themis fdmo cdr peer review − l&eo and normal operations 1june 1-2, 2004 l&eo and normal...
TRANSCRIPT
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 1 June 1-2, 2004
L&EO and Normal Operations
Manfred Bester
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 2 June 1-2, 2004
L&EO and Normal Operations
Overview• Launch• Early Orbit Checkout• Maneuver Operations• Instrument Commissioning• Normal Science Operations
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 3 June 1-2, 2004
L&EO Operations
Launch & Early Orbit Operations• Delta II Launch Sequence with Release of Probes• Probe A Radiating During Separation, Monitored Via TDRSS• Subsequent Round Robin State-of-Health Monitoring• Initial Attitude and Orbit Determination• Uplink of First Set of Command Loads to Each Probe• Change Attitude from Release to Commissioning Attitude• Systematic Instrument Power-up and Check-out• Decision of Probe Placement − Based on Functional Check-out• Orbit Placement Maneuvers• Critical Operations Performed Real-time Contact• Approval to Proceed via Command Authorization Meetings
(CAMs)
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 4 June 1-2, 2004
Launch Configuration
Third Stage and Probe Carrier Assembly
Delta II 7925-10
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 5 June 1-2, 2004
Probe Exterior and Interior View
Probe Bus – Exterior View with Magnetometer Booms Stowed
Probe Bus – Interior View
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 6 June 1-2, 2004
Probe Separation
Separation from PCA• Monitoring of Separation via TDRSS• One Probe Will Be Transmitting (THEMIS A, Top of PCA)• All Probes Will Be Recording Data• Round-robin Status Polling After Separation• Each Probe Will Be Contacted for 5 Minutes Initially
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 7 June 1-2, 2004
Dispersion Analysis
Post-launch Probe Dispersion Analysis• Use Relative Separation Velocities• Perform Inter-probe Range Analysis (Not Yet Completed)
Relative Separation Velocities
X [m/s] Y [m/s] Radial [m/s] Z [m/s]
PCA + LV 0.0000 0.0160 0.01600 -0.2700
Probe A 0.0084 -0.0349 0.03590 0.2563
Probe B 1.5726 -0.9411 1.83269 0.1549
Probe C 0.9456 1.5864 1.84684 0.1416
Probe D -1.5818 0.9589 1.84975 0.1326
Probe E -0.9545 1.5681 1.83576 0.1460
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 8 June 1-2, 2004
Mission Profile
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 9 June 1-2, 2004
Post-launch Scenario
Power Profile• Probes Are Power Positive with Minimum Loads• Need to Perform Attitude Maneuver to Orient Probe +Z Axis
Perpendicular to Probe-sun Line to Allow for Check-out Activities
Thermal Profile• Worst Case Is Top or Bottom Deck to Sun
Communications Coverage• Scenario Based on Launch Trajectory Provided by KSC• Modeled Probe Antenna Pattern• Dynamic Link Margin Calculated for Telemetry Data Rate of
4.096 kbps
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 10 June 1-2, 2004
Launch Scenario
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 11 June 1-2, 2004
Launch Scenario
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 12 June 1-2, 2004
Launch Scenario
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 13 June 1-2, 2004
Launch Scenario
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 14 June 1-2, 2004
Probe Antenna Pattern
Calculated Probe Antenna Pattern
Specification:-3 dB Points at 90° ± 45°
Polarization: LHCP
Pattern: Toroidal, Centered in X−Y Plane
Top Deck of Probe Body Affects Gain Pattern:Blockage at −ZRipples at +Z
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 15 June 1-2, 2004
Launch Scenario
Data Rate: 4.096 kbps
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 16 June 1-2, 2004
Launch Scenario
Data Rate: 4.096 kbps
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 17 June 1-2, 2004
Launch Scenario
Polar Plot of First Two BGS View Periods
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 18 June 1-2, 2004
L&EO Timeline
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 19 June 1-2, 2004
