tilt-up construction guest speaker: karen s. hand, p.e

61
TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E.

Upload: vivian-billow

Post on 31-Mar-2015

221 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

TILT-UP CONSTRUCTION

GUEST SPEAKER:KAREN S. HAND, P.E.

Page 2: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

IntroductionKaren S. Hand, P.E.

BSCE – University of Missouri-RollaMay 1993

Needham & Associates, Inc.Consulting EngineersMay 1998-Present

TCA - Charter Member2004 Achievement Award Winner for Innovation

Page 3: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Topics

• Panelizing the Building

• Connections

• Architectural Considerations

Page 4: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Project Procurement

• Clients can be Architect, Engineer of Record, Subcontractor, General Contractor

• Design Build Specialty Engineer

• Engineer of Record with Additional Scope

Page 5: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Tackling the Project

• PLANNING!!!!!!– With the Architect

• PLANNING!!!!!!– With the Engineer of Record

• PLANNING!!!!!!– With the Contractor

Page 6: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Preliminary Design

• Know what your constraints are..Not the typical “design” issues…Think beyond the paper…know what assumptions have been made in the proposal by the contractor.– Limited Site– Crane Size– Weather

Page 7: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Planning

• Decide the approach

• Are there any unique issues to consider?

Page 8: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Panelizing the Building

• One of the most important steps in Design

• What is panelizing?– Determining how the walls are divided into

panels, what their shapes are and where the joints between them occur

Page 9: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Panelizing the Building

• Coordinate with Architect and Steel Framing Engineer and Contractor

• Goal for Panel Sizes:– Maximum Panel Size– Minimize Panel Joints

Page 10: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Panelizing the Building

• Factors to Consider– Crane Capacity and Reach– Steel Framing Layout and Bearing Locations –

Typical Embedment Pattern– Opening Locations – Adequate Jambs, Lintel

Panels, Vertically Stack Openings– Locate Girders at Center of Panel or at Joint– Footing Step Locations

Page 11: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Panelizing the Building

• Takes the same time to lift and set a large panel as a small panel. Take Advantage.

• Efficient Panel Layout Effects the Cost of the entire project and should be considered one of the most important issues to coordinate.– Cost in Formwork– Cost in Embeds/Connections

Page 12: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Planning the Connections

• Base Connections

• Corner Connections

• Roof Framing Connections

• Miscellaneous Connections

Page 13: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Types of Connections

• Welded Embedded Metal– Most Common

• Embedded Inserts– Allows for Bolted Connection– Eliminates Field Welding– Accuracy in Locating

• Drilled In Anchors– Post installed

• Cast-In-Place Concrete– At Slabs

Page 14: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Base Connections

• What type of foundation system is being used? – Continuous Footing

• Reinforced Top and Bottom layer

• Centered Under Panel

– Spread Footing• Panel Spans Corner to Corner

• Allow for Expansion and Contraction

Page 15: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Base Connections

• Diagonal Shrinkage cracks in the corners due to restraint of bearing pads– Grout under the panels as soon as possible– Shim Packs or Grout Pads should be located ¼

from the end of the panel

Page 16: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Base Connections

• Friction – Old Days

• Pourback Strips and Slab Dowels

• Embedded Plates or Angles– To Slab Option– To Footing Option

• Free Standing Walls

• Spandrel/Grade Beam Type

Page 17: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Pourback Strips and Slab Dowels

• Slab is poured short of the panel location with a “closure strip” of about 3’-0”.

• Dowels are “wet set” into the panel at the correct elevation to meet the center of the floor slab.

• Backfill and insert rebar between slab dowel and panel dowel.

• Closure strip is poured to finish off the slab.

Page 18: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Pourback Strip At Dock Wall

Page 19: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Pourback Strips and Slab Dowels

• Problems with the procedure– “Wet setting” the dowels is cumbersome

• Accurate placement

• Finishing

• Variations of Detail

– Backfilling becomes a safety concern• Braces are still attached

• Access is a problem

Page 20: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Backfilling

• ACI 551 Section 4.10.2– Prior to backfilling, place a strip of felt over the

joint between adjacent panels below grade and pack with plastic roof cement. This prevents dirt, mud or water from leaking through the joint in the panels

Page 21: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Embedded Base Connections

• Allows for the slab to be poured to inside face of where tilt-up panel will go

• Eliminates Backfilling on Inside of Bldg

• Connections can me made immediately

Page 22: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Embedded Base Connections

• To Slab– Angle Embedded in the Slab, Plate Embedded in the

Panel - Welded– Consider Expansion/Contraction in Slab and Panel

• To Footing– Angle Embedded at Base of Panel– Second Angle is welded to Embed and Bolted to Ftg– Consider Additional Unbraced Length for Panel Design– Consider Corrosion– Consider Expansion/Contraction

Page 23: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Dock High Walls

• Connection at Slab and at Footing

• Slab Connection– Resists Lateral Load– Reduces Unbraced Length for Compression

• Footing Connection– Resists Lateral Soil Pressure behind Panel

• Advantage - Base Fixity for Panel Design

Page 24: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Panel to Panel Connections

• Are they needed?

