the world bank · pdf filenovember 26, 2014 ... a. economic analysis ... pest management op...
TRANSCRIPT
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: 88797-BY
INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVLOPMENT
PROJECT APPRAISAL DOCUMENT
ON A
PROPOSED LOAN
IN THE AMOUNT OF US$250 MILLION
TO THE
REPUBLIC OF BELARUS
FOR A
TRANSIT CORRIDOR IMPROVEMENT PROJECT (P149697)
November 26, 2014
Transport and ICT Global Practice
Europe and Central Asia
This document has a restricted distribution and may be used by recipients only in the
performance of their official duties. Its contents may not otherwise be disclosed without World
Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
(Exchange Rate Effective November 24, 2014)
Currency Unit = BYR (Belarusian Ruble)
US$1 = BYR 10,860
BYR 1 = US$0.00009
FISCAL YEAR
January 1 – December 31
ABBREVIATIONS AND ACRONYMS
AADT Annual Average Daily Traffic
AMF Accident Modification Factor
BCP Border Crossing Points
BoQ Bill of Quantity
CES Common Economic Space
CPS Country Partnership Strategy
CSO Civil Society Organization
ECU Eurasian Customs Unions
EA Environmental Assessment
EAEU Eurasian Economic Union
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EIRR Economic Internal Rate of Return
ENPV Economic Net Present Value
FIDIC Federation of Consulting Engineers
FM Financial Management
FY Financial Year
GA GROGNOAVTODOR
GDP Gross Domestic Product
GOB Government of Belarus
HDM Highway Development and
Management Model
IBRD International Bank for Reconstruction
and Development
ICB International Competitive Bidding
ICT Information and Communications
Technology
IFC International Finance Corporation
IFR Interim Financial Reports
ITS Intelligent Transport System
IRI International Roughness Index
MA-C MINSKAVTODOR - Center
MoTC Ministry of Transport and
Communications
NCB National Competitive Bidding
ORAF Operational Risk Assessment
Framework
PAPs Project Affected Persons
PDO Project Development Objectives
PIT Project Implementation Team
PPP Public-Private Partnership
POM Project Operations Manual
RAP Resettlement Action Plan
RPF Resettlement Policy Framework
SBC State Border Committee
SCC State Customs Committee
SMA Stone Mastic Asphalt
SME Small Medium Enterprises
SOE State-owned Enterprise
TRSCC Traffic and Road Safety Coordination
Center
VAT Value-added Tax
VMS Variable Message Sign
VOC Vehicle Operating Costs
WIM Weigh – in – Motion
Regional Vice President: Laura Tuck
Country Director: Qimiao Fan
Senior Global Practice Director: Pierre Guislain
Practice Manager: Juan Gaviria
Task Team Leader: Simon David Ellis
REPUBLIC OF BELARUS
Transit Corridor Improvement Project (P149697)
TABLE OF CONTENTS
Page
I. STRATEGIC CONTEXT .................................................................................................1
A. Country Context ............................................................................................................ 1
B. Sectoral and Institutional Context ................................................................................. 2
C. Higher Level Objectives to which the Project Contributes .......................................... 5
II. PROJECT DEVELOPMENT OBJECTIVES ................................................................6
A. PDO............................................................................................................................... 6
B. Project Beneficiaries ..................................................................................................... 6
C. PDO Level Results Indicators ....................................................................................... 7
III. PROJECT DESCRIPTION ..............................................................................................7
A. Project Components ...................................................................................................... 7
B. Project Financing ........................................................................................................ 10
C. Project Cost and Financing ......................................................................................... 10
D. Lessons Learned and Reflected in the Project Design ................................................ 10
IV. IMPLEMENTATION .....................................................................................................11
A. Institutional and Implementation Arrangements ........................................................ 11
B. Results Monitoring and Evaluation ............................................................................ 12
C. Sustainability............................................................................................................... 13
V. KEY RISKS AND MITIGATION MEASURES ..........................................................13
A. Risk Ratings Summary ............................................................................................... 13
B. Overall Risk Rating Explanation ................................................................................ 13
VI. APPRAISAL SUMMARY ..............................................................................................14
A. Economic Analysis ..................................................................................................... 14
B. Technical ..................................................................................................................... 15
C. Financial Management ................................................................................................ 16
D. Procurement ................................................................................................................ 17
E. Social (including Safeguards) ..................................................................................... 17
F. Environment (including Safeguards) .......................................................................... 18
G. Other Safeguards Policies Triggered .......................................................................... 19
Annex 1: Results Framework and Monitoring .........................................................................20
Annex 2: Detailed Project Description .......................................................................................25
Annex 3: Implementation Arrangements ..................................................................................31
Annex 4: Operational Risk Assessment Framework (ORAF) .................................................39
Annex 5: Implementation Support Plan ....................................................................................44
Annex 6: Economic Analysis .......................................................................................................47
Annex 7: Impact Analysis ...........................................................................................................51
Annex 8: Project Map ..................................................................................................................53
i
PAD DATA SHEET
Belarus
Transit Corridor Improvement Project (P149697)
PROJECT APPRAISAL DOCUMENT
EUROPE AND CENTRAL ASIA
GTIDR
Report No.: PAD996
Basic Information
Project ID EA Category Team Leader
P149697 B - Partial Assessment Simon David Ellis
Lending Instrument Fragile and/or Capacity Constraints [ ]
Investment Project Financing Financial Intermediaries [ ]
Series of Projects [ ]
Project Implementation Start Date Project Implementation End Date
01-Mar-2015 30-Jun-2020
Expected Effectiveness Date Expected Closing Date
30-Apr-2015 30-Jun-2020
Joint IFC
No
Practice
Manager/Manager
Senior Global Practice
Director Country Director Regional Vice President
Juan Gaviria Pierre Guislain Qimiao Fan Laura Tuck
Borrower: Republic of Belarus
Responsible Agency: Ministry of Transportation and Communications
Contact: Sivak Anatoly Aleksandrovich Title: Minister
Telephone No.: 375172597910 Email: [email protected]
Project Financing Data(in USD Million)
[ X ] Loan [ ] IDA Grant [ ] Guarantee
[ ] Credit [ ] Grant [ ] Other
Total Project Cost: 270.01 Total Bank Financing: 250.00
Financing Gap: 0.00
ii
Financing Source Amount
Borrower 20.01
International Bank for Reconstruction and
Development
250.00
Total 270.01
Expected Disbursements (in USD Million)
Fiscal
Year
2015 2016 2017 2018 2019 2020 0000 0000 0000 0000
Annual 0.00 90.00 75.00 40.00 25.00 20.00 0.00 0.00 0.00 0.00
Cumulati
ve
0.00 90.00 165.00 205.00 230.00 250.00 0.00 0.00 0.00 0.00
Institutional Data
Practice Area / Cross Cutting Solution Area
Transport & ICT
Cross Cutting Areas
[ ] Climate Change
[ ] Fragile, Conflict & Violence
[ ] Gender
[ ] Jobs
[ ] Public Private Partnership
Sectors / Climate Change
Sector (Maximum 5 and total % must equal 100)
Major Sector Sector % Adaptation
Co-benefits %
Mitigation
Co-benefits %
Transportation Rural and Inter-Urban
Roads and Highways
100
Total 100
I certify that there is no Adaptation and Mitigation Climate Change Co-benefits information
applicable to this project.
Themes
Theme (Maximum 5 and total % must equal 100)
Major theme Theme %
Financial and private sector development Infrastructure services for private sector
development
30
Public sector governance Other public sector governance 40
Trade and integration Regional integration 30
iii
Total 100
Proposed Development Objective(s)
The Project Development Objective is to improve transport connectivity, border crossing procedures and
safety for domestic and international road users on selected sections of the M6 corridor.
Components
Component Name Cost (USD Millions)
Component 1: Improvement of Sections of M6 'Minsk -
Grodno' Transit Corridor
259.28
Component 2: Road Safety and Network Management 6.80
Component 3: Border Management Enhancement 3.30
Front-end fees 0.63
Compliance
Policy
Does the project depart from the CAS in content or in other significant
respects?
Yes [ ] No [ X ]
Does the project require any waivers of Bank policies? Yes [ ] No [ X ]
Have these been approved by Bank management? Yes [ ] No [ X ]
Is approval for any policy waiver sought from the Board? Yes [ ] No [ X ]
Does the project meet the Regional criteria for readiness for implementation? Yes [ X ] No [ ]
Safeguard Policies Triggered by the Project Yes No
Environmental Assessment OP/BP 4.01 X
Natural Habitats OP/BP 4.04 X
Forests OP/BP 4.36 X
Pest Management OP 4.09 X
Physical Cultural Resources OP/BP 4.11 X
Indigenous Peoples OP/BP 4.10 X
Involuntary Resettlement OP/BP 4.12 X
Safety of Dams OP/BP 4.37 X
Projects on International Waterways OP/BP 7.50 X
Projects in Disputed Areas OP/BP 7.60 X
Legal Covenants
Name Recurrent Due Date Frequency
Section I.A. 3 of Schedule 2 to the LA X CONTINUOUS
iv
Description of Covenant
The Borrower shall maintain during the implementation of the Project, its offices, units and subordinated
agencies with technical, environmental and social safeguards, fiduciary and other Project related
responsibilities for implementing the Project, all with powers, functions, capacity, staffing and resources
acceptable to the Bank to fulfill their respective responsibilities under the Project.
Name Recurrent Due Date Frequency
Section I.D. 1 of Schedule 2 to the LA X CONTINUOUS
Description of Covenant
The Borrower, through MoTC and MA-C, shall carry out the Project in accordance with the
Environmental Management Plan (EMP) and the Resettlement Policy Framework (RPF). Except as the
Bank shall otherwise agree, the Borrower, through MoTC and MA-C, shall not assign, amend, abrogate
or waive the EMP and the RPF or any of their provisions.
Name Recurrent Due Date Frequency
Section I.D.2 of Schedule 2 to the LA X CONTINUOUS
Description of Covenant
Prior to commencement of any works to be carried out in the Grodno region under Part 1 of the Project,
the Borrower shall, through MoTC and MA-C, implement the Resettlement Action Plan, in accordance
with its terms and in a manner acceptable to the Bank, including the obligation of full payment of
compensation and/or the provision of relocation to all Displaced Persons prior to any displacement.
Conditions
Source Of Fund Name Type
IBRD Section 5.01 (a) of the LA Effectiveness
Description of Condition
The Project Operational Manual has been adopted by the Borrower.
Source Of Fund Name Type
IBRD Section 5.01 (b) of the LA Effectiveness
Description of Condition
The Inter-Ministerial Resolution has been duly issued and published in the National Registry of Legal
Acts, and is in full force and effect.
Team Composition
Bank Staff
Name Title Specialization Unit
Rodrigo Archondo-
Callao
Sr Highway Engineer Transport Economist GTIDR
Irina Babich Sr Financial
Management Specialist
Financial Management GGODR
Yevhen Bulakh Transport Specialist Highway Engineering GTIDR
Jacques Bure Lead Transport
Specialist
Peer Reviewer GTIDR
v
Funda Canli Program Assistant Administration GTIDR
Sebastian Eckardt Senior Economist Peer Reviewer GMFDR
Simon David Ellis Lead Transport
Specialist
Team Lead GTIDR
Clayton Bryant Kerswell Senior Trade Facilitation
Specialist
Customs and Trade
Facilitation
GTCDR
Elena Klochan Sr Country Program
Officer
Country Program
Management
ECCBY
Klavdiya Maksymenko Social Development
Specialist
Social Development GSURR
Juan Navas-Sabater Program Leader ICT ECCU1
Luis M. Schwarz Senior Finance Officer Disbursements CTRLA
Robert Charles Seekings E T Consultant Highway Engineering GTIDR
Elena Segura Labadia Senior Counsel Legal LEGLE
Jennifer Shkabatur Consultant Social Development GSURR
Hanna Shvanok E T Temporary Administration ECCBY
Maryna Sidarenka Research Analyst Customs and Trade
Facilitation
GMFDR
Alexei Slenzak Senior Environmental
Specialist
Environmental GENDR
Paul Vallely Sr Transport. Spec. Peer Reviewer GTIDR
Wei Wang Young Professional ICT and Instituional GTIDR
Barbara Ziolkowska Procurement Analyst Procurement GGODR
Non Bank Staff
Name Title City
Locations
Country First
Administrative
Division
Location Planned Actual Comments
Belarus Minsk X Project will cover Minsk
and Grodno Oblasts
1
I. STRATEGIC CONTEXT
A. Country Context
1. Macroeconomic Situation. The Republic of Belarus, a country with a population of
about 9.47 million, is highly urbanized – 77 percent of the population lives in 203 cities and
urban settlements and only 23 percent lives in 23,250 rural settlements in 2014. State presence in
and regulation of economic activity is still significant; the private sector accounts for just 22.6
percent of GDP1. While the role of the state has been gradually reduced, state owned enterprises,
which are supported by an extensive system of state support, still account for over half of output
and two thirds of employment. Equally, the financial sector is dominated by state owned banks,
which account for over 70 percent of bank assets and which channel a significant share of
financing to less productive parts of the economy, including through state programs and directed
lending. Despite recent liberalization efforts, the government also continues to regulate prices for
socially important goods and services, most importantly foodstuff and communication services.
2. Until 2008, Belarus was a strong growth performer in a fast growing region. During
2001–08, Belarus’s GDP grew on average by 8.3 percent annually but growth slowed
substantially following the global economic crisis of 2008–09, and since then, the country has
gone through a period of recurring macroeconomic instability and soaring inflation. Tight
monetary and fiscal policy in late 2011 and through 2012 led to some macroeconomic stability
being restored during 2013 but inflation remained stubbornly high at 16.5 percent and real GDP
growth slowed to 0.9 percent down from 1.7 percent in 2012.
3. Over the past decade, rapid economic growth translated into remarkable progress in
poverty reduction, although the recent crisis was associated with a modest poverty increase. The
absolute poverty rate (national poverty line) declined from 30 percent in 2002 to about 6.3
percent in 2012. The country has also been one of the most successful countries in the region in
sharing growth with the lowest 40 percent income group. In the 2006-2011 period mean income
growth averaged 6.4 percent, while growth of the lowest 40 percentile averaged 9.1 percent. As a
result, this group of the population earned 23.4 percent of total income in 2012.
4. Absolute poverty in rural areas is twice as high as in urban areas, and large heterogeneity
in poverty incidence is found among regions. While Belarus follows principles of equality and
non-discrimination in its policies and has a basic legal framework in place, gender equality
appears to be given lower priority compared to other social issues, and gender gaps persist in the
areas of worker remuneration and economic opportunities.
5. Nevertheless, the macroeconomic crises of the past years have revealed deep structural
constraints in Belarus’ state-centered economic model. Given the dominance of state-owned
enterprises, the private sector and especially small and medium-sized enterprises remain
marginalized. The economy continues to depend on energy- and resource-intensive exports.
6. The Government fully shares this assessment as reflected in the Country Economic
Memorandum and has formally requested Bank technical assistance to design a medium term
1 http://data.worldbank.org/indicator/FS.AST.PRVT.GD.ZS
2
structural reform program. This reform program would be comprehensive and consistent with the
key structural challenges facing the country. The reform program will include corporate
governance of State Owned Enterprises, reform of state programs and directed credits, industrial
policy, reforming the insolvency framework and social protection.
