theory_(1 - 6)_without numbers

Upload: alekhya99

Post on 06-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    1/38

    Maintenance and operation of 33/11KV SUBSTATION Page 1

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    2/38

    INTRODUCTION

    Maintenance is an important part of the life-cycle of systems, and must be

    considered from the design stage through the end-of-life stage of the system. Maintenance

    covers two aspects of systems - operation and performance. Maintenance is generally

    performed in anticipation of, or in reaction to, a failure. Maintenance is performed to ensure

    or restore system performance to specified levels. Improperly performed or timed

    maintenance can exacerbate problems because of faulty parts, maintainer error, or decreased

    profits. A systematic and structured approach to system maintenance, starting during the

    design process, is necessary to ensure proper and cost-effective maintenance.

    Past and current maintenance practices in both the private and Government sectors

    would imply that maintenance is the actions associated with equipment repair after it is

    broken. The dictionary defines maintenance as follows: the work of keeping something in

    proper condition; upkeep. This would imply that maintenance should be actions taken to

    prevent a device or component from failing or to repair normal equipment degradation

    experienced with the operation of the device to keep it in proper working order.

    Unfortunately, data obtained in many studies over the past decade indicates that most private

    and Government facilities do not expend the necessary resources to maintain equipment in

    proper working order. Rather, they wait for equipment failure to occur and then take

    whatever actions are necessary to repair or replace the equipment. Nothing lasts forever and

    all equipment has associated with it some pre-defined life expectancy or operational life. The

    design life of most equipment requires periodic maintenance

    Maintenance and operation of 33/11KV SUBSTATION Page 2

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    3/38

    TYPES OF MAINTENANCES

    Over the last 30 years, different approaches to how maintenance can be

    performed to ensure equipment reaches or exceeds its design life have been developed. In

    addition to waiting for a piece of equipment to fail (reactive maintenance), we can utilize

    preventive maintenance, predictive maintenance, or reliability centered maintenance.

    REACTIVE MAINTENANCE: (Breakdown or Run-to-Failure Maintenance)

    Reactive maintenance is basically the run it till it breaks maintenance mode. No

    actions or efforts are taken to maintain the equipment as the designer originally intended to

    ensure design life is reached.

    Basic philosophy

    Allow machinery to run to failure.

    Repair or replace damaged equipment when obvious problems occur.

    This maintenance philosophy allows machinery to run to failure, providing for the repair

    or replacement of damaged equipment only when obvious problems occur. The advantages of

    this approach are that it works well if equipment shutdowns do not affect production and if

    labor and material costs do not matter.

    PREVENTIVE MAINTENANCE: (Time-Based Maintenance)

    Actions performed on a time- or machine-run-based schedule that detect, preclude, or

    mitigate degradation of a component or system with the aim of sustaining or extending its

    useful life through controlling degradation to an acceptable level. While we will not prevent

    equipment catastrophic failures, we will decrease the number of failures. Minimizing failures

    translate into maintenance and capitol cost savings.

    Basic philosophy

    Schedule maintenance activities at predetermined time intervals.

    Repair or replace damaged equipment before obvious problems occur.

    This philosophy entails the scheduling of maintenance activities at predetermined time

    intervals, where damaged equipment is repaired or replaced before obvious problems occur.

    The advantages of this approach are that it works well for equipment that does not run

    Maintenance and operation of 33/11KV SUBSTATION Page 3

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    4/38

    continuously, and with personnel who have enough knowledge, skills, and time to perform

    the preventive maintenance work.

    PREDICTIVE MAINTENANCE: (Condition-Based Maintenance)

    Measurements that detect the onset of a degradation mechanism, thereby allowing

    causal stressors to be eliminated or controlled prior to any significant deterioration in the

    component physical state. Results indicate current and future functional capability. Basically,

    predictive maintenance differs from preventive maintenance by basing maintenance need on

    the actual condition of the machine rather than on some preset schedule. You will recall that

    preventive maintenance is time-based.

    Basic philosophy

    Schedule maintenance activities when mechanical or operational conditions warrant.

    Repair or replace damaged equipment before obvious problems occur.

    This philosophy consists of scheduling maintenance activities only if and when

    mechanical or operational conditions warrant-by periodically monitoring the machinery for

    excessive vibration, temperature and/or lubrication degradation, or by observing any other

    unhealthy trends that occur over time. When the condition gets to a predetermined

    unacceptable level, the equipment is shut down to repair or replace damaged components so

    as to prevent a more costly failure from occurring. In other words, Dont fix what is not

    broke.

    Advantages of this approach are that it works very well if personnel have adequate

    knowledge, skills, and time to perform the predictive maintenance work, and that it allows

    equipment repairs to be scheduled in an orderly fashion. It also provides some lead-time to

    purchase materials for the necessary repairs, reducing the need for a high parts inventory.

    Since maintenance work is only performed when it is needed, there is likely to be an increase

    in production capacity.

    Depending on a facilitys reliance on reactive maintenance and material condition, it

    could easily recognize savings opportunities exceeding 30% to 40%. In fact, independent

    surveys indicate the following industrial average savings resultant from initiation of a

    functional predictive maintenance program:

    Maintenance and operation of 33/11KV SUBSTATION Page 4

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    5/38

    Return on investment: 10 times

    Reduction in maintenance costs: 25% to 30%

    Elimination of breakdowns: 70% to 75%

    Reduction in downtime: 35% to 45%

    Increase in production: 20% to 25%.

    RELIABILITY CENTERED MAINTENANCE: (Pro-Active or Prevention

    Maintenance)

    A process used to determine the maintenance requirements of any physical asset in its

    operating context. It recognizes that all equipment in a facility is not of equal importance toeither the process or facility safety. It recognizes that equipment design and operation differs

    and that different equipment will have a higher probability to undergo failures from different

    degradation mechanisms than others. It also approaches the structuring of a maintenance

    program recognizing that a facility does not have unlimited financial and personnel resources

    and that the use of both need to be prioritized and optimized. In a nutshell, RCM is a

    systematic approach to evaluate a facilitys equipment and resources to best mate the two and

    result in a high degree of facility reliability and cost-effectiveness. RCM is highly reliant on

    predictive maintenance but also recognizes that maintenance activities on equipment that is

    inexpensive and unimportant to facility reliability may best be left to a reactive maintenance

    approach.