L&EO Timeline
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 20 June 1-2, 2004
L&EO Timeline
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 21 June 1-2, 2004
L&EO Timeline
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 22 June 1-2, 2004
Maneuver Planning & Execution
Maneuver Planning• Determine Pre-maneuver State Vector and Attitude with Required Accuracy• Perform Maneuver Analysis with Current and Target State Vectors• Verify Delta V Budget• Perform Contact Schedule and Shadow Analysis• Develop Detailed Thruster Firing Sequence• Validate Probe Configuration and Maneuver Sequence on Probe Simulator
Maneuver Execution• Establish Two-way Communications with Probe• Ramp Down ESA High-voltage Supply, Place SST into Attenuated Mode• Uplink Command Sequence to Perform Reorientation and Orbit Maneuvers• Download and Verify Command Buffer and Verify Firing Attitude• Monitor Maneuver Execution in Real-time• De-configure Probe Systems and Monitor Health and Safety
Maneuver Calibration• Determine Post-maneuver Orbit and Attitude• Calibrate Thrusters and Analyze Overall Maneuver Efficiency and Accuracy• Perform Accurate Bookkeeping of Fuel Usage
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 23 June 1-2, 2004
Pre-launch Testing & Validation
Pre-launch Testing and Validation of Maneuvers• Develop Representative Command Profile
– Required to Perform End-to-end Tests for All Operational Scenarios for Each Probe
• Post-test Analysis of Captured VirtualSat Telemetry Data– Validate ACS Flight Software for Thruster Control, On-orbit
Attitude Determination and Fault Protection– Validate Ground-based Attitude Determination Software
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 24 June 1-2, 2004
Probe Operations Functions
Ground Operations Functions
Perform Mission Design to Determine Target Probe Orbit
and Attitude
Perform GMAN Run with Current and Target Orbit
and Attitude
Formulate Specific Maneuver Events,
Attitudes and Durations
Generate Discrete Thruster Profile and Pulse
Firing Sequence
Generate Discrete Stored Command
Sequence Via MPS
Upload TLM Table, Firing Sequence
and Downlink Data Rate
Perform Off-line Validation of Entire Stored Command
Sequence on Hi-fidelity Probe Simulator
Turn On Gyros and Catalyst Bed Heaters (Pre-heat)
Downlink On-board
CMD Buffer
Compare Flight and Ground
Reference Image to
Verify Load
Verify CMD & TLM Link Via BGS, WGS or
TDRSS
Verify Current
Attitude Via Sun Sensor
Data
Verify Gyro Performance,
Catalyst Bed Heater Functionality,
Propellant Tank Pressure, Valve and
Fuel Line Temperatures and States, and Pre-
Maneuver Attitude
Turn Off Catalyst
Bed Heaters
Execute Burn Sequence
Monitor Key Temperatures, Tank Pressure,
Attitude and State Vector
On-board Failure Detection &
Correction (FDC) Logic (Gyro Rates,
Sun Sensor Attitude Limits, etc.) Aborts
Sequence if Anomaly Detected
Turn Off
Gyros
Verify Tank Pressure, General Probe Health and
Safety, and Perform Two-way
Ranging
Turn Off Transmitter
Determine New Orbit
and Attitude,
and Calibrate Maneuver
Typical Maneuver Sequence
Perform Long-term Calibration of Pulse
Timing and Thruster Efficiency
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 25 June 1-2, 2004
Maneuver Types
Maneuver Type
Thrusters Involved
Purpose, Requirements and Fuel EfficiencyOrbit Position for Maneuver
GMAN Compatibility
Orbit Maneuver
A1 and A2 Continuous
Firing
Perigee or Apogee ChangePreceded and Followed by Attitude Maneuver
High Fuel EfficiencyArc Limited Near Perigee to Minimize Cosine Loss
Apogee or Perigee
Yes
Orbit Maneuver
A1 and A2 Continuous
Firing
Inclination Change with or without Arg Per Change
Preceded and Followed by Attitude ManeuverHigh Fuel Efficiency
Apogee Yes
Orbit Maneuver
A1 and A2 Continuous
Firing
Combined In-plane and Out-of-plane Orbit Change
Preceded and Followed by Attitude ManeuverHigh Fuel Efficiency
Arc Limited Near Perigee to Minimize Cosine Loss
Apogee or Perigee
Yes
Orbit Maneuver
A1 and A2 Continuous
