timber frame isometric view

Upload: sertackcdg

Post on 01-Mar-2016

45 views

Category:

Documents


1 download

DESCRIPTION

Timber Structures

TRANSCRIPT

  • Timber FrameIsometric cut-away view

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Detail 3.00

    Structural timber frame

    Vapour control layer

    Insulation

    Wall ties

    Cavity

    Outer leaf (brick shown)

    Sheathing board

    Breather membrane

    Timber batten /service void (option)

    Rigid insulation /plasterboard composite

    LegendInsulation zone

    Air tightness barrier(note: this can alsoact as a vapourcontrol layer)

    Guidance on thermalcontinuity

    Blue text

    Guidance on airtightness

    Red text

    General guidance notes

    Alternative constructions1. The rigid insulation / plasterboard

    construction can be replaced otherfinishes but this will require that thickerinsulation is used in the wall. Ensurethat the thermal conductivity of thisinsulation is equal or less than thatused in the cavity of the timber frame,to prevent interstitial condensationproblems.

    2. Different constructions can be used toprovide an outer leaf but check thatthere is sufficient ventilation provisionto prevent moisture from being trappedwithin the wall.

    Sealing membrane junctions3. All membranes should be taped,

    stapled or bedded in adhesive asidentified by manufacturer. Repair alltears in membranes beforecommencing next stage of work.

    Psi-value calculations4. For details of all thermal conductivity

    values of materials used in thepsi-value calculations, see Appendix Bof the Introduction.

    Material ?-values usedin calculations(W/mK)

    Plasterboard 0.21Insulation (generic) 0.04Plywood sheathing 0.13Brick outer leaf 0.77Mineral wool insulation 0.044Concrete block(dense) protected

    1.13

    Concrete block(lightweight, high strength)

    0.19

    Timber frame 0.13Concrete floor beam 2.3Concrete screed 1.15Render (cement/sand) 1.0Gypsum plaster(1000kg/m3)

    0.4

    Concrete roof tiles 1.5EPDM membrane 0.25Timber battens 0.13Timber flooring 0.13Chipboard 0.13Floor joists 0.13Aluminium 160Steel 50Stainless steel 17Glass 1Sarking felt 0.23Insulation board 0.022

    Values used in psi calculations

  • Timber FramePitched Roof: Ventilated Roofspace - EavesPsi value = 0.0464W/mK

    Thermal continuity checklist

    1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions

    2. Ensure that roof insulation fully laps timberframe insulation

    3. Install cavity barrier at the top of the wall.

    Detail 3.01

    Proprietary cross flowventilator to maintainminimum 25mm air gap

    Ventilation gap equivalent to10mm minimum continuousopening is required where???????????????????????orventilation gap equivalent to25mm minimum continuousopening is required where???????????????????????????

    Vapour control layer inwall and ceiling

    Ventilation gap equivalent to 5mmminimum continuous opening at ridgeis required where the roof pitch is????????????????????????????????????more than 10m

    Insulation between the studsmust be tightly fitted leaving no

    gaps

    Cavity barrier giving 30 minutefire resistance - ensure cavitybarrier is not breeched byinappropriate rigid sheathinginsulation material

    Timber batten to providefixing for plasterboard sheet

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????????????????????????????????

    Note: See detail numbers 3.02 and 3.21 forother junctions using this roof construction

    20x38mm timber battens /services void (optional)

    Composite rigid insulation /plasterboard

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps and is robustly joinedto the barrier in the ceiling

  • Timber FramePitched Roof: Ventilated Roofspace - GablePsi value = 0.1006W/mK Detail 3.02

    Loft insulation continued upto outer face of the rigidsheathing

    Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial

    Vapour control layer inwall and ceiling

    Cavity ventilator

    Timber runner to provide fixingfor plasterboard sheet

    Insulation between thestuds must be tightly fitted

    leaving no gaps

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????????????????????????????????

