  • 7/31/2019 TKR 14 - Cargo Equipment Status

    1/13

    FLEET MANAGEMENT LIMITED

    CARGO EQUIPMENT STATUS

    VESSELS NAME: MT DATE:

    1. TANK CLEANING MACHINES

    A.

    FIXED:

    MAKE:

    TYPE: NOZ DIA: JET LENGTH:

    NUMBERS:

    STATUS:

    B.

    PORTABLE:

    MAKE:

    TYPE:

    NUMBERS:

    STATUS:

    C.

    PORTABLE HOSES & SADDLES ON BOARD:

    LENGTH:

    NUMBERS:

    RECORD OF CONTINUITY MAINTAINED:

    STATUS:

    2. CARGO HEATING SYSTEM

    DATE LAST PRESS TESTED:

    DATE LAST HEATED CARGO CARRIED:

    MATERIAL:

    HEATING RATIO: SURFACE AREA/VOLUME:

    STATUS:

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    2/13

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    3/13

    5. BALLAST PUMPS

    NUMBERS:

    TYPE:

    MAKE:

    CAPACITY:

    STATUS:

    6. TANK CLEANING PUMPS

    NUMBERS:

    TYPE:

    CAPACITY:

    STATUS:

    7. CARGO PIPELINES / MANIFOLD

    MATERIAL:

    LAST PRESSURE TESTED:

    STATUS:

    PRESSURE GAUGE FITTED OUTBOARD OF MANIFOLD:

    8. BUTTERWORTH HEATER

    MAKE:

    TYPE:

    CAPACITY:

    MAX TEMP RISE AT RATED CAPACITY:

    DATE LAST CLEANED:

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    4/13

    9. PORTABLE TANK GAUGES

    NUMBER OF MMC TAPE:

    TYPE:

    MAKE:

    STATUS:

    NUMBER OF CARGO SAMPLER:

    TYPE:

    MAKE:STATUS:

    VAPOUR LOCKS FOR PORTABLE GAUGES:

    MAKE:

    10. CARGO TANKS HIGH LEVEL & OVERFILL ALARM

    TYPE:

    MAKE:

    STATUS:

    SETTING (AT WHAT LEVEL):

    11. CARGO TANKS LEVEL & TEMPERATURE GAUGE

    TYPE:

    MAKE:

    STATUS:

    12. CARGO TANKS GAS FREEING SYSTEM

    A.

    FIXED:

    MAKE:

    CAPACITY:STATUS:TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    5/13

    B.

    PORTABLE:

    MAKE:

    TYPE:

    NUMBERS:

    CAPACITY:

    STATUS:

    13. PORTABLE PUMPS ON BOARD

    TYPE:

    NUMBER:

    MAKE:

    CAPACITY:

    STATUS:

    DATE WHEN LAST TRIED OUT:

    14.OIL DISCHARGE MONITOR

    TYPE:

    MAKE:

    STATUS:

    16. GAS MEASURING INSTRUMENTS

    A.

    OXYGEN METERS:

    NUMBERS:

    TYPE:

    MAKE:

    SERIAL NUMBERS:

    LAST CALIBRATED: SHORE: SHIP:

    STATUS:

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    6/13

    B.

    COMBUSTIBLE GAS DETECTORS:

    NUMBERS:

    TYPE:

    MAKE:

    SERIAL NUMBERS:

    LAST CALIBRATED: SHORE: SHIP:

    STATUS:

    C.

    TOXIC GAS DETECTORS:

    NUMBERS:

    TYPE:

    MAKE:

    SERIAL NUMBERS:

    STATUS:

    17. CHEMICAL SPRAY PUMP

    NUMBERS:

    TYPE:

    MAKE:

    STATUS:

    18. PNEUMATIC LIGHTS

    NUMBERS:

    MAKE:

    STATUS:

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    7/13

    19. LOADICATOR

    TYPE:

    MAKE:

    STATUS:

    20. WALKIE TALKIE AVAILABLE FOR CARGO OPERATIONS

    MAKE:

    TYPE:

    NUMBERS:

    STATUS:

    21. CARGO TANK OPENINGS WATER TIGHTNESS

    ACCESS HATCHES & BUTTERWORTH POCKETS

    STATUS:

    REMARKS:

    22. CHEMICALS ON BOARD FOR TANK WASHING

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    8/13

    23. OTHER EQUIPMENT ON BOARD

    A.

    CARGO HOSES:

    NUMBERS:

    MANUFACTURERS CERTIFICATE:

    CERTIFICATES:

    MAX SAFE WORKING PRESSURE:

    LAST PRESSURE TESTED: DATE: PRESS:

    TYPE:

    TYPE:

    TYPE:TYPE:

    B.

    REDUCERS:

    SIZES:

    NUMBERS:

    MATERIAL:

    C.

    U PIECES:

    SIZES:

    NUMBERS:

    MATERIAL:

    D.