Firing Alternating with T1 and T2 Pulsed Firing
In-plane and Out-of-plane Orbit Tweak in Mission Attitude
Large Beta Angle LossSunlight on Sun Sensor Required
Arc Limited Near Perigee to Minimize Cosine Loss
Apogee or Perigee
Yes
Attitude Maneuver
A1 and / or A2 Pulsed Firing
Attitude Change to or from Mission or Maneuver Attitude
High Efficiency Prior to Spin-plane Boom DeployLow Efficiency after Spin-plane Boom Deploy
Sunlight on Sun Sensor Required
Any Yes
Spin Up or Spin Down
T1 or T2 Pulsed Firing
Spin Rate AdjustmentSunlight on Sun Sensor Required
Any Yes
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 26 June 1-2, 2004
Maneuver Sequence
Earth
Precession Maneuver to
Normal Attitude
Upload: Thruster Enable
Precession Maneuver to Axial Thrust AttitudeAttitude Monitoring
(MSSS / IRU)
Ground-Based Attitude
Determination(MSSS / FGM)
Upload: Thruster Commands
Upload: Thruster Enable
Upload: Thruster Enable
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 27 June 1-2, 2004
Mission Orbit Placement
Mission Orbit Placement for P1• Accelerated Maneuver Sequence Modeled with GMAN
– Apogee and Perigee Raises– Inclination Adjustment
• Goals of Study– Determine Communications Coverage
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 28 June 1-2, 2004
Communications Coverage
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 29 June 1-2, 2004
Maneuver Details
Spin-up and Spin-down Maneuvers • Spin Rate Limits: 2 - 25 rpm
Timing of Pulse Maneuvers• Ensure Pulse Frequencies Do Not Coincide with Probes’
Fundamental Frequencies (Nutation, Spin-plane Booms, Axial Booms, Propellant Slosh)
Flight Rules Related to Maneuver Operations• RCS Configuration• Maintain Spin Rate Within Allowable Limits• Select Pulse Timing to Avoid Exciting of Resonances
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 30 June 1-2, 2004
Real-time Maneuver Support
Real-time Maneuver Support• Communications Requirements
– Ground Station Contact– TDRSS Contact
• Real-time Monitoring– Tank Pressure– Thruster Temperatures– Probe Attitude Vector– Doppler Profile
• Compare Observed Against Predicted Performance– Real-time Trend Plots for Observed Minus Calculated Attitude
and Doppler Residuals– Plotting Doppler Residuals Requires Real-time Data from
Ground Stations– Plotting Attitude Angle Residuals Requires Data from Probe
Telemetry Via ITOS
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 31 June 1-2, 2004
Attitude Control Plan
Attitude Control Plan• Probe Release from Launch Vehicle, Nominally at 15 rpm• Optional De-spin to 15 rpm, in Case of Off-nominal Release• Attitude Maneuver to Place Spin Axis Perpendicular to
Probe-to-sun Line at 15 rpm• Deploy of Magnetometer Booms at 15 rpm• Spin-up to 20 rpm• Attitude and Orbit Maneuvers at 20 rpm• Attitude Maneuver to Point Spin Axis Towards Ecliptic South
pole at 20 rpm• Spin-up to 25 rpm Prior to Spin-plane Boom Deploy• Spin-plane Boom Deploy at Variable Spin Rate 5 - 25 rpm• Spin-up to 20 rpm After Last Spin-plane Boom Deploy Step• Axial Boom Deploy at 20 rpm
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 32 June 1-2, 2004
Instruments
Instruments
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 33 June 1-2, 2004
IDPU Power Modes
IDPU Power ModesMode IDPU & Instrument Status Power Consumption
Shut Down Mode IDPU OffAll Instruments Off
0.0 W
Safe Mode IDPU OnAll Instruments Off
7.8 W
Low Power Mode IDPU OnFGM OnAll Other Instruments Off
8.0 W
Engineering Mode IDPU OnInstrument States Vary Depending on Activity
N/A
Science Mode IDPU OnAll Instruments On
11.8 W
IDPU Power Modes• Launch Configuration: Shut Down Mode• FGM Operation: Requires at Least Low Power Mode
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 34 June 1-2, 2004
Instrument Commissioning
Instrument Commissioning1. IDPU Turn-on As Soon As Probe Power System Is Stable and Temperature
Within Operating Limits, Verification of Nominal Voltages and Currents, Command Communications and DCB Functionality