    Note: See detail numbers 3.01 and 3.21 forother junctions using this roof construction

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps and is robustly joinedto the barrier in the ceiling

    Thermal continuity checklist

    1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions

    2. Ensure that roof insulation butts against the timber sheathing in the wall

    3. Install cavity barrier at the top of the wall.

    Full depth dwang required tosecure roof bracing at a levelabove the rafter ties.Alternative batten and bracingdetails can also be used

  • Timber FramePitched Roof: Ventilated Rafter Void - GablePsi value = 0.0472W/mK Detail 3.03

    Thermal continuity checklist

    1. Ensure that insulation is fitted tightly withinthe timber frame

    2. Ensure that insulation layers in roof arefitted perpendicularly to cover junctions

    3. Install cavity barrier at the top of the wall.

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps with the barrier in theceiling

    Masonry built upbetween ladder legs

    Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial

    Vapour control layer inwall and ceiling

    Cavity ventilator

    Timber runner to provide fixingfor plasterboard sheets

    Insulation between thestuds must be tightly fitted

    leaving no gaps

    Minimum 50mm ventilation path over insulation

    Where two insulation types areused together see

    supplementary guidance

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????????????????????????????????

    Note: See detail numbers 3.04, 3.05 and 3.22for other junctions using this roof construction

    Note: this construction istypically used where thereare habitable rooms withinthe roof construction

  • Timber FramePitched Roof: Ventilated Batten Void (warm roof) - EavesPsi value = 0.0284W/mK Detail 3.04

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps with the barrier in theceiling

    Rigid insulation used as sarking.Insulation to be vapour permeable

    Proprietary overfascia ventilator

    Vapour control layer inwall and ceiling

    Cavity barrier giving 30 minutefire resistance - ensure cavity

    barrier is not breeched byinappropriate rigid sheathing

    insulation materialInsulation between the

    studs must be tightlyfitted leaving no gaps

    Timber batten to provide fixingfor plasterboard sheets

    Ventilation tobatten void

    Vapour permeable membrane(with a vapour resistance ofnot more than 0.6MN.s/g)

    Lap roof and wall insulationminimum 150mm thickness atnarrowest point

    Ventilation gap equivalent to5mm minimum continuousopening is required at ridgeto batten space

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????????????????????????????????

    Note: See detail numbers 3.03, 3.05 and 3.22for other junctions using this roof construction

    Thermal continuity checklist

    1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions

    2. Ensure that roof insulation overlaps with the top of the timber frame wall, with minimum 50mm overlap at the narrowest point

    3. Install cavity barrier at the top of the wall

    Alternative position forplasterboard ceiling

    Note: this construction istypically used where thereare habitable rooms withinthe roof construction

  • Timber FramePitched Roof: Ventilated Batten Void (warm roof) - GablePsi value = 0.0431W/mK Detail 3.05

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps with the barrier in theceiling

    Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial

    Vapour control layer inwall and ceiling

    Cavity ventilator

    Insulation between the studs mustbe tightly fitted leaving no gaps

    Minimum 50mm ventilation path over insulation

    Where two insulation types areused together see

    supplementary guidance

    Vapourpermeablemembrane(with a vapourresistance ofnot more than0.25 MN.s/g)

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????????????????????????????????

    Note: See detail numbers 3.03, 3.04 and 3.22for other junctions using this roof construction

    Compressible filler

    Thermal continuity checklist

    1. Ensure that insulation layers are fittedperpendicularly, to cover junctions

    2. Ensure that roof insulation fully laps timberframe insulation

    3. Install cavity barrier at the top of the wall.

    Timber runner to provide fixingfor plasterboard sheets

    Note: this construction istypically used where thereare habitable rooms withinthe roof construction

  • Timber FrameTimber Flat RoofPsi value = 0.0536W/mK Detail 3.06

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps with the barrier in theceiling

    Verge - tightly fit insulationinto void over wall andunder deck (not shown)

    Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial

    Vapour control layer in wall

    Cavity ventilator Timber batten to be provided tocover over junction between

    plasterboard sheets

    Insulation between thestuds must be tightly fitted

    leaving no gaps

    Compressible filler

    Eaves - fix full height blockingpiece and tightly fit insulation intovoid and under deck

    Vapour control layer turned up edgeof roof insulation, lapped with roofwaterproofing layer and sealed

    Membrane roof construction

    Vapour control layer in ceiling

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling2. A vapour barrier is required at ceiling

    level, to prevent moisture from enteringinto the roof construction

    3. The option shown here includes a vapourcontrol layer and insulation as part of amembrane roof construction. Similardetails could be used for a profiled metaldecking roof but consult withmanufacturer regarding ventilationrequirements.

