TINJAUAN METODE PELAKSANAAN DAN ANGGARAN BIAYA
STRUKTUR ATAS GEDUNG D2 PROYEK
PESANTREN TARBIYAH SUNNAH BATUJAJAR
OVERVIEW OF IMPLEMENTATION METHODS AND BUDGET
PLAN FOR THE UPPER STRUCTURE OF THE D2
TARBIYAH SUNNAH BATUJAJAR ISLAMIC BOARDING
SCHOOL BUILDING
TUGAS AKHIR
Tugas Akhir ini disusun untuk memenuhi salah satu syarat menyelesaikan
pendidikan Diploma Tiga Program Studi Teknik Konstruksi Gedung Jurusan Teknik
Sipil
Oleh :
IRPAN M. PEBRIANDI M. IHSAN HADIYAT
NIM 171111042 NIM 171111051
POLITEKNIK NEGERI BANDUNG
2020
ii
TINJAUAN METODE PELAKSANAAN DAN ANGGARAN BIAYA
STRUKTUR ATAS GEDUNG D2 PROYEK
PESANTREN TARBIYAH SUNNAH BATUJAJAR
OVERVIEW OF IMPLEMENTATION METHODS AND
BUDGET PLAN FOR THE UPPER STRUCTURE OF THE D2
TARBIYAH SUNNAH BATUJAJAR ISLAMIC BOARDING
SCHOOL BUILDING
Oleh:
IRPAN M. PEBRIANDI M. IHSAN HADIYAT
NIM 171111042 NIM 171111051
Menyetujui,
Bandung, Oktober 2020
Pembimbing
Udi Raharjo, Drs MM
NIP. 195807211986031003
Ketua Jurusan Teknik Sipil,
Hendry, Dipl. Ing. Htl., MT
NIP. 19630606199512001
iii
TINJAUAN METODE PELAKSANAAN DAN ANGGARAN BIAYA
STRUKTUR ATAS GEDUNG D2 PROYEK
PESANTREN TARBIYAH SUNNAH BATUJAJAR
OVERVIEW OF IMPLEMENTATION METHODS AND
BUDGET PLAN FOR THE UPPER STRUCTURE OF THE D2
TARBIYAH SUNNAH BATUJAJAR ISLAMIC BOARDING
SCHOOL BUILDING
TUGAS AKHIR
Oleh:
IRPAN M. PEBRIANDI M. IHSAN HADIYAT
NIM 171111042 NIM 171111051
Menyetujui
Tim
Penguji
Ketua : Yulianto Petrus Krisologus, Drs, MM.
NIP. 196007301986031002 : …………………..
Anggota I : Ir. Taufik Hamzah, MT, MBA.
NIP. 195612251985031002 : …………………..
Anggota II : Drs. Udi Raharjo, MM
NIP. 195807211986031003 : …………………..
iv
PERNYATAAN PENULIS
HALAMAN PERNYATAAN
Saya yang bertandatangan dibawah ini menyatakan bahwa laporan Tugas Akhir ini
adalah murni hasil pekerjaan saya sendiri. Tidak ada pekerjaan orang lain yang saya
gunakan tanpa menyebutkan sumbernya.
Materi dalam laporan Tugas Akhir ini tidak/belum pernah disajikan/digunakan
sebagai bahan makalah/Tugas Akhir lain, kecuali saya menyatakan dengan jelas bahwa
saya menggunakannya.
Apabila dikemudian hari ditemukan adanya unsur plagiarisme pada laporan Tugas
Akhir saya, maka hasil penilaian dari Tugas Akhir ini dicabut dan bersedia menerima
sanksi sesuai dengan ketentuan yang berlaku.
Demikian pernyataan ini dibuat dengan sesungguhnya dalam keadaan sadar
sepenuhnya.