2. FGM Turn-on, Power Verification and Uplink of Parameter Load for 32 Hz Bx, By and Bz, Verification of Sensitivity Control on Each Axis, Select Sensitivity
3. EFI Turn-on, Power Verification and Configuration for 32 Hz E & B Sample Rates
4. SCM Turn-on, Power Verification and Activation of Calibration Sequence5. Magnetometer Boom De-spin to <15 rpm and Deployment With FGM at 32 Hz
Real-time Science TLM; Cross-calibration of Magnetometers While Probe Separations Are Still Small
6. SST Turn-on After Initial Outgassing Phase, Power Verification, High-voltage Ramp-up and Attenuator Functional Test
7. ESA Turn-on After Initial Outgassing Phase, Power Verification, Cover Release and High-voltage Ramp-up
8. EFI Spin Plane Boom Deployment − Procedure Controlled by IDPU9. EFI Axial Boom Deployment − Procedure Controlled by IDPU
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 35 June 1-2, 2004
EFI Deployment Details
EFI Deployment Overview• Initial On-orbit Check-out
– EFI SOH Determined Using Stowed DC and AC Functional Test Capability
• Booms Deployed After Completion of Initial Orbit Placement– Attitude Maneuvers with Deployed Booms Too Expensive
• Deployment Sequence– Spin-plane Boom Deployment
– 5 to 6 Intermediate Deploy Lengths with Interleaved Spin-up
– Axial Boom Deployment– 1 Step to Deploy Both Axial Booms
• Primary Constraints for Deploy and Commissioning– Transmit Time Limited to 30 min– Required Transmitter Cool-down Period of 3.5 h– Desire to Gather Science Data at Intermediate Deploy Lengths
and in Different Plasma Regimes
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 36 June 1-2, 2004
EFI Deployment Sequence
EFI Deployment Sequence Per Probe• Deploy SPB-X
– Deploy Boom Section– Wait for Transmitter to Cool Down– Run Slow Sweep and Take Diagnostic Mode Data
• Deploy SPB-Y– Deploy Boom Section– Wait for Transmitter to Cool Down– Run Slow Sweep and Take Diagnostic Mode Data
• Spin Up to 20 rpm– Prepare for Next Deploy Cycle
Slow Sweep• Large Parameter Space to Be Explored
– 4 Braid, 3 Usher, 3 Guard and 32 Bias Settings– 1152 Steps, 1 Step / Spin– Sweep Duration Approximately 1 hour
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 37 June 1-2, 2004
EFI Deployment Order
EFI Deployment Order• P3 and P4 Deploy First
– 2-day, 2-orbit Cycle:– P3 Deploying and P4 Pausing– P4 Deploying and P3 Pausing
– Full deploy and commissioning takes 14 days• P1 and P2 Deploy Next
– P2 on 2-day (1-orbit) Cycle– Deploy on Outbound, Quiescent on Inbound; 14 Days Total
– P1 on 4-day (1-orbit) Cycle– Deploy on Outbound, Quiescent on Inbound; 28 Days Total
– P1 Deploy Cycle May Be Accelerated– Depends on Experience Gained and Data Gathered During P3 and P4
Deploy and Commissioning
• P5 Deploys Last– 1 or 2-day cycle
– Full Deploy and Commissioning Takes 7-14 Days
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 38 June 1-2, 2004
EFI Normal Science Operations• EFI Instrument Mode
– Slow Survey, Fast Survey, Particle Burst, Wave Burst and Diagnostic Mode
– Set by ~30 Registers on BEB– Configurable Data Rates Via DFB Mode Commands– Typical Mode Specified with ~200 Commands– Valid Over a Typical One-month Period, Once Deploy and
Commissioning Completed• Slow Sweeps and Diagnostic Data
– Taken Several Times per Year– Upon First Entry into New Plasma Regime– After Long Shadows
– Maintain Optimal Bias Settings– Monitor EFI State-of-health
EFI Science Operations
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 39 June 1-2, 2004
Flight Rules
Flight Rules• Preliminary Collection for All Subsystems
– Power System– Telecommunications Subsystem– Reaction Control System– Attitude Control System– Flight Software– Command & Data Handling– Instruments
• Detailed List Developed During I&T
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 40 June 1-2, 2004
Power System Flight Rules
Power System Flight Rules
Activity Flight Rule Potential Impact of Violation
Subsystem power-on Subsystems must be powered on only when their temperatures are within the specified limits.