B. Sectoral and Institutional Context
7. Transport in Macroeconomics. Contributing about 6 percent of GDP in 2012, transport
is an important economic sector in Belarus. It generates significant revenues from transit
services, facilitates trade and transportation, and contributes to the country’s balance of
payments. In addition, the transport sector accounted for about 6 percent of total employment in
2012, with the largest proportion of transport employment in roads (100,900 persons), followed
by rail (69,100 persons).
8. The transport system. The transport system in Belarus is dominated by the rail and road
systems. The Belarusian Railways, a state-owned company under the authority of the Ministry of
Transport and Communications (MoTC) operates a rail network of 5,500 km. The rail transport
accounts for the bulk of freight transport (about 66 percent in 2013 excluding pipeline transport)
and a sizable but declining portion of the passenger traffic. Passenger rail transport – particularly
for transit journeys between Russia and Kaliningrad – struggles to compete with air travel
because of long journey times, while rail freight transport suffers from long loading and
unloading times. Belarus has around 86,660 kilometers of roads, including 75,030 kilometers of
hard-surface pavement which are generally in good condition, particularly for the Republican
road network. Belarus’ road sector is quite strategic and still accounts for about 34 percent of
freight and the majority of passenger traffic in the country. Aviation and inland waterway
transport remain insignificant with respect to passenger and freight traffic volumes, despite the
fact that aviation has seen some growth in the passenger market.
9. Road infrastructure development. In terms of road infrastructure, the main challenge is
the need to increase capacity in a safe manner on certain transport routes and corridors. Key road
corridors are now being upgraded to a Category 1 standard, which consists of four lanes, paved
shoulders and controlled access. These roads are equipped with high standard safety equipment
including central/side crash barriers and road lighting, the introduction of which is substantially
reducing the incidence of fatalities in vehicle accidents. There are two Trans-European
international corridors passing through Belarus which are Corridor II (Berlin – Warsaw – Minsk
- Moscow) which is the M1 road in Belarus and Corridor IX (Black Sea – Kiev – Minsk - Baltic
countries) which includes the M5, M7, M6 and M8. A section of the M5 was improved under the
first World Bank funded project, the Road Upgrading and Modernization Project (RUMP).
10. In addition to these formally defined international corridors there are also a number of
other major transit corridors linking Europe to/from Russia, Central Asia and China. The busiest
of these is the M6 which is the road to be upgraded to Category I standard under this project. The
M6 has a total length of 280 km in Belarus and connects Minsk with Grodno and then to Kuznica
at the border with Poland. On the Polish side the road connects through Bialystok to Warsaw
and about 110 of 250 km have already been improved to expressway standard and there are plans
to improve a further 90 km by 2017 and the remainder by 2019 partly with funding from the
3
European Union (EU). This corridor is one of the priority corridors identified under the Eastern
Partnership program of the EU.
11. Regional development and logistics. Belarus has a generally advantageous geographic
position, and physical infrastructure, that provides speed and flexibility to modern producers in
transporting perishables and high-value goods between Europe to/from Russia and Asia. Despite
unfavorable macroeconomic conditions, Belarus has been a net exporter of services in practically
all modes of transport, with total freight traffic volumes increasing slightly in 2012 to about 70.5
billion ton-km. Even though Russia is still the dominant trade partner for Belarus (35 percent of
exports, 60 percent of imports), trade between the Eurasian Customs Union (ECU) and the world
grew faster than trade among the three ECU members (Belarus, Russia and Kazakhstan).
However, the potential of Belarus as a transit and trade hub is presently far from fully exploited
and the overall performance of the Belarus logistics sector has been slipping relative to its
regional competitors. In 2008 it ranked 74th in the logistics performance index but has since
dropped to 91st in part due to complex and lengthy customs procedures at border crossing points.
The improved road infrastructure referenced above will only be fully effective if more is done to
facilitate the movement of trucks across the border in a timely manner. This project will work to
address border crossing delays on the M6 corridor.
12. Customs and border management. In an attempt to simplify procedures and facilitate
trade at border crossing points (BCPs), the Government of Belarus (GoB) is currently
implementing a reform, which will result in reducing the number of agencies at the border to
only two, namely State Customs Committee (SCC) and State Border Committee (SBC). The
SCC will be responsible for all government regulatory responsibilities (transport, sanitary,
veterinary, and phytosanitary inspections) and the SBC will be in charge of security (including
immigration controls). The SCC has already commenced administering MoTC technical
regulations (weight control). Delays at the border posts with Poland, which naturally link to the
M6 transit corridor, are to be reduced under the GoB reforms supported by the border
management enhancement component of this project, which will facilitate a reduction in rates of
physical inspections. The BCP at Bruzgi currently has a throughput capacity of 5,000 vehicles
per day, including 700 trucks. In 2013 the daily average number of truck movements through
Bruzgi was 815. To meet the growing demand, the SCC estimates that capacity may have to be
increased to 1,700 per day. In some instances it takes trucks in excess of 24 hours to complete
border clearance procedures, including waiting and queuing time. While such delays cannot
always be directly attributed to customs or other border management agency procedures, border
management is contributing to these delays through inefficient procedures as well as lack of
adequate infrastructure. Implementation of the ‘two agency’ policy will help address some of
these issues.
13. On May 29, 2014 the three members of Customs Union have signed an establishment
agreement to move from the Customs Union to a more integrated Eurasian Economic Union
(EAEU). The Customs Union came into effect on January 1, 2010 while the EAEU is to become
active on January 1, 2015. From a border management perspective the progression to an EAEU
is unlikely to have a major impact on this ‘outward facing’ EU border. Experience from Bank
projects with the other existing ECU members (Russia and Kazakhstan) suggests that most
impact occurs when the internal ‘fiscal’ borders between member states are eliminated (when the
4
customs union was established). It is possible however that Belarus will suffer some increased
border compliance ‘costs’, particularly regarding transit and standards/conformity.
14. Road sector reform. Belarus has a good capacity to plan, manage and maintain its road
infrastructure, with a very good track record over the past decades. The state operates several
enterprises for road design, planning, research, standards, maintenance, and construction. The
condition of the road network is generally good, which is due in large part to the adequate
allocation of resources for road maintenance over the past decades.
15. The road sector has undergone some reform over the last few years and as part of the
improvement of state management system, there has been some optimization of the institutional
structure at the MoTC. Until recently, the roads agency, Belavtodor, had responsibility for
planning, implementation and management of the network and “owned” the country’s
contractors and consultants. As part of the reform, Belavtodor has now been liquidated and
replaced by the Head Directorate of the Road Network, which is a structural unit responsible for
network management, at the MoTC. The new structure provides a road organization (‘Avtodor’)
in each Oblast to perform the project and road owner functions. A new organization called
Belavtodor Holding Management Company Republican Unitary Enterprise (RUE) was founded
in July 2013, which comprises 19 independently managed road and bridge contractors of Belarus
(i.e., large and small size construction companies). It is hoped that this framework will
eventually make the contracting industry in Belarus more competitive and capable of competing
internationally for works. In the future, the government could be in a position to consider that
some Oblast Avtodor functions related to maintenance could be separated.
16. Sustainable sector finance. Following a number of years of declining sector revenues
the government has undertaken important steps towards sustainable sector finance and has
introduced substantial increases in sector revenues and budget allocations for the road sector
starting in 2014. An important development is the promulgation of a new vehicle tax from
January 2014 which will be collected during the annual technical inspection of motor vehicles.
The new fee is expected to finance only capital expenditures including for instance financing for
the upgrading of road corridors such as the M6. The government expects to collect some BYR
1.6 trillion (US$160 million) from this new fee in 2014, out of which half will be for capital
expenditures in republican roads and half for capital expenditures on local roads.
17. Another significant development is the introduction of the e-tolling system, which has now
been deployed in selected roads in the country under concession to an international private
operator. The system has been operational since 2013, now covers 1,191 km and will be
expanded to cover all major road corridors including the M6 corridor, the modernization of
which will be financed under this project. Estimated revenues to the budget for 2014 are BYR
550 billion (US$55 million). Other sources of revenue include minor revenues from fuel excise
tax, axle load fees and transit cargo fees accounting for a further BYR 300 billion (US$30
million) per year.
18. Road safety. The Government of Belarus has been making continued efforts to improve
road safety in the nation. Since 2006, traffic accidents have been steadily decreasing, especially
in terms of fatalities and severe injuries. Recent statistics show a 30 percent fall in severe injuries
5
despite a threefold increase in automobile ownership since 1992. Belarus in general, is in the
middle range of road safety among European countries with relatively higher fatalities compared
with EU countries. In the current “Roads of Belarus” program till 2015, it was aimed to reduce
traffic fatalities by 100 every year, which is the so called “-100” program. For the new strategy
from 2015 till 2019, the goal is to fully eliminate traffic fatalities on main roads and road
corridors are now being upgraded to Category 1 standard, which includes high specification
safety equipment. A key issue now is with vulnerable road users including pedestrians and two
wheelers which account for 15 percent of road accidents. Bus stops are also a concern as many
are isolated and not equipped with lights at night, and therefore a source of insecurity, mainly for
women. The pedestrian crossings at bus stops are dangerous and the number of road accidents
involving a vehicle and a pedestrian on the M6 corridor increased from 15 in 2012 to 21 in 2013.
Improved design measures will be adopted in this project to adequately protect those using bus
stops and pedestrian crossings.
19. Road network management and user services. The overall management of the road
network is given high priority in Belarus to sustain a safe high quality road system. The MoTC
maintains good quality data on road condition, traffic levels, accident statistics and employs a
number of Intelligent Transport Systems (ITS) to monitor the road network and provide limited
feedback to users. These systems include e-tolling, temperature monitors, network cameras,
enforcement cameras, and the planned weigh-in-motion (WIM) system (financed under RUMP).
The outcomes from these initiatives are generally good with both the overall condition of the
network and level of road accidents comparing favorably to other countries in the region.
However, the MoTC wants to further improve its capacity for network management by properly
integrating the various systems so that data collection and analysis can be strengthened. The
results will be used to inform network development and maintenance priorities and to improve
user information. A key activity of this project will be the development of a Traffic and Road
Safety Coordination Center (TRSCC) to address these issues. Within the MoTC key
beneficiaries of the TRSCC will be the design institute (Belgiprodor) which periodically prepares
a prioritized “Roads of Belarus” program and the Oblast Avtodors to prioritize their maintenance
activities particularly during the winter months. Road users will benefit through improved road
information, better mechanisms to allow user feedback and citizens monitoring and improved
links with emergency services. This project will also support a more market-oriented approach to
the development of road-side services which are essential for road safety and overall user
comfort. The road-side services are also seen as a key way to promote small- and medium-sized
enterprises (SMEs) and employment in the more rural areas.
C. Higher Level Objectives to which the Project Contributes
20. This project supports a key area of the joint IBRD/IFC Country Partnership Strategy
(CPS) for the Republic of Belarus for the period of FY14-17, which focuses on improving
economic competitiveness, sustaining growth and job creation and boosting shared prosperity for
all citizens of Belarus. To address these objectives, one of the key actions is to increase
competitiveness of the economy through structural reform and improving the quality and
efficiency of public infrastructure. This project contributes to the overarching country goal to
increase economic growth, and create employment through an investment program which will
improve infrastructure critical to economic growth and export. The project will invest in the key
transit corridor connecting Belarus and Poland, and support the on-going reform of the roads and
6
customs sector and the move to commercialize key economic entities such as the contractors and
consultants.
21. The project will contribute toward alleviating poverty and boosting shared prosperity, the
two corporate goals under the World Bank Group strategy. By removing transport bottlenecks in
the national road network, it is expected that poor and disadvantaged communities will take
advantage of higher connectivity to get engaged in regional value chains, thus creating
possibilities for income generation. Additionally, improved transport links should contribute
towards improving the living standards of citizens by providing safer, quicker, and more reliable
access to public amenities.
22. Encouraging private sector participation in the transport sector is a key government
strategy. An infrastructure investment council and Public Private Partnership (PPP) unit has
recently been established under the leadership of the Ministry of Economy. A significant step has
been made in the roads sector with the first private sector concession for e-tolling which now
covers over 1,000 kms of the national road network, increasing revenues for the sector and
creating high quality private sector employment. This project will also promote private
participation in the roads sector through the development of road side services and provision of
open source data from the TRSCC. As traffic volumes increase on the main road network there
will be increasing interest from the private sector and having the correct investment framework
will be key to diversifying the economy.
23. The project will also contribute to broader country priorities as the institutional
components of this project move away from pure management of the infrastructure to take a
more user focused approach to service provision. The project through the TRSCC will not only
provide user information but will also encourage feedback and social accountability. In addition,
the evidence suggests that streamlining border clearance procedures will facilitate trade and
increase domestic job opportunities. The design of the infrastructure is also user focused with
attention to safety features particularly for pedestrians and security features around bus stops
particularly beneficial for women. With the expected increase in freight traffic on M6, the
corridor can serve as a strategic location for investors interested in supplying the EU and EAEU
markets. These infrastructure and institutional elements of the project will have a significant
impact in creating the opportunities that will contribute towards the alleviation of poverty and
boosting of shared prosperity.
II. PROJECT DEVELOPMENT OBJECTIVES
A. PDO
24. The Project Development Objective is to improve transport connectivity, border crossing
procedures and safety for domestic and international road users on selected sections of the M6
corridor.
B. Project Beneficiaries
25. The improvement of M6 transit corridor will bring better and safer connectivity and
improved logistics performance to both domestic and international road users. Main project
7
beneficiaries include road users who will have improved connectivity to border crossings, public
amenities and services, reduced travel time, reduced vehicle operating costs and reduced road
accident risks. These road users include long distance truck drivers, local road users, bus-users
and pedestrians. The local population will also benefit from improved connectivity and the
employment opportunities that will be generated through SMEs investing in the road side
services and other business opportunities. This will enable the local population, particularly the
poor and bottom 40 percent, to expand their income-generating opportunities beyond their
villages and towns, and to contribute to better and more sustainable livelihoods. The historical
growth data shows that the overall economic growth in Belarus has been equitably spread, with
the growth of the lowest 40 percent being nearly 3 percentage points above the overall growth.
Therefore, this project is expected to boost shared prosperity by contributing to the creation of a
more efficient and competitive road sector and to the overall economic growth for Belarus.
26. In addition, during road construction, the project will provide jobs for hundreds of skilled
and non-skilled men and women from the area, helping them learn skills, increase their income,
and lower unemployment rate for a fixed period of time. Improved border management
procedures will have a positive impact on logistics costs, attracting more international road users
and increasing economic opportunities for Belarus through provision of logistics (transport)
services for transit and supply of inputs to SMEs. This project will also contribute to
strengthening capacity of the MoTC, to better manage road traffic and road-side services,
improve road safety and promote citizen engagement.
27. In order to adequately monitor and evaluate the relevant transport induced effect on
project beneficiaries, baseline data will be collected jointly with IFC before project
implementation and follow up surveys will be undertaken at mid-term and the end of the project
period. More details are provided in Annex 7. The scope of work, methodological framework,
and data collection techniques will be further defined in close consultation with the MoTC.
C. PDO Level Results Indicators
28. The key indicators to measure successful achievement of the Project Development
Objective are as follows:
i) Reduction in travel time between Minsk and Grodno;
ii) Reduction in vehicle operating costs for medium trucks along the project road;
iii) Reduction in severe injuries and fatalities on road sections under this project;
iv) Reduction in average time to complete inwards border clearance procedures
(commercial vehicles) at Bruzgi BCP; and
v) Percentage of project beneficiaries expressing satisfaction with project roads.
