theory of constraints and project management: challenging the dominant paradigm
DESCRIPTION
TRANSCRIPT
![Page 1: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/1.jpg)
McElroy Translation
Theory of Constraints and Project Management:
Challenging the Dominant Paradigm
Bob Donaldson, VP Strategy, McElroy Translation Company
![Page 2: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/2.jpg)
Setting the Stage: Technology Pressures
CMS/TMS Integration– Automates Localization Project Initiation– Impact on Capacity Planning?
Translation Memory & Advanced Leverage Tools– Improves Translation Reuse– Impact on Translator Involvement?
Collaborative Working Models & Environments– Enables More Parallelism– Impact on Quality Control?
Machine Translation Integration– Improves Translator Productivity– Impact on Business Model?
![Page 3: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/3.jpg)
Typical Project Problems
Challenges & Symptoms Survey Results (1998)*
Late
Only 44% of all projects finish on schedule or before. The rest tend to be very late. On average, projects are 222% longer than planned.
Over budget By 189%
Fall short of planned technical content
70% of projects
Canceled before finished 30% of projects
Day-to-day chaos & frustrations
Epidemic
No reliable way to measure project status
Until it's too late
Source: National survey conducted by The Standish Group
![Page 4: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/4.jpg)
Project or Standard Services or Life Cycle?
Localization Project– Historical Usage– Describes Initial Localization of Legacy Material– Implies Unique Set of Goals, Tasks, Challenges
Localization Life Cycle– Standard Component of Product/Content Development– Better Describes Buyer Viewpoint– Implies Regularity & Repetition
Localization Services– Standard Tools, Processes & Deliverables– Better Describes Vendor Viewpoint– Implies Global Perspective on Multi-Project Management
![Page 5: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/5.jpg)
Service Delivery Challenges
Service delivery depends upon people who …– Do not always work at the same rate– Do not always communicate effectively– Constitute a capacity constraint
Customer satisfaction depends upon …– Service Quality standard processes– Service Responsiveness flexible processes– Management intervention to adjust priorities
Suboptimal processes & metrics often create – Interdepartmental friction– An environment of chaos
![Page 6: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/6.jpg)
Dilbert’s Perspective on Coordination
![Page 7: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/7.jpg)
Service Delivery Dilemma
GOAL: Become a Good Service Company
Maintain ConsistentQuality
Meet TimelinessExpectations
Work to StandardProcesses
Work Flexibly
Source: TOC Resultants: www.toc-resultants.com
![Page 8: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/8.jpg)
PMBOK – The Current Standard
Initiating– Sponsorship, Project Goals, etc.
Planning– Schedule, Budget, Resource Allocation, etc.
Executing– Monitoring, Problem Resolution, QA, etc.
Controlling– Performance/Risk Reporting, Forecasting, etc.
Closing– Delivery, Lessons Learned, etc.
![Page 9: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/9.jpg)
Why Projects Fail
The Dilbert Principle:
“Anything I don’t understand must be easy.”
Do we really understand the difference between project management & project monitoring?
![Page 10: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/10.jpg)
Typical Project Plan
end
start
end
start
Critical Path
Local ‘Safety Time’ Embedded Throughout
Note the illusion of certainty!
![Page 11: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/11.jpg)
end
start
end
start
Typical Plan w/Resource Leveling
Critical Path
Local ‘Safety Time’ Embedded Throughout
Resource Contention
Illusion of certainty remains
![Page 12: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/12.jpg)
Multi-Project [Standard Services] Issues
end
start
end
start
end
start
end
startend
start
end
startend
start
end
start
Early Late
Expected Performance
Actual Performance?
Early Late ……
![Page 13: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/13.jpg)
Parkinson’s Law
1 C. Northcote Parkinson; The Economist, Nov. 1955
Work expands to fill the time available for its completion1
The root problem is “Safety” time!
![Page 14: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/14.jpg)
Implications for Project Execution
Resources scheduled to maximize utilization Late completion is penalized (obviously)
– So local safety time expands Early completion is also penalized
– “Excess” capacity invites more work– Utilization is often part of performance reviews– Credibility of estimates may be in question
On-time delivery is placed at risk– Current ‘on time’ status not indicative of risk– Time ‘saved’ by early completion is typically wasted– Time ‘lost’ by late completion cascades to subsequent
tasks (and projects!)