• Not typical for tilt up

• Common in Precast

• Larger Panels and Wider Panels

Page 25: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Panel to Panel Connections

• Tie panels together for Overturning Forces– Re-entrant Corners with Drag Strut Forces

• Laterally stabilize two adjacent panels– Use a Butterfly Connection

• Expansion and Contraction– Do not restrain any more movement with the

connection than structurally required.

Page 26: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Corner Connections

• Thermal Bowing

• Caulked Joints can fail prematurely – Not a structural performance issue

• Expansion and Contraction– Do not restrain any more movement with the

connection than structurally required.

Page 27: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Roof Framing Connections

• Diaphragm – Chord Connections – Continuous Angle also acts as Deck Bearing Angle

• Drag Strut Connections• Joist Bearing Connections

– Embedded Plate and Bearing Angle– Joist Pocket

• Girder Bearing Connections– Embedded Plate and Angle/Plate– Beam Pocket

Page 28: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Ledger Connection

• Diaphragm Chord – Shear Forces• Deck Bearing – Gravity Forces• Lateral Restraint – Tension Forces• Continuous Angle• Different Thermal Coefficient of Expansion• Rigid Connection for Shear at Center of Panel• Sliding Connection for Gravity and Tension

Forces

Page 29: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Typical Ledger Connection

Page 30: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Typical Joist Connection

Page 31: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Typical Girder Connection

Page 32: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Other Connections

• Mezzanine Connections– Smaller Joist Spacing– Resist Temptation to use a Continuous Angle

Welded at each Joist

• Spandrels

Page 33: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Expansion/Contraction

• Did I mention Expansion/Contraction is the most important thing to remember when designing connections?

• Expansion/Contraction is the most important thing to remember when designing connections.

• Let the panels “breathe”

Page 34: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Design Panels

• Once connections have been planned you can design the panels for the constraints you have provided.– Eccentric Loads due to Bearing Connections– Unbraced Length for Panel Buckling– Base Fixity

Page 35: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Reinforcing Schedules

• Once Panels have been designed, you will indicate the required reinforcing on the structural drawings.

Page 36: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Reinforcing

• Design Note regarding Reinforcing:– ACI 318 Section 14.3.5 allows bar spacing up to 18

inches.

– Best practice is to use smaller bars not to exceed 15 inches o.c.

– When using a double mat of steel, you could stagger the mats to reduce the effective spacing if stretching to 18” but this requires additional chairs to support the upper and lower mat independently. Check with Contractor for cost impact.

Page 37: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Engineering Documents

• Need to Transmit, with completeness and clarity, the general and specific requirements for tilt up panels.

• Key Plan – Locate panels and indicate designation

• Elevations– Each panel uniquely numbered– Drawn from inside of building looking out– Panel Dimensions and connection detail references– Joint sizes

Page 38: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Engineering Documents

• Connection Details– Anchor sizes required– Embed Plate sizes and stud spacing

• Reinforcement Details– Typical rebar placement– Clear coverages– Special Tie Configurations– Pilaster reinforcement if required

• Specifications• Shop Drawings – Panel Layout

Page 39: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Detailing the Panels

• Biggest Source of Field Problems are results of inadequate checking and correlating between Architectural and Structural drawings.

• Design Engineer typically isn’t too concerned about getting all the architectural features coordinated.

Page 40: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Panel Layout• Panel Identification• Locate and Identify Embedded

Items• Locate Openings• Location of any recesses or

reveals with details• Locate Architectural Finishes• Pull all dimensions from upper

left corner

Page 41: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E
Page 42: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Communication

• Communication with the Architect is vital to the success of the project

• Communication with the Engineer is vital to the success of the project

• Communication with the Contractor is vital to the success of the project

Page 43: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Architectural Considerations

• Accent Panels

• Applied Treatment

• Surface Treatment– Reveals (Rustication)– Protrusions

Page 44: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Reveals (Rustication)

Most basic Architectural influence

Page 45: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Architectural

• Sandblasting

• Exposed Aggregate

• Painting

• Applied

Page 46: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Surface TreatmentsFormliners with Brick or CMU Pattern

Page 47: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Thinset Brick Installation

Page 48: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Architectural Features

Page 49: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Thinset Brick

Patterns with Thinset Brick

Page 50: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

CMU Facade

• Chameleon Wall

• Placed in Sand Casting Bed

• Concrete Poured over the CMU Face

Page 51: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Curved Panels

• Target – Lee’s Summit

Page 52: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Protrusions

• Platforming

• Form up the recesses to allow for panel surfaces to protude from the face

Page 53: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Architectural Accent Panels2004 Award Winning Project

Page 54: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

EPA Panel FormingForming required unusual techniques

Page 55: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

EPA Panel Forming

Reveals on each side of the panel required innovation to achieve

Page 56: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

EPA Panel Forming

Penetrations in the panel for ductwork

Page 57: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

EPA Reinforcing

Forced Column and Beam Strips into the Panel to allow for Insulated Voids

Page 58: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

EPA Panels Lifting 32 inch

thick panel weighing 186,000 pounds

Page 59: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E
Page 60: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E
Page 61: TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E

Questions

If you have questions in the future please feel free to contact me!!!