III. PROJECT DESCRIPTION
A. Project Components
29. Component 1: Improvement of Sections of M6 Transit Corridor (total cost US$259.28
million of which US$239.27 million financed by IBRD loan). This Component will finance
widening works (from a two-lane road to a four-lane road) in selected sections of the M6
8
Corridor between the cities of Minsk and Grodno for approximately 86 km in the aggregate. It
will include the installation of central crash barriers, side barriers, bus stops, road signs and
markings and the improvement of vertical alignments located in selected sections of the M6
Corridor. The road improvement will meet two strategic objectives for the government by: (i)
improving links between Minsk and Grodno as part of their national strategy of connecting all
six Oblast centers to high standard roads; and (ii) developing international transit corridors to
promote cross border trade. The crucial M6 transit route provides links between Minsk, Grodno
and the Polish border. There are insufficient finances for the whole road but sections have been
prioritized based on their overall economic returns. The road will be designed for the European
standard axle load of 11.5 tons and also include two level interchanges and road safety features
according to European standards. The route carries a substantial proportion of transit traffic with
volumes averaging 5724 vehicles per day, of which 44 percent are trucks. This component will
also finance financial and technical audits, and consultancy services to supervise implementation
of Federation of Consulting Engineers (FIDIC) type of contracts for civil works. Through
counterpart financing, the government will finance the feasibility studies, engineering design,
technical and environmental supervision, land acquisition, and infrastructure loss. Following
improvement, the road will be tolled and have Weigh-In-Motion sensors installed (not financed
through this loan).
30. The road will be built to meet high safety standards and all designs will be signed off by
the traffic police. The majority of fatalities on the road are from head on collisions (37 percent)
and vehicle roll overs (19 percent). Fatalities involving pedestrians and cyclists (15 percent) are
also a key issue. This component will focus on the engineering measures to improve road safety,
including provision of central crash barriers along the entire road and side barriers in dangerous
locations, safer pedestrian crossings and bus stops, and signs and markings in select road
sections. In the highest risk part of the corridor, between km 198 and km 211, the vertical
alignment of the road will be improved to correct the current poor sight line.
31. Component 2: Road Safety and Network Management (total cost US$6.80 million of
which US$ 6.80 million financed by IBRD loan). This Component includes the following two
sub-components:
32. Sub-component 2.1: Traffic and Road Safety Coordination Center (total cost US$6.5
million of which US$ 6.5 million financed by IBRD loan). The proposed Traffic and Road
Safety Coordination Center (TRSCC) will be established within Beldor Center to promote safer
roads through improved traffic management, emergency response and traveler information
dissemination in the road sector. The TRSCC will collect and analyze road traffic and condition
related data and provide real-time feedback to users, such as on traffic congestion, detour
suggestions due to severe weather and road maintenance works. The data from the TRSCC will
also be available to other entities within MoTC such as Belgiprodor (the design institute) and the
Oblast Avtodors who are responsible for regional roads maintenance. The data will strengthen
their ability to manage the development and maintenance of the network and allow more
effective long term planning including the optimization of toll fees.
33. The MoTC has already set up hotlines for citizens to report road problems. In order to
further promote public participation and enhance government accountability, the MoTC will
apply Information and Communications Technology (ICT) tools such as crowdsourcing
9
techniques to promote citizen engagement in identifying accident black spots and other road
maintenance and safety issues from road users’ point of view. The TRSCC will also promote
public awareness campaigns on issues particularly related to road safety. The MoTC will
continue its engagement with the private sector on using these open source data to develop
applications for practical usage. The following activities will be financed for the establishment of
TRSCC:
i) Consultancy services including: (a) the preparation of the technical design of TRSCC
and the necessary bidding documents for its establishment; (b) the development of the
necessary monitoring and evaluation mechanisms including the design and
implementation of road users’ satisfaction surveys; the carrying out of impact
evaluations of road sector interventions; and the carrying out of road safety awareness
campaigns.
ii) Providing capacity building needed for staffing such a center and for the staff of other
MoTC entities to utilize the asset management tools of the TRSCC;
iii) Provision of ICT systems that will comprise the TRSCC and associated infrastructure,
including systems integration services and equipment.
34. Sub-component 2.2: Road-side services (total cost US$ 0.3 million of which US$ 0.3
million financed by IBRD loan). The provision of road side services is important for the safety
and convenience of road users but is also a potential source of employment for local
communities and particularly women. The MoTC already has a detailed master plan for the
development of road side services, regulations governing their use and the government is
providing some incentives for investors such as tax breaks. However, recent attempts to attract
investors have been largely unsuccessful partly because of constraints related to the availability
of land and finance but partly because of the overall investment framework. This activity,
coordinated with IFC, will finance: (i) the design and implementation of a market survey on
road-side services to identify user needs and private sector interests in the road transport sector;
and (ii) a review of MoTC regulatory framework for the development of road-side services based
on a market-oriented approach.
35. Component 3: Border Management Enhancement (total cost US$3.3 million of
which US$ 3.3 million financed by IBRD loan). This Component will finance activities designed
to improve the overall performance of border management in Belarus, facilitating the movement
of cross-border trade at the Bruzgi BCP by reducing average clearance times and the number of
transactions conducted when crossing the border. This component will support the
implementation and increase the effectiveness of the ‘two agencies at the border’ policy being
implemented in Belarus. It will also support national ambitions to transition to a one-stop-shop
approach as part of a single electronic window environment.
36. Through parallel finance, an IFC advisory services grant will be used to undertake a time
release study to identify current constraints in border clearance procedures and other technical
assistance activities to support business process improvements in response to areas of priority
identified by the SCC. The following activities will be included in this project:
10
i) Consultancy services to re-design the physical layout of the ‘inward’ registration,
vehicle control, processing and examination areas to allow implementation of the
revised business processes to be adopted by the SCC under the “two agency”
approach.
ii) Goods and works necessary for implementation of the physical layout proposed by
the re-design services.
B. Project Financing
37. The Bank will finance the project through an IBRD Investment Project Financing Loan
with the total amount of US$250 million.
C. Project Cost and Financing
38. The total project financing requirements are estimated at US$270.01 million. Table 1
shows the financing for each component.
Table 1: Project Cost and Financing
Project Components
Project cost
(million US$)
IBRD Financing
(million US$)
IBRD
Financing (%)
Component 1: Improvement of Sections of M6
Transit Corridor 259.28 239.27 92.3%
Component 2: Road Safety and Network
Management 6.8 6.8 100%
Component 3: Border Management Enhancement 3.3 3.3 100%
Front-end-fee (0.25%) 0.63 0.63 100%
Total 270.01 250 92.6%
39. All contracts to be financed under the project will be exempt from VAT. The government
will contribute US$20.01 million from the state budget to cover the costs for technical and
environmental supervision, land acquisition, and infrastructure loss.
D. Lessons Learned and Reflected in the Project Design
40. Strong implementation capacity. Implementation of RUMP is satisfactory and the
implementing agency has demonstrated strong capacity to prepare designs and safeguard
assessments and to subsequently manage their implementation. However, experience from the
RUMP suggests that decisions made at the ministerial level can sometimes be overturned
(permanently or temporarily). The project legal agreement needs to consider introducing
sufficient flexibility to allow minor changes without major restructuring and complex approval
processes.
41. Procurement of contractors. Experience from Belarus and more widely in the region is
that some contractors present very low prices in the winning bids and afterwards delay the
execution of works through requests for variations. There is also a problem where large
international contractors obtain awards and then sub-contract a significant portion of works to
11
local contractors. For this project particular attention will be given to prequalification criteria and
the past performance of contractors in the region.
42. International best practice. The experience from the ongoing project (RUMP) indicates
that MoTC is a quick adopter of innovative practices in the sector. The MoTC is well advanced
implementing e-tolling, WIM and other network management tools and are now looking to
incorporate international best practice to bring these tools together in support of improved
network management. Through the inclusion of components such as the TRSCC and private
sector involvement with road side services, the project is designed to increase the client’s
exposure to these solutions. IEG project reviews support the positive role that the Bank can have
in catalyzing such integration.
43. Logistics performance. Substantial work has been carried out through the on-going
project on the diagnostics of the logistics sector. The government has also invested heavily in the
supporting infrastructure. However, the experience is that the elements of the logistics chain are
being addressed independently of one another. Through the inclusion of Component 3, the
design of this project will seek to improve coordination and a more seamless logistics chain.
IV. IMPLEMENTATION
A. Institutional and Implementation Arrangements
44. The project will be implemented over a five-year period by the MoTC, which is the
national authority in charge of road construction and maintenance in Belarus and will have the
overall responsibility for project coordination and monitoring of implementation progress. The
MoTC has formally delegated the responsibility for managing the day-to-day preparation and
implementation of the proposed project to the Republican Unitary Enterprise Minskavtodor-
Center (MA-C). MA-C is a unit of the MoTC in charge of the management and maintenance of
the Republican road network in Minsk oblast.
45. Within MA-C, a Project Implementation Team (PIT) was created in 2009 for the on-
going RUMP Project, which consists of experienced engineering, procurement and financial
management staff. The PIT will be augmented by staff from Grodnoavtodor (responsible for the
region where much of the proposed road is located under component 1). The PIT has less
experience with social issues and the team from Grodnoavtodor has not worked with the Bank
before. The Road Design Institute (Belgiprodor) and the National Academy of Sciences will be
involved in monitoring the adherence to environmental safeguards requirements. Beldor Center
will coordinate implementation of the TRSCC under component 2 of the project.
46. MA-C will also be responsible for the implementation of the border management
enhancement component although the day to day management of the component will be done by
the SCC of Belarus and its Grodno Regional Customs Agency (GRCA). Both the SCC and
GRCA will assign coordinators (project managers) responsible for project implementation to
work closely with the MoTC and MA-C. The customs agencies will be responsible for the
overall design and implementation quality of this component. They will prepare terms of
reference for design documents (or approving design documents when they are available),
ensuring appropriate technical supervision of the contracts, accepting payment orders, and
12
submitting adequate documentation to the MA-C so that it can prepare and sign withdrawal
applications. The customs agencies will prepare bidding documents for Component 3, identify
personnel to sit on procurement committees and jointly sign with MA-C relevant contract
documents.
47. The Bank will continue supporting the various entities with the necessary training on the
use of World Bank guidelines and procedures for procurement, financial management and
environmental/social safeguards management. Before and after project effectiveness, the PIT
staff will receive targeted training on land acquisition and resettlement given their more limited
experience in this area.
48. The implementation arrangements specified above will be formalized through an Inter-
Ministerial Resolution setting out MA-C as the sole implementing entity. This resolution will
also set out the roles and responsibilities for the other beneficiaries including Grodnoavtodor for
component 1, Beldor Center for component 2 and SCC and GRCA for component 3 of the
project.
B. Results Monitoring and Evaluation
49. The Results and Monitoring (R&M) Framework developed for the project is included in
Annex 1. The overall monitoring and evaluation will be the responsibility of the MA-C except
that SCC will be responsible for the R&M for Component 3. The PDOs will be monitored and
reported through periodic World Bank implementation support missions every six months. The
MA-C and SCC will conduct frequent inspections to prepare quarterly and annual progress
reports with detailed evaluation surveys and analysis. It is expected that the TRSCC will also
collect beneficiary satisfaction data in a variety of formats which will be used for project R&M.
Much of this data will be network wide but where possible the data will be specific to the project
interventions and provide for gender disaggregated data.
50. In order to identify the channels through which the project will impact the beneficiaries,
adequately measuring the relevant transport-induced effect on their livelihoods, baseline data
will be collected. Mid-term and end of project survey data will also be collected and compared
against a proper comparison group in an effort to capture project-related impacts on selected
welfare and accessibility indicators. More details are provided in Annex 7. To allow for possible
differences in demands and experiences from women and men, the surveys will consult with
women and men separately, ask gender specific questions and will allow disaggregation of data
by gender.
51. The ongoing project (RUMP) did not require land acquisition and resettlement whereas
the proposed new project will have to address these issues. As such the Bank will provide
additional support to MA-C and Grodnoavtodor in this area to ensure that their specialists have
the necessary knowledge and training. The Bank team will monitor the implementation of the
Resettlement Action Plans (RAPs) in the course of its regular monitoring missions.
13
C. Sustainability
52. The sustainability of the project depends on the institutional, technical and financial
capacity in the long term to provide adequate and regular maintenance of the road infrastructure
and maintain the smooth and safe traffic flow along the M6 corridor. This project will provide
technical support to the SCC to improve customs border control on M6, so that freight traffic
will be improved. This project will also support the MoTC to establish the TRSCC, which will
provide the MoTC and Beldor Center with state-of-the-art equipment for highway monitoring,
operations and maintenance. It will be the technical and institutional hub to bring together
various jurisdictions, modal interests, and service providers to optimize the performance of the
surface transportation system. Additionally, this project will support improving / expanding road
side services which will make this corridor more attractive. Finally, the road safety initiative will
help ensure this corridor is safe to travel and thus sustainable in the long run.
V. KEY RISKS AND MITIGATION MEASURES
A. Risk Ratings Summary
Table 2: Risk Ratings Summary
Risk Category Rating
Stakeholder Risk Low
Implementing Agency Risk
- Capacity Moderate
- Governance Moderate
Project Risk
- Design Moderate
- Social and Environmental Moderate
- Program and Donor Low
- Delivery Monitoring and Sustainability Low
Overall Implementation Risk Moderate
B. Overall Risk Rating Explanation
53. The overall implementation risk rating for the project is Moderate. The government and
implementing agencies have experience implementing World Bank financed projects and the
outcomes have been good in terms of the quality of the infrastructure. Environmental
management has been very good to date but there is less knowledge on land acquisition and
resettlement, and while Grodnoavtodor is one of the most experienced implementing agencies in
Belarus it has not had experience with World Bank procedures to date. The design of the project
is relatively straight forward in terms of the civil works component but there is a substantial
14
institutional component and the implementation arrangements are complicated given the
involvement of both the MoTC and SCC. The overall risk rating for the project is moderate.
VI. APPRAISAL SUMMARY
A. Economic Analysis
54. The economic feasibility of this project was assessed based on an analysis of the vehicle
operating costs savings and users’ travel time reduction as well as reduced road traffic fatalities
resulting from the improvement of the project road. Savings in vehicle operating costs were
evaluated using the Highway Development and Management Model, HDM-4 (version 2.8),
which computes annual costs for the road agency and road users for with and without project
alternatives over the evaluation period. Benefits arising from road safety improvements were
assessed using the estimated reduction of fatalities along the road, and the monetary value of loss
of human life, evaluated on the basis of the current income level.
55. The existing two-lane road will be widened to four-lanes. The average annual daily traffic
on the concerned road sections in 2013 was 5,724 vehicles per day with 44 percent composed of
trucks. The existing road has a bituminous pavement in fair condition with an average riding
quality, measured by the International Roughness Index (IRI), at 3.7-4.3 m/km. The total
economic construction cost is estimated to be US$237.87 million, which corresponds to
US$2.75 million per km. The road improvement investments under Component 1 are
economically justified with a total NPV of US$156.7 million, at 8.95 percent discount rate, and
an overall Economic Internal Rate of Return (EIRR) of 16.2 percent. Even under the pessimistic
scenario of increasing costs by 15 percent and decreasing traffic growth rate by 15 percent, the
project is still economically justified with an EIRR higher than 12.9 percent. The switching
values analysis shows that costs would have to increase by 105 percent to yield an EIRR equal to
8.95 percent, which indicates a robust economic justification of the project. The outcomes of the
economic evaluation are summarized below in Table 3, with more details provided in Annex 6.
