to acquire theory on open channel flow
TRANSCRIPT
EAH 225 HYDRAULICSEAH 225 HYDRAULICS
Prof. Dr. Aminuddin Ab Ghani
Open Channel FlowOpen Channel Flow
OBE TOPIC OUTCOMES
To acquire theory on open channel flow To apply relevant equations to compute flow in open channelsin open channels To determine required size of channel
(Ch l D i )(Channel Design) To acquire theory on sediment transport in
rivers To apply relevant equations to computeTo apply relevant equations to compute
sediment discharge in rivers
ContentsContentsContentsContents
Introduction Existing Drainage System Channel Design Flow Modelling
References
SI Edition
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
Introduction
O h l fl i th fl f t i d it
DEFINITIONS
Open channel flow is the flow of water in a conduit with a free surface at atmospheric pressure The flow in an open channel is mainly governed by gravity (i.e. channel bed slope)
Menam Chao Praya, Bangkok Kulim River, Serdang
Artificial or Man made Channels (e g swales)OPEN CHANNEL CLASSIFICATION
Artificial or Man-made Channels (e.g. swales)vs. Natural Channels (e.g. rivers)
River
Swale
Rigid Boundary Channels: Channels withOPEN CHANNEL CLASSIFICATION
Rigid Boundary Channels: Channels with immovable bed and sides (e.g. concrete drains)
Irrigation channel
Stormwater drain
Mobile Boundary Channels: ChannelOPEN CHANNEL CLASSIFICATION
Mobile Boundary Channels: Channel boundary is composed of loose sedimentary particles moving under the action of flowing water (e.g. rivers) Bed Erosiong
Bank Erosion
Deposition
Water Level and Flow DischargeWater Level and Flow Discharge
Water Level and Flow Discharge
• Open channel flows are found in large and small
Water Level and Flow Discharge
p gscale.
• For example the flow depth can vary between ayfew cm in water treatment plants and over 10 min large rivers.
• The mean velocity of flow may range from lessthan 0.01 m/s in tranquil waters to above 50 m/si hi h h d illin high-head spillways.
• The range of total discharges may extend from0 001 l/ i h i l l t t t th0.001 l/s in chemical plants to greater than10000 m3/s in large rivers or spillways.
Sungai Muda
Jambatan Ladang Victoria
Peak Flood Discharge - Sungai Muda’s 2003 Flood
2003 Hydrograph @ Ldg Victoria
(6 October 2003)
y g p @ g
1200
1300
1400
Q = 1340m3/s
800
900
1000
1100
m3 /s
)
500
600
700
800
Dis
char
ge, Q
(m
200
300
400
500D
0
100
0 1000 2000 3000 4000 5000 6000 7000 8000
HourHour
Jan Feb Mac Apr May Jun Jul Aug Sep Oct Nov Dec
Maximum Water Level (06.10.2003 @ 1600Hrs)
Flood plain
Flood plain
Main Channel Inundation depths in theMain Channel Inundation depths in the flood plains = 1 – 2 m
Flood Inundation AreasSungai Muda’s 2003 FloodSungai Muda’s 2003 Flood
Ladang Victoria Station
Sungai Pahang
Temerloh
Peak Flood Discharge - Sungai Pahang’s 2007 Flood
6000
2007 Hydrograph @ Temerloh
(14 December 2007)
5000
5500
6000
14/12/2007 (6.00 pm)(Q = 5397 55 m3/s)
3500
4000
4500
(m3 /s
)
(Q = 5397.55 m /s)
2000
2500
3000
Dis
char
ge, Q
(
1000
1500
2000
0
500
0 1000 2000 3000 4000 5000 6000 7000 8000
Hour
Jan Feb Mac Apr May Jun Jul Aug Sep Oct Nov Dec
2007 Sungai Pahang FloodEsplanade TemerlohEsplanade, Temerloh
20072007
2010
Sungai Pahang
Pekan
2007 Sungai Pahang Flood2007 Sungai Pahang Floodg gg g
2007 Sungai Pahang Flood2007 Sungai Pahang Flood2007 Sungai Pahang Flood2007 Sungai Pahang Flood
2007 Sungai Pahang Flood2007 Sungai Pahang Flood2007 Sungai Pahang Flood2007 Sungai Pahang Flood
2007 Sungai Pahang Flood2007 Sungai Pahang Floodg gg g
UNIFORM AND VARIED FLOWS
Uniform flow: If the flow depth (and thus the average velocity) remains constantremains constant.Uniform flow conditions are commonly encountered in practice in long straight sections of channels with constant slope, constant roughness, and constant cross section.The flow depth in uniform flow is called the normal depth yn,
hi h i i t t h t i ti t f h lwhich is an important characteristic parameter for open-channel flows.