    Basic philosophy

    Utilizes predictive/preventive maintenance techniques with root cause failure analysis

    to detect and pinpoint the precise problems, combined with advanced installation and repairtechniques, including potential equipment redesign or modification to avoid or eliminate

    problems from occurring.

    This philosophy utilizes all of the previously discussed predictive/preventive

    maintenance techniques, in concert with root cause failure analysis. This not only detects and

    pinpoints precise problems that occur, but ensures that advanced installation and repair

    Maintenance and operation of 33/11KV SUBSTATION Page 5

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    6/38

    techniques are performed, including potential equipment redesign or modification, thus

    helping to avoid problems or keep them from occurring.

    One advantage to this approach is that it works extremely well if personnel have the

    knowledge, skills, and time to perform all of the required activities. As with the predictive-

    based program, equipment repairs can be scheduled in an orderly fashion, but additional

    improvement efforts also can be undertaken to reduce or eliminate potential problems from

    repeatedly occurring. Furthermore, it allows lead-time to purchase materials for necessary

    repairs, thus reducing the need for a high parts inventory. Since maintenance work is

    performed only when it is needed, and extra efforts are put forth to thoroughly investigate the

    cause of the failure and determine ways to improve machinery reliability, there can be a

    substantial increase in production capacity.

    HOW TO INITIATE RELIABILITY CENTERED MAINTENANCE:

    The road from a purely reactive program to a RCM program is not an easy one. The

    following is a list of some basic steps that will help to get moving down this path.

    1. Develop a Master equipment list identifying the equipment in your facility.

    2. Prioritize the listed components based on importance to process.

    3. Assign components into logical groupings.

    4. Determine the type and number of maintenance activities required and periodicity

    using:

    a. Manufacturer technical manuals

    b. Machinery history

    c. Root cause analysis findings - Why did it fail?

    d. Good engineering judgment

    5. Assess the size of maintenance staff.

    6. Identify tasks that may be performed by operations maintenance personnel.

    7. Analyze equipment failure modes and effects.

    8. Identify effective maintenance tasks or mitigation strategies.

    Maintenance and operation of 33/11KV SUBSTATION Page 6

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    7/38

    IMPORTANT SUB-STATION EQUIPMENTS

    The expected life of equipment such as circuit breakers, transformers, etc is 25 years as

    per O&M manuals of power utilities. However, it is specified to be 35 years in the case of

    large sized power transformers. This life expectancy is based on the assumption that the

    equipment is operated and maintained as per standards. Abnormal operation like continuous

    overloading, non-operation of protective devices, equipment repeated feeding faults, and non-

    adherence to preventive schedules will also cause premature ageing and reduce the lifetime.

    The following are the main equipment at 33 / 11 KV Substations.

    1) CIRCUIT BREAKERS ( 33 KV, 11 KV):

    GENERAL:

    It is known that low voltage switches and fuses are used at home. The switch is a

    mechanical

    device which is used to put ON (make) and put OFF (break) the electric circuit. Thefuse

    is protective device which blows out during fault condition such as short circuit thereby

    protecting wiring etc. In the same way, switching and protection in transmission &

    distribution network at high voltage is done / performed by switchgear. Circuit breaker is the

    switching and interruption/ breaking device in switchgear.

    It serves two purposes

    a) Switching during normal operating conditions for operation &maintenance.

    b) Switching during abnormal conditions such as short circuits and interrupting the fault

    current.There are several types of faults and abnormal conditions in power system. The fault currents

    can damage the power system equipment if allowed to flow longer duration. In order to avoid

    damage to the equipment protective relaying is provided.

    The relays sense the fault and send signal to the circuit breaker to open. The

    circuit breaker opens and clears the faults. So circuit breaker is a mechanical switching

    device which is capable of making (closing), braking (opening) and carrying current in power

    system under normal as well as abnormal conditions. All the equipment, associated with

    Maintenance and operation of 33/11KV SUBSTATION Page 7

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    8/38

    switching, interrupting and protection is covered by the switchgear. Circuit breaker is the

    heart of switchgear.

    Why switchgear, when we have switches and fuses for switching, interruption

    and protection. It known that a common experience at home to see a spark in the switch when

    putting off. The spark is seen, because the gap between the contacts of switch becomes

    conducting and current begins to flow in the gap. The spark is extinguished by the natural

    flow of air. At higher system voltage, the natural flow of air is not sufficient to extinguish the

    spark (arc) which is dangerous magnitude. Hence switchgear is must & should used for high

    voltage system.

    VARIOUS TYPES OF CIRCUIT BREAKER:

    When currents are interrupted, an arc strikes between the two contacts (fixed &

    moving). An arc is column of charged particles moving across the contacts. Various media

    used to extinguish arc in the circuit breaker is air, oil, gas (SF6) and vacuum. Now a days

    vacuum technology used for circuit breaker at 33/11KV Sub-stations because of they do not

    need daily observations and maintenance free and low cost affair.

    VACCUM CIRCUIT BREAKER:

    Fig. Vacuum circuit breaker

    Maintenance and operation of 33/11KV SUBSTATION Page 8

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    9/38

    This breaker employs the principle of contact separation under vacuum (in the vacuum

    interrupter or bottle which is provided in top bushing).

    VCB is suitable for rapid closing and tripping and its operations i.e. closing

    and tripping shall be obtained from compressed /or elongation of spring charging

    mechanism.

    The closing spring is charged by motor operation /or with manual lever. As

    soon as the breaker is closed, the tripping spring are get automatically compressed/or

    elongated. Closing spring and associated to spur gears, closing levers, tripping

    levers/linkages and trip & close coils are housed in separate operating mechanism box. All

    breakers shall be provided with 66 trip free mechanisms. These gear and linkages design

    arrangements are varies company to company. But basic theory is same. In the market the

    following companies are available and they are used in APCPDCL.