Judul Tugas Akhir:
“TINJAUAN METODE PELAKSANAAN DAN ANGGARAN BIAYA
STRUKTUR ATAS GEDUNG D2 PROYEK PESANTREN TARBIYAH
SUNNAH BATUJAJAR”
Bandung, 11 Oktober 2020
Irpan Muhamad Pebriandi
NIM. 171111041
Muhammad Ihsan Hadiyat
NIM. 171111051
Materai
Rp.6000,-
Materai
Rp.6000,-
v
PERNYATAAN PENULIS
Dengan ini menyatakan bahwa laporan Tugas Akhir dengan judul “TINJAUAN
METODE PELAKSANAAN DAN ANGGARAN BIAYA STRUKTUR ATAS
GEDUNG D2 PROYEK PESANTREN TARBIYAH SUNNAH BATUJAJAR”
adalah benar bagian lengkap dari laporan Tugas Akhir yang sudah disahkan oleh
pembimbing dan penguji, serta merupakan laporan yang telah diturnitin.
Apabila dikemudian hari ditemukan hasil turnitin bukan bagian lengkap dari Tugas
Akhir saya, maka hasil penilaian dari Tugas Akhir ini dicabut dan bersedia menerima
sanksi sesuai dengan ketentuan yang berlaku.
Demikian pernyataan ini dibuat dengan sesungguhnya dalam keadaan sadar
sepenuhnya.
Bandung, 11 Oktober 2020
Irpan Muhamad Pebriandi
NIM. 171111041
Muhammad Ihsan Hadiyat
NIM. 171111051
Materai
Rp.6000,-
Materai
Rp.6000,-
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|vi
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|vi
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|vi
ABSTRAK
Pada proyek pembangunan Pondok Pesantren Tarbiyah Sunnah merupakan salah
satu proyek yang dikelola secara swasta. Dengan sumber daya berasal dari pihak
internal dan sebagian besar dana yang diperoleh dari para donatur. Metode
pelaksanaan dan rencana anggaran biaya pun harus benar-benar diperhatikan dan
dihitung dengan tepat supaya tidak terjadi kerugian akibat biaya berlebih. Maka, topik
dari Tugas Akhir ini yaitu “Tinjauan Metode Pelaksanaan dan Anggaran Biaya
Struktur Atas Gedung D2 Pesantren Tarbiyyah Sunnah Batujajar”.
Bahasan dalam Tugas Akhir ini diawali dengan menyusun Work Breakdown
Structure (WBS), meninjau metode pelaksanaan, dan menghitung Rencana Anggaran
Biaya (RAB). Dengan memperhatikan peraturan yang ada, rencana anggaran biaya
mengacu pada AHSP PERMEN PU Bidang Cipta Karya no. 28 tahun 2016. Selain itu
dasar teori yang digunakan dari berbagai sumber, diantaranya referesni dari Karya
Ilmiah, Jurnal, dan Internet.
Hasil dari tinjauan ini didapatkan metode pelaksanaan struktur atas menggunakan
metode konvensional. Akan tetapi pada struktur pelat lantai sudah ada yang
menggunakan pelat lantai precast. Berdasarkan hasil perhitungan didapatkan Rencana
Anggaran Biaya Struktur atas sebesar Rp. 273,546,304.82.
Kata kunci: Metode pelaksanaan, struktur atas, rencana anggaran biaya.
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|vii
ABSTRACT
The construction project of the Tarbiyah Sunnah Islamic Boarding School is one
of the privately managed projects. With resources coming from internal parties and
most of the budget funds obtained from contributor donors. The implementation method
and cost budget plan must also be considered and calculated precisely so that there are
no losses due to over excess costs. So, the topic of this final project is "Overview of
Implementation Methods and Budget Plan for the Upper Structure of the D2 Tarbiyyah
Sunnah Batujajar Islamic Boarding School Building".
The discussion in this Final Project begins with compiling a Work Breakdown
Structure (WBS), reviewing the implementation method, and calculating the Budget
Plan (RAB). With regard to existing regulations, the budget plan refers to AHSP
PERMEN PU in the Human Settlements Sector no. 28 of 2016. In addition, the
theoretical basis used is from various sources, including references from scientific
papers, journals, and the Internet.