Non niform or Varied flo : The flo depth aries ith distanceNonuniform or Varied flow: The flow depth varies with distance in the flow direction.
FLOW CLASSIFICATION BY DEPTH VARIATION
Reservoir
GVF – Gradually Varying Flow Sungai KurauGVF Gradually Varying Flow
RVF – Rapidly Varying Flow
TYPICAL CROSS SECTIONS
Values showing isovelocity contours
Parameters for Open Channel FlowParameters for Open Channel FlowParameters for Open Channel FlowParameters for Open Channel Flow
V = Average Velocity y = Flow depth
S = Channel bed slope A = Flow area
P = Wetted Perimeter R = Hydraulic Radius
SIDE VIEW CROSS SECTION
Geometric Properties Necessary For Analysisp y y
FLOW CLASSIFICATION BY FROUDE NUMBER, Fr
For any type of channel :For any type of channel :
Fr = Q2 Bg A3
Fr <g A
1.0 Subcritical Flow
Fr =
Fr >
1.0 Critical Flow
1.0 Supercritical Flowr p
For rectangular channel : VFr = gyo
Velocity Distribution In A ChannelVelocity Distribution In A Channel
Depth-averaged velocity is aboveDepth averaged velocity is above the bed at about 0.4 times the depth
Flow Velocity MeasurementFlow Velocity Measurement
Current Meter & Data Logger
Electromagnetic Current Meter
Flow MeasurementFlow MeasurementSungai Kulim SerdangSungai Kulim SerdangSungai Kulim, SerdangSungai Kulim, Serdang
Velocity = 0.18 m/s
Water Surface Slope, SoWater Surface Slope, So
Electronic Digital Measurement (EDM)
Distance = 100 Distance = 100 –– 250 m250 m
COMPOUND CHANNEL
Flood plainFl d l i
pFlood plain
Main ChannelMain Channel
Natural river during “normal” flow conditions
COMPOUND CHANNEL
Natural river during flood! (Floodplain Inundation)
COMPOUND CHANNEL
Flood Plain Flood PlainMain Channel
A1, n1 A3, n3
P P
A2, n2
P1 P3
• The roughness of the flood plains will be different (generally rougher) than
P2
that of the main channel
Q = A1
n1R1
2/3 +A2
n2R2
2/3 +A3
n3R3
2/3 So 1/2
1 2 3
Determination of Bankfull Width for Natural River
Flow Rating Curve
ENERGY COMPONENTS
ENERGY GRADEhf2gV2
ENERGY GRADE LINE (EGL)
WATER SURFACEH
f
yo
2g
WATER SURFACE
CHANNEL BED
H1
H2
yo
CHANNEL BED
DATUMZ
H = + yo + 2gV2
Z
Velocity Head
Conservation of Energy : H1 = H2 + hf ; hf = Frictional loss
SPECIFIC ENERGY
Specific Energy, Es = the height of the energy line (EGL) above the channel bottom: V2
Es = Y0 + 2g
Critical flow occur at minimum energy, Es min
yc = Q2
2
1/3
=q2 1/3
yc gB2 = g
Flow Classification:
> V < V S bcritical (F < 1)yo > yc , V < Vc : Subcritical (Fr < 1)
y = y , V = V : Critical (F = 1)yo yc , V Vc : Critical (Fr 1)
yo < yc , V > Vc : Supercritical (Fr > 1)
Energ Dissipator H dra lic J mpEnergy Dissipator: Hydraulic Jump
Energy Dissipator: Hydraulic JumpEnergy Dissipator: Hydraulic Jump
Classification of Hydraulic Jumps
Undular Jump
W k JWeak Jump
Oscillating Jump
Steady Jump
St JStrong Jump
GVF: Energy Balance
Water Surface Curves for GVF
Water Surface Profiles
Flow Modelling
http://www.hec.usace.army.mil/software/hec-ras/p y
Existing Drainage System
Rigid Boundary ChannelRigid Boundary Channel
Rigid Boundary ChannelRigid Boundary Channel(D P i d)(D P i d)(Dry Period)(Dry Period)
Rigid Boundary ChannelRigid Boundary ChannelTrunk Drain During Dry Period
Rigid Boundary ChannelRigid Boundary ChannelWet PeriodWet Period
Rigid Boundary ChannelRigid Boundary ChannelTrunk Drain - Wet Period
Feasibility Study On Drainage Improvement in Prai Industrial Complex Seberang Perai Tengah PenangIndustrial Complex, Seberang Perai Tengah, Penang