Table 3: Economic Evaluation Summary
NPV EIRR B/C
Section Location (Million US$) (%) Ratio
1 km 57.2 to km 91.07 52.4 13.9% 0.44
2 km 91.07 to km 130.4 56.4 16.6% 0.60
3 km 197.7 to km 211.0 47.9 25.3% 1.62
Total 156.7 16.2% 0.72 Source: World Bank Calculations
56. Rationale for public sector financing. With few exceptions, roads are a public good that
are provided and often managed by the public sector. In this case public sector financing is also
the appropriate vehicle for financing the improvement of the project road. This is because while
the road sections are economically viable, traffic is not high enough to generate sufficient
financial receipts to justify a concession to the private sector for their improvement and
management. Following completion, in this case, a private sector concession will be used for
subsequent tolling. In addition, public investment and management of road infrastructure
15
provides the government a better handle to exercise control over key activities such as the
enforcement of axle weight control, and road safety regulations.
57. Value added of Bank's support. The World Bank is well positioned to support Belarus
in the sustainable investment and management of its road network with modern traffic
management practices and the incorporation of road safety in project designs, particularly for
vulnerable road users. In addition, the Bank’s international experience and expertise in the road
sector will help ensure the use of reliable procurement processes, sound social and environmental
management practices, the application of modern technical standards, and the execution of work
with proper quality control. Similarly, regarding the border management enhancement, the
Bank’s experience will help ensure best practice outcomes.
B. Technical
58. The detailed engineering design for the three sections of road to be upgraded has been
completed by Belgiprodor according to Belarusian standards that are a further improvement from
norms of the former Soviet Union, with adaptation to European axle loads. The road will be
widened to four lanes, and will include modern safety equipment including central crash barriers
and side crash barriers where required. The road will include the construction or reconstruction
of grade separated interchanges and bridges, include provision of fiber optic cables and will
ultimately be tolled and equipped with a weigh-in-motion system.
59. The pavement design is based on the use of Stone Mastic Asphalt (SMA), which provides
a deformation resistant and durable surfacing material, suitable for heavily travelled roads. SMA
has a high coarse aggregate content that interlocks to form a stone skeleton that resists permanent
deformation, including deformation caused by large temperature variations such as those present
in Belarus. SMA is an efficient solution for Belarus and its climate and has already been used
extensively in the country.
60. Road safety issues are addressed both through sound engineering design and the
implementation of a detailed traffic management plan during construction. The upgrading of the
road from two lanes to four lanes will provide the alignment with a median, which has very
positive effects on safety, given that most fatalities on that road are caused by head-on collisions.
Placement of metal guardrails will all but eliminate cross-median head-on crashes while
mitigating median-related crashes through adequate shock absorption. The choice of provision of
central cable (crash) barriers and reinforced shoulders has been made, because this has shown the
potential to further improve safety. Several grade separated interchanges will provide a safe
environment for crossings of the M6 road. Speed limits will be adjusted along the alignment at
the remaining level crossings. On the section in Grodno region (km 198- km 211) the vertical
alignment will be changed for improving visibility and bringing sharp horizontal and vertical
curvatures to the standards for category I roads (highways).
61. Particular attention has been given to pedestrian crossing and bus stop design to provide
additional safety for road users. Given low pedestrian numbers most pedestrian crossings will be
at grade but designers have adopted best practice and included staggered crossings, central
holding areas, and direct and approach lighting along with advance warning signs. Bus stops will
also have direct lighting and deceleration lines. The road will also include rest stops, sidewalks
16
to bus stops and crossings, traffic signs and deceleration lines on all exits to the road. Moreover,
the rest stops will include “economic zone” for possible commercial road services with parking
area for freight, passenger cars and disabled people - located as close as possible to the facilities.
During construction a traffic management plan, which will be reviewed and certified by the State
Motor Vehicle Inspection Department, will include diversion roads, temporary signs and
markings. In addition, through the establishment and functioning of the TRSCC, traffic accident
response time will be reduced and thus more lives can be saved following severe traffic
accidents.
62. Among engineering structures such as culverts and cattle crossings, design includes
social and environment protection measures such as noise protecting barriers, fencing to protect
against wild animals and measures to ensure the minimum influence during road construction
works. The TRSCC will integrate the various Intelligent Transport Systems that are available in
Belarus to improve monitoring, operations and maintenance of the road network and feedback of
road user information. This will support user satisfaction, road safety and road maintenance.
C. Financial Management
63. Financial management (FM) arrangements for the implementation of the project are
Satisfactory, and related FM risk is Moderate. The FM assessment focused on the capacity
assessment of Minskavtodor-Center (MA-C), which was appointed by MoTC as the agency
responsible for the technical implementation of the project, including financial management of
all project components. MA-C is in process of implementing RUMP, and therefore the current
assessment was based on the FM arrangements that are in place for the ongoing project, with
additional focus on strengths and weaknesses identified during its implementation. A number of
roads agencies, and particularly Grodnoavtodor RUE and the SCC will also be engaged in the
project implementation, particularly on the technical side of the project. Given the successful
experience of MA-C in the day-to-day implementation of the ongoing project, the fiduciary
responsibilities will continue to be carried out by MA-C in the new project.
64. The FM and disbursement capacity of the MA-C has grown substantially during the years
of implementation of the first project, and the FM arrangements were confirmed as Satisfactory
during the latest FM monitoring visit in September 2014. All key aspects of FM and
disbursement of the project are in place; although the MA-C was still to address the findings of
its auditors related to the accounting and reporting procedures of MA-C (auditors’ findings do
not affect the validity of project records, but are related to general capacity building of MA-C).
The audit reports issued on project financial statements for the last years were all unqualified
(clean). Requirements on quarterly reporting and annual auditing were fully and timely complied
with, including requirement on public disclosure of audits.
65. The Transit Corridor Improvement Project will continue to use the same experienced
fiduciary staff of MA-C for project implementation. Project accounting will be done in the same
accounting software (Galaktika), on a segregated set of accounts. Quarterly IFRs will be
prepared, and will include information on all components and contracts under implementation.
Annual audit of project financial statements will be carried out by eligible private auditors.
Additionally, MA-C will continue to submit the audit of its consolidated financial statements
prepared under requirements of National Accounting Standards, mainly for the purposes of
17
capacity building. A Project Operational Manual (POM) including the FM sections will need to
be adopted prior to effectiveness. Details of the FM arrangements, including disbursement
arrangements, are provided in Annex 3.
D. Procurement
66. Procurement activities under the proposed project would be carried out by Minskavtodor-
Center (MA-C) – Project Implementation Team (PIT), in accordance with the World Bank’s
“Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD Loans
and IDA Credits and Grants by World Bank Borrowers,” dated January 2011 and revised on July
1, 2014 and “Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA
Credits and Grants by World Bank Borrowers,” dated January 2011 and revised on July 1, 2014,
and the provisions stipulated in the Loan Agreement. A procurement assessment initiated in
April 2014 concluded that the PIT has adequate experience and capacity to carry out the
procurement activities related to the project. Taking into account MA-C’s long experience with
Bank-financed projects and successful implementation of the ongoing project (RUMP), the
assessment found the overall procurement risk for the project to be Moderate.
67. There is a potential risk of delays in the implementation of the procurements, especially for
large civil works contracts. In addition, in civil works contracts there is a risk of cost overruns
due to variation orders and claims. To mitigate the procurement risks the PIT will implement
measures agreed with the Bank which will include: (i) preparation of bidding documents for the
first year of project implementation for Component 1 in advance; (ii) a business outreach
organized by the PIT for the private sector on future business opportunities under the project
before launching first bidding procedures; (iii) the hiring of a consultant, experienced in FIDIC
type of contracts, who will assist the PIT in supervision of large civil works; (iv) the preparation
of procurement progress reports by MA-C during project implementation.
68. The Bank will closely supervise the project and will review the procurement arrangements as
performed by the PIT—including contract packaging, applicable procedures, methods, and the
scheduling of procurement processes—for conformity with the Loan Agreement, the proposed
implementation program, and the disbursement schedule. The Bank’s prior review thresholds
will be provided in the agreed Procurement Plan. The remaining procurement procedures, will be
subject, on a random basis, to the Bank’s ex-post review. One in 10 contracts under the project
will be subject to ex post review. More detailed findings of the assessment, the proposed
procurement arrangements, and measures to address the identified risks are presented in Annex
3. The Procurement Plan covering the first 18 months of the project implementation has been
agreed by the Bank and is presented in Annex 3.
E. Social (including Safeguards)
69. Safeguards: The project will require land acquisition from about 20 private owners for
widening the road from two-lane to four-lane. This will also cause small scale physical
displacement of about 5 households and one or two cases of economic displacement. The exact
number of people affected will be known after the technical design for the section of the road in
Minsk region is completed. A Resettlement Policy Framework (RPF) was prepared for the
project, agreed by the Bank and disclosed in Belarus in Russian and in English in Bank’s
18
Infoshop in May 2014. A Resettlement Action Plan (RAP) was prepared for the section of the
road in Grodno oblast where the technical designs have been completed and the exact alignment
known (km 57.2 - 91.1 and km 197.7 - 211.0). The Grodno RAP was agreed by the Bank and
duly disclosed in Russian on the site of Grodnoavtodor and in Bank Infoshop on September
2014. The RAP for the remaining section of road in the Minsk oblast (km 57.2 - 91.1) will be
prepared once the technical designs for that section have been completed and the exact alignment
known. The designs for the Minsk section were started after those in Grodno and are being
developed to avoid the acquisition of private land to the extent possible and to obey the sanitary
norms of the country. The PIT will identify the specialist responsible for monitoring the
implementation of the RAPs and reporting to the Bank on resettlement implementation. Bank’s
specialists will monitor resettlement issues in the course of their regular implementation support
missions. The hot line of the MoTC will be used as additional grievance mechanism for project
implementation and resettlement monitoring. The grievances and queries related to the project
will be redirected to the project support team for addressing them.
70. Social Accountability: A wide consultative process to identify the key problems and
opportunities for strengthening the project impact will be supported by the project. Business
associations of the international cargo services (such as BAIRC2) and trade unions of transport
workers will be involved in discussing the road improvements and providing their feedback on
the road safety, roadside services organization, and overall improvements in functioning of the
transport corridor as the result of the project. Beldor Center will be supported in engaging
citizens in identifying black spots and road safety concerns around the M6 corridor using ICT in
the TRSCC.
71. Gender Considerations: In the framework of establishing the TRSCC the project will
support Beldor Center in improving the monitoring of the roads sector and collecting gender
disaggregated information on travel needs, road users’ satisfaction, and complaints. Road safety
improvements will be conducive to reducing the number of traffic accidents and improving
safety on the roads both for men and for women. Some of the improvements on the road (lighting
at bus stops) will particularly benefit women by providing them with a safer travel environment.
Given that the optimization of the highway will entail the development of local roadside
infrastructure and services, this may have a positive impact on the increase of small businesses
run both by men and women and will create additional employment opportunities for rural
women in the non-agricultural sector (the service sector is largely represented by women).
F. Environment (including Safeguards)
72. The road alignment runs through the landscape which has been modified by human
activity (mainly agriculture and forestry) for many decades. Environmental impacts of road
rehabilitation/repairs, road widening and road infrastructure safety improvements will be
undertaken within the existing right of way of the road. These impacts are similar to those under
the ongoing RUMP and broadly include: (i) air pollution and noise from trucks, other
construction machinery and asphalt plants, (ii) soil disturbance, and (iii) tree-cutting. These
environmental impacts can be mitigated by good construction and housekeeping practices. Based
2 http://www.bamap.org/activities/about/regions/
19
on the nature and scope of anticipated negative environmental impacts the project is assigned
Environmental Category B.
73. A corridor-specific Environmental Impact Assessment/OVOS (EIA/OVOS 2013),
documenting baseline conditions and environmental risks for the road alignment was prepared
along with section specific Environmental Management Plans (EMPs). These documents were
disclosed and consulted upon in country in November-December 2013 and June-July 2014.
InfoShop disclosure took place in September 2014. The EIA/EMP indicates that the alignment
goes through the territory of the nature protected area (Zakaznik Naliboksky) at km 78.400 – km
100.00. The status of the protected area was given to Zakaznik Naliboksky in 2005 when the
road already existed and – according to local experts – one of the main reasons for protected
status was to keep this area as a hunting ground. On-the-ground verification with participation of
local environmental specialists suggests that the areas of Zakaznik Naliboksky in the immediate
proximity to the projected alignment do not represent significant ecosystem value. Cutting of
low-value tree species will be needed for the purposes of construction. Also, the Ministry of
Natural Resources and Environmental Protection of Belarus in its letter dated March 7, 2013
provided no-objection to the Scheme of the alignment within the boundaries of Zakaznik
Naliboksky in Grodno oblast.
74. Special mitigation measures to protect potentially affected animal species – as
recommended by the EIA/EMP – are being taken into account by the design and the trajectory of
the alignment will be adjusted accordingly. Environmental mitigation measures for construction
phase, including special engineering solutions for protection of amphibians and hooved animals
(underpasses and guide way fencing) have been proposed by the EIA/EMP and are being
incorporated in the design.
75. The proposed interventions at the border checkpoint involve minor expansion of the
border guards’ area (from 2 lanes each way to 4 lanes each way), and minor works (construction
of scale points, booths for custom officers, open sheds) at the paved area of the checkpoint.
Impacts will be site-specific and minor (installation of pre-fabricated sheds and small scale
construction). No significant negative environmental impacts are expected. Site-specific
mitigation measures have been developed with preparation of detailed design documentation.
G. Other Safeguards Policies Triggered
76. There are no registered historic or cultural heritage sites in the project area and standard
chance finds procedure is applied and in case of chance finds (immovable or movable) the
contractor and/or other parties involved follow the procedure prescribed by the legislation of
Belarus.
20
Annex 1: Results Framework and Monitoring
Country: Belarus
Project Name: Transit Corridor Improvement Project (P149697)
Results Framework
Project Development Objectives
PDO Statement
The Project Development Objective is to improve transport connectivity, border crossing procedures and safety for domestic and
international road users on selected sections of the M6 corridor.