The results of this review obtained the upper structure implementation method
using conventional methods. However, there is already a floor slab structure that uses
precast floor plates. Based on the results of the calculation, the Budget Plan for the
Structure Fee is Rp. 273,546,304.82.
Key words: Implementation method, upper structure, budget plan.
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|viii
KATA PENGANTAR
Puji dan syukur kami panjatkan kehadirat Allah SWT atas berkat rahmat dan
karunia-Nya penulis dapat menyelesaikan laporan Tugas Akhir dengan judul
“Tinjauan Metode Pelaksanaan dan Rencana Anggaran Biaya Struktur Atas
Gedung D2 Proyek Pesantren Tarbiyyah Sunnah Batujajar”. Laporan ini
disusun untuk memenuhi salah satu syarat kelulusan mata kuliah Tugas Akhir pada
semester VI yang diwajibkan untuk mahasiswa tingkat akhir Jurusan Teknik Sipil
Politeknik Negeri Bandung.
Penulisan laporan ini tidak lepas dari bimbingan dan dukungan dari berbagai
pihak. Penulis menyampaikan terima kasih atas segala dukungan dan bantuan
dalam penyusunan laporan ini, kepada :
1. Kedua orang tua yang tidak pernah berhenti memberikan dukungan berupa
materi maupun moril serta kasih sayang kepada kami,
2. Bapak Hendry, Dipl.Ing.HTL, MT. selaku Ketua Jurusan Teknik Sipil
Politeknik Negeri Bandung,
3. Bapak Krish Madyono H, Dipl.Ing.HTL, MT. selaku koordinator
pelaksanaan Tugas Akhir,
4. Bapak Udi Raharjo, Drs, MM. selaku dosen pembimbing 1 yang telah
memberikan arahan dan masukan kepada penulis dalam menyusun laporan
Tugas Akhir,
5. Bapak Drs. Yulianto Petrus Krisologus, Drs, MM. sebagai penguji 1 Tugas
Akhir.
6. Bapak Taufik Hamzah, Ir, MT, MBA. sebagai penguji 2 Tugas Akhir
Pada penyusunan laporan ini penulis menyadari masih terdapat kekurangan,
karena itu penulis terbuka untuk saran dan kritik sebagai acuan dalam penulisan
laporan yang lebih baik lagi. Atas perhatiannya penulis mengucapkan terima kasih.
Bandung, Agustus 2018
Penulis
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|ix
DAFTAR ISI
HALAMAN JUDUL ................................................................................................ i
HALAMAN PENGESAHAN ................................................................................. ii
HALAMAN PERNYATAAN ............................................................................... iv
ABSTRAK ............................................................................................................. vi
ABSTRACT ............................................................................................................ vii
KATA PENGANTAR ......................................................................................... viii
DAFTAR ISI .......................................................................................................... ix
DAFTAR LAMPIRAN .......................................................................................... xi
DAFTAR GAMBAR ............................................................................................ xii
DAFTAR TABEL ................................................................................................ xiv
DAFTAR ISTILAH .............................................................................................. xv
DAFTAR SINGKATAN DAN LAMBANG ...................................................... xvi
BAB I : PENDAHULUAN................................................................................... I-1
1.1. Latar Belakang....................................................................................... I-1
1.2. Lokasi .................................................................................................... I-1
1.3. Rumusan Masalah ................................................................................. I-2
1.4. Tujuan .................................................................................................... I-3
1.5. Ruang Lingkup dan Batasan Pembahasan ............................................. I-3
1.6. Sistematika Penulisan ............................................................................ I-3
BAB II : TINJAUAN PUSTAKA....................................................................... II-1
2.1. Proyek .................................................................................................. II-1