![Page 15: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/15.jpg)
Dilbert’s Perspective on Project Status
![Page 16: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/16.jpg)
Theory of Constraints – Focus on Throughput
Identify
Exploit
Subordinate
Elevate
Evaluate
Strategic (Corporate) Loop
Tactical (Project) Loop
![Page 17: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/17.jpg)
Tactical Constraints – Single Project
Goal is to deliver project benefit as quickly as possible
Effective project management involves – Identifying the critical chain of tasks that are
constraining the project’s completion– Exploiting potential capacity constraints
through effective scheduling– Subordinating non-critical tasks & Controlling
uncertainty through buffer management Focus on throughput not utilization
![Page 18: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/18.jpg)
Theory of Constraints in PMBOK Context
Initiating
Planning– Critical Chain Schedule (vs. Critical Path)
Executing– Maximize Throughput (vs. Utilization)
Controlling– Buffer Management (vs. Task Completion)
Closing
![Page 19: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/19.jpg)
end
start
end
start
Back to our Familiar Project Plan
Critical Path
![Page 20: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/20.jpg)
end
start
end
start
Critical Chain Plan w/Buffers
Critical Chain
![Page 21: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/21.jpg)
end
start
end
start
Critical Chain Plan w/Buffers
Gating Buffer
Constraint Buffers
Feeding BufferProject BufferCritical Chain
![Page 22: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/22.jpg)
100%100% 100%100%
Typical Resource Utilization PlanAdjusted by removing “safety” time …
![Page 23: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/23.jpg)
The Roadrunner … Sprint Capacity
Roadrunners have two speeds …
Stopped (but ready for action)
and Fast !
![Page 24: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/24.jpg)
Roadrunner Advantages
Working to capacity per schedule generates throughput
Not working ahead protects throughput by– Preserving “sprint capacity”– Avoiding unnecessary work– Reducing work in progress
It’s all about throughput!
![Page 25: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/25.jpg)
Strategic Constraints
Goal is to maximize organizational throughput
“Hard” Constraints– Resource Capacity– Infrastructure Capacity
“Soft” Constraints– Existing Policies– Existing Performance Metrics
![Page 26: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/26.jpg)
A Few Words on Metrics
Typical metrics are cost-centric– Resource utilization levels– Task duration & on-time completion– Project cost & on-time delivery
We need throughput-centric metrics– $’s of throughput per unit of time– $-days of buffer consumption– $-days of work in progress
![Page 27: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/27.jpg)
Performance Metrics w/Buffers
Source: http://www.dbrmfg.co.nz
Throughput Dollar DaysLate
Throughput Dollar DaysLate
Near-the-endMiddleBeginning End
Track
Feeding Buffer End Time
0 Buffer
CheckingTime
Constraint Buffer End Time
0 Buffer
CheckingTime
Tracking Zone
![Page 28: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/28.jpg)
Resolving the Dilemma
GOAL: Become a Good Service Company
Maintain ConsistentQuality
Meet TimelinessExpectations
ConstraintManagement
Buffer Management
Throughput OrientedMetrics
![Page 29: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/29.jpg)
Summary
Identify the Constraint – Select the best leverage point
Exploit the Constraint– Maximize throughput with system schedule– Protect throughput with project buffers
Subordinate everything else to the Constraint– Beware of legacy performance metrics– Provide for “Roadrunner” responses
Elevate the Constraint– Address capacity or productivity limits
Repeat!
![Page 30: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/30.jpg)
Further Reading
A Guide to Implementing the Theory of Constraints (TOC). Dr. K. J. Youngman. www.dbrmfg.co.nz
Any book by Eliyahu Goldratt …
TOC Resultants – www.toc-resultants.com
![Page 31: Theory of Constraints and Project Management: Challenging the Dominant Paradigm](https://reader033.vdocuments.net/reader033/viewer/2022051110/54b5abb24a7959e13c8b457d/html5/thumbnails/31.jpg)
Contact Details
Bob DonaldsonVP StrategyMcElroy Translation Company910 West AvenueAustin, TX 78701