Damage to flight hardware.
Load shedding Bus voltage must be kept within specified operating limits.
Load shedding will occur autonomously on-board when under-voltage condition is detected.
Battery state-of-charge too low.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 41 June 1-2, 2004
Telecom Flight Rules
Telecom Flight Rules
Activity Flight Rule Potential Impact of Violation
Transmitter operation Transmitter on-time limited to 30 min.
For nominal science operations planning and analyses, transmitter on-time is limited to 30 min per day.
Overheating of transmitter.
Transmitter operation Minimum transmitter off-time of 3 hours between transmitter on-times.
Current thermal analyses show that transmitter needs to be off for 3 hours to cool down completely.
Overheating of transmitter.
Transmitter operation Minimum period of transmitter off-time prior to entry and after exit of long shadows.
Exact times are driven by operational activities and overall power management.
Battery state-of-charge too low.
Transmitter operation Transmitter on-time during shadows limited to less than 30 min.
Allowed transmitter-on times for a given shadow period are driven by overall power management.
Battery state-of-charge too low.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 42 June 1-2, 2004
RCS Flight Rules
RCS Flight Rules
Activity Flight Rule Potential Impact of Violation
Thruster operation Catalyst bed heaters must be turned on 60 min before thrusting to heat up, and turned off before thrusting.
Damage to catalyst beds.
Thruster firing Thrusters must not be fired unless ESA HV is ramped down and SST attenuators are closed.
Damage to ESA and/or SST.
Thruster firing Maneuvers must not be performed in shadow. Erroneous maneuver execution.
Tangential thruster firing Tangential thruster T1 (spin-up thruster) must not be fired until SCM boom is deployed.
Damage to SCM sensor by thruster plume.
Pyro valve operation Pyro valve used to repressurize fuel tanks must not be opened until pressure in fuel tanks has dropped to 580 kPa.
Bursting of fuel tanks. Destruction of probe.
Latch valve operation Latch valves must be configured to allow for equal depletion of fuel tanks in case mass properties are off-nominal.
This situation may occur if the spin-plane booms do not deploy symmetrically.
Gas migration into fuel lines due to unequal depletion of fuel tanks.
Load shedding Both RCS heater services must not be turned off simultaneously.
Freezing of fuel and bursting of fuel lines.
Thruster monitoring Limits for allowable thruster sum current must be set prior to thruster operation.
Erroneous limit violations.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 43 June 1-2, 2004
RCS Flight Rules - Cont.
RCS Flight Rules - Continued
Activity Flight Rule Potential Impact of Violation
FDC management Maximum angular rates measured by IRUs must be set according to planned attitude maneuver.
Premature or late maneuver abortion.
FDC management Maximum thruster on-time must be configured for expected duration of thruster operation.
Premature maneuver termination.
Pulsed thruster firing Pulsed operation of thrusters must not be performed at pulse rates at or near natural frequencies of nutation, spin-plane booms, axial booms and propellant slosh.
Loss of dynamic stability.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 44 June 1-2, 2004
ACS Flight Rules
ACS Flight Rules
Activity Flight Rule Potential Impact of Violation
Spin rate control Spin rate must be maintained within 2 - 25 rpm. Loss of dynamic stability. Damage to booms.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 45 June 1-2, 2004
FSW / C&DH Flight Rules
FSW / C&DH Flight Rules
Activity Flight Rule Potential Impact of Violation
RTS operation FDC algorithms and ATS loads must be set up such that not more than two RTSs operate at the same time.
Erroneous command execution.
FDC management Turn off Data Monitors when components are turned off.
Erroneous limit violations.
FDC management Disable Data Monitors that use delta time before setting the clock.
Erroneous limit violations.
FDC management Reset time before enabling Data Monitors that use delta time.
Erroneous limit violations.
Clock adjustment Clock adjustments must not be performed during critical operations such as maneuvers.
Erroneous maneuver execution.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 46 June 1-2, 2004
Instrument Flight Rules
Instrument Flight Rules
Activity Flight Rule Potential Impact of Violation
IDPU power power-on IDPU temperature must be within allowed operational limits prior to powering up.
Damage to IDPU electronics.