    Y PIECES:

    SIZES:

    NUMBERS:

    MATERIAL:

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    9/13

    24. PIPE LINES

    STATUS & GENERAL CONDITION

    CARGO

    HYDRAULIC

    TANK

    CLEANING

    BUNKER

    STEAM

    FIRE

    25. PROTECTIVE CLOTHING

    NUMBERS STATUS & GENERAL CONDITION

    CLOTHES

    GLOVES

    BOOTS

    PROTECTIVE

    MASK

    CANISTER

    CHEMICAL

    CARTRIDGE

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    10/13

    26. MISCELLANEOUS

    NUMBERS STATUS & GENERAL CONDITION

    STEAMING HOSE

    DUCTS FOR GAS

    FREEING

    NON-SPARKING

    TOOLS

    *To be sent to office every three months on 31stMarch, 30thJune, 30thSeptember,

    31st December and to be attached with Chief Officers handling / taking over

    report.

    Master CHIEF OFFICER

    TKR-14 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    11/13

    FLEET MANAGEMENT LIMITED

    INSPECTION REPORT OF PORTABLE

    CARGO PUMP

    M.T. ___________________________________CARGO NAME _______________________________

    VOY. NO. _______________________________ TANK NO. __________________________________

    DATE OF DISCH. _________________________QUANTITY _______________________________M/T

    PORT OF DISCH. _________________________ RATE OF DISCH. _______________________MT/H

    CHIEFOFFICER___________________________ MASTER __________________________________

    Inspection before operation (Condition has to be inspected in ample time advance)

    No Detail of Inspection Result of Inspection

    1

    2

    3

    4

    5

    Have you reported to Company why you must useportable pump?

    Are the Hydraulic Oil pump, pipe line system, couplingof Hydraulic Oil hoses and valves in sound condition?(The hydraulic oil hose should be actually tested incase of long time kept unless use).

    Are the Hydraulic Oil hose, coupling of hose and nut insound condition? (If any damage are found, should berepaired without fail).

    Are the cargo hose, which intended to use in normalcondition?

    Is the pump condition normal?

    Has visual inspection being done for hydraulicoil hose, connection coupling flange of cargo

    hose, any contamination of pump and foreignmatters in pump impeller?

    Has the plug of the cofferdam shaft sealopened and checked any inflow of driving oil orcargo?

    If any leak is found, measure the quantity andrecheck after test running which is necessary whenbig quantity is found. After inspection is done, theplug with seal tape is secured without fail.

    ** How much the leaked quantity** What kind of liquid.

    TKR-15 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    12/13

    6

    7

    8

    Is the portable lifting gear normal condition?(Check the condition of wire, hook by actual lifting test)

    Has the hydraulic oil lines been connected properly ?(you must observe instruction manual)The return hose must be connected first and then thehigh-pressure hose has to be connected. Open themain valve by inches. Caution if hoses are connectedin inverse way, this is one of the causes of pumpdamage. If there is some air in hose at first stage, airdischarge is necessary.

    Has the pump running test been done?

    Pump testing:Put a blind flange on outlet of pump and put the pumpbody into half sized drum with water and try the test.Caution if pump is running dry, the shaft seal oncargo side might be damaged by overheat.During pump testing, put a blind on the cargo hoseoutlet, then pressure test of the cargo hose can alsobe done.

    Confirm whether any leak, deformation ofhydraulic line, hose and connection parts

    (especially, connection part of high pressurehose).

    Confirm whether any leak, deformation, etc. oncargo hose.

    Confirm whether any leak, deformation onpump body.

    Is there any leak from shaft seal of pump incofferdam? If any abnormal leak is found, try touse other pump or renewed the shaft seal.

    Is the hydraulic oil pressure normal? (See

    instruction manual). The hydraulic pressure willbe indicated about 60-80 kg/cm2 during closerunning test and make sure that the hydraulicoil pressure can be adjusted by Flow ControlValve.

    If ship has the equipment for measuring ofdelivery pressure, then confirm whetherpressure is normal or not (under the normalRPM of pump, the delivery pressure will beindicated about 9 kg/cm2)

    TKR-15 REV 0/ 10-02

  • 7/31/2019 TKR 14 - Cargo Equipment Status

    13/13

    9

    10

    11

    12

    13

    14

    15

    16

    17

    If any air remains in cargo hose, pressure will bevariable and hard to get exact pressure.And if output pressure is lower than normal, theimpeller and mouth ring have to be checked by

    engineers. After complete the running test, all the water in the

    pump hose must be drained out before use ofcargo.

    Cargo pump can be dipped into cargo but hydraulic oilhose should be remained above cargo level because itis necessary to check any leak from these hosesduring cargo operation?

    Have you maintained the continuous monitoring to

    adjust pump position and find any problems?

    Do you consider to prevent spark by bump into pumpbody and the structures inside the tank.

    Do you consider and monitor against the unexpecteddamage on cargo hose, hydraulic oil hose and line.(Especially leaking of hydraulic oil)

    AFTER OPERATIONAre hydraulic oil hose and cargo hose in normalcondition?

    Is cargo pump in normal condition?How much is the leaked quantity of hydraulic oil orcargo in cofferdam?

    Has the disconnection procedure been done as perthe instruction? Caution (Return hose should bedisconnected at last)

    Have the proper cleaning of cargo pump, cargo hoseand hydraulic oil hose been done?

    Are the cargo hose, pump and hydraulic oil hosestowed properly?If hydraulic hose is stowed with big bend, it is liable toget damaged because the material is thiokol rubber.Cover the hose and pump to prevent any foreignmatters.

    Above check list to be filled every 6 months when the pump is being tried out.TKR-15 REV 0/ 10-02