for data gathering

• Engage industry to provide more feedback over time on project level and market level trends

4

Value of Commissioning Study - Goals

Page 5: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

5

Data Survey Statistics

New Construction Cx 2009 Study 2018 Study

# of Buildings 82 101

# of Projects (w/cost data) 74 71

Floor Area (SF) 8,813,925 22,217,059

Construction Cost $2.2B $10.1B

# of States Represented 10 18

Existing Building Cx 2009 Study 2018 Study

# of Buildings (total) 562 738

# of Projects (w/energysavings data)

300 705

Floor Area (SF) 90,410,884 252,159,847

# of States Represented 21 18

Page 6: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Value of Cx (NCCx) Study Results

Cost Summary

Market Demand Factors

Scope of Work Observations

6

Page 7: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

$-

$1.00

$2.00

$3.00

$4.00

$5.00

$6.00

New Construction Commissioning Cost ($2018/sq.ft.) (n=67)

25th Percentile $0.40

Median $0.82

75th Percentile $1.36

Mean $1.06

NCCx Cost per Square Foot

2009

$0.59

$1.16

$2.14$1.94

2018

Page 8: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Building Size Distribution: NCCx

Min 2,700

Median 115,908

Mean 232,409

Max 3,500,000

Min 1,227

Median 69,500

Mean 114,467

Max 685,000

Page 9: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx Cost Summary 9

0%

5%

10%

15%

20%

25%

30%

35%

R HE O HI K12 PA I L LOD W HO W FSA POS

Perc

ent of to

tal p

roje

cts

with c

ost data

Market Segment Breakdown (Projects with Cost Data)

2009 2017

NCCx Cost by Building Type

Page 10: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx Cost by Building Type

2009 2018Building Types n= % total #

of projects

Avg $/sq.ft n= % total #

of projects

Avg $/sq.ft

Higher Education 3 4% $ 7.59 15 22% $ 1.44Office 10 14% $ 0.57 20 30% $ 0.82Healthcare – Inpatient 9 12% $ 3.08 8 12% $ 0.96K12 Schools 7 10% $ 0.82 15 22% $ 0.85Laboratory 16 22% $ 2.87 2 3% $ 0.79

xx

Page 11: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx Cost by Building Type

2009 2018Building Types n= % total #

of projects

Avg $/sq.ft n= % total #

of projects

Avg $/sq.ft

Higher Education 3 4% $ 7.59 15 22% $ 1.44Office 10 14% $ 0.57 20 30% $ 0.82Healthcare – Inpatient 9 12% $ 3.08 8 12% $ 0.96K12 Schools 7 10% $ 0.82 15 22% $ 0.85Laboratory 16 22% $ 2.87 2 3% $ 0.79

xx

Page 12: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

1. Overall NCCx costs/SF appear lower, but…..

2. 2018 data field contains 2X more SF per building

3. Building type mix is different. Less data for Public Assembly, Laboratories, and Public Safety (higher $/SF in 2009).

4. NCCx fee ranges for higher education and healthcare are less volatile than 2009. NCCx fee ranges for office and schools are more stable (and increasing).

5. Over 40% of NCCx work is selected based on qualifications vs. price

6. Cx firms are reporting stable/increased project profitability

7. Be very careful to qualify NCCx costs using other metrics than just overall $/SF

8. Use a range to report NCCx costs12

NCCx Commoditization Concerns

Page 13: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Value of Cx (NCCx) Study Results

Cost Summary

Market Demand Factors

Scope of Work Observations

13

Page 14: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

14

Reasons for Executing NCCx

0

10

20

30

40

50

60

70

80

Voluntary

Rating

Programs

Owner

Awareness

Utility

Programs

Trade

Associations

Public Policies Building Codes Other

Not Important Slightly Neutral Important Very Important

Factors that Drive Cx? (Out of 5.0)