    1) S&S (OFVP) -vacuum 2) S&S (OFV) -vacuum

    3) System Control -vacuum 4) JYOTHI -vacuum

    5) SIEMENS -vacuum 6) BHEL -vacuum

    7) ALSTOM/GEC/AREVA-vacuum 8) VICTORY -vacuum

    9) G.R.Power -vacuum 10) ABB VCB & SF6

    11) A bond strand -vacuum 12) Mega win -vacuum

    13) Kirloskar -vacuum 14) VOLTAS -SF6

    15) Andrew Yule -vacuum 16) A Lind -vacuum

    17) CGL VCB 18) CGL SF6

    19) BHEL MOCB 20) OLG -vacuum

    21) S&S, SF6 22) HITACHI -Bulk oil

    23) BHEL -Bulk oil

    The operating mechanism shall be operated by local electrical control. Manual

    closing & tripping devices are also provided in the mechanism. Mechanical indicators such

    as to show the close or open and spring charge position of the breaker are also provided

    in mechanism box.

    The VCB / Circuit breaker (except some) shall comprise of three independent

    poles filled with a common operation mechanism. Each pole of the circuit breaker shall

    Maintenance and operation of 33/11KV SUBSTATION Page 9

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    10/38

    consist of a separate breaking chamber. These breaking chambers shall be mounted on a

    common chassis and connected together for common operation i.e. simultaneously tripping /

    closing.

    Every month oiling / or quarterly black grease shall be applied for mechanism

    parts. Do not pour oil / lubrication for close or trip coil plungers. If it is applied, dust & oil

    may get jam trip plunger, the breaker will not trip during normal or fault current. Due to,

    plunger sluggishness, the breaker opening time will be high and it is possible to burn /

    damage relay trip contact. There by protective relaying purpose is defeated. Thus, it is an

    operator duty to vigil or daily check up the healthiness of relay contacts. Relay contacts

    should be always normally open condition i.e. do not make / touch each other.

    It may be happened sometimes that relay trip contacts are got melted touched

    each other or broken due to heavy continuous spark which will be generated by trip coil

    (Auxiliary switch make / brake operation problem).Healthy trip circuit is checked up daily

    once by operator. Even it is found alright, if relay trip contacts are damaged, the breaker did

    not trip but relay flag indications will show.

    MOCB /OCB:

    When transformer oil is used in oil circuit breakers, the main function of the oil is to

    extinguish the arc which is formed between the contacts when an electric circuit is opened. In

    order to effectively quench the arc formed during operation, the oil must have proper

    characteristics so as to offer less resistance to the moving contacts and avoid the risk of fire.

    There by, for every 3 No earth faults, the oil shall be replaced with new oil.

    The arc consists of conducting ionized particles and is of low electrical

    resistance. Electrical stress and temperature are very high. Therefore oil is de ionize and

    quench the arc.

    Maintenance and operation of 33/11KV SUBSTATION Page 10

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    11/38

    Fig. Bulk oil circuit breaker

    Fig. minimum oil circuit breaker

    Maintenance and operation of 33/11KV SUBSTATION Page 11

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    12/38

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    13/38

    3) FEEDERS:

    A feeder is a conductor which converts the substation to the area where the power is

    to be distributed. Generally, no tapings are taken from the feeders so that the current in it

    remains the same throughout. The main consideration of a feeder is the current carrying

    capacity while the voltage drop consideration is relatively unimportant. It is because the

    voltage drop in a feeder can compensate by means of voltage regulating equipment at the

    substation. As a good voltage regulation of a distribution system is probably the most

    important factor responsible for delivering good service to the consumers, the design of

    feeder requires careful consideration.

    4) RELAYS:

    Function of Protective relays is to cause a prompt removal from service of any

    element of a power system when it suffers a short circuit or when it starts to operate in any

    abnormal manner that might cause damage or otherwise interface with the effective operation

    of the rest of the system. The relaying equipment is added in this task by circuit breakers that

    are capable of disconnecting the faulty element when they are called upon to do by the

    relaying equipment.5) INSTRUMENT TRANSFORMERS CTs & PTs 33KV, 11KV:

    CURRENT TRANSFORMERS:

    Current transformers shall be of the steroidal core type preferably encapsulated in epoxy

    resin. The current transformers shall contain no hygroscopic materials, which could affect the

    moisture contents of the SF6 gas in the CT chamber. The rated short-time thermal current

    shall not be less than the through fault capacity of the associated circuit breakers.

    The characteristics of current transformers shall be submitted to the Authority for approval

    together with details of the protection, instrumentation or measuring equipment with which

    each current transformer is to be used. Each current transformer shall be capable of providing

    the necessary output to operate the related devices satisfactorily at the lead burdens involved.

    Each current transformer shall have a continuous extended current rating of at least l.2 times

    the rated current. The characteristics and capacities of current transformers used for

    protection circuits shall be calculated by the relay manufacturer who shall prove by

    Maintenance and operation of 33/11KV SUBSTATION Page 13

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    14/38

    calculation, the suitability of the CT's being provided in conjunction with the relay

    manufacturers requirements for the relays and equipment offered. Where multi-ratio

    secondary windings are specified a label shall be provided at the secondary terminals of the

    current transformer indicating clearly the connections required for each ratio. These

    connections and the ratio in use shall also be shown on the diagram of connections. All

    connections from secondary windings shall be brought out and taken by means of separate

    insulated leads to a terminal blocks specially designed for the CT circuits, mounted in the

    Local Control Cubicle. The secondary windings shall be earthed at one point through a

    removable link, which shall be in the relay panels for protection and in the control panel for

    instrumentation. CT terminal blocks located in the local control cabinets shall have shorting/

    disconnecting links to allow testing with the circuit in service and on load. It shall be possible

    to carry out primary injection testing of the CTs including magnetizing curve testing, when

    the switchgear is fully assembled, or retesting of the CTs during the service life of the

    switchgear without interruption of supply to adjacent circuits. The secondary windings of

    each set of current transformers shall be capable of being open circuited for one minute with

    the primary winding carrying the rated current. Unless otherwise approved, all current

    transformers shall be installed with the P1 terminals adjacent to the bus bars. The polarity of

    the primary and secondary windings of each transformer shall be clearly indicated at the

    respective terminals and in addition labels shall be fitted in a readily accessible position to

    indicate the ratio, class and duty ofeachtransformer.