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????????????????????????????????

    Thermal continuity checklist

    1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions

    2. Ensure that roof insulation fully laps timberframe insulation

    3. Install cavity barrier at the top of the wall.

  • Timber FrameTimber Flat Roof with ParapetPsi value = 0.0299W/mK Detail 3.07

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps with the barrier in theceiling

    Cavity barriergiving 30 minutefire resistance -ensure cavitybarrier is notbreeched byinappropriate rigidsheathinginsulation material

    Vapour control layer inwall and ceiling

    Insulation between the studs must betightly fitted leaving no gaps

    Compressible fillerRoofing membrane to be taken minimum

    150mm above finished roof level

    Vapour control layer turned up edgeof roof insulation, lapped with

    breather membrane from cavity wall

    Tightly fit compressible insulant between the wallstuds above the level of the roof deck

    Vapour control layer

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling2. A vapour barrier is required at ceiling

    level, to prevent moisture from enteringinto the roof construction

    3. The option shown here includes a vapourcontrol layer and insulation as part of amembrane roof construction. Similardetails could be used for a profiled metaldecking roof but consult withmanufacturer regarding ventilationrequirements.

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????????????????????????????????

    Thermal continuity checklist

    1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions

    2. Ensure that roof insulation butts against the timber wall sheathing with a minimum of 50mm overlap at narrowest point

    3. Install cavity barrier at the top of the wall

  • Timber FrameLintel at Window HeadPsi value = 0.121W/mK

    Thermal continuity checklist

    1. Check that there is no debris in the cavity2. Install cavity barrier around opening

    Air tightness checklist

    1. Install window to overlap with outer leaf ofwall finish.

    Alternative:If window lines through with the bottom ofthe opening in the external finish, somemeans of preventing a direct line of airinfiltration will be required

    2. Install air tightness seal between theinside face of the window and thestructural finish of the window opening

    Insulation between thestuds must be tightly

    fitted leaving no gaps

    30 minute fireresistingproprietaryinsulating cavitybarrier withintegral DPC

    Detail 3.08

    Insulate the window reveal

    Sealant to back of frame

    Sealant at window frame

    Weep Hole

    Air tightness tape

    Compressible fill

    Use approved lintoldetails from timber

    frame supplier

    Vapour control layer

    Cavity tray withminimum upstandof 140mm andstop ends

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Alternative internal finish at window

    reveal - use insulation backedplasterboard

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????

    If position of window head islower than or level with theunderside of the lintol, a largercompressible filler will berequired to stop up a potentialair infiltration route

  • Timber FrameWindows and Doors - Jambs and Cills

    Psi value (jamb)=0.0328W/mK Psi value (cill) = 0.0934W/mK

    Thermal continuity checklist

    1. Check that there is no debris in the cavity2. Install cavity barrier around opening

    Air tightness checklist

    1. Install window to overlap with outer leaf ofwall finish.

    Alternative:If window lines through with the bottom ofthe opening in the external finish, somemeans of preventing a direct line of airinfiltration will be required

    2. Install air tightness seal between theinside face of the window and thestructural finish of the window opening

    Detail 3.09

    Insulate the window reveal

    Air tightness tape andsealant to back of frame

    Sealant at window frame

    30 minute fire resisting cavitybarrier with integral DPC

    Vapour controllayer in wall

    Insulation between thestuds must be tightly

    fitted leaving no gaps

    DPC lappedbehind cill andbelow window

    Solid cill acts as cavitycloser. If pressed cill isused, a 30 minute firerated thermally insulatedcavity closer will berequied

    Insulate the window reveal

    Air tightness tape andsealant to back of frame

    Compressiblefiller betweenwindow and cill

    Vapour control layer in wall

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Alternative internal finish at window

    reveal - use insulation backedplasterboard

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????