These results are at Project Level
Project Development Objective Indicators
Cumulative Target Values
Indicator Name Baseline YR1 YR2 YR3 YR4
YR5
End Target
Reduction in travel time
between Minsk and Grodno
(min)
220 220 220 210 198 178 178
Vehicle operating costs for
medium trucks, along the
project road reduced
(US$ veh-km)
0.55 0.55 0.55 0.53 0.53 0.495 0.495
Reduction in average time to
complete inwards border
clearance procedures
0
Target data will be
provided once the time
release study has been
21
(commercial vehicles) at
Bruzgi BCP
(Minutes)
completed
Reduction in severe injuries
and fatalities on road
sections under this
project(Number)
35 35 35 30 30 21 21
Percentage of project
beneficiaries expressing
satisfaction with improved
travel experiences through
implementation of TRSCC
and new road-side
services(Percentage)
0
Target data will be
provided once base line
surveys have been
conducted through the
TRSCC
Intermediate Results Indicators
Cumulative Target Values
Indicator Name Baseline YR1 YR2 YR3 YR4
YR5
End Target
Roads constructed, non-rural
(kilometers) – (Core) 0 10 25 50 86 86 86
Development of a Traffic
and Road Safety
Coordination Center
(TRSCC)
No
Specification
for TRSCC
prepared
Oblast
Avtodor staff
trained in the
asset
management
tools of the
TRSCC
TRSCC operational and
providing regular road
agency and road user
information
Improved climate for SME
investment in road side
services
No
Market
survey
conducted
revised
market
oriented
framework
Revised market oriented
framework for road side
services prepared using
findings from market
22
for road side
services
prepared
survey
Implementation of the “in –
channel” clearance
procedures policy by State
Customs Committee
No
Time release
study
completed
Specifications
for
infrastructure
improvement
prepared
In – channel
clearance
policy
operational
Final time
release study
In – channel clearance
policy operational with
demonstrated reduction in
procedures and clearance
time
Direct project beneficiaries
(number), of which female
(percentage):
Short term construction jobs:
Long term maintenance/road
side services jobs:
Daily road user and border
crossing beneficiaries:
Annual road safety
beneficiaries:
0
600 (30%)
1200 (30%)
1200 (30%)
275 (36%)
26,575
65 (40%)
275 (36%)
26,575
65 (40%)
275 (36%)
26,575
65 (40%)
23
Indicator Description
Project Development Objective Indicators
Indicator Name Description (indicator definition etc.) Frequency Data Source /
Methodology
Responsibility for Data
Collection
Reduction in travel time
between Minsk and Grodno
(minutes)
This indicator measures the average travel time
reduction along the M6 corridor. This indicator
will be measured at the end of the project and
will be monitored annually for the roads
improved under the project.
Annual Project Progress
Reports
MoTC
Vehicle operating costs for
medium trucks, along the
project road reduced
This indicator measures the vehicle operating
costs for medium trucks along the M6 corridor
to be improved under the project. Vehicle
operating costs are expressed in US$ per
vehicle-kilometer. This indicator will be
measured at the end of the project and will be
monitored annually for roads improved under
the project.
Annual Project Progress
Reports
MoTC
Reduction in average time
to complete inwards border
clearance procedures
(commercial vehicles) at
Bruzgi BCP (Minutes)
This indicator will measure the impact on the
average time required for commercial vehicles to
complete the inwards border clearance
procedures at Bruzgi BCP
Annual Time release study and
SCC customs data
SCC
Reduction in severe injuries
and fatalities on road
sections under this project
This indicator will measure the reduction of
severe injuries and fatalities on road sections
under this project
Annual Project Progress
Reports
MoTC
Percentage of project
beneficiaries expressing
satisfaction with improved
travel experiences through
implementation of TRSCC
and new road-side services
(Percentage)
This indicator will measure the percentage of
project beneficiaries that express satisfaction
with the improved travel experiences through
implementation of TRSCC and new road-side
services
Annual Project Progress
Reports
MoTC
24
Intermediate Results Indicators
Indicator Name Description (indicator definition etc.) Frequency Data Source / Methodology Responsibility for Data
Collection
Roads constructed, non-
rural (kilometers) – (Core)
This indicator will measure the distance of
the M6 corridor that will be improved
under this project. This is a core indicator
of the World Bank.
Quarterly Project Progress Reports MoTC
Development of a Traffic
and Road Safety
Coordination Center
(TRSCC)
This indicator will measure the
development of the TRSCC
Quarterly Project Progress Reports Beldor Center
Improved climate for SME
investment in road side
services
This indicator will measure the
improvement of investment climate for
SME to participate in providing road side
services
Quarterly Project Progress Reports MoTC
Implementation of the “in –
channel” clearance
procedures policy by State
Customs Committee.
This indicator will measure the
development of the improved physical
environment necessary to give effect to the
policy.
Quarterly Time release study and
SCC customs data
SCC
Direct project beneficiaries
(number), of which female
(percentage)
This indicator measures the number of
direct project beneficiaries and percentage
of female beneficiaries among them.
Annual Project Progress Reports MoTC
25
Annex 2: Detailed Project Description
BELARUS: Transit Corridor Improvement Project (P149697)
1. The Project Development Objective is to improve transport connectivity, border
clearance procedures and safety for domestic and international road users on selected sections of
the M6 corridor.
2. Component 1: Improvement of Sections of M6 Transit Corridor (total cost
US$259.28 million of which US$239.27 million financed by IBRD loan). This Component will
finance the reconstruction and upgrading of selected sections of the M6 road, from a two-lane to
a four-lane road. The road improvement will meet two strategic objectives for the government
by: (i) linking Minsk to Grodno as part of their national strategy of connecting all six Oblast
centers to high standard roads; and (ii) developing international transit corridors to promote cross
border trade. The crucial M6 transit route provides links between Minsk, Grodno and the Polish
border. This component will finance the extension of the current four lane road from Minsk for a
further 73.2 kilometers (km 57.2 to km 130.4) and extend the current four lane road from Grodno
for a further 13.3 kilometers (km 197.7 to km 211.0). There are insufficient finances for the
whole road but these sections have been prioritized based on their overall economic returns. The
road will be designed for the European standard axle load of 11.5 tons and also include two level
interchanges and road safety features according to European standards. The route carries a
substantial proportion of transit traffic with volumes averaging 5,724 vehicles per day, of which
44 percent are trucks. The Bank will also finance financial and technical audits. Through
counterpart financing, the government will finance the feasibility studies, engineering design,
technical and environmental supervision, land acquisition, and infrastructure loss. Following
improvement, the road will be tolled and have Weigh-In-Motion sensors installed (not financed
through this loan).
3. The road will be built to meet high safety standards and all designs will be signed off by
the traffic police. The majority of fatalities on the road are from head on collisions (37%) and
vehicle roll overs (19%). Fatalities involving pedestrians and cyclists (15%) are also a key issue.
This component will focus on the engineering measures to improve road safety, including
provision of central crash barriers along the entire road and side barriers in dangerous locations,
safer pedestrian crossings and bus stops and signs and markings in select road sections. In the
highest risk part of the corridor, between km 198 and km 211, the roads vertical alignment will
be improved to correct the current poor sight line.
4. The widening of the road will be carried out almost exclusively within the existing right
of way, as the proposed road follows the alignment of the existing two-lane road. No major
technical issues are expected during the construction, given the flat terrain and well-known soil
conditions. Nevertheless, some sections of the road require the removal of peat and other
unsuitable materials up to several meters depth. This, combined with the high water table in
those areas, requires specific equipment and capacities of the contractors. The construction
works will be divided in three sub-sections (or lots).
5. The road will follow the geometric standards of Category I-b in line with national
standards as follows:
26
Cross Profile Parameter Standard Specifications
Road Category I-b
Type of Road National Roads, 1st class access roads to airports and rings
around cities
Traffic level threshold Over 10,000 vehicle /day
Speed Limit 100 km/h
Number of lanes 4
Lane width 3.5
Carriageway width 7x2
Shoulder width 3
Minimum Median width At least 2 meters, equipped with metal guardrails
Total roadway width 22+ s
6. The pavement design is based on the use of Stone Mastic Asphalt (SMA) for covering,
which provides a deformation resistant and durable surfacing material, suitable for heavily
travelled roads. SMA has a high coarse aggregate content that interlocks to form a stone skeleton
that resists permanent deformation, including deformation caused by large temperature variations
such as those present in Belarus. SMA is an efficient solution for Belarus and its climate and has
already been used extensively in the country.
7. Road safety issues are addressed both through sound engineering design and the
implementation of a detailed traffic management plan during construction. The upgrading of the
road from 2 lanes to 4 lanes will provide the alignment with a median, which has very positive
effects on safety, given that most fatalities on that road are caused by head-on collisions
Placement of central crash barriers will all but eliminate cross-median head-on crashes while
mitigating median-related crashes through adequate shock absorption. The choice of provision of
central cable (crash) barriers and reinforced shoulders has been made, because this has shown the
potential to further improve safety as they have a greater Accident Modification Factor (AMF).
Several multi-level interchanges will provide a safe environment for crossings of the M6 road.
Speed limits will be adjusted along the alignment at the remaining level crossings. Pedestrian
connections, including underpasses, will facilitate safe connections between left and right hand
sides of the road. Road lighting will be included at several sections of the alignment in order to
increase visibility and facilitate pedestrian movements and safety. A traffic management plan,
that will be reviewed and certified by the State Motor Vehicle Inspection department, will
include diversion roads, temporary signs and markings.
8. Design is being carried out by the national design institute Belgiprodor, which was
founded in 1932. Design has been developed according to Belarusian standards that are a further
development from norms of the former Soviet Union, with adaptation to European axle loads.
Belgiprodor, the leading design organization of Belarus in the field of engineering, research and
design of roads, bridges and airfields has about 450 staff members including a technical and
engineering department, and is certified ISO 9001:2008. Belgiprodor has actively participated in
many major road project designs and supervision in Belarus, including more recently the
27
reconstruction of the Minsk ring road (Category I, 6 lanes), the modernization of the road M5
Minsk-Bobrujsk (Category I), which was funded from the World Bank loan, the road M-1/E-30
Brest-Minsk (Category I), the M-2 Minsk-National airport Road, the reconstruction and repair of
roads in a 50-kilometer zone of Minsk in line with Category I-B, and the reconstruction of the
road R-20 Vitebsk-Polotsk-Latvia (Category II). All these projects have demonstrated sound
design, including modern road safety features, and their actual condition is generally good; i.e.
none of these roads shows premature fatigue or deformation.
9. Component 2: Road Safety and Network Management (total cost US$6.80 million of
which US$6.8 million financed by IBRD loan). This Component includes the following two sub-
components:
10. Sub-component 2.1: Traffic and Road Safety Coordination Center. The proposed
Traffic and Road Safety Coordination Center (TRSCC) will be established within Beldor Center
to promote road safety through improved traffic management, emergency response and traveler
information dissemination in the road sector. The TRSCC is likely to comprise the following
elements: (a) equipment for the center itself, including high performance servers, storage
capacity, modular high definition monitors and networking equipment, among others; (b) a
specialized software providing the functionality of a management information system for the
center; (c) networking devices in locations that are currently not equipped with such facilities;
(d) new digital cameras to replace the existing analog cameras in the road and to extend the
coverage of the road video surveillance system; (e) new VMS boards with road condition
information for users, with a priority for the roads in the Minsk area where most of the traffic
concentrates; (f) additional software applications and connectivity as needed to enable
integration of weather radars from airports, and other sources of information (including the
tolling system, the future WIM system, as well as integration with the road traffic police,
emergency services, etc.; and (g) other support necessary to implement the citizen feedback and
open data concepts, in particular through enhancements to the web portal of the MoTC and
Beldor Center.
11. The TRSCC will collect and analyze road traffic related data so that road agencies can
provide real-time feedback to users, such as on traffic congestion, detour suggestions due to
severe weather and road maintenance works. It will also use the data to better manage the
development and maintenance of the network and allow more effective long term planning
including the optimization of toll fees. The MoTC has already set up hotlines for citizens to
report road problems. In order to further promote public participation and enhance government
accountability, the MoTC will apply Information and Communications Technology (ICT) tools
such as crowdsourcing techniques to promote citizen engagement in identifying black spots and
other road maintenance and safety issues from road users’ point of view. The TRSCC will also
promote public awareness campaigns on issues particularly related to road safety. The MoTC
will continue its engagement with the private sector on using these open source data to develop
applications for practical usage. The following activities will be financed:
i) Consultancy services including: (a) developing a detailed concept, technical design
and preparing the bidding documents including technical specifications for
developing such a TRSCC and underlying infrastructure; and (b) developing the
necessary monitoring and evaluation frameworks to measure user satisfaction,
28
conduct impact evaluations of road sector interventions and undertake road safety
awareness campaigns.
ii) Providing capacity building for staffing such a center; and
iii) Providing financing for the necessary systems that would comprise the TRSCC and
associated infrastructure, including systems integration services and equipment.
12. Sub-component 2.2: Road-side services. The provision of road side services is
important for the safety and convenience of road users but is also a potential source of
employment for local communities and particularly women. The MoTC already has a detailed
master plan for the development of road side services, regulations governing their use and the
government is providing some incentives for investors such as tax breaks. However, recent
attempts to attract investors have been largely unsuccessful partly because of constraints related
to the availability of land and finance but partly because of the overall investment framework.
This activity will be coordinated with IFC to take advantage of their connections with business
associations in Belarus and finance: i) a market survey to better understand user needs and
private sector interest in the sector; ii) review of the overall framework for road side services
development taking a more market oriented approach with an aim to limiting obstacles or
introducing new policies to promote active engagement from the private sector.
13. Component 3: Border Management Enhancement (total cost US$3.3 million of
which US$3.3 million financed by IBRD loan). This Component will finance activities designed
to improve the overall performance of border management in Belarus, facilitating the movement
of cross-border trade at the Bruzgi BCP by reducing average clearance times and the number of
transactions conducted when crossing the border. The component will support the
implementation and increase the effectiveness of the ‘two agencies at the border’ policy being
implemented in Belarus. It will also support national ambitions to transition to a one-stop-shop
approach as part of a single electronic window environment through implementation of new
procedures - clearance in channel. It is expected that implementation of clearance “in-channel”
procedures will significantly reduce the time for clearance of trucks not requiring secondary
screening and reduce the number of vehicles referred for secondary inspection (usually
documentary check) by up to 50 percent.
14. Through parallel finance, an IFC advisory services grant will be used to undertake a time
release study to identify current constraints in border clearance procedures and other technical
assistance activities to support business process improvements in response to areas of priority
identified by SCC. The following activities will be included in this project:
i) Consultancy services to re-design the physical layout of the ‘inward’ registration,
vehicle control, processing and examination areas (starting at the initial Border Guard
control point upon entry to Belarus territory). This activity will take into
consideration the impact of revised business processes to be adopted by SCC under
the ‘two agency’ approach, the need to coordinate (integrate) the design with other
proposed improvements (construction of the Non-Intrusive Inspection facility) and
anticipated increase in traffic volumes. It will identify and consider best practice
examples of BCP design (particularly those identified by the E.U., OECD and the
29
Bank), especially where they apply to the implementation of the ‘in-channel’
clearance approach.
ii) Goods and equipment procurement of two automated low speed (< 5 km/h) ‘weigh-
in-motion’ units, with CCTV interface and automated number plate recognition, with
data made electronically available to customs and border guards.
iii) Civil works based on the design outputs of the consultancy services to address key
physical limitations including:
a. Widening the access road for commercial vehicles from 1 to 2 lanes.
b. Installation of the 2 automated ‘weigh-in-motion’ units along the access road.
c. Creation of up to 8 individual processing channels.
d. Other road works as necessary to support appropriate movement of vehicles and
traffic flow within the processing area.
e. Building/installation of sufficient offices or control booths to allow border guard
and customs official to effect clearance procedures in-channel.
f. Weather proof roofing over the clearance area to protect clients and staff when
effecting physical inspections of vehicles.
g. Connection of necessary services to support operations.
h. Re-surfacing and line marking of hard-stand/ parking area.
i. Other works as agreed.