    Fig. 132kv current transformer

    Maintenance and operation of 33/11KV SUBSTATION Page 14

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    15/38

    VOLTAGE TRANSFORMERS:

    Voltage transformers shall be of electromagnetic type and of metal-enclosed design,

    which shall be compatible with the switchgear. They shall contain no hygroscopic insulating

    material, which could affect the moisture contents of the SF6 gas in the VT chamber. The bus

    voltage transformers shall be provided with motor operated disconnections for disconnecting

    the VT for maintenance, testing etc. Line voltage transformers shall be supplied with manual

    disconnections.

    The voltage transformers shall be capable of discharging the capacitance of line, cables and

    switchgear, which may remain connected to them during switching operations. The

    Contractor shall declare any limitations of the equipment for this duty. Voltage transformer

    secondary and tertiary circuits shall be provided with miniature circuit breakers or fuses asclose to each voltage transformer as possible and shall be labeled with winding and phase

    indication. For single-phase voltage transformers separate earth links for each secondary shall

    be provided and each neutral lead shall be connected together at a single earth point in the

    local control cubicle. Earthing of the VT HV winding shall be through a link separate from

    the LV winding. A fixed ladder or other arrangement shall be provided for each voltage

    transformer to enable an easy access to the voltage transformer and to the VT MCB/fuse box.

    The ratio and phase angle errors of voltage transformers shall not exceed the permissible

    limits prescribed in the relevant Standard and shall be capable of meeting the following

    additional requirements from 5% rated primary voltage to 90% rated primary voltage: Voltage

    error - not exceeding + 3% Phase angle error - not exceeding + l20 minutes. The voltage

    transformer shall have a voltage factor withstand rating of 1.2 continuous 1.9 times for 8

    hours without saturation. Voltage transformers shall be capable of carrying continuously

    without injurious heating 50% burden above their rated burden. Damping resistors shall be

    supplied for VT open delta windings.

    Maintenance and operation of 33/11KV SUBSTATION Page 15

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    16/38

    Fig. voltage transformer

    6) PLCC AND CONTROL PANEL:

    This is relevant in power line career communication (PLCC) systems for communicationamong various substations without dependence on the telecom company network. The signals

    are primarily tele protection signals and in addition, voice and data communication signals

    The line trap offers high impedance to the high frequency communication signals thus

    obstructs the flow of these signals into the substation bus bars. If there were not to be there,

    then signal loss is more and communication will be ineffective.

    The voice signals are converted/compressed into the 300 Hz to 400 Hz range, and this audio

    frequency is mixed with the career frequency. The career frequency is again filtered

    amplified and transmitted. The transmission of these HF career frequencies will be in the

    range of 0 to +32 db.These range is set according to the distance between stations.

    Maintenance and operation of 33/11KV SUBSTATION Page 16

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    17/38

    CONTROL PANEL:

    The relays and its alarms circuit are placed in control panel, which will be placed in the

    maintained building, the secondary of the CTs and pts will be brought to the panel through

    the underground cables.

    7) EARTHING:

    The first step in designing a substation is to design an earthing system. The function of

    an earthing system is to provide an earthing system connection to which transformer neutrals

    or earthing impedances may be connected in order to pass the maximum fault current. The

    earthing system also ensures that no thermal or mechanical damage occurs on the equipment

    within the substation, there by resulting in safety to operation and maintenance personnel. Italso improves reliability of power supply.

    The earthing is broadly divided as:

    SYSTEM EARTHING:

    Connection the part of plant in an operating system like LV neutral of the power

    transformer winding and earth.

    EQUIPMENT EARTHING:

    Connecting bodies of equipment like transformer tank, switch gear box, operating

    rods of air break switches, LV breaker body, hv breaker body, etc to earth.

    The system earthing and safety earthing are interconnected and therefore fault current

    flowing through system ground raises the potential of the safety ground and also cause step

    potential gradient in and around the substation but separating the two earthing systems have

    disadvantages like higher short circuit current, low current flows through relays and long

    distance to be converted to separate the two earths.

    After weighing the merits and demerits in each case the common practice of common and

    solid grounding system designed for effective earthing safe potential gradients is being

    adopted the earth resistance shell be as low as possible and shall not exceed the following

    limits.

    Maintenance and operation of 33/11KV SUBSTATION Page 17

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    18/38

    Power stations - 0.5 ohms

    EHT stations - 1.0 ohms

    33KV - 2.0 ohms

    Tower foot resistance - 10 ohms

    D/t structures - 5.0 ohms

    8) BUS BAR:

    A bus bar in electrical distribution refers to thick strips of copper or aluminum that

    conduct electricity within a switch board, distribution board, substation, or other electrical

    apparatus.

    The size of the bus bars is important in determining the maximum amount of current

    that can be safely carried. Bus bar can have a cross-sectional area of as little as 10mm2 but

    electrical substations may be use metal tubes of 50mm in diameter.

    At extra high voltages(more than 300KV) in outdoor buses, corona around the connections

    becomes a source of radio frequency inference and power loss, so connection fittings

    designed for these voltages are used.

    The most commonly used bus bar arrangements are:

    1) Single bus bar arrangement.2) Single bus bar with sectionalisation and

    3) Double bus bar arrangement.

    9) CAPACITOR BANK:

    Capacitors are used to control the level of the voltage supplied to the consumer by

    reducing or eliminating the voltage drop in the system caused by inductive reactive load.

    They supply fixed amount of reactive power to the system at the point where they are

    installed. Its effect is felt in the circuit from the location towards source only. It improves the

    power factor of the system and also decreases KVA loading on the source. The location has

    to be as near the load point as possible. In practice due to high compensation required it is

    found economical to prove group compensation on lines at substation.

    Maintenance and operation of 33/11KV SUBSTATION Page 18

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    19/38

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    20/38

    operating volatages, the impedance of lighting arrester, placed in parallel to the equipment to

    be protected,is very high and allow the equipment to per form its respective function.

    OPERATION AND MAINTAINANCE OF VARIOUS SUB-STATIONEQUIPMENTS:

    Regular inspections and preventive maintenance to be done on each of the above

    equipment are codified as Preventive Maintenance schedules fixing periodicity for each

    item. The main objective of the maintenance is to maintain the insulation in good condition

    and to avoid entry of moisture and to remove dirt.