    Cill detail

    Jamb detail

  • Timber FrameGround Bearing Floor: Insulation Above SlabPsi value = 0.1145W/mK

    20mm strip of perimeterinsulation with thermal

    conductivity (? value) notexceeding 0.025 W/mK around

    slab and any screed

    Detail 3.10

    Thermal continuity checklist

    1. Use a lightweight loadbearing concreteblock where the wall abuts the concreteslab to minimise thermal bridging

    2. Use a perimeter strip of insulation wherethe concrete slab abuts the concreteblockwork wall

    Air tightness checklist

    1. Ensure that any air tightness barrier usedin the wall overlaps onto the floor slab

    External ground level

    Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    Damp proof membraneabove or below slab

    Vapour control layer belowtimber floor finish

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that concrete slab is level and

    clear of debris before fitting the insulationat floor level

    2. If a screed finish is used instead of a timber floor, use a strip of perimeter insulation with a minimum R value of ??????????????????????????????????????

    Alternative detail3. Using lightweight blockwork (e.g. with ?

    value of 0.19W/mK) to improve thethermal performance at the junction wherethe external wall and ground floorconstructions meet will change the psivalue

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????????????????????????

  • Timber FrameGround Bearing Floor: Insulation Below SlabPsi value = 0.1733W/mK Detail 3.11

    50mm strip of perimeterinsulation with thermal

    conductivity (? value) notexceeding 0.025 W/mK around

    slab and any screed

    Thermal continuity checklist

    1. Use a lightweight loadbearing concreteblock where the wall abuts the concreteslab to minimise thermal bridging

    2. Use a perimeter strip of insulation wherethe concrete slab abuts the concreteblockwork wall

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps onto the floor slab

    External ground level

    Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    Damp proof membrane

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. If a screed finish is used instead of a

    timber floor, use a strip of perimeter insulation with a minimum R value of ??????????????????????????????????????

    Alternative detail2. Using lightweight blockwork (e.g. with ?

    value of 0.19W/mK) to improve thethermal performance at the junctionwhere the external wall and ground floorconstructions meet will change the psivalue

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????????????????????????

  • Timber FrameTimber Suspended Ground FloorPsi value = 0.0423W/mK Detail 3.12

    Sub floor ventilation should be?????????????????????????

    per run of external wall or???????????????????????????

    Thermal continuity checklist

    1. Ensure that floor insulation butts againstthe insulation in the external wall

    Air tightness checklist

    1. Check that any air tightness barrier usedin the wall overlaps with the barrier in thefloor

    External ground level

    Add timber batten to cover the floor/wall junction. Useair tightness tape at junction of air barrier in wall and

    floor. Seal between the wall and floor membrane with aflexible sealant or seal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    Damp proof membrane

    Air tightness barrier belowtimber floor finish

    Insulation directly under flooringsupported on netting draped over

    joists and stapled at required depths

    Solum

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that all ventilation paths are clear

    before installing the floor insulationAlternative detail2. Using lightweight blockwork (e.g.

    with ? value of 0.19W/mK) to improvethermal performance at the junctionwhere the external wall and ground floorconstructions meet will change the psivalue

    3. If there are concerns about damaging theair tightness membrane in the floor finishduring construction, an additional servicesvoid can be created using timber battenson top of the floor joists

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????????????????????????

  • Timber FrameSeparating WallPsi value = 0.0725W/mK

    Thermal continuity checklist

    1. Check that there is no debris in the cavity2. Install cavity barrier at junction of wall

    Detail 3.13

    Air tightness checklist

    1. Check that any air tightness barrier usedin the internal wall overlaps with thebarrier in the external wall

    Cavity barriers giving 30 minutefire resistance - ensure cavitybarriers are not breeched by

    inappropriate insulation materialin the timber frame

    For more information onacoustic details see

    guidance in Section 5 ofthe Technical Standards

    Vapour control layer in wall

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that insulation is fitted between

    timber studs at corner junctions

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????????????????????????????????

    Plan view

  • Timber FrameTimber Separating FloorPsi value = 0.0353W/mK

    Thermal continuity checklist

    1. Check that there is no debris in the cavity2. Install cavity barrier in line with floor

    construction

    Detail 3.14

    Air tightness checklist

    1. Check that any air tightness barrier usedin the external wall overlaps with thebarrier in the floor

    Cavity barriergiving 30 minutefire resistance -ensure cavitybarrier is notbreeched byinappropriate rigidsheathinginsulation material Vapour control layer in wall

    Cavityventilator

    Insulation between the studs must betightly fitted leaving no gaps

    Seal between the wall and floormembrane with a flexible sealant or sealthe gap between skirting board and floor

    using a flexible sealant

    Vapour control layer in wall

    Separating floors to comply withSection 2: Fire and Section 5:

    Noise

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that insulation is tightly fixed to the

    timber studs adjacent to the floor junction,leaving no gaps

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????????????????????????