15. Detailed project costing estimates are summarized in the table below:
Components
Project
Cost
(million
US$)
IBRD
Financing
(million
US$)
% of
IBRD
Financing
Component 1: Improvement of M6 Transit Corridor
Road Civil Works 237.86 237.86 100.00%
Financial Audit 0.15 0.15 100.00%
Technical Audit 0.30 0.30 100.00%
Consultant for FIDIC 0.96 0.96 100.00%
Financing of Preparation Works 5.54 0.00 0.00%
Engineering surveys and design works 4.98 0.00 0.00%
Feasibility study 0.05 0.00 0.00%
Preparation of bidding documents 0.50 0.00 0.00%
Funding in future periods: 14.47 0.00 0.00%
Technical supervision and administrative costs 5.19 0.00 0.00%
Contingencies costs 7.42 0.00 0.00%
Designer’s Supervision 0.52 0.00 0.00%
Environmental Supervision 0.16 0.00 0.00%
Land Acquisition 0.22 0.00 0.00%
Infrastructure Loss 0.54 0.00 0.00%
30
State expertise, State Construction Supervision and Inspection
Service 0.43 0.00 0.00%
Subtotal Component 1 259.28 239.27 92.3%
Component 2: Road Safety and Network Management
Sub-component 2.1 - Traffic and Road Safety Coordination
Center (TRSCC) 6.50 6.50 100.00%
TRSCC - building and hardware equipment for the center 0.50 0.50 100.00%
TRSCC Software 1.50 1.50 100.00%
TRSCC field equipment 3.70 3.70 100.00%
TRSCC staff training 0.10 0.10 100.00%
Consultant Services for TRSCC (design and monitor and
evaluations) 0.70 0.70 100.00%
Sub-component 2.2 - Road -side Services 0.30 0.30 100.00%
Subtotal Component 2 6.80 6.80 100.00%
Component 3: Border Management Enhancement
Design work 0.30 0.30 100.00%
Physical infrastructure work 3.00 3.00 100.00%
Grant from IFC for Time Release Study and Technical Assistance
on Selected Topics
Subtotal Component 3 3.30 3.30 100.00%
Front-end fees (0.25%) 0.63 0.63 100.00%
Total 270.01 250.00 92.6%
31
Annex 3: Implementation Arrangements
BELARUS: Transit Corridor Improvement Project (P149697)
Project Institutional and Implementation Arrangements
Project administration mechanisms
1. The project will be implemented over a five-year period by the MoTC, which is the
national authority in charge of road construction and maintenance in Belarus and will have the
overall responsibility for project coordination and monitoring of implementation progress. The
MoTC has formally delegated the responsibility for managing the day-to-day preparation and
implementation of the proposed project to the Republican Unitary Enterprise Minskavtodor-
Center (MA-C). MA-C is one of six regional operational subsidiaries in charge of the
management and maintenance of the Republican road network.
2. Within MA-C, a Project Implementation Team (PIT) was created in 2009 for the on-
going RUMP Project, which consists of experienced engineering, procurement and financial
management staff. The PIT will be augmented by staff from Grodnoavtodor (responsible for the
region where much of the proposed road is located). Through the on-going project the team at
MA-C has developed good expertise in procurement, financial management and environmental
issues. The PIT has less experience with social issues and the team from Grodnoavtodor has not
worked with the Bank before. For project preparation stages (road design, feasibility studies,
environmental and social assessments, etc.) MA-C will collaborate with the Road Design
Institute (Belgiprodor) whose performance has also been good. Belgiprodor in cooperation with
the National Academy of Sciences will also be involved in monitoring the adherence to
environmental safeguards requirements. Beldor Center will be coordinating the implementation
of the Traffic and Road Safety Coordination Center (TRSCC).
3. MA-C will also be responsible for the implementation of the customs performance
enhancement component although, through agreement, the day to day management of the
component will be done by the State Customs Committee (SCC) of Belarus and its Grodno
Regional Customs Agency. Both the SCC and the Grodno Regional Customs Agency (GRCA)
will assign coordinators (project managers) responsible for project implementation to work
closely with the MoTC and MA-C. The customs agencies will be responsible for the overall
design and implementation quality of this component. They will prepare terms of reference for
design documents (or approving design documents when they are available), ensuring
appropriate technical supervision of the contracts, accepting payment orders, and submitting
adequate documentation to the MA-C so that it can prepare and sign disbursement applications.
The customs agencies will prepare bidding documents for Component 3, identify personnel to sit
on procurement committees and jointly sign with MA-C any contract documents.
4. The Bank will continue supporting MA-C, Grodnoavtodor and the SCC in particular, in
the necessary training on the use of World Bank guidelines and procedures for procurement,
financial management and environmental/social safeguards management. Before and after
project effectiveness, the PIT staff will receive targeted training on land acquisition and
resettlement, areas where PIT is not very experienced with.
32
5. The implementation arrangements specified above will be formalized through an Inter-
Ministerial Resolution setting out MA-C as the sole implementing entity. This resolution will
also set out the roles and responsibilities for the other beneficiaries including Grodnoavtodor for
component 1, Beldor Center for component 2 and SCC and GRCA for component 3 of the
project.
Financial Management, Disbursements and Procurement
Financial Management
6. Financial management arrangements for the implementation of the project are
Satisfactory, and related FM risk is Moderate. The FM assessment focused on the capacity
assessment of Minskavtodor-Center (MA-C). MA-C is in process of implementing RUMP, and
therefore the current assessment was based on the FM arrangements that are in place for the
ongoing project. The FM and disbursement capacity of the MA-C has grown substantially during
the years of implementation of the first project, and the FM arrangements confirmed as
Satisfactory during the latest FM monitoring visit in September 2014. All key aspects of FM and
disbursement of the project are in place, although the MA-C was still to address and implement
the findings of its auditors related to the accounting and reporting procedures of MA-C (that
extend beyond the scope of the project, but are related to general capacity building). The FM
arrangements, as in the ongoing project, have been designed with the view of maximizing the use
of country systems.
7. Staffing. The same fiduciary staff of MA-C will continue to work on all aspects of
financial management and disbursements of the entire project. The financial staff of MA-C
gained substantial experience in the World Bank procedures related to financial management and
disbursements, and attended recent training events. Involvement of several staff with overlapping
responsibilities ensures proper segregation of duties. FM procedures and internal controls in
place for project implementation will be included in Project Operational Manual (POM), which
will need to be adopted prior to project effectiveness.
8. Accounting and Reporting. Project accounting will be done on the accounting and
reporting software (Galaktika), on a segregated set of accounts. The system was modified during
implementation of the ongoing project to ensure fully automated accounting and reporting in the
World Bank financed projects. Quarterly IFRs will be prepared, and will include information on
all components and contracts in the project. The format of the reports will be based on the
formats currently in use for the ongoing project.
9. Internal Controls. The internal controls structure for this project will be based on
procedures that were in place during implementation of the ongoing project, and they will be
detailed in project POM which will be adopted prior to project effectiveness. The POM will
specify (a) the role of specialists of Grodnoavtodor and SCC in preparation and signing of
contracts in their respective components as well as technical acceptance of goods/services
provided under those contracts (b) division of roles and responsibilities between MA-C financial
staff and representatives of Grodnoavtodor and SCC.
33
10. Government financing. Counterpart financing is envisaged to finance the feasibility
studies, engineering design, technical and environmental supervision, land acquisition, and
infrastructure loss. These payments will be made from the state budget following the national
legislation requirements. MA-C will be responsible for monitoring the timeliness of these
payments and keeping their records.
11. Auditing. Annual audit of project financial statements will be carried out by eligible
private auditors. The scope of the audit will be determined in the TORs that are subject to
approval of the World Bank. The scope will cover SOEs, Designated Accounts, and auditors will
be required to report any weaknesses of internal controls that were noticed during audit.
Additionally, MA-C will continue to submit the audit of its consolidated financial statements
prepared under requirements of National Accounting Standards, mainly for the purposes of
capacity building. Both sets of audited financial statements will be subject to public disclosure
in accordance with the World Bank Information Disclosure Policy. Additionally, periodic
technical audits will be carried out to confirm the acceptable quality works, and such technical
audits will be financed from government financing.
Disbursements
12. Disbursement Arrangements. The proceeds of the IBRD loan will be disbursed in
accordance with the traditional disbursement procedures of the Bank. These will be used to
finance project activities through the disbursement procedures currently used—that is, Advances,
Direct Payments, Reimbursements, and Special Commitments accompanied by appropriate
supporting documentation (Summary Sheets with records and/or Statements of Expenditures
(SOEs)) in accordance with the procedures described in the Bank’s Disbursement Guidelines.
The minimum application size for direct payment, reimbursement and special commitments will
be specified in the Disbursement Letter.
13. Designated Account. MA-C will open a segregated Designated Account in a Commercial
Bank acceptable to the Bank in U.S. dollars to cover the eligible project expenditures. The
Ceiling of the Designated Account will be specified in the disbursement letter. The PMU will be
responsible for submitting monthly replenishment applications with appropriate supporting
documentation along with a reconciled bank statement. The Designated Account will be audited
annually in conjunction with the audit of the project financial statements.
14. Statement of Expenditures (SOEs). Necessary supporting documents will be sent to the
Bank as indicated in the Disbursement Letter. The documentation supporting expenditures will
be retained at the MA-C and be readily accessible for review by the external auditors and
periodic Bank supervision missions. All disbursements will be subject to the conditions of the
Loan Agreement and disbursement procedures as defined in the Disbursement Letter.
Procurement
General
15. Procurement of goods, works, and non-consulting services for the proposed project
would be carried out in accordance with the World Bank’s “Guidelines: Procurement of Goods,
34
Works and Non-Consulting Services under IBRD Loans and IDA Credits and Grants by World
Bank Borrowers,” dated January 2011 and revised on July 1, 2014 (Procurement Guidelines);
and procurement of consultant services will be carried out in accordance with the World Bank’s
“Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits and
Grants by World Bank Borrowers,” dated January 2011 and revised on July 1, 2014 (Consultant
Guidelines), and the provisions stipulated in the Loan Agreement. The Bank's “Guidelines on
Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA
Credits and Grants,” dated October 15, 2006, and revised in January 2011 (Anti-Corruption
Guidelines) will apply to this project. A General Procurement Notice has been published on the
Bank’s external website and the UN Development Business website. The following section
describes the procurement implementation arrangements agreed with the Project Implementation
Team.
Procurement Capacity and Risk Assessment
16. A Procurement Capacity and Risk Assessment of the project’s implementing agency
(Minskavtodor-Center) were initiated in April 2014. The PIT will be directly responsible for the
day-to-day implementation of all the activities under the project. The PIT will be in charge of the
entire procurement process, including planning, preparation of bidding documents, evaluation of
bids, award of contracts, and contract management. With respect to the border management
enhancement component, MA-C will coordinate all procurement processes, however the State
Customs Committee will be in charge of preparation of terms of reference for design documents,
quality check and approval of consultant’ works and technical supervision of infrastructure
contracts. The PIT’s procurement function will be managed by a Procurement Specialist, who
has gained practical knowledge of procurement through implementation of the ongoing RUMP
Project. In addition, the Procurement Specialist participated in the Procurement Capacity
Building Workshop in Moldova between April 7 and10, 2014.
17. The key issues and risks concerning procurement for implementation of the project have
been identified and include: (i) potential risk of delays in the implementation of the large works
contracts, and (ii) costs overruns due to claims and variation orders.
18. Given the findings of the assessment as presented above the procurement risk for the
proposed project is rated as Moderate.
19. To mitigate the identified procurement-related risks, the following mitigation actions
were agreed between the Bank and the client during project preparation.
Mitigation measure
Responsible
party Deadline
1 Prepare a detailed procurement plan for the
first 18 months of the implementation of the
project
PIT Completed
2 Organize a business outreach for potential
bidders or consultants before launching the
first bidding procedures
PIT Recurrent
35
Mitigation measure
Responsible
party Deadline
3 Start preparation of the bidding documents
for the first year of project implementation of
Component 1 well in advance to facilitate the
initiation of the procurement procedures as
soon as the project becomes effective
PIT Underway
4 Hire a consultant, experienced in FIDC type
of contracts
PIT Signing of civil
works contracts
5 The Bank's procurement specialist will work
closely with PIT and will organize
procurement refresher training events to
project staff whenever required during
project implementation
Bank Recurrent
6 Preparation of procurement progress reports
by the Borrower during Project
implementation
MA-C Implementation
Procurement Implementation Arrangements
20. Procurement of Works. The project will include rehabilitation, reconstruction and
upgrading of the M6 road, from a two-lane to a four-lane road between Minsk and Grodno.
These large civil works will be procured through International Competitive Bidding (ICB)
procedure, following prequalification For contracts above US$10 million, the Bank’s recent
Standard Bidding Documents (SBD) Procurement of Works will be used. Currently, the project
does not envisage any smaller works in the project, below US$10 million per contract. However
if there are any such contracts, the Bank’s most recent Standard Bidding Documents (SBD)
Procurement of Small Works will be used. International Competitive Biddings (ICBs) shall be
conducted for all contracts above US$5 million per contract. For contracts below US$5 million
per contract, the same SBD for Procurement of Small Works will be used; however the National
Competitive Bidding (NCB) procedure will apply, instead of ICB. For very small value civil
works contracts estimated to cost not more than US$200,000 per contract a shopping procedure
may be used.
21. Procurement of Goods and Non-consulting Services. The project may involve
procurement of traffic control equipment. The most recent version of the Bank’s Standard
Bidding Documents (SBD) for Goods shall be used for all International Competitive Biddings
(ICBs) above US$1 million per contract. For contracts below US$1 million, the Bank's sample
Bidding Documents for Goods under the National Competitive Bidding (NCB) may be used and
a shopping procedure for goods estimated to cost up to the equivalent of US$100,000 per
contract. Where the value of the plant and equipment represents the major part of the contract;
the contracts require comprehensive testing and acceptance procedures; or the contracts require
essential functional guarantees from the contractor on a single-responsibility basis, the Bank’s
latest Standard Bidding Documents for Procurement of Plant Design, Supply, and Installation
will be used (i.e. procurement of weigh-in-motion units). For the ICT related procurement
under components 2 and 3, the following different procurement strategies may be applied: 1)
36
Goods approach - a general purpose hardware and off-the-shelve software (without
customization) based on SBD for Goods, 2) Consulting Services approach - if the hardware
and packaged software content is minimal, e.g., less than 20% of the estimated contract value, a
consultancy selection procedure may be applicable with the Bank’s Standard Request for
Proposal 3) Single Stage IT SBD - if procurement package combines critical goods and services
elements, sophisticated hardware requiring an informed performance comparison and special
training requirements, a dominating value of the software packages, extra installation and
support requirements for these, software design, large-scale adaptation and/or development,
requirements for the supplier to continue to operate the equipment after installation, for contracts
requiring pricing for both investment & recurrent costs (life-cycle).
22. Logistical services for training and workshops related to technical assistance shall be
procured as non-consulting services.
23. State-Owned Enterprises (SOEs). The project’s first component may attract several
small and large size local construction companies that are part of the Belavtodor Holding
Management Company, created in July 2013. The Bank will review these companies Charters
and other relevant documents in order to determine, whether these companies will be eligible to
participate in Bank’s financed bidding procedures as per paragraph 1.10 (b) of the Bank’s
Procurement Guidelines.
24. Selection of Consultants. The consultant services under the project will include inter
alia: technical assistance, various road sector studies, logistics and impact analysis, as well as
support to the supervision of large civil works contracts including annual financing audit of the
project. For assignments estimated to cost US$300,000 per contract, the short-list may comprise
entirely national consultants.
25. Procurement Plan and Procurement Thresholds. The PIT has developed a Procurement
Plan for the first 18 months of the project that also provides a basis for the procurement methods
and thresholds. This plan has been agreed between the PIT and the Bank and will be published
on the Bank’s external website. The Procurement Plan will be updated at least annually or as
required to reflect actual project implementation needs. Procurement under the project will
include the following categories: Works, Goods and Non-Consulting and Consulting Services.