    The sustained operating temperature of about 8 to 10 Degrees Centigrade more thanthe operating temperature of 75 Degrees Centigrade will shorten the life of

    transformer oil, circuit breaker etc. Hence, over loading should be avoided.

    As far as possible the temperature of oil and windings shall be maintained at 400 C

    and 450 C above ambient temperature.

    If the acidity of oil exceeds 1.0 mg. KOH/Gm of oil, the oil should be replaced with

    fresh oil.

    Dielectric strength for H.T. equipment (power transformer circuit breaker etc.) shall

    be 30 KV for 60 Sec. and 40 KV instantaneous.

    Earth resistance should not exceed 2 ohms for 33/11 KV sub-stations. Earth pits are

    to be wetted daily.

    Fencing should be checked and any missing barbed wire lacings should be replaced to

    keep away unauthorized persons or animals entering the sub-station yard.

    Grass and weeds growing in the SS yards must be cleared daily.

    Maintenance and operation of 33/11KV SUBSTATION Page 20

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    21/38

    ----I/P---> ---O/P--->

    BLOCK DIAGRAM OF 33/11 KV SUB STATION

    The general operation of sub- station is simple and easy to understand, a sub-station mainly

    involves Power transforms, circuit breakers, relays. Its main block diagram consists of circuit

    breakers , potential transforms, the power transformers and capacitor banks .The circuit

    breakers are given the supply directly from distributor systems then which is, fed to power

    transformers with a summation of potential transformers and Capacitance bank.

    The power transformers step up or step down based on requirement then they are again

    connected with potential transformers and capacitor bank then they are connected to circuit

    breakers , the entire arrangement of circuit breakers , potential transformers , capacitor

    banks is for the purpose of detecting the faults which occur transmission. Sub-stations play

    very important role in distribution hence are must be protected with much care. The circuit

    breakers are used to detect the faults onincoming as well as outgoing power, incase of any

    faults the circuit breakers trip s itself and thus protects power transformers from engaging

    with the fault currents.

    Maintenance and operation of 33/11KV SUBSTATION Page 21

    CIRCUIT

    BREAKERPOWER

    TRANSFORMER

    CIRCUIT

    BREAKER

    POTENTIAL

    TRANSFORMER

    CAPACITANCE

    BANK

    POTENTIAL

    TRANSFORMER

    CAPACITANCE

    BANK

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    22/38

    Power transformers at generating stations are used to Step up the voltage for transmission

    and at receiving stations to step down the voltage for primary and secondary distribution

    on. Transformers are generally installed up to lengths of rails fixed on concrete slabs

    having foundation of 1 to 1.5 m deep. The potential transformers are employed for voltage above 380V to fed the potential coils

    of indicating and metering instruments and relays. These transformers make the ordinary

    low voltage, instruments suitable for measurements of high voltage and isolate them from

    high voltage.

    The current transformers are connected in A.C power circuit to feed the current coil of

    indicating and metering instruments and protective relays. The primary is directly inserted

    in the power circuit and to the secondary windings, the indicating and metering

    instruments and protective relays, is connected. The standard secondary rating adopted

    are 5A or 1A. 1A rating is used for major sub-stations which remote controls.

    Vacuum circuit breakers are more popular at distribution voltage level up to 33KV

    voltage class. They require minimum maintenance except to replace the vacuum

    interrupter if a leak has occurred. The reasons being they have no fire risk and have high

    reliability with long maintenance free period. For these breakers the main contacts are

    housed within a vacuum in an insulating cylinder of glass or ceramic having metal end

    plates supporting the contacts.

    Maintenance and operation of 33/11KV SUBSTATION Page 22

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    23/38

    RECORD & REPORTS

    The following records and reports should be maintained so that the cause of the

    fluctuations in voltages and defects in daily operation can be thoroughly examined andrectified immediately.

    Some important records and reports are:

    1) HOURLY READING BOOK:

    All the hourly reading of voltmeters, ammeters, energy-meters, Etc. of all the Feeders

    and equipments are noted.

    This readings help for calculating M.D. and of the sub-station and it gives us the

    information about the extra load which it can take up.

    2) DAILY REPORT:

    Daily Report of the sub-station should be sent to the Engineer concerned, giving full

    information of operations carried out interruptions caused to the feeders during the day.

    Load particulars of all the feeders, giving peak load, minimum load, and average loads of

    each feeder.

    Maintenance and operation of 33/11KV SUBSTATION Page 23

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    24/38

    SOME OF THE OPERATING INSTRUCTIONS:

    1) A.B. switches are meant for operating on no load.

    2) When workmen are on work spot the line or equipment on which they are working, itshould be first discharges and earthed property

    3) Transformers having different KVA ratings may operate in parallel.

    The conditions to satisfy for successful parallel operations of the transformer are as follows:

    a) They should belong to some vector groundb) Transformers should have the same voltage ratio

    c) The percentage impendence of the transformers should be equal when each percentage is

    expressed on the KVA base of its respective transformer.

    d) It is also necessary that the ratio of resistance in the transformers should be equal

    Maintenance and operation of 33/11KV SUBSTATION Page 24

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    25/38

    MAINTENANCE SCHEDULES FOR POWER TRANSFORMERS:

    1. Checking the Colour of silica gel in the breather and also oil

    level of the oil seal. If silica gel Colour changes from blue to

    pink by 50% the silica gel is to be reconditioned or replaced .

    Daily

    2. Observation of oil levels in (a) main conservator tank (b) OLTC

    conservator (c) bushings and examining for oil leaks if any from

    the transformer

    Daily

    3. Visual check for overheating if any at terminal connections (Red

    hot) and observation for any unusual internal noises.

    Daily in each shift

    4. Checking for noise, vibration or any abnormality in cooling fans

    & oil pumps of power transformers standby pumps & fans are

    also to be run condition to be observed.

    Daily

    5. Observation of oil & winding temperatures & recording Hourly

    6. Visual check of explosion vent diaphragm for any cracks Daily7. Checking for any water leakage into cooler in case of forced

    cooling system.