Study Area
Existing Primary Drains
Pump
Legend:P i D i
Pump House A
PumpPrimary DrainExisting Pump StationRailway
Pump House B
Existing Primary Drains
Pump
Legend:P i D i
Pump House A
PumpPrimary DrainExisting Pump StationRailway
Pump House B
Existing Trunk Drains
Legend:
Pump House A
Legend:Primary DrainExisting Pump StationRailway
Pump House B
Existing Trunk Drains
B-2EL-6B Rubber Pitching :Rubber Pitching :T Width 30’ 46’Top Width = 30’ - 46’
Depth = 5’ – 13’
T-6E Rectangular :Rectangular :Width = 5’ – 8’
Legend:
Pump House A Depth = 16’
Legend:Primary DrainExisting Pump StationRailway
Pump House B J-2A
Feasibility Study and Detail Design of Flood Mitigation and Drainage Improvement in Taman Sentul Tamanand Drainage Improvement in Taman Sentul, Taman Sentul Jaya, Taman Pinang & Taman Mangga, Juru,
S.P.T, Penang, g
Utara
Tol Juru
ra
Study Area
Lebuhraya Utara-Selatan
Taman Sentul Jaya Area
Parit
Kawasan Perusaha
an
JayaTama
n Sentul
TNo. 5
Perkampungan Juru
Ringan
Taman
M
Taman
Pinang
Mangga
Precast Concrete Drain900mm
Precast Concrete Drain1200mm
Precast Concrete Covered Drain
1200mm1200mm
Precast ConcreteConcrete
Drain3000mm3000mm
Feasibility Study of Flood Mitigation and Drainage Improvement in Kampung Tersusun Juru SeberangImprovement in Kampung Tersusun, Juru, Seberang
Perai Tengah, PenangStudy AreaStudy Area
Secondary Drain
Primary Drain Trunk Drain
Flow sequence from
Natural WaterwaySungai Juru
sequence from drain to river
Parit No. 5
Sediment Transport in RiversSediment Transport in Rivers
Point Bar
Bed form
Sg Jelai, Batu Kurau
Sediment Transport in RiversSediment Transport in Rivers
Bed formBed form
Sediment Rating Curve for Dengkil Reach,Sediment Rating Curve for Dengkil Reach,Sungai LangatSungai Langat
100
Sungai LangatSungai Langat
For Q = 50 m3/s, Tj = 20 kg/s
10
T j(K
g/s)
1teria
l Loa
d, T
DengkilJ d
Tota
l Bed
Mat Jemderam
Jalan Tangkas
Kg Dusun Nanding
Jambatan Bt 14 Cheras
Jambatan Kg Rinching, Semenyih
0.11 10 100 1000
T
Discharge, Q (m3/s)g ( )
Sediment Transporting Capacity for a River
Sediment Rating Curves for Sungai Muda, Sediment Rating Curves for Sungai Muda, Sungai Kurau and Sungai LangatSungai Kurau and Sungai Langat
10000
Sungai Kurau and Sungai LangatSungai Kurau and Sungai Langat
1000
10000
/s)
100
Load
, Tj
(Kg/
1
10
Bed
Mat
eria
l L
0.1
Tota
l B
Sungai MudaSungai langatSungai Kurau
0.011 10 100 1000 10000
Discharge, Q (m3/s)
Comparison of Sediment Transporting Capacity Curves
Sediment Transport in RiversSediment Transport in Rivers
Meandering River: Sg Pahang atTemerloh
M d i A RiMeandering Amazon River
Deposited Sands at Sg Pahang River MouthDeposited Sands at Sg Pahang River Mouth
Obstructed river mouthObstructed river mouth
Sg Pahang, Pekan
Sand Depositionp
Sand Dredging
Scour at Bridge Piers
Kuala Muda BridgeKuala Muda Bridge
Channel Design
Design Objectives
The hydraulic design of anh l i fopen channel consists of
determining the dimensions ofdetermining the dimensions ofa channel section to carry thedesign discharge under thecontrolling conditionscontrolling conditions
UNIFORM FLOWFlow in a channel is called uniform flow if the flow depth (and thus theaverage flow velocity remains constant. Uniform flow conditions arecommonly encountered in practice in long straight runs of channels withy p g gconstant slope, constant cross section, and constant surface lining.
