this program has been made possible by the new south … … · this program has been made possible...
TRANSCRIPT
This program has been made possible by the New South Wales Government through the EPAs Contaminated Land Management Program under funding provided by the NSW Environmental Trust
• SEPP55 introduced in 1998 to ensure planning decisions take into account possible land contamination
• Promotes remediation to reduce harm by: • Specifying when consent for
remediation is and isn’t required
• Specifying assessment considerations relevant to rezoning, to DA’s in general and DA’s for remediation
• Requiring remediation work to meet certain standards and notification requirements
Planning Function Decisions to be made
Rezoning of land Is the land suitable or can it be made
suitable for the rezoned use?
Processing and determining a
development application
Is the land suitable, or can it and will it
be made suitable, for the proposed
development?
Modifying a development consent
Will the land be suitable for the
proposed use under the modified
consent?
Published in 1998 they support the SEPP
and address:
• The policy framework
• Identification and investigation of contamination
• The decision making process
• Management of contaminated sites and remediation
• Information management
• Principles for proactively preventing future contamination
• Changes to Part 3 of the EP&A Act and CLM Act mean that
the Planning Guidelines are now dated and do not fully
reflect SEPP 55 as currently amended nor the EP&A Act
• Changes arising from consultation (2008) and from further
proposed changes (2012) have been delayed, but a review
is currently underway by DoP as part of broader review of
SEPP’s
• The general principles in the 1998 guidelines still remain
largely valid, although some `translation’ of the terms and
concepts is required
• Clause 6 of SEPP55 refers specifically to the preparation of Environmental Planning Instruments
• Subsequent changes to Part 3 of the EP&A Act have simplified the plan making process
– Councils are now responsible for preparing and submitting planning proposals to the Minister for consideration
– Preparation of a draft LEP is no longer required
• As a result the status of Clause 6 is unclear
• Nevertheless it is considered prudent to consider possible contamination when preparing planning proposals for rezoning – particularly if the proposal could increase risk exposure
• Proponents are responsible for investigating contamination
issues on land that they propose to use and demonstrating
to the planning authority that planning approval should be
granted.
• The planning authority must evaluate the information it
already has and the information provided before making a
decision.
• The planning authority should seek further information if
the information available is insufficient.
• Planning decisions and factual information must be
recorded for future use.
The Planning Guidelines identify:
• `it is strongly recommended that council develop and adopt a formal policy for managing land contamination to provide a context for decision making’
• While `council’s policy on Contaminated Land may be contained within a number of documents, such as planning instruments that contain land use restrictions relevant to contamination and a DCP or plans……it is advisable to have a formal `stand alone’ policy document’
• `Restrictions on land use due to contamination will only apply to certain land and council’s policy needs to state the circumstances in which this applies’
• First step in evaluating whether
contamination will affect a
proposed change in land use
• Historic and current land uses of
the site and adjacent sites need to
be considered as an indicator of
potential contamination
• Table 1 of the Guidelines identify
potentially contaminating activities
• If there is no reason to suspect
contamination the proposal can
proceed in the usual way
Previous investigations and results
Existing EMP or monitoring in place
Records indicate a previous potentially contaminating activity (Table 1)
Is there a potentially contaminating activity underway
Has site previously been zoned industrial, agricultural or defence purposes?
Was, or is the land regulated through licensing or other mechanism related
to a potentially contaminating activity
Land use restrictions (e.g. orders or notices issued under CLM Act)?
Site inspection indicates likelihood of past or present activities
Any information regarding contamination of adjacent land
Ambient background levels of substances presenting a risk of harm to
human health or the environment
Further information may be
needed if initial evaluation finds:
• Contamination is suspected due
to known past uses
• Land has been remediated but
validation information is unclear
• A sensitive land use is proposed
(e.g. residential, educational,
recreational, hospital or
childcare)
The appropriate level of investigation will depend on the
circumstances and may involve one or more of the
following stages:
1. Preliminary Investigation
2. Detailed Investigation
3. Remedial Action Plan
4. Validation and Monitoring
• Should be carried out where the `initial evaluation’
indicates there may be contamination, and where
proposed land use change has potential to increase risk of
exposure to contamination
• Aims to identify any past or present potentially
contaminating activities
• Provides a preliminary assessment of any site
contamination
• If required, provides a basis for more detailed investigation
• Is only necessary when the Preliminary Investigation indicates that the land is contaminated
• Objectives:
– To define the nature, extent and degree of contamination
– Assess potential risk posed by contaminants to health and the environment
– Obtain sufficient information to develop a remedial Action Plan (RAP) if required
• Needs to be undertaken as part of a remediation proposal
• If it is already known that the land is contaminated then the Preliminary and Detailed Investigations can occur concurrently
• Sets objectives and documents
the process to remediate the
site after the nature, extent
and degree of contamination
have been fully delineated
• The need for an Environmental
Monitoring Plan should also be
considered at this stage
• Purpose is to demonstrate
whether the objectives stated
in the Remedial Action Plan
and any conditions of
development consent have
been achieved
• SEPP55 requires a notice of
completion for all remediation
work, of which validation is an
important prerequisite
• A planning authority should, as far as possible, conduct
the appropriate evaluation internally
• It may be necessary for an independent expert to assist in
the evaluation
• The expert chosen should be appropriately qualified and
experienced to deal with the type of land contamination
in question and be independent of both the proponent
and the proponent’s consultant.
• SEPP 55 does not require a site audit at any stage of the
planning process for remediation work
• An independent review is only necessary when the
planning authority:
– believes on reasonable grounds that the information
provided by the proponent is incorrect or incomplete
– wishes to verify that the information provided by the
proponent adheres to appropriate standards, procedures
and guidelines
– does not have the internal resources to conduct its own
technical review.
• Are PCAs appointed for building work or subdivision work able to “sign off” on site audit reports?
• They are not
– Clause 161 of the EP&A Regulation lists matters for which it is appropriate for a PCA to “sign off”
– It does not apply to a site audit completed under the CLM Act or to the section of the EPA Site Auditor Guidelines dealing with Site Audit Statements
• A PCA is therefore not considered to be a `relevant authority’ under the Site Auditor guidelines
• A planning authority should not delegate its role in considering site audit statements.
• While remediation is desirable it can also cause impacts
• SEPP 55 provides consistent state wide planning and
development controls for the remediation of contaminated
land
– Category 1 – requires consent as has potential for significant
environmental impacts
– Category 2 - can proceed without consent but notice must be
provided to Council
Areas to be covered include:
• Health and safety
• Air-quality
• Water quality
• Erosion and sediment control
• Noise and waste
• Landscaping and rehabilitation
• Consultants
• Validation
• Performance bonds (as required)
• Ongoing monitoring
Key Principles • Maintain efficient property information systems to ensure
records are accurate and up-to-date.
• Section 149(2) planning certificates are an appropriate system of legal notification re the application of council policies which place restrictions on land use due to contamination risks
• Information relating to past land use and other matters relevant to contamination may also be provided, even when land use is not restricted – possibly through s. 149(5) certificates
• When land has been investigated and is considered suitable for a proposed land use change, this information must be retained in council records
• While dated the principles of the 1998 Guidelines remain valid
• Importance of a policy framework
• No planning decision should be made unless sufficient information is available for an appropriate evaluation
• A DA should only proceed if: – the land is/or can be made suitable for the intended use, or
– conditions are attached to the development consent to ensure that the subject land will be remediated to a level appropriate to its intended use prior to, or during, the development stage
• A planning authority should not delegate its role in considering site audit statements.
• Information management systems are very important