    Daily

    8. Physical examination of diaphragm of vent pipe for any cracks Monthly

    9. Cleaning of bushings, inspect for any cracks or chippings of the

    porcelain and checking of tightness of clamps and jumpers

    Monthly

    10. Measurement of IR values of transformer with 2.5 KV meager

    up to 33KV rating and 5.0 KV meager above 33KV rating.

    Recording of the values specifying the temperature which

    measurements are taken.

    Monthly

    11. Cleaning of Silica gel breather Monthly

    12. Checking of temperature alarms by shorting contacts byoperating the knob.

    Monthly

    13. Testing of main tank oil for BDV and moisture content Quarterly

    14. Testing OLTC oil for BDV & moisture content Quarterly

    15. Testing of Buchholz surge relays & low oil level trips for correct

    operation

    Quarterly

    16. Checking auto start of cooling fans and pumps Quarterly

    17. Checking of Buchholz relay for any gas collection and testing

    the gas collected

    Quarterly or during

    fault

    18. Checking of operation of Buchholz relay by air injection

    ensuring actuation alarm & trip

    Half yearly or

    during shutdown19. Noting the oil level in the inspection glass of Buchholz relay and

    arresting of oil leakages if any.

    Monthly

    20. Checking of all connections on the transformer for tightness

    such as bushings, tank earth connection

    Quarterly

    21. Lubricating / Greasing all moving parts of OLTC mechanism Quarterly or as

    given in the

    manufacturers

    manual

    22. Checking of control circuitry, interlocks of oil pumps and

    cooling fans for auto start and stop operation at correct

    Maintenance and operation of 33/11KV SUBSTATION Page 25

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    26/38

    temperatures and also for manual operation

    23. Testing of motors, pumps and calibrating pressure gauge Half yearly

    24. Pressure testing of oil coolers Half yearly

    25. Testing of oil samples for dissolved gas analysis (for 100MVA

    transformers)

    Half yearly

    26 Testing of oil for dissolved gas analysis of EHV transformers upto 100KVA capacity

    Once in a year

    27. Overhauling of oil pumps and their motors also cooling fans &

    their motors.

    Once in a year

    28. Testing of oil in main tank for acidity, tan delta, interface tension

    specific resistively

    Once in a year

    29. Bushing testing for tan delta Once in a year

    30. Calibration of oil & winding temperature indicators Repeats

    31. Measurement of magnetizing current at normal tap and extreme

    taps

    One in a year

    32. Measurement of DC winding resistance Once in a year 33. Turns ratio test at all taps Once in a year

    34. Inspection of OLTC mechanism and contacts its diverter switch Once in a year or

    number of

    operation as

    recommended by

    manufacturers are

    completed

    whichever is earlier.

    35. Overhaul of tap changer and mechanism One in a year

    36. Replacement of oil in OLTC Once in year or

    whenever numbersof operations as

    recommended by

    manufacturer are

    completed

    whichever is earlier.

    37. Calibration of thermometers (temperature indicators) and tap

    position indicator.

    Yearly

    38. Remaining old oil in thermometer pockets, cleaning the pockets

    and filing with new oil.

    Yearly

    39. Checking oil in the air cell (for transformers of 100 MVA &

    above capacity)

    Yearly

    40. Bushings partial discharge test and capacitance (EHV

    transformers)

    Yearly

    41 Filtration of oil / replacement of oil and filtration Whenever the IR

    values of

    transformer are

    below permissible

    limits and oil test

    results require

    filtration /

    Maintenance and operation of 33/11KV SUBSTATION Page 26

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    27/38

    replacement of oil

    42. General overhaul (consisting 1) Inspection of core & winding (2)

    Through washing of windings (3) Core tightening (4) Check-up

    of core bolt insulation (5) Replacement of gaskets (6) Overhaul

    of OLTC

    One in 10 years

    MAINTENANCE SCHEDULE FOR BATTERIES:

    S. No. ITEM OF MAINTENANCE PERIODICITY

    1. Taking specific gravity and voltage of pilot cells. Daily.2. Checking specific gravity and voltage of each cell

    a) Lead-acid cell.

    b) Nife cells.

    (Before and after charging.

    Weekly when trickle charge

    exists)

    Monthly.

    3. Cleaning of terminals applying Vaseline and topping up

    with distilled water.

    Weekly for Lead-acid batteries.

    4. Over-haul of Nife Battery recommended by manufacturers. Yearly.

    5. Leakage test by lamp or voltmeter method Each shift

    6. Checking all connections of charger and battery for

    lightness

    Quarterly

    EARTHING:

    Maintenance schedule of station earths includes transformer, and lightening arrestors earths.

    S. No. ITEM OF MAINTENANCE PERIODICITY

    1. Combined earth resistance Monthly

    2. Checking earth connection at joints Monthly

    3. Watering of sub-station earth Daily

    4. Water distribution transformer earth Twice a week (Earth)

    RECOMMENEND MAINTAINENCE SHEDULE FOR CERTAIN IMPORTANT

    FACTORS:

    S. No. INSPECTION

    FREQUENTLY

    ITEMS TO BE

    INSPECTED

    INSPECTION

    NOTE

    ACTION REQUIRED IF

    INSPECTION SHOWS

    UNSATISFACTORY

    CONDITIONS

    1. Hourly Ambient temp.

    2. Hourly Winding temp. Check that temp.

    rise is reasonable

    Shut down the Transformers and

    investigate if temp. is persistently

    higher than normal.

    Maintenance and operation of 33/11KV SUBSTATION Page 27

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    28/38

    3. Hourly Oil temp.

    4. Hourly Load (amperes) Check against

    rated figure

    Note: An improper tap position

    can cause Transformers failure.

    5. Hourly Voltage

    6. Daily Oil level in

    Transformer

    Check against oil

    gauge

    If low, examine the Transformers

    for leak.7. Daily Relief vent

    diaphragm

    Replace if cracked or broken

    8. Daily Dehydrating

    Breather

    Check colour of

    the active agent

    If silica gel is pink, change it with

    new one

    9. Quarterly Bushing Examine for crack

    and dirt deposits

    Clean or replace

    10. Quarterly Oil in

    Transformers

    Check the electric

    strength and water

    content (B.D.V ,

    P.P.M)

    Take suitable action to restore

    quality of oil

    11. Quarterly Dehydrating

    breather

    Check oil level in

    oil cap and that airpassages are free.