yThe flow depth in uniform flow is called the normal depth yn, and theaverage flow velocity is called the uniform-flow velocity V0.
Computations In Uniform FlowComputations In Uniform Flow
Two calculations are usually performed to l if fl blsolve uniform flow problems:
- Discharge from a given depth
- Depth for a given discharge- Depth for a given discharge
Manning’s EquationManning’s EquationManning's formula is normally used for steadyuniform flow:
21
321 SRV 231 SRnV
M i ’ h ffi in = Manning’s roughness coefficient
Computations In Uniform FlowComputations In Uniform Flow
• It is desirable to limit the design flow• It is desirable to limit the design flow Froude number (Fr) such that it is less h 0 86 h 1 13 dthan 0.86 or greater than 1.13 due to
the formation of the undular surface waves near critical depth (Fr = 1.0)
Computations In Uniform FlowComputations In Uniform Flow
• Specification of freeboard is needed to• Specification of freeboard is needed to allow for uncertainties in estimation of h l h (M i ’ ) dchannel roughness (Manning’s n) due
to accumulation of debris and aquatic qgrowth in the channel.
Computations In Uniform FlowComputations In Uniform Flow
Values of Freeboard for EngineeredValues of Freeboard for Engineered Waterway (Channel width > 1m):
Rectangular Channel = 0.3 - 0.6 m Trapezoidal Channel = 0 3 0 8 m Trapezoidal Channel = 0.3 – 0.8 m Earth Channel = 0.3 – 0.9 m
V l f F b d f ll d iValues of Freeboard for small open drain (Channel width ≤ 1m): 50 mm
MANUAL SALIRANMANUAL SALIRAN MESRA ALAM (MSMA)MESRA ALAM (MSMA) (JPS, 2000)( , )
Open Drains Volume 10 (Chapter 26)
Cross Section for Open Drain
0.5 m
Drainage Reserve
0.5 m Design flow width + freeboardgmin min
(a) Grassed Swale
Drainage Reserve
1.5 m minimum 1.0 m
Drainage Reserve
(b) Lined Open Drain
Manning’s Roughness Coefficient, nManning s Roughness Coefficient, n (Design Chart 26.1)
Surface Cover or Finish Suggested n values
Minimum Maximum
ConcreteConcrete
Trowelled finish 0.011 0.015
Off form finish 0.013 0.018Off form finish 0.013 0.018
Stone Pitching
Dressed stone in mortar 0 015 0 017Dressed stone in mortar 0.015 0.017
Random stones in mortar or rubble masonry 0.020 0.035
Rock Riprap 0.025 0.030
Brickwork 0 012 0 018Brickwork 0.012 0.018
Precast Masonry Blockwork 0.012 0.015
Solution to Manning Equation for Lined Open Drains
10
0.9
8
9
501 1
504
14
1
Swale reserve width, R (m)( including required freeboard )
y
0.8
0.7
5
6
7 Base width, B (m)
3
0.6
4
, QD
(m3 /s
)
Base width, B (m)
Flow depth, y (m)
1
2
Swale reserve width, R (m)( including required freeboard )
y
z1
z1
'Vee' shaped Section
3
4
5
1 2
0.5
3
Des
ign
Flow
,
Use 'vee' shaped section
0.5
Q n
S 01/
2
Z = 5.5
Z = 6
0.42
1.5 0.1
Valu
e of
Q S
Z = 5
Z = 4.5
Z = 4
1
1 5
0.3
2 3 41.5
0.05
Longitudinal Grade, S0 (%)
0.01
0.1 0.90.5
Flow Depth, y (m)
0.2 0.3 0.4 0.6 0.7 0.8
0.005
0.15
Lined Drains Volume 10 (Chapter 26.3)
Uncovered Open Lined DrainUncovered Open Lined Drain (Minor System – Chap. 26)( y p )
Drainage Reserve Width
B = 0.5 – 1.0 m 1.5 m minimum1.0 m
g
H max = 0.5 m50 mm
C d O Li d D iCovered Open Lined Drain (Minor System – Chap. 26)(Minor System Chap. 26)