ESA HV power-on ESA HV must not be turned on until initial outgassing is completed.
Damage to ESA.
ESA HV ramp-down ESA HV must be ramped down prior to thruster operations.
Contamination of ESA.
SST HV power-on SST HV must not be turned on until initial outgassing completed.
Damage to SST.
SST attenuator operation
SST attenuators must be closed prior to thruster operations.
Damage to SST.
Boom deployment Booms must be deployed only when their temperature is within allowed range.
Probe attitude may have to be adjusted to bring temperature into allowed range.
Unsuccessful boom deploy. Damage to boom deployment mechanism.
Magnetometer boom deployment
Magnetometer booms must be deployed at spin rates from 2 to 15 rpm.
Damage to magnetometer booms.
EFI radial boom deployment
EFI radial booms must be deployed at spin rates from 2 to 25 rpm.
Unsuccessful boom deploy. Damage to boom deployment mechanism.
EFI axial boom deployment
EFI axial booms must not be deployed unless spin-plane booms are deployed to their nominal distance.
Loss of dynamic stability.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 47 June 1-2, 2004
Instrument Flight Rules - Cont.
Instrument Flight Rules - Continued
Activity Flight Rule Potential Impact of Violation
EFI axial boom deployment
EFI axial booms must be deployed at spin rates from 2 to 25 rpm.
Damage to axial booms.
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 48 June 1-2, 2004
Normal Science Operations
Mission Planning• Pass Schedule and Command Load Generation
Probe Command and Control• Probe Health and Safety Monitoring• Recovery of Science and Engineering Data• Command Load Uplink Twice Per Week• Probe Clock Adjustments• Instrument Configuration and Data Trending
Orbit and Attitude Determination• Routinely Performed Multiple Times per Week
Maneuver Planning and Execution• Orbits of P1 and P2 Adjusted Few Times Per Year to Optimize
Conjunctions and Annually to Avoid Shadows• Orbit of P5 Adjusted for First Year Dayside and Second Year
Tail and Dayside Seasons
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 49 June 1-2, 2004
Weekly Operations Schedule
Week Operations Schedule for the ConstellationMon Tue Wed Thu Fri Sat Sun5 Pass
Supports
FOT On Console
5 Pass Supports
FOT On Console
5 Pass Supports
FOT On Console
5 Pass Supports
FOT On Console
5 Pass Supports
FOT On Console
5 Pass Supports
Lights-out Operation
5 Pass Supports
Lights-out Operation
Generation and Uplink of
ATS Loads
Pass Scheduling
Uplink of Table Loads
(If Required)
Pass Scheduling
Generation and Uplink of
ATS Loads
Telemetry Recovery
Telemetry Recovery
Telemetry Recovery
Telemetry Recovery
Telemetry Recovery
Telemetry Recovery
Telemetry Recovery
Data Trending and Limit Checking
Data Trending and Limit Checking
Data Trending and Limit Checking
Data Trending and Limit Checking
Data Trending and Limit Checking
Data Trending and Limit Checking
Data Trending and Limit Checking
Tracking Data Pre-
processing
Attitude Validation
Maneuver Calibration
Tracking Data Pre-
processing
Attitude Validation
Orbit Determination
Attitude Determination
Maneuver Planning
Orbit Determination
Attitude Determination
Ephemeris and Product Generation
Ephemeris and Product Generation
Ephemeris and Product Generation
Ephemeris and Product Generation
Ephemeris and Product Generation
Ephemeris and Product Generation
Ephemeris and Product Generation
Delivery of IIRVs and
PSATs
Delivery of IIRVs and
PSATs
Delivery of IIRVs and
PSATs
Delivery of IIRVs and
PSATs
Delivery of IIRVs and
PSATs
Delivery of IIRVs and
PSATs
Delivery of IIRVs and
PSATs
THEMIS FDMO CDR Peer Review − L&EO and Normal Operations 50 June 1-2, 2004
Probe Safing Operations
Probe Safing Operations• Power System
– Automatic Load Shedding• Attitude Control System
– Spinning Platform• Reaction Control System Shutdown
– Various Fault Detection Mechanisms– Time-out for Thrusting– Rate Monitoring Via IRUs
• Instrument Safing– HV Ramped Down and Attenuators Moved into FOV for Thruster
Operations