Owner Awareness 3.82

Building Codes 3.74

Voluntary Rating Programs 3.65

Public Policies 3.54

Utility Programs 3.11

Other 2.92

Trade Associations 2.75

Page 15: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

3%

0%

0%

3%

5%

6%

11%

32%

34%

34%

48%

50%

53%

55%

65%

79%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90%

Other

Comply with existing buildings ordinance

Research/demonstration/pilot

Participation in utility program

Qualify for rebate, financing, or other services

Reduce liability

Increase occupant productivity

Obtain energy savings

Extended equipment life

Ensure adequate indoor air quality

Comply with organizational mandate/policy

Train and increase awareness of building operators or…

Ensure or improve thermal comfort

Smoother process and turnover (new construction)

Comply with LEED or other sustainability rating system

Ensure system performance (energy and non-energy-…

Fraction of reporting projects with reason (New Construction)

Reasons for Implementing NCCx

Page 16: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Reasons for Implementing NCCx

Reasons that Increased (2009 to 2018)

Fraction of reasons to embark on NCCx 2009 2018 Difference

Comply with LEED or other sustainability rating system

15% 65% 50%

Comply with organizational mandate/policy

0% 48% 48%

Smoother process and turnover (new construction)

26% 55% 29%

Page 17: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Reasons for Implementing NCCx

Reasons that Decreased (2009 to 2018)

Fraction of reasons to embark on NCCx 2009 2018 Difference

Ensure adequate indoor air quality 75% 34% -41%

Participation in utility program 42% 3% -39%

Obtain energy savings 65% 32% -33%

Ensure or improve thermal comfort 72% 53% -19%

Train and increase awareness of building operators or occupants

61% 50% -11%

Page 18: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

90%

79%

77%

74%

62%

56%

18%

95%

90%

87%

87%

72%

69%

21%

13%

10%

3%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

FIRST COST SAVINGS

Project on schedule, problems detected and corrected earlier

Occupied on schedule

Improvements to system design, equipment sized correctly

Improve construction team coordination, reduce disagreements

Building occupied sooner, call-backs reduced, TAB costs reduced

Fewer change orders; warranty claims

Other or unspecified first-cost

ONGOING (RECURRING) IMPROVEMENTS

Thermal Comfort

Maintenance

Improved O&M

Training; education

Indoor Air Quality

Equipment Life

Liability

Tenant retention; turnover

Productivity/Safety

Other (or combination of above)

(n=39)

NCCx: Projects Reporting Non-Energy Benefits

Page 19: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

43%

76%

98%

23%

90%

98%

97%

98%

87%

90%

79%

75%

55%

6%

98%

33%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Commissioning provider development of design intent…

Write specifications

Develop commissioning plan

Develop sequences of operation (if not well-developed by…

Review submittals

Construction observation

Verification checks/prefunctional testing

Functional testing; use of diagnostic tools

Commissioning provider significantly involved in issue…

Oversee training

Review O&M manuals

Develop systems manual/recommissioning manual

Perform trend analysis, modeling, or benchmarking

Evaluate energy cost savings

Final report

Ongoing commissioning, or other ongoing related…

Activities included in New Construction Commissioning Scope (n=62)

Page 20: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

43%

76%

98%

23%

90%

98%

97%

98%

87%

90%

79%

75%

55%

6%

98%

33%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Commissioning provider development of design intent…

Write specifications

Develop commissioning plan

Develop sequences of operation (if not well-developed by…

Review submittals

Construction observation

Verification checks/prefunctional testing

Functional testing; use of diagnostic tools

Commissioning provider significantly involved in issue…

Oversee training

Review O&M manuals

Develop systems manual/recommissioning manual

Perform trend analysis, modeling, or benchmarking

Evaluate energy cost savings

Final report

Ongoing commissioning, or other ongoing related…

Activities included in New Construction Commissioning Scope (n=62)