Drainage Reserve Width
B = 0.5 – 1.0 m 1.5 m minimum1.0 m
g
H = 0.5 m – 1.0 m
Cover 50 mm
V l it Li it tiVelocity Limitation (Minor System – Chap. 26.3.6)
T t di t ti d t ti th
(Minor System Chap. 26.3.6)
To prevent sedimentation and vegetative growth
Min Average Flow Velocity = 0 6 m/sMin Average Flow Velocity 0.6 m/s
To prevent Channel Surface ErosionTo prevent Channel Surface Erosion
Max Average Flow Velocity = 4.0 m/sMax Average Flow Velocity 4.0 m/s
Note: Average Flow Velocity > 2.0 m/s, drain provided with a handrail fence, or covered with solid or grated cover
Composite Drains Volume 10 (Chapter 26.4)
G d S ti
Recommended Composite Drain
C
Q50 mm freeboard
Grassed Section
14 i
Qminor
4 i1
4 min4 min
Lined drain
Design flow width + freeboard
Lined drain
Design flow width + freeboard
• Provided in locations subject to dry-weather base flows which wouldotherwise damage the invert of a grassed swale, or in areas with highlyerodible soils.
•The lined drain section is provided at the drain invert to carry dry-weatherbase flows and minor flows up to a recommended limit of 50% of the 1 monthARI.
Grassed Swale Volume 10 (Chapter 26.2)
Constructed Swale
gluttons
Filter layer
storagegeotextiile
drain
Bio-Ecological Drainage System(BIOECODS)
Perimeter SwalePerimeter Swale
Type Type AA
Type BType B Type CType C
Recommended Swale Cross-Sections
Freeboard (Mi S t Ch 26 2 4)(Minor System – Chap. 26.2.4)
Min freeboard of 50 mm above the design stormwater level
Velocity Limitation (Mi S Ch 26 2 5)(Minor System – Chap. 26.2.5)
Max Average Flow Velocity < 2.0 m/sg y
Manning’s Roughness Coefficient, n Design Chart 26.1
Surface Cover or Finish Suggested n valuesSurface Cover or Finish Suggested n values
Minimum Maximum
Grassed Swales
Short grass cover 0.030 0.035
Tall grass cover 0.035 0.050
Engineered WaterwaysVolume 11 (Chapter 28)
(Major System)(Major System)
Engineered WaterwaysEngineered Waterways
Drainage Reserve Width
W VariesVaries
g
H300 mm
Minimum Longitudinal Slopeg p
0.2 % - Lined Channel0.5 % - Grassed floodways and natural waterway
To prevent sedimentation and vegetative growth
Min Velocity = 0.8 m/s
T t Ch l S f Li i E iTo prevent Channel Surface Lining Erosion
Max Velocity = 4 0 m/s (Li d Ch l / L fl i t)Max Velocity = 4.0 m/s (Lined Channel / Low flow invert)
= 2.0 m/s (Floodways and Natural Waterway)
Suggested Values of Manning’s Suggested Values of Manning’s Roughness Coefficient, Roughness Coefficient, nn
Surface CoverSuggested n values
Minimum Maximum
Grassed FloodwaysGrass cover only
Short grass 0.030 0.035Short grass 0.030 0.035
Tall grass 0.035 0.050
Shrub cover
Scattered 0.050 0.070
Medium to dense 0.100 0.160
Tree cover
Scattered 0.040 0.050
Medium to dense 0.100 0.120
Suggested Values of Manning’s Suggested Values of Manning’s Roughness Coefficient, Roughness Coefficient, nn
Surface Cover Suggested n values
Minimum Maximum
Natural Channels
S ll tSmall streams
Straight, uniform and clean 0.025 0.033
Clean, winding with some pools and shoals 0.035 0.045
Sluggish weedy reaches with deep pools 0.050 0.080
Steep mountain streams with gravel, cobbles, and boulders 0.030 0.070