2.2. Metode Pelaksanaan ............................................................................ II-2
2.2.1. Pekerjaan Kolom, Balok dan Pelat Lantai ................................... II-2
2.2.2. Pekerjaan Pelat Lantai Precast..................................................... II-3
2.2.3. Pekerjaan Bekisting dan Perancah ............................................... II-3
2.2.4. Persyaratan Teknis Menurut SNI ................................................. II-4
2.3. Work Breakdown Structure (WBS) ................................................... II-14
2.4. Biaya Pelaksanaan ............................................................................ II-16
2.4.1. Rencana Anggaran Biaya ........................................................... II-16
BAB III : METODOLOGI ................................................................................ III-1
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|x
3.1 Tahapan Penyelesaian Tugas Akhir ................................................... III-1
3.2 Alur Analisa Data ............................................................................... III-4
3.2.1 Pengamatan Analisa Metoda Konstruksi .................................... III-4
3.2.2 Pengolahan Anggaran Biaya ....................................................... III-5
BAB IV : ANALISA DAN PERHITUNGAN.................................................. IV-1
4.1. Data Proyek ........................................................................................ IV-1
4.1.1. Data Umum Proyek ..................................................................... IV-1
4.1.2. Data Administrasi Proyek ........................................................... IV-1
4.1.3. Data Teknis Proyek ..................................................................... IV-2
4.2. Work Breakdown Structure (WBS) .................................................... IV-3
4.3. Metode Pelaksanaan ........................................................................... IV-6
4.3.1. Struktur Atas ............................................................................... IV-6
4.3.1.1 Pelaksanaan Pekerjaan Kolom .................................................. IV-6
4.3.1.2 Pelaksanaan Pekerjaan Balok dan Pelat Lantai Site Mix ....... IV-25
4.3.1.3 Pelaksanaan Pekerjaan Pemasangan Pelat Lantai Precast ..... IV-45
4.4. Perhitungan Volume Pekerjaan Struktur Atas .................................. IV-53
4.5. Rencana Anggaran Biaya ................................................................. IV-64
BAB V : PENUTUP ............................................................................................ V-1
5.1. Kesimpulan ........................................................................................... V-1
5.2. Saran ..................................................................................................... V-1
DAFTAR PUSTAKA ......................................................................................... xvii
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|xi
DAFTAR LAMPIRAN
Lampiran 1 Gambar Kerja Detail
Lampiran 2 Daftar Harga Satuan Bahan Bangunan Kota Bandung 2018
Lampiran 3 Analisa Harga Satuan Pekerjaan (AHSP)
Lampiran 4 Rencana Anggaran Biaya (RAB)
Lampiran 5 Kurva S
Lampiran 6 Administrasi
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|xii
DAFTAR GAMBAR
Gambar 1.1 Peta Lokasi Batujajar ........................................................................... I-2
Gambar 1.2 Peta Lokasi Proyek Pesantren tarbiyah Sunnah ................................... I-2
Gambar 2.1 WBS Pembangunan Pondok Pesantren Tarbiyah Sunnah ................... II-15
Gambar 3.1 Diagram Alir Tahapan Penyelesaian Tugas Akhir .............................. III-3
Gambar 3.2 Diagram Alir Tahapan Analisa Metoda Konstruksi ............................ III-4
Gambar 3.2 Diagram Alir Tahapan Pengolahaan Rencana Anggaran Biaya .......... III-5
Gambar 4.1 WBS Proyek ........................................................................................ IV-6
Gambar 4.2 WBS Struktur Atas ............................................................................. IV-7
Gambar 4.3 Diagram Alir Pekerjaan Kolom ........................................................... IV-7