Page 21: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

1. Owner awareness – highest driving factor

2. NCCx demand driven by regulation and codes

3. Several non-energy benefits obtained thru NCCx

a) Schedule improvement

b) Smooth turnover

c) Training

4. Building performance metrics (energy, IAQ) has lost some emphasis

5. Core Cx scope of work is performed on each project

6. Opportunity to improve frequency of scope items:

a) OPR/Design Intent document

b) Controls sequence development

c) Energy cost calculations

d) Post-occupancy tasks

NCCx Market Factors

Page 22: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Value of Cx (NCCx) Study Results

Cost Summary

Market Demand Factors

Scope of Work Observations

22

Page 23: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 23

Percentage of NCCx Projects include Design Phase Cx Services? (26)

Less than 20% 20-40% 40-60% 60-80% Greater than 80%

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

Weighted Avg. = 60%

Page 24: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 24

Percentage of NCCx Projects where OPR is Developed for Owner? (30)

Less than 20% 20-40% 40-60% 60-80% Greater than

80%

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

31% Weighted Avg. = 47%

Page 25: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 25

Percentage of Cx Issues Discovered during Design Phase? (33)

Less than 20% 20-40% 40-60% 60-80% Greater than 80%

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

45.0%

50.0%

Weighted Avg. = 25%

Page 26: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 26

How often are Cx Review Comments in Design Phase incorporated into Contract Docs? (43)

Never Rarely Sometimes Often Always

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

45.0%

84% 46%

Page 27: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 27

How often were control sequences created without collaboration between design and Cx? (39)

Never Rarely Sometimes Often Always

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

67%

Page 28: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

28

How often does NCCx meet with facility personnel during design? (41)

Never Rarely Sometimes Very Often Always

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

72%

35%

Page 29: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

29

How often do controls coordination meetings occur (engineer, contractor, Cx)? (45)

Never Rarely Sometimes Very Often Always

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

Page 30: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 30

How often do Cx issues remain open after Beneficial Occupancy? (52)

Never Rarely Sometimes Often Always Don't know

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

34%37%

Page 31: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 31

How often is a Post-turnover occupant survey of satisfaction conducted? (53)

Never Rarely Sometimes Often Always Don't know

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

33%34%

Page 32: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

NCCx SOW Observations 32

How often are OCx tasks included after Warranty is complete? (54)

Never Rarely Sometimes Very Often Always Don't know

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

45.0%

56%

16%

Page 33: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

1. Design phase Cx services are included in over 60% of NCCx projects.

2. Design phase Cx review comments are incorporated in contract documents over 80% of the time.

3. Design phase issues constitute ≈ 25% of all NCCx issues.

4. Opportunity to improve frequency of NCCx scope items:

a) OPR/Design Intent document

b) Controls sequence development/Controls coordination meetings during submittals

c) Scheduling/Equipment startup coordination

d) Collaboration with facility personnel/Follow-up with occupants

5. OCx SOW is included more often (44% = “sometimes” or better)

NCCx Market Survey – SOW Takeaways

Page 34: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

EBCx - Discussion Topics

34

• Building data: Preliminary narratives regarding Cx Value metrics

1. EBCx – Cost Summary

2. EBCx – Market Demand Factors

3. EBCx – Scope of Work Observations

• Review Data Survey Results

What’s Changed?

Check Calibration

Market Drivers & Issues

Page 35: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

EBCx Cost per Square Foot

N = MedianUtility_1 414 $0.17

Non-Utility 36 $0.24Utility_2 156 $0.42

Utility_MBCx 54 $1.61

$0.26 Median overall

Page 36: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

EBCx Cost per Square Foot (Bldg. Size)

Size)

$0.26 Median overall

Page 37: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Median nUtility_1 5% 326Utility_2 7% 156

Utility_MBCx 9% 41Other_EBCx 14% 107

EBCx Percent Savings by Project

Type

• Median energy savings =

6%

• Utility typical range = 3 to 11%

• 2018 median less than 2009 savings of 10%

n=533

n=107

n=41Median 6% (all data)

Page 38: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

EBCx Percent Savings by Project

Type

8.5%

22.0%

46.3%

22.0%

1.2%

Less than 5% 5 to 10% 10 to 20% 20% to 30% More than 30%

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

50%

Median energy savings = 12%

Page 39: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

-

5

10

15

20

25

30

35

Sim

ple

Pa

yba

ck (

Yre

ars

)

(n=300 bldgs.)