    Make up oil , required

    12. Yearly or earlier

    if Transformer

    can conveniently

    be taken out for

    checking

    Oil in

    Transformers

    Check for acidity

    and sludge

    Filter or replace

    13. Yearly or earlier

    if Transformer

    can conveniently

    be taken out for

    checking

    Insulation

    resistance

    Compare with

    value at time of

    commissioning

    Filter or replace

    14. Yearly or earlier

    if Transformer

    can conveniently

    be taken out for

    checking

    Gasket joints Tighten the bolts evenly to avoid

    uneven press.

    15. Yearly or earlier

    if Transformer

    can conveniently

    be taken out for

    checking

    Relays , alarms ,

    their circuit etc.

    Examine relay and

    alarm contacts and

    their operations,

    fuses etc. check

    relay accuracy etc.

    Clean the components or replace

    contacts and fuses if necessary.

    Change the setting if necessary.

    16. Yearly or earlier

    if Transformer

    can conveniently

    be taken out for

    checking

    Temperature

    indicator ; WTI,

    OTI

    Pockets holding

    the thermo meter

    should be checked.

    Oil to be replenished if required

    17. Yearly or earlier

    if Transformer

    can conveniently

    be taken out for

    checking

    Dial type Oil

    gauge

    Check pointer for

    freedom

    Adjust if required

    18. Yearly or earlier

    if Transformer

    Earth resistance Take suitable action, if resistance

    is high.

    Maintenance and operation of 33/11KV SUBSTATION Page 28

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    29/38

    can conveniently

    be taken out for

    checking

    19. Two- yearly Oil conservator Internal inspection Should be thoroughly cleaned

    20 Two yearly Buchholz relay Mechanicalinspection Adjust floats, switches etc asrequired.

    COMMON DEFECTS NOTICED AND THE CAUSE

    S. No PARTS DEFECTS CAUSES

    1. Tank a. Leakage of oil

    b. Deformation

    c. Overheating

    Corrosion / mechanical damageGaskets worn out

    excessive internal pressureImproper circulation of

    cooling oil and / or inadequate ventilation.

    2. Radiators a. Leakage of Oil

    b. Deformation

    c. Overheating

    Corrosion / mechanical damageGaskets worn out

    excessive internal pressureImproper circulation of

    cooling oil and / or inadequate ventilation.

    3. Conservator a. Leakage of Oil

    b. Deformation

    c. Overheating

    Corrosion / mechanical damageGaskets worn out

    excessive internal pressureImproper circulation of

    cooling oil and / or inadequate ventilation.

    4. Breather Ineffective Inlet choked Silica gel saturated

    5. Explosion Glass broken Mechanical

    6. Core a. Loose

    b. Increased Losses

    c. Excess Noise

    Bolts loosening up change in characteristics due to

    heating vibration of stampings

    7. Winding a. Short Circuited

    b. Loosening

    c. Insulation Brittle

    d. Open circuited

    Overloading Air bubbles loss of insulation

    shrinkage displacement Overheating decomposition

    burn out.

    8. Oil a. Discoloration

    b. High Acidity

    c. Low BDV

    d. Sludge

    Contamination Increased moisture

    Decomposition chemical action with other parts.

    9. Terminal

    Bushing

    a. Breakage

    b. Leakage of Oil

    Strain Gasket Worn out Loose fit.

    10 Tap Switch a. Inoperative

    Broken leverb. Burnt Contact

    c. Short Circuit

    Mal operation Insulation failure Failure of

    operation mechanism overheating

    Maintenance and operation of 33/11KV SUBSTATION Page 29

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    30/38

    Types of faults against which Buchholz relays gives successful protection:

    Visible or Audible Alarm (Upper Float

    Actuates)

    Trip Circuit Operates (Lower Float Actuates)

    1. Core bolt insulation failure 1. Short circuit between phases

    2. Short circuited core laminations 2. Winding earn fault3. Bad electrical contacts 3. Winding short circuits

    4. Local overheating 4. Puncture of busing

    5. Loss of oil due to leakage

    6. Ingress of air into the oil system

    CONDITIONS FOR THE PARALLEL OPERATION OF TRANSFORMERS:

    The conditions that must be observed for the parallel operation to transformers bothprimary and secondary side.

    1. Same voltage ratio.

    2. Same polarity.

    3. Same phase sequence and

    4. Zero relative phase displacement.

    Maintenance and operation of 33/11KV SUBSTATION Page 30

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    31/38

    A L A R M S

    S. No ALARMS ACTION TO FOLLOW

    1. Oil temperature Alarm

    for a transformer

    Cancel the alarm and feel temperature by touching

    transformer body and verify winding temperature also and

    compare with the other transformer. If no-abnormality is

    observed. It is a false alarm. Inform AE & ADE. If

    excess temperature is observed cut-off few loads and

    inform AE & ADE & ECR.

    2 Winding Temperature

    Alarm for a transformer

    - DO -

    3 Buchholz Alarm Cancel the Alarm and isolate if both from HV and L.V.

    side. Restrict the loads to the available capacity. Inform

    AE, ADE, ECR & MRT.

    4 Buchholz TRIP Cancel the Alarm and disconnect the leads connecting to

    trip and isolate the transformer. Restrict loads to available

    capacity.

    5 Neutral displacement

    relay of capacitor bank

    Cancel alarm, isolate the bank and inform to ADE, MRT.

    6 Any feeder breaker Cancel the alarm and follow for operating instruction.

    Maintenance and operation of 33/11KV SUBSTATION Page 31

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    32/38

    STATION BATTERIES

    PRINCIPLE OF CHARGING AND IDENTIFICATIONS:

    TYPE OF BATTERY USED: LEAD ACID BATTERIES

    The A.C. 3 phase 11KV supply volts which are stepped down by the STATION

    TRANSFORM to 3 phase 440V supply with a neutral. A single phase 230 volts which is

    available from 3 phase with a neutral is sufficient for the station batteries to get charged. A

    RECTIFIER UNIT is used to convert the A.C. current to unidirectional current. The output of

    the rectifier is directly given to the batteries for charging.