Gambar 4.4 Diagram Alir Persiapan Pekerjaan Kolom........................................... IV-8
Gambar 4.5 Diagram alir Penentuan As Kolom ..................................................... IV-15
Gambar 4.6 Diagram Alir Penulangan Kolom ........................................................ IV-16
Gambar 4.7 Alat Gerinda ......................................................................................... IV-17
Gambar 4.8 Alat Bar Bender ................................................................................... IV-17
Gambar 4.9 Distribusi Tulangan.............................................................................. IV-18
Gambar 4.10 Pemasangan Tulangan Kolom ........................................................... IV-18
Gambar 4.11 Diagram Alir Pemasangan Bekisting ................................................. IV-19
Gambar 4.12 Ukuran Bekisting Kolom .................................................................. IV-20
Gambar 4.12 Pemasangan Bekisting Kolom ........................................................... IV-21
Gambar 4.13 Pemasangan Bekisting Kolom ........................................................... IV-21
Gambar 4.14 Bekisting siap Cor .............................................................................. IV-22
Gambar 4.15 Diagram Alir Pengecoran Kolom ...................................................... IV-23
Gambar 4.16 Pengadukan Beton ............................................................................. IV-24
Gambar 4.17 Pengecoran ........................................................................................ IV-24
Gambar 4.18 Diagram Alir Pekerjaan Balok ........................................................... IV-25
Gambar 4.19 Diagram Alir Pkerjaan Bekisting Balok dan Pelat Lantai Site Mix ... IV-33
Gambar 4.20 Diagram Alir Penentuan Acuan Ketinggian ...................................... IV-34
Gambar 4.21 Diagram Alir Pekerjaan Perancah dan Bekisting .............................. IV-35
Gambar 4.22 Keadaan Multiplak Tidak Rapat ........................................................ IV-35
Gambar 4.23 Diagram Alir Pekerjaan Pembesian Balok ........................................ IV-36
Gambar 4.24 Diagram Alir Pekerjaan Pembesian Pelat Lantai ............................... IV-37
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
Irpan Muhamad Pebriandi, Muhammad Ihsan Hadiyat, Tinjauan Metode Pelaksanaan…..|xiii
Gambar 4.25 Bekisting Balok Siap Cor. ................................................................. IV-38
Gambar 4.26 Pemasangan Besi Penopang ............................................................... IV-39
Gambar 4.27 Diagram Alir Pekerjaan Pengecoran .................................................. IV-40
Gambar 4.28 Pengadukan Beton Menggunakan Mixer ........................................... IV-41
Gambar 4.29 Pengecoran Dengan Cara Estafet ....................................................... IV-41
Gambar 4.30 Penumbuk Beton Segar ...................................................................... IV-42
Gambar 4.31 Meratakan Beton Segar ...................................................................... IV-42
Gambar 4.32 Diagram Alir Pembongkaran Bekisting ............................................. IV-43
Gambar 4.33 Hasil Pengecoran ............................................................................... IV-44
Gambar 4.34 Diagram Alir Pekerjaan Pelat Lantai Precast .................................... IV-45
Gambar 4.35 Diagram Alir Pekerjaan Persiapan ..................................................... IV-46
Gambar 4.36 Diagram Alir Pekerjaan ..................................................................... IV-48
Gambar 4.37 Memasang Bambu ............................................................................. IV-49
Gambar 4.38 Memindahkan Panel Precast .............................................................. IV-49
Gambar 4.39 Memasang Tali Tambang .................................................................. IV-50
Gambar 4.40 Mobilisasi Panel ................................................................................. IV-50
Gambar 4.41 Bambu Landasan ................................................................................ IV-51
Gambar 4.42 Memindahkan Panel .......................................................................... IV-51