  • Timber FrameIntermediate Floor / External WallPsi value = 0.0574W/mK

    Thermal continuity checklist

    1. Check that there is no debris in the cavity2. Install cavity barrier as necessary

    Detail 3.15

    Air tightness checklist

    1. Check that any air tightness barrier usedin the external wall overlaps with thebarrier in the floor

    Vapour control layer in wallInsulation between the

    studs must be tightlyfitted, leaving no gaps

    Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that insulation is tightly fixed to the

    timber studs adjacent to the floor junction,leaving no gaps

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????

    Install air tightness barrier aroundjoists, then lap membrane from

    walls over it and tape junction

  • Timber FrameGround Floor/Separating Wall Junction- timber suspended floorPsi value = 0.0713W/mK

    Thermal continuity checklist

    1. Ensure that insulation is tightly fittedbetween the timber floor joists

    2. Install cavity barrier as necessary

    Detail 3.16

    Air tightness checklist

    1. Check that any air tightness barrier usedin the internal wall overlaps with thebarrier in the floor

    Sub floor ventilation should be?????????????????????????

    per run of external wall or???????????????????????????

    Damp proof membrane

    Use air tightness tape at junction of air barrier in walland floor. Seal between the wall and floor membrane

    with a flexible sealant or seal the gap between skirtingboard and floor using a flexible sealant

    Vapour contol layer in wall

    Air tightness barrier belowtimber floor finish

    Insulation directly under flooring -supported on netting draped over

    joists and stapled at required depths

    Solum

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that all ventilation paths are clear

    before installing the floor insulationAlternative Detail2. Lightweight thermal blockwork can be

    used in the separating wall to improve thethermal performance but this will alsoreduce the acoustic performance of thewall. If this alternative is used thenadditional elements will be required tomeet Section 5 of the TechnicalStandards.

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????

  • Timber FrameConcrete Ground Floor/ Separating Wall: Insulation Below SlabPsi value = 0.2765W/mK

    Thermal continuity checklist

    1. Ensure that insulation is tightly fittedagainst the separating floor

    Detail 3.17

    Air tightness checklist

    1. Check that any air tightness barrier usedin the internal wall overlaps onto the floorslab

    Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    Damp proof membrane

    Lightweight loadbearing concreteblockwork to minimise thermal bridging

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. If a screed finish is used instead of a

    timber floor, use a strip of perimeter insulation with a minimum R value of ??????????????????????????????????????

    Alternative Detail2. Heavyweight thermal blockwork can be

    used in the separating wall below slablevel but this will reduce the thermalperformance of this junction. Additionalconstruction elements may be requiredalong with lightweight blockwork in orderto meet the acoustic requirements ofSection 5 of the the Technical Standards

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????

  • Timber FrameConcrete Ground Floor/ Separating Wall: Insulation Above SlabPsi value = 0.0146W/mK

    Thermal continuity checklist

    1. Ensure that insulation is tightly fittedagainst the separating floor

    Detail 3.18

    Air tightness checklist

    1. Check that any air tightness barrier usedin the internal wall overlaps onto the floorslab

    Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    Damp proof membrane

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that concrete slab is level and

    clear of debris before fitting the insulationat floor level

    2. If a screed finish is used instead of a timber floor, use a strip of perimeter insulation with a minimum R value of ??????????????????????????????????????

    Alternative Detail3. Lightweight thermal blockwork can be

    used in the separating wall to improve thethermal performance but this will alsoreduce the acoustic performance of thewall. If this alternative is used thenadditional elements will be required tomeet Section 5 of the TechnicalStandards.

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????