The applicable thresholds for procurement methods and Bank prior review applied for
procurement are presented below.
26. The Bank will review the procurement arrangements as performed by the PIT. The
procurements not receiving prior review by the Bank would be subject, on a random basis, to the
Bank’s ex post review in accordance with the procedures set forth in appendix 1 of the
Procurement and Consultant Guidelines. One in 10 contracts under the project will be subject to
the Bank’s ex post review. The ex post review of procurement documents will normally be
undertaken during the Bank’s implementation support missions or as the Bank may request for
any contract at any time.
37
Project Procurement Plan
№ Contract Description Contract type Procurement
method
Issue of
Bidding/Proposal
Documents
Expected
Contract
Completion
Component 1: Improvement of Sections of M6 ‘Minsk – Grodno’ Transit Corridor
1
ICB with 3 lots:
LOT 1
Reconstruction of 33,87 km of road, including
road, bridge and auxiliary works (km 57,2 –
91,07).
Civil Works
(CW) ICB
03/2015
10/2018
2
LOT 2
Reconstruction of 39,33 km of road,
including road, bridge and auxiliary works
(km 91,07 – km 130,4).
Civil Works
(CW) ICB 10/2018
3
LOT 3
Reconstruction of 13 km of road, including
road, bridge and auxiliary works (km 198,0 –
km 211,0).
Civil Works
(CW) ICB 10/2018
4 Financial audit Consultant
Services (CS) LCS 03/2015 07/2019
5 Technical audit Consultant
Services (CS) LCS 01/2016 12/2018
6 Consultant services (FIDIC) Consultant
Services (CS) LCS 03/2015 10/2018
Component 2: Road Safety and Network Management
Sub-component 2.1: Traffic and Road Safety Coordination Center
7 Consultancy services to develop the
framework for Traffic Management System
Consultant
Services (CS) QCBS 05/2015 06/2017
8 TRSCC - building and hardware equipment
for the center including software
Goods/IT
Systems
ICB/NCB TBD TBD
9 TRSCC field equipment Goods/IT
Systems
ICB/NCB TBD TBD
10 TRSCC staff training Operating
Costs
NA TBD TBD
Sub-component 2.2: Road-side Services
11 Market survey to better understand user needs
and private sector interest in the sector
Consultant
Services (CS) CQS 03/2015 06/2016
12
Consultancy services to develop the
framework for introducing Private Public
Partnership to road side services
Consultant
Services (CS) CQS 03/2016 06/2017
Component 3: Border Management Enhancement
13
Detailed design and preparation of biding
documents for physical layout of the border
control point
Consultant
Services (CS) QCBS 05/2015 06/2016
14 Physical infrastructure work Civil
Works/Goods ICB/NCB TBD TBD
38
Environmental and Social (including safeguards)
27. MA-C has nominated a specific team of specialists who will work on the preparation and
implementation of the project in close interaction with the World Bank. The team is headed by a
senior manager and will be augmented as needed during the implementation stage by hiring
additional specialists to cover the increasing work load. The team includes procurement and
financial management specialists, a lawyer, and an environmental specialist. The team will also
engage specialists from the environmental unit from Belgiprodor and Academy of Science.
28. The institutional capacity of the borrower was evaluated during the project preparation
stage. It was concluded the State Enterprise Belgiprodor has adequate capacities to perform
effective enforcement of EMP provisions. The institution employs highly qualified staff and is
equipped with analytical equipment to perform the required analyses of environmental quality.
Furthermore, this institution has previous experience in dealing with environmental safeguards
while implementing other similar projects in the country.
29. MA-C and Grodnoavtodor will be responsible for implementation of the RAPs and
coordination with the local authorities. The PIT will have a designated specialist who will
monitor implementation of the RAPs. For every oblast the annual plan for resettlement
implementation linked to the plan of civil works will be issued and implemented prior to the start
of the works. The PIT will report on resettlement in the framework of the regular annual report to
the Bank.
Monitoring & Evaluation
30. Monitoring and evaluation of results for components 1 and 2 will be the responsibility of
MA-C and will include: (1) monitoring of project physical progress (i.e. lengths of upgraded
roads, development of the Traffic and Road Safety Coordination Center, improved climate for
SME to participate in providing road-side services), and (2) evaluation of project socio-economic
impacts (i.e., benefits to local population and communities such as traffic fatalities reduction and
beneficiary satisfaction). The State Customs Committee will be responsible for monitoring and
evaluation of results from Component 3 (customs performance enhancement), which includes: (1)
monitoring the physical progress; and (2) evaluating the reduction in average time to complete
inwards border clearance procedures (commercial vehicles) and reduced number of commercial
transactions referred for secondary screening at Bruzgi BCP.
31. Progress towards PDO will be monitored and reported on through periodic World Bank
implementation support missions every six months. The MA-C and SCC will conduct frequent
inspections to prepare quarterly and annual progress reports with detailed evaluation surveys and
analysis. The ongoing RUMP project did not have any land acquisition and resettlement issues
whereas the proposed new project will have to address these issues. As such, the Bank will
provide additional support to MA-C and Grodnoavtodor in this area to ensure that their
specialists have the necessary knowledge and training. The Bank team will monitor the
implementation of the RAPs during its course of its regular monitoring missions.
39
Annex 4: Operational Risk Assessment Framework (ORAF)
Belarus: Transit Corridor Improvement Project (P149697)
Risks
Project Stakeholder Risks
Stakeholder Risk Rating Low
Risk Description: Risk Management:
The Belarussian road sector investment
program was prepared several years ago
and is being implemented by MoTC. The
priorities as set out in that document are
unlikely to change and it is unlikely that
changes in senior personnel will have any
significant impact on priorities. The
upgrading of the M-6 road to Category I
standard is universally supported, both
politically and also by road users; there is
very low likelihood of this support being
withdrawn.
There are no particular risk mitigation measures envisaged, besides monitoring any possible (but
unlikely) changes in the Government's road investment program.
Resp:
Both
Status:
In Progress
Stage:
Both
Recurrent:
Due
Date: Frequency:
SemiAnnual
Implementing Agency (IA) Risks (including Fiduciary Risks)
Capacity Rating Moderate
Risk Description: Risk Management:
This project will be implemented by the
MoTC through its Minskavtodor-Center
(MA-C). Within MA-C, a Project
Implementation Team (PIT) was created in
2009 for the on-going Road Upgrading and
Modernization Project, which consists of
experienced engineering, procurement and
financial management staff. The PIT will
be augmented by staff from Grodnoavtodor
At this stage the only specific recommendation to MA-C is to appoint a full time person responsible for
the social aspects of the project. The Bank will continue supporting MA-C, and Grodnoavtodor and the
Customs Committee in particular, in the necessary training on the use of World Bank guidelines and
procedures for procurement, financial management and environmental/social safeguards management.
Before and after project effectiveness, the PIT staff will receive targeted training on land acquisition
and resettlement, areas where PIT is not very experienced with.
Resp:
Both
Status:
In Progress
Stage:
Both
Recurrent:
Due
Date: Frequency:
SemiAnnual
40
(responsible for the region where much of
the proposed road is located). Through the
on-going project the team at MA-C has
developed good expertise in procurement,
financial management and environmental
issues. The PIT has less experience with
social issues and the team from
Grodnoavtodor (GA) has not worked with
the Bank before. For project preparation
stages (road design, feasibility studies,
environmental and social assessments, etc.)
the MA-C collaborates with the Road
Design Institute (Belgiprodor) whose
performance has also been good.
The Component 3 will be implemented
through the State Customs Committee of
Belarus and its Grodno Regional Customs
Agency, neither of which have worked
with the Bank before. Both of them have
assigned coordinators responsible for
project implementation to work with the
MoTC and MA-C. The MA-C will thus be
responsible for managing the project
implementation, in coordination with the
State Customs Committee and MoTC, and
will be the World Bank’s interlocutor. The
risk during project implementation will be
the effective coordination between the
various stakeholders.
Governance Rating Moderate
Risk Description: Risk Management:
GAC in the sector is generally quite good
with future improvements likely to come
from the demand side and by taking a more
user focused approach to management of
the sector. This will mean improved
information dissemination to users and
increased use of social accountability tools.
Through development of the TRSCC increased emphasis will be placed on the user and social
accountability mechanisms. Special regulatory mechanism will be developed by the MoTC to ensure
proper coordination and distribution of labor between MA-C and GA. Regional authorities will be
involved in the discussion on the RPF to ensure their understanding of their role and responsibilities as
regards to the land acquisition and resettlement.
Resp:
Both
Status:
In Progress
Stage:
Both
Recurrent:
Due
Date: Frequency:
SemiAnnual
41
Most of the road to be improved is situated
in Grodno region that is managed by GA.
There is currently no line of subordination
between MA-C, the main implementing
entity, and GA. In addition, land
acquisition for the project will be done
through the regional authorities which are
not otherwise stakeholders of the project.
Project Risks
Design Rating Moderate
Risk Description: Risk Management:
Project design for the civil works is
straightforward and follows the design of
the ongoing Road Upgrading and
Modernization Project. The project scope
and scale are also similar to the ongoing
project and include similar and proven
technical design features. The design
agency, Belgiprodor, has experience with
the design of these category 1 roads and
preliminary designs are already well
advanced. Road safety is a key element that
is being integrated into the design process.
The institutional component of the project
will develop some of the on-going reforms
in the road sector but some of these might
be difficult to implement further. There
may also be risks associated with the
coordination between MA-C and SCC
potentially raising the risks of institutional
relationships, and monitoring.
The Bank team will continue to monitor progress with the design of the road sections to ensure they
meet the required standards and work with the MoTC to develop an effective institutional component to
the project. Before implementation an Inter-Ministerial Resolution will be agreed between MA-C, SCC
and other entities to detail their roles and responsibilities
Resp:
Both
Status:
In Progress
Stage:
Both
Recurrent:
Due
Date: Frequency:
SemiAnnual
Social and Environmental Rating Moderate
Risk Description: Risk Management:
Through the on-going project the team at
MA-C has developed good expertise in
environmental issues and handled
The client will be supported by the Bank’s team at every stage of planning, consultations with affected
population and implementation of the resettlement and land acquisition process in compliance with
Bank’s policies.
42
environmental management very
effectively. The EIA that has been prepared
for the new project is also of high quality.
The client has no experience in Bank
implemented land acquisition and
resettlement. National legislation on the
matter is rather developed, though not fully
compliant with Bank’s OP 4.12 policy.
Resp:
Both
Status:
In Progress
Stage:
Both
Recurrent:
Due
Date: Frequency:
SemiAnnual
Program and Donor Rating Low
Risk Description: Risk Management:
The execution of this project is not
dependent on any other project or donor.
Resp: Status: Stage: Recurrent:
Due
Date: Frequency:
Delivery Monitoring and
Sustainability Rating Low
Risk Description: Risk Management:
The risks associated with poor quality
construction are considered low given the
strong oversight mechanisms within project
design and through government controls.
Evidence from the first project suggests
that construction quality will be high and
that the MA-C will provide regular
monitoring reports to evidence progress.
The sustainability of the investments is also
considered to be likely given the generally
good condition of the national roads
network to date and the various initiatives
to increase maintenance funding including
through a program of e-tolling and
licensing fees on vehicles.
The Bank team will monitor these aspects through implementation of the project and the project will
procure an independent technical audit company to monitor quality of civil works.
Resp:
Both
Status:
In Progress
Stage:
Both
Recurrent:
Due
Date: Frequency:
SemiAnnual
4.5 Other (Optional) Rating
Risk Description: Risk Management:
43
Resp: Status: Stage: Recurrent:
Due
Date: Frequency:
4.6 Other (Optional) Rating
Risk Description: Risk Management:
Resp: Status: Stage: Recurrent:
Due
Date: Frequency:
5. Overall Risk
Overall Implementation Risk: Moderate
Risk Description:
The overall implementation risk is rated as Moderate. As with preparation, the main risks are related to coordination between SCC and MA-C and
implementing some quite challenging institutional components even though the capacity of the implementing agencies is good.
44
Annex 5: Implementation Support Plan
BELARUS: Transit Corridor Improvement Project (P149697)
Strategy and Approach for Implementation Support
1. The implementation support will focus on implementation of risk mitigation measures
defined in the Operational Risk Assessment Framework (ORAF), namely the capacity,
governance, environmental and social safeguards, which are rated as moderate. Implementation
support missions, including field visits will be carried out semi-annually, and will focus on: (a)
technical aspects of works, (b) institutional strengthening; and (c) environmental and social
safeguards training.
a) Technical aspects of works. Close cooperation and review of planned road works will be
carried out from the design phase until completion of works. Engineering inputs will be
provided to all designs to ensure proper technical specifications, and appropriate
consideration of road safety. During bid evaluation, the review will ensure fair assessment of
the technical aspects of bids. During construction and commissioning, technical supervision
will be provided to ensure technical, environmental and social contractual obligations are
met. The team’s engineers will conduct site visits on a semi-annual basis throughout project
implementation.
b) Institutional strengthening. As a part of the PDO, institutional strengthening will receive
substantial focus during the project implementation and related implementation support. This
will include a regular dialogue on the progress of M6 improvement work, integrated systems
in TRSCC, private sector involvement in providing road side services and customs
performance enhancement.
c) Environment and social safeguards training. The PIT has had a training session in Bank
safeguards policies. Support will be provided in updating the Project Operations Manual to
include there provisions for resettlement implementation and reporting. Advanced training on
the implementation of resettlement plan will be provided to the specialists responsible for
resettlement in MA-C and GRODNOAVTODOR.
Implementation Support Plan
2. The project implementation support missions will coincide with the missions on the
ongoing roads project. The implementation support missions will involve engineering,
procurement and safeguards specialists and at least once annually also financial management.
Particular focus will be put on supervising the implementation of the road safety measures.
3. Capacity regarding environmental and social safeguards will be continuously monitored
by the World Bank environmental and social specialists who will participate regularly in
implementation support missions and provide input directly to the client in the course of EMP
and RFP preparation and works supervision.
45
4. The Mid-term review of the project, expected to take place in the first quarter of 2017,
will include technical workshops to discuss traffic management, road safety, road side services
and border control.
Main focus in terms of support to implementation during project
Time Focus Skills Needed
First twelve months Procurement
Concept design for TRSCC
Time-release study for Component 3
Road Engineering
Procurement
Safeguards
Project Management skills
Road safety
Customs/border control
12-48 months Civil works
Procurement
Road Engineering
Procurement
Project Management skills
Road safety
Skills Mix Required
Skills Needed Number of Staff Weeks Number of Trips
Task Team Leader 10 / year 3 / year
Transport Economist/Specialist 8 / year 3 / year
Road Engineer 8 / year 3 / year
Financial Specialist 4 / year 2 / year
Customs & Border Management
Specialist 2 / year 1 / year
Procurement Specialist 6 / year 2 / year
Environmental Management Specialist 2.5 / year 2 / year
Social Development Specialist 1.5 / year 1 / year
Partners
Agency Institution or owner Role in the project
Ministry of Transportation
and Communications
(MoTC)
Council of Ministers of the
Republic of Belarus
Overall responsibility for the
implementation of the project
Republican Unitary
Enterprise
MINSKAVTODOR-
Center (MA-C)
Roads Department MoTC Daily preparation and
implementation of the project
including procurement, contract
supervision, financial
management and reporting,
implementation progress
monitoring, and preparation of
progress reports
46
Republican Unitary
Enterprise
GRODNOAVTODOR
Roads Department MoTC Arranging land transfer for the
sections of the road on the
territory of Grodno oblast,
obtaining work permits, and
supervising works in Grodno
oblast
Public Enterprise
BELGIPRODOR
Roads Department MoTC Development of bidding
package, including both legal
part such as instructions to
bidders, conditions of contracts
and technical part such as bill of
quantities, specifications,
drawings and etc.