Gambar 4.43 Dimensi Kolom .................................................................................. IV-52
Gambar 4.44 Dimensi Balok ................................................................................... IV-56
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
DWI RIZQY PRATAMA PUTRA, SYIFA FAUZIAH NURRAHMAH, METODE PELAKSANAAN...|xiv
DAFTAR TABEL
Tabel 4.1. Bahan Pembesian Kolom ................................................................... IV-9
Tabel 4.2. Alat Pembesian Kolom ...................................................................... IV-9
Tabel 4.3. Bahan Perancah .................................................................................. IV-10
Tabel 4.4. Bahan Pekerjaan Bekisting ................................................................ IV-11
Tabel 4.5 Alat Pekerjaan Bekisting ..................................................................... IV-12
Tabel 4.6. Bahan Pengecoran .............................................................................. IV-13
Tabel 4.7. Alat Pengecoran ................................................................................. IV-14
Tabel 4.8. Bahan Perancah Balok ....................................................................... IV-27
Tabel 4.9. Alat Perancah Balok .......................................................................... IV-28
Tabel 4.10. Alat Bekisting ................................................................................. IV-29
Tabel 4.11. Bahan Pembesian ............................................................................. IV-29
Tabel 4.12. Alat Pembesian ................................................................................ IV-30
Tabel 4.13. Bahan Pengecoran ............................................................................ IV-31
Tabel 4.14. Alat Pengecoran ............................................................................... IV-32
Tabel 4.15. Alat Pemasangan Pelat Precast ........................................................ IV-47
Tabel 4.16. Bahan Pelat Precast .......................................................................... IV-48
Tabel 4.17. Tabel Durasi Pekerjaan .................................................................... IV-75
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
DWI RIZQY PRATAMA PUTRA, SYIFA FAUZIAH NURRAHMAH, METODE PELAKSANAAN...|xv
DAFTAR ISTILAH
Asrama : Tempat tinggal sementara.
Barchart : Bentuk penyajian data dalam bentuk diagram batang yang
menunjukkan suatu kegiatan pada kolom vertikal serta nilai pada
kolom horisontal.
Beton Decking : suatu spesi yang dibentuk sesuai dengan ketebalan selimut beton.
Durasi : rentang waktu.
Grouting : menyutikkan suatu cairan dengan tekanan yang sesuai dengan uji
tekanan air.
Homogen : terdiri atas jenis, macam, sifat, watak, dan sebagainya yang sama.
Overhead : biaya operasional.
Peil : ketinggian muka tanah.
Produktivitas : kemampun untukmenghasilkan sesuatu; daya produksi;
keproduktifan.
Scaffolding : struktur sementara yang berfungsi sebagai penyangga.
Uji Slump : pengujian kelecakan beton segar.
D3 TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG
DWI RIZQY PRATAMA PUTRA, SYIFA FAUZIAH NURRAHMAH, METODE PELAKSANAAN...|xvi
DAFTAR SINGKATAN DAN LAMBANG
AHSP Analisa Harga Satuan Pekerjaan
PERMEN PU Peraturan Menteri Pekerjaan Umum
RAB
SNI
Rencana Anggaran Biaya
Standar Nasional indonesia
WBS Work Breakdown Structure
`
DWI RIZQY PRATAMA PUTRA, SYIFA FAUZIAH NURRAHMAH, METODE PELAKSANAAN...|xvii
DAFTAR PUSTAKA
Badan Standarisasi Nasional. (2002). SNI 03-2847-2002
Persyaratan Beton Struktural Untuk Bangunan Gedung. Jakarta.
Badan Standarisasi Nasional. (2013). SNI 2847-2013 Persyaratan
Beton Struktural Untuk Bangunan Gedung. Jakarta.
Ervianto, Wulfram I. (2002). Manajemen Proyek Konstruksi. Yogyakarta: Graha
Ilmu
Istimawan, Dipohusodo. (1996). Manajemen Proyek dan Konstruksi.
Yogyakarta: Penertbit Kanisius.
Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Republik
Indonesia. (2016). Pedoman Analisis Harga Satuan Pekerjaan Bidang
Pekerjaan Umum, PRT. No. 28 Tahun 2016. Jakarta
Wiryanto Wordpress. 2010. “Metode Pelaksanaan Konstruksi Bangunan
Gedung 2”.http://www.scribd.com/doc/39907301/Metoda-Pelaksanaan-
KonstruksiBangunan-Gedung-2.