    Seal air tightnessmembrane to floor slab

    Vapour barrier in floor

  • Timber FrameSeparating Floor / Wall JunctionPsi value = 0.0241W/mK

    Thermal continuity checklist

    1. Ensure that insulation is tightly fitted

    Detail 3.19

    Air tightness checklist

    1. Check that any air tightness barrierused in the internal wall overlaps withthe barrier in the floor

    Alternative:Ensure that a continuous air tightnessbarrier from the wall wraps around theend of the floor construction, leavingno gaps

    Vapour control layer in wall

    Insulation between the studsmust be tightly fitted

    Vapour control layer in ceiling

    Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    Vapour control layer belowtimber floor finish

    Separating floors requireadditional layers and components

    to comply with Section 2: Fireand Section 5: Noise

    Cavity barrier

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk

    See general guidance notes

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????

  • Timber FrameIntermediate FloorPsi value = 0.0333W/mK

    Thermal continuity checklist

    1. Ensure that insulation is tightly fitted

    Detail 3.20

    Vapour control layer in wall

    Insulation between the studsmust be tightly fitted

    Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board

    and floor using a flexible sealant

    Vapour control layer in wall

    Cavity barrier

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk s

    See general guidance notes

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????

    Air tightness checklist

    1. Check that any air tightness barrierused in the internal wall overlaps withthe barrier in the floor

    Alternative:Ensure that a continuous air tightnessbarrier from the wall wraps around theend of the floor construction, leavingno gaps

    Install air tightness barrier aroundjoists, then lap membrane from

    walls over it and tape junction

  • Timber FramePitched Roof: Cold Roof / Separating Wall junctionPsi value = 0.0132W/mK

    Thermal continuity checklist

    1. Install a cavity barrier at the top of the wall2. Ensure that insulation layers in the roof are

    fitted perpendicularly, to cover junctions

    Air tightness checklist

    1. Check that there are no gapsbetween the top of the masonry andthe underside of the roof

    2. Check that the air tightness barrier inthe wall overlaps with the barrier inthe ceiling

    Vapour control layer inwall and ceiling

    Insulation between the studsmust be tightly fitted

    Where two insulation typesare used together see

    supplementary guidance

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????

    Note: See detail numbers 3.01 and 3.02 forother junctions using this roof construction

    Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial

    Separating walls requireadditional layers and componentsto comply with Section 2: Fireand Section 5: Noise

    Detail 3.21

    Cavity barrier is used in line withceiling insulation to prevent thermalbypass.Use dense insulation orproprietary cavity barrier in sleeve

  • Timber FramePitched Roof: Ventilated Batten Void / Separating Wall JunctionPsi value = 0.0481W/mK Detail 3.22

    Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial

    Vapour control layerin wall and ceiling

    Insulation between the studsmust be tightly fitted

    Where two insulation typesare used together see

    supplementary guidance

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check ventilation paths are clear before

    installing insulation above the ceiling

    Thermal Resistance of insulation used indetails:

    ????????????????????????????????????????????????

    Note: See detail numbers 3.03, 3.04 and 3.05for other junctions using this roof construction

    Minimum 50mm ventilation path over insulation

    Thermal continuity checklist

    1. Install a cavity barrier at the top of the wall2. Ensure that insulation layers in the roof are

    fitted perpendicularly, to cover junctions

    Air tightness checklist

    1. Check that there are no gapsbetween the top of the masonry andthe underside of the roof

    2. Check that the air tightness barrier inthe wall overlaps with the barrier inthe ceiling

    Separating walls requireadditional layers and componentsto comply with Section 2: Fireand Section 5: Noise

    Note: this construction istypically used where thereare habitable rooms within

    the roof construction

  • Timber FrameWall JunctionPsi value = 0.0179W/mK

    Thermal continuity checklist

    1. Check that there is no debris in the cavity2. Install cavity barrier

    Detail 3.23

    Air tightness checklist

    1. Ensure that any air tightness barrier usedin the external wall overlaps at the corner

    Plan view

    Cavity barrier giving 30 minutefire resistance - ensure cavity

    barrier is not breeched byinappropriate insulation

    material

    Insulation betweenthe studs must betightly fitted leavingno gaps

    Vapour controllayer

    HEAT 2.7 software image of isothermsthrough junction detail.

    For illustrative purposes only.

    This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.

    Design advice

    Minimising condensation risk1. Check that insulation is tightly fixed to

    the timber studs at the corner junction,leaving no gaps

    Thermal Resistance of insulation used indetails:

    ?????????????????????????????????????????????????????????