Republican Unitary
Enterprise Beldor Center
Roads Department MoTC Cooperation with the PIT in
implementation of Component
2.1 (TRSCC),preparation of
consultant’s selection documents
Public Enterprise
BELGIPRODOR
Public Enterprise
BELGIPRODOR
Designer’s supervision during
road rehabilitation
State Customs Committee
(SCC) and Grodno
Regional Customs Agency
The Council of Ministers of
the Republic of Belarus
Supervision, implementation,
quality control and monitoring
for Component 3 – Border
Management Enhancement
47
Annex 6: Economic Analysis
BELARUS: Transit Corridor Improvement Project (P149697)
1. The economic feasibility of the project was assessed based on an analysis of the savings in
vehicle operating costs and users’ travel time cost and reduced road traffic fatalities resulting
from the improvement of the project road. Savings in vehicle operating costs were evaluated
using the Highway Development and Management Model, HDM-4 (version 2.8), which
computes annual costs for the road agency and for road users for with and without project
alternatives over the evaluation period. Benefits arising from road safety improvements were
assessed using the estimated reduction of fatalities along the road, and the monetary value of loss
of human life, evaluated on the basis of the current income level.
2. Using the HDM-4 software, benefits and costs of road widening were computed for a 23-year
analysis period, 2015-2037. The Net Present Value (NPV) of the project costs was calculated
assuming three years of initial construction period, routine maintenance each year, and periodic
maintenance triggered in response to the road roughness. The financial costs are the same as the
economic costs given that the funds for project implementation will be exempt from VAT and
import duties. The NPV of the project benefits was calculated aggregating savings in vehicle
operating costs and users’ travel time, and reduction in accident costs, in comparison to the
Without Project scenario. The key inputs to the HDM-4 model, including the costs associated
with vehicles and parts replacement, fuel costs, wages, costs of various road maintenance
activities, have been calibrated in order to reflect the country-specific conditions.
3. For the purpose of the economic evaluation, the road to be upgraded under the project was
divided into four sections based on the proposed contract Lots. Table 1 shows the location of
each section, the average roughness of the existing road sections and the 2014 average annual
daily traffic (AADT), in vehicles per day. The average annual daily traffic on the four road
sections in 2013 was 5,724 vehicles per day with 44 percent composed of trucks. The existing
road has a bituminous pavement in fair condition with an average riding quality, measured by the
International Roughness Index (IRI), at 3.7-4.3 m/km.
Table 1: Road Sections Characteristics
Length Width Traffic Trucks Roughness Cracks
Section Location (km) (m) (AADT) (%) (IRI) (%)
1 km 57.2 to km 91.07 33.9 9 6,043 43% 3.7 22.0
2 km 91.07 to km 130.4 39.3 9 5,129 45% 4.3 17.9
3 km 197.7 to km 211.0 13.3 9 6,666 43% 4.1 0.0
Total 86.5 9 5,724 44% 4.0 16.8
Source: Feasibility Study
4. The existing two-lane road will be widened to four-lanes. The total financial construction
cost, inclusive of consultancy services for FIDIC and financial and technical audits, is estimated
to be US$239,275 million, which corresponds to US$2,766 million per km (Table 2). The
analysis considered planned routine maintenance and over-haul, based on the existing standard
building structures, approved by the order №11-D of the Ministry of Transport and
Communications of the Republic of Belarus dated April 28, 2014. Maintenance was appointed
48
when the maximum permissible values of IRI for the category 2 (Without Project scenario) and
the category 1 (With Project scenario), were reached respectively.
Table 2: Financial Costs of Road Works
Length Financial Costs
Section Location (km) (US$ Million) (US$/km)
1 km 57.2 to km 91.07 33,9 120,131 3,547
2 km 91.07 to km 130.4 39,3 90,231 2,294
3 km 197.7 to km 211.0 13,3 27,503 2,068
Financial Audit, Technical
Audit, Consultant for FIDIC 1,410
Total 86,5 239,275 2,766
Source: Feasibility Study
5. Normal traffic, i.e., traffic that is expected to materialize both in With Project and Without
Project scenarios, is expected to grow at 3.4 percent per year for cars and 2.6 percent per year for
trucks and buses from 2015 to 20253. From 2026 onwards, traffic is expected to grow at 3.0
percent per year for all vehicles. In addition to the normal growth of traffic, it was assumed that
additional traffic will be generated as a result of the economic development impact of typical
major road investments, at 9 percent of the normal traffic for cars, and 33 percent for trucks.
6. The economic unit costs and basic characteristics of the vehicle fleet (Table 3) were obtained
from the feasibility study of the project. The estimate of the road safety benefits was based on the
monetized values of fatalities, calculated using the International Road Assessment Program
(iRAP) methodology that relates the value of life to the GDP per capita of the country. The
resulting cost per fatality for Belarus is US$ 547,213. On the existing road, there are on average
6.7 fatalities per 100 million vehicle-km. It is forecasted that the project will reduce fatality rates
to 1.7 fatalities per 100 million vehicle-km. Table 3 presents the unit road user costs, in US$ per
vehicle km, for different roughness levels and the average traffic composition.
Table 3: Vehicle Fleet Characteristics and Unit Road User Costs
Medium Heavy Artic. Small Medium
Car Pickup Truck Truck Truck Bus Bus
Economic Unit Costs
New Vehicle (US$/vehicle) 16,279 12,751 40,698 80,930 97,800 106,047 233,783
New Tire (US$/tire) 54.8 92.7 99.0 182.1 286.8 84.2 133.2
Fuel (US$/liter) 0.47 0.47 0.47 0.55 0.55 0.47 0.55
Lubricant (US$/liter) 12.6 7.2 8.90 8.90 8.90 8.90 8.90
Maintenance Labor (US$/hr) 2.97 2.97 3.27 3.43 6.39 3.33 3.66
Crew (US$/hr) 4.34 4.34 4.34 4.34 7.51 4.34 3.76
Overhead (US$/year) 0 0 3,000 4,550 10,000 10,500 10,500
Interest Rate (%) 12.00 12.00 12.00 12.00 12.00 12.00 12.00
Working Passenger Time (US$/hr) 1.77 1.77 1.77 1.77 1.77 1.77 1.77
Non-working Passenger Time (US$/hr) 0.89 0.89 0.89 0.89 0.89 0.89 0.89
3 This was based on: (i) the fact that country’s average GDP grew at about 6 percent per year during 2005-2013, and the observed
traffic growth during this period on the project road was 9 percent for cars and 7 percent for trucks and buses; (ii) the GDP
growth from 2014 to 2019 projected by the IMF is 2.3 percent per year; and (iii) assuming the same future elasticity of traffic
growth to GDP growth found on the 2005-2013 period.
49
Cargo Delay (US$/hr) 0.00 0.88 9.39 12.07 19.78 0.00 0.00
Basic Characteristics
Kilometers Driven per Year (km) 10000 30000 30000 35000 100000 50000 70000
hrs Driven per Year (hr) 123 369 484 565 3000 1094 1094
Service Life (years) 14 8 15 15 7 15 15
Percent Private Use (%) 90 0 0 0 0 0 0
Number of Passengers (#) 3 0 0 0 0 20 28
Work Related Passenger-Trips (%) 30 0 0 0 0 70 20
Gross Vehicle Weight (tons) 1.03 2.00 7.34 15.40 35.00 16.00 14.20
Equivalent Standard Axels (ESA) 0.00 0.10 0.23 0.52 6.50 0.74 1.44
Typical Traffic Composition (%) 55% 12% 11% 2% 19% 1% 1%
Unit Road User Cost, US$/Veh-km
2 IRI four lane 0.30 0.18 0.53 0.90 1.06 0.91 1.17
2 IRI two lane 0.31 0.18 0.53 0.90 1.06 0.93 1.18
4 IRI two lane 0.31 0.19 0.55 0.94 1.11 0.97 1.26
6 IRI two lane 0.33 0.20 0.60 1.02 1.21 1.07 1.42
8 IRI two lane 0.36 0.22 0.67 1.14 1.35 1.19 1.66
10 IRI two lane 0.40 0.24 0.75 1.30 1.52 1.34 1.95
12 IRI two lane 0.44 0.26 0.85 1.47 1.72 1.51 2.25
7. Table 4 summarizes the economic evaluation results. The road improvement investments
under Component 1 are economically justified with a total NPV of US$156.7 million, at 8.95
percent discount rate, and an overall Economic Internal Rate of Return (EIRR) of 16.2 percent.
Table 4: Economic Evaluation Summary
NPV EIRR B/C
Section Location (M US$) (%) Ratio
1 km 57.2 to km 91.07 52,4 13,9% 0,44
2 km 91.07 to km 130.4 56,4 16.6% 0,60
3 km 197.7 to km 211.0 47,9 25,3% 1,62
Total 156,7 16.2% 0,72
Source: World Bank Calculations
8. Table 5 shows the results of a sensitivity analysis, increasing costs and decreasing traffic
growth rate by 15 percent. The results show that even under the pessimistic scenario of
increasing costs by 15 percent and decreasing traffic growth rate by 15 percent, the project is still
economically justified with an EIRR higher than 12.9 percent. The switching values analysis
shows that costs would have to increase by 105 percent to yield an EIRR equal to 8.95 percent,
which indicates a robust economic justification of the project.
Table 5: EIRR Sensitivity Analysis
Base Cost
+ 15%, Traffic
Growth - 15% Section Location Case
1 km 57.2 to km 91.07 13.9% 10.9%
2 km 91.07 to km 130.4 16.6% 13.3%
4 km 197.7 to km 211.0 25.3% 21.2%
Total 16.2% 12.9%
Source: World Bank Calculations
50
9. Public sector financing is the appropriate vehicle for financing the upgrading of the project
road because of the large initial costs that cannot be recovered through tariffs. Public investment
in road infrastructure is a way the government plays a key role in the country’s development by
handling a range of issues that can only be accomplished or implemented through government
actions, such as axle weight controls, and road safety regulations. The World Bank’s role is
justified because of the Project’s economic and social benefits and because of the value added it
brings beyond financing in areas such as: construction quality control, sustainability of road
maintenance, transport planning, environmental risk management, safeguards, procurement, and
financial management.
51
Annex 7: Impact Analysis
BELARUS: Transit Corridor Improvement Project (P149697)
Poverty and Shared Prosperity in Belarus
1. Rapid economic growth in Belarus has translated into remarkable poverty reduction over
the past decade, despite a modest increase in poverty in the aftermath of the recent crisis.
Evidence shows that consumption-based absolute poverty between 2000 and 2010 (latest data
available) decreased from 6.1 to 0.1 percent using a regional poverty line of $2.5 a day, and from
39 percent to 4 percent, using a regional poverty line of $5 a day4. Belarus’ poverty rates are far
below the ECA regional averages of 5.8 and 18.8 percent ($2.5 and $5 poverty lines in 2010). In
2013, a fast GDP growth and a rapid rise in real wages and incomes (by 15.4 percent) brought a
further decrease in poverty. This positive trend in poverty reduction is matched by Belarus’s high
level of shared prosperity. Growth in consumption for the bottom 40 percent of the population
was not only higher than in other countries of the region, but also above national average growth
in consumption, suggesting a positive trend in income equality between 2002 and 2008. Belarus
also ranks high in terms of the Human Development Index (HDI) (50th out of 187 countries in
2012), largely thanks to the achievements in education.
Expected transport-related impacts on low-income groups
2. Adequate connectivity and accessibility are both critical requirements for poverty
reduction and shared prosperity. While transport alone cannot reduce poverty, the construction of
roads, railways, and inland waterways or the improvement of existing infrastructure, serve a
pervasive role in boosting household incomes and reducing income inequality (booth et. al,
2001). From a distributional perspective, the economic and transportation literature in general
supports the hypothesis that investment in road infrastructure may have a significant impact on
the poorest population of society, by enhancing their chances to access employment and
investment opportunities, markets, and basic public services.
3. Road investments in particular, can unambiguously boost economic activity within a
specific locality, potentially closing the income divide that is often observed in lagged regions.
Improving the quality of a road has both direct and indirect effects on the livelihoods of the poor.
At the most direct (and measurable) level, road rehabilitation projects reduce the time and costs
associated with transportation. The increased demand for transport may ensure that more trips
are made along the improved road, that transport fares decrease and commodities are transported
cheaply and more conveniently. Indirect impacts would then be observed at the household level,
as real consumption increases by virtue of both lower prices for consumer goods as well as
increased earnings from employment and business opportunities created during project execution
(e.g. short-term labor intensive works and associated forward linkages) and after the project is
completed (e.g. added investment and jobs throughout the catchment area). Finally, another
indirect effect would stem from enhanced access to health, education and other services, thereby
strengthening capabilities and enabling the poor to accumulate human capital. In sum, road
4 World Bank, ECAPOV
52
investments are relevant in reducing poverty because of their effect in the general conditions that
enable pro-poor economic growth to occur.
Framework of analysis, data collection, and methodology
4. An underlying priority for the proposed project is to identify design parameters and
implementation arrangements which could potentially yield the biggest pro-poor impacts
outlined above and optimize the project’s distributional implications. Therefore, it is necessary to
conduct rigorous analysis of how the bottom 40 percent would be positively or negatively
affected. This project will finance innovative assessments and evaluations to better articulate the
benefits of the planned road improvement works at the community and household levels.
5. The impact analysis will be geared towards examining project outcomes in the following
three areas:
a) Connectivity, mobility and accessibility, including traffic counts, vehicle speeds,
travel time, travel costs, availability and fare of public transport;
b) Local and international market development, investment, and employment including commodity prices, agricultural productivity, small business development,
and land use patterns in areas of influence;
c) Household welfare including income, consumption, asset ownership, and access to
market and public services.
6. The study will emphasize project outcomes on the bottom 40 percent and other
vulnerable groups (elder and people with disabilities). Contingent on resource availability and
timing of data collection, the impact assessment would generate quantitative and qualitative
analysis with the use of traffic surveys as well as household and community level surveys
emphasizing the following:
a) Major mobility/transport constraints faced by households in the immediate catchment
area of the selected road segments for their inter-regional transport needs and their
livelihood strategies.
b) Perceptions of poor and vulnerable households, small-scale farmers, and other groups
on the affordability, adequacy, and reliability of existing inter-regional transport
choices.
c) Theoretical and empirical channels, through which these road links taken together
with other investments could directly influence local economic development, improve
the functioning of product and labor markets, and enhance opportunities and welfare
of the bottom 40 percent.
d) Ideas where associated investment or infrastructure could be designed to leverage the
development impact in the area of influence.
While the specific methodologies, survey instruments, measurements, and scope of work will be
further defined and developed before and during project implementation, at the most basic level,
main activities of the impact analysis will include collection and analysis of relevant qualitative
and quantitative data, conducting an assessment of potential poverty and social impacts through
the project road with recommendations for enhancement, and examining induced effects on local
and regional economies.