    When the cells are full charged, the voltage ceases to raise the co lour of plates; on

    full charge is deep chocolate brown for positive plate and grey for negative plate. The

    approximate value of the E.M.F. is 2.1V. During charge in the density of electrolyte increases

    due to absorption of water or the Electrolyte assumes a milky appearance the specific gravity

    can be measured with a suitable Hydrometer.

    NUMBER OF END CELLS:

    When the battery is fully charged with each having an emf of 2.1 V, then the number of

    cells required is volts/2.1 =110 cells.

    TRICKLE CHARGING:

    It is essential that the batteries should be fully charged and ready foe service when an

    emergency rises. To keep it fresh, the battery is kept on a trickle charge. The rate of trickle

    charge is small and is just sufficient to balance the open circuit losses. It keeps the sells fully

    charges with out any passing in good conditions.

    Maintenance and operation of 33/11KV SUBSTATION Page 32

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    33/38

    MAINTENANCE OF STATION BATTERIES:

    1) The level of the electrolyte should be 10 to 15mm above the top of the plates and mustnot be exposed to air.

    2) The battery terminals and metal and supports should be cleaned down to bars metal and

    covered with Vaseline or petroleum jelly.

    3) The acid and the corrosion on the battery top should be washed off with a cloth moistened

    with baking soda or ammonia and water.

    4) It must be taken care that the batteries should not be left in discharged condition for long.

    Since acid does not vaporize, none should be added

    Maintenance and operation of 33/11KV SUBSTATION Page 33

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    34/38

    SAFETY MEASURES

    SAFETY MEASURES FOR SUB-STATIONS:

    1) Lifting of should be made by lugs or jacks wheels, never by cooling tubes.

    2) Transportation of transformer should be on large diameter wheels unless strength and

    acidity.

    3) Transformer oil should be tapped periodically for checking of dielectric strength and

    acidity.

    4) Co lour of breather needs daily watch.

    5) For proper rating, instrument fuses should be checked.

    6) No cotton waste would be used to clean the dirty/dust.

    7) At every shift D.C. supply may be checked. It is essential for safety.

    8) Maintenance registers of sub-station should be studied thoroughly to gain lot of future

    warnings.

    9) In order to reduce fire troubles, cable trenches must be fill with sand.

    10) Insulators should not be able to work while O.C.B. is closed and so interlocking system

    should be checked.

    11) No new comers should be allowed to switch gear. Visitors should have authorized person

    of sub-station.

    12) Do not take chance without safety measures.

    Maintenance and operation of 33/11KV SUBSTATION Page 34

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    35/38

    PRECAUTIONS AGAINST FIRE IN TRANSFORMER:

    1) Transformers should be installed at a reasonable place from inflammable material.2) For out-door sub-stations.

    a) Provided with drainage.

    b) Stone chippings are filled around the plinth area.

    3) For in-door sub-station

    a) Stop the spreading of oil.

    b) The floor should be non-flammable.

    c) The main space between the transformer and walls should be one meter.

    4) Fix fighting equipment should be installed.

    5) Emergency relief pipe should point in a safe direction. In case of fault condition, burning

    oil may be ejected from it.

    PRECAUTIONS AGAINST SHOCK:

    1) All parts of the metal tank should be effectively bonded together and properly earthed.

    2) The transformer should be fully protected with cable boxes, terminals boxes so that live

    metal parts are totally enclosed.

    3) When the transformer is energized an enclosure to the transformer with a door or gate

    which our be kept locked, should be provided.

    4) Precautions should be taken against exposed metal ends of bushings.

    Maintenance and operation of 33/11KV SUBSTATION Page 35

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    36/38

    CASE STUDY

    At a 33/11kv substation we find many number of equipments involved in it starting from the

    input to the output feeders. A 33kv from jubilee hills provided at the input feeder and with the

    help of AB switches the direction of the flow is changed depending up on the requirements.

    At first the 33kv input is given to the LV side of the first transformer of 12MVA and only up

    to 800MW it is used. We are provided with the group circuit breakers (GCB) where the

    charging takes places after that only the transformer will be oned. Another transformer with

    33kv is provided on the HV side then it gets step down to 11kv on LV side. From the LV side

    we have four individual feeders they are city City centre, Rainbow, Tata rao & Erramanzil.

    From these four feeders the supply to the required area can be given through transmission

    system. The GCBS provided will have energy meters as well as relays which operate at the

    time of faults.

    Sample readings of energy meter:

    Daily reading:

    Feeder1(MWH) Feeder2(KWH) Feeder3(KWH)

    9955.49 1810157 2199307

    9961.88 1811468 2200286

    9968.12 1812709 2201234

    Monthly reading:

    Feeder1(MWH) Feeder2(KWH) Feeder3(KWH)

    435620 668040 936140

    Maintenance and operation of 33/11KV SUBSTATION Page 36

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    37/38

    CONCLUSION

    With the high demand of power, it has become necessary to have high voltage

    distribution thus casing construction of high voltage sub-station like 66 KV, 132 KV, and 200

    KV and so on. For operating the high voltages, the need for reliable protective devices and

    switch gear has become paramount important. When short circuit occurs, an enormous power

    can be fed into the fault with considerable damage and interruption of service.

    As it is equipped with many protection circuit breakers for the protection of various

    buses or lines from faults, even if the faults remains for a moment then, due to high current

    all the equipments connected to the line would damage. At the same time identifying and

    isolating the faults is important which is done by various relays and circuit breakers in the

    substation. If the fault is not cleared then the faulty line is isolated by using the bus couplers

    in substation.

    Thus maintenance and operation of substation is very important and it will represent the

    healthy network.

    Maintenance and operation of 33/11KV SUBSTATION Page 37

  • 8/3/2019 Theory_(1 - 6)_without Numbers

    38/38

    REFERENCE

    1. Technical reference book of substation (aptransco).

    2. www.whitepapers.com3. www.technologyreview.com

    4. www.onlinetaken.com.

    5. Wikipedia (Google search).

    http://www.whitepapers.com/http://www.technologyreview.com/http://www.onlinetaken.com/http://www.whitepapers.com/http://www.technologyreview.com/http://www.onlinetaken.com/