EBCx Simple Payback (Years)

2.2

1.1

2018

25th Percentile 1.3

Median 2.2

75th Percentile 4.2

Page 40: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

EBCx Implementation by Payback

• 2 year payback or less: Implemented 55%• 3 to 4 year payback: 34%• 5 year payback or greater: 18%

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

less than10%

10 - 20% 20 - 40 % 40 - 60% 60 - 80% Greater than80%

2 years or less payback 3 to 4 years payback 5 year payback

Page 41: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Reasons for Implementing EBCx

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Other

Reduce liability

Research/demonstration/pilot

Comply with existing buildings ordinance

Increase occupant productivity

Extended equipment life

Comply with organizational mandate/policy

Comply with LEED or other rating system

Participation in utility program

Train/increase awareness of operators or occupants

Qualify for rebate, financing, or other services

Ensure adequate indoor air quality

Ensure or improve thermal comfort

Ensure system performance

Obtain energy savings

Fraction of reporting projects with reason (EBCx), 2009 vs. 2018

2009 2018

Page 42: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Other

Reduce liability

Research/demonstration/pilot

Comply with existing buildings ordinance

Increase occupant productivity

Extended equipment life

Comply with organizational mandate/policy

Comply with LEED or other rating system

Participation in utility program

Train/increase awareness of operators or occupants

Qualify for rebate, financing, or other services

Ensure adequate indoor air quality

Ensure or improve thermal comfort

Ensure system performance

Obtain energy savings

Fraction of reporting projects with reason (EBCx), 2009 vs. 2018

2009 2018

Reasons for Implementing EBCx

Page 43: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Were Cost and Energy Savings

calculations included with EBCx?

Never Rarely Sometimes Often Always

0%

5%

10%

15%

20%

25%

30%

35%

61%

Page 44: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Significant repairs before EBCx?

Never Rarely Sometimes Often Always

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

45%

87%

Page 45: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

How often is TAB included?

Never Rarely Sometimes Often Always

0%

5%

10%

15%

20%

25%

30%

35%

40%

75%

36%

Page 46: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Level of TAB investigation

Central plant only AHUs only Central plant andAHUs

Including someterminal unitequipment

Including allterminal unitequipment

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

53%

Page 47: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

35.1%

16.4%

19.6%

11.9%

13.1%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Contr

ibution to O

vera

ll P

rogra

m S

avi

ngs (

%)

Utility Program EBCx Measure Types (n = 3,695 measures, 503 projects)

Loop Tuning

Calibration

Maintenance - Other

Mechanical Fix

Modify Sequence of Operations

Modify Setpoint

Implement Advanced Reset

Operations & Control - Other

Scheduling

EBCx Measure Mix

Page 48: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

How were EBCx issues addressed?

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

Page 49: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

1. Energy Savingsa. Median 6%, typical range 3% to 11% (combined utility and non-

utility EBCx programs)

b. EBCx outside utility programs could hit 10% to 25% range

c. 2018 median down from 2009, though looking at project type suggests no major market shift

2. Simple Paybacka. Median 2.2 years. Range generally 1 and 4 years payback

b. Median $0.26 project cost per sq.ft., with a typical range $0.15 to $0.56

c. Projects at lower percent savings can still be highly cost-effective

3. Owner’s reasons for implementing EBCx: Top 4 are unchanged from 2009 study

4. EBCx Measures: Top 5 measures account for 95% of all measures

Conclusion

Page 50: The Value of Building Commissioning Study · 2020. 5. 18. · Learning Objectives 1. Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of commissioning

Deliverables will be posted to website,

https://www.bcxa.org/knowledge-center/value-of-cx-project/

• Technical Narratives

• Blogs

• Presentations

• Data, Research

• Related Surveys

50

Additional Information

[email protected]