Large streams
Regular cross-section with no boulders or brush 0.025 0.060
Irregular and rough cross-section 0.035 0.100
Overbank flow areas
Short pasture grass, no brush 0.025 0.035
Long pasture grass, no brush 0.030 0.050
Light brush and trees 0 040 0 080Light brush and trees 0.040 0.080
Medium to dense brush 0.070 0.160
Dense growth of trees 0.110 0.200
Suggested Values of Manning’s Suggested Values of Manning’s Roughness Coefficient, Roughness Coefficient, nn
S f CSuggested n values
Surface CoverMinimum Maximum
Lined Channels and Low Flow InvertsConcrete
Trowelled finish 0.011 0.015
Off form finish 0.013 0.018
Shotcrete
Trowelled, not wavy 0.016 0.023
T ll d 0 018 0 025Trowelled, wavy 0.018 0.025
Unfinished 0.020 0.025
Stone Pitching
Dressed stone in mortar 0.015 0.017
Random stones in mortar or rubble masonry 0.020 0.035
Rock Riprap 0 025 0 030Rock Riprap 0.025 0.030
Suggested Values of Manning’s Suggested Values of Manning’s Roughness Coefficient, Roughness Coefficient, nn
Surface CoverSuggested n values
Minimum MaximumMinimum Maximum
RoadwaysKerb & Gutter 0.011 0.015
Hotmix Pavement
Smooth 0.012 0.014
Rough 0 015 0 017Rough 0.015 0.017
Flush Seal Pavement
7 mm stone 0.017 0.019
14 mm stone 0.020 0.024
I. Composite WaterwaysI. Composite Waterways(With Increased Capacity - Chap 28)
Estimate the Overall Roughness Coefficient
m An 3/5
Coefficient
m
i
i i
ii
*
AP
An
n3/5
13/2
/
(28.1)
i i
i
PA
13/2
where,n* = equivalent Manning’s roughness coefficient for the whole
cross-sectionni = Manning's roughness coefficient for segment iAi = flow area of segment i (m2)P = wetted perimeter of segment i (m)m = total number of segments
II. Natural WaterwaysII. Natural Waterways
Minimum Longitudinal Slope0.5 %
To prevent Channel Erosion
M V l i 2 0 /Max Velocity = 2.0 m/s
oror
Critical Velocity y
V l it Li it tiVelocity Limitation (Major System - Chap 28)(Major System Chap 28)
Minimum Longitudinal SlopeMinimum Longitudinal Slope0.5 %
To prevent Channel Erosion
M V l i 2 0 /Max Velocity = 2.0 m/s
oror
Critical Velocity y
Critical Velocities, (m/s) for various conduit materialsvarious conduit materials
III. Grassed FloodwaysIII. Grassed Floodways
6
1
6
1
C Low FlowProvision
6 61
50501
Batter BatterBase
Figure 28.3 Typical Grassed Floodway Cross-SectionC Terracing
Qmajor
Qminor
C Terracing
161
5050
BatterTerrace Base
Figure 28.4 Typical Grassed Floodway Terracing
Low Flow Provision:Low Flow Provision:Minimum capacity of 50% of the 1 month ARI flow.
1.2
1.3
Design ChartDesign Chart
1.1
1.0
0.9Design Chart Design Chart 28.228.2 0.8
7
Flow
, (m
3 /s)
5055
60
4045
1.4
1.5
1.6
0.7
Floodway Base Width –Preliminary Estimate(Manning's n = 0.035,
A i 2 / )
Des
ign
F
2025
3035
4
Average Velocity = 2 m/s)15
10
5
Flow Modelling
HEC-RAS Modellingg
Sungai Muda Model Set-up
Cross Section at CH 41.2 (Ladang Victoria)(Ladang Victoria)
Longitudinal Flood Profile for Sg Muda (Q=1340m3/s) (Q=1340m3/s)
dge
Mud
a B
arra
ge
Mer
deka
B
ridg
eE
xpre
ssw
ay
Bri
dge
Rai
lway
Bri
dge B
rid
Pipe
Bri
dge
M M B E B
What Is a Bund?What Is a Bund?• The U.S. Federal Emergency Management Agency (FEMA)
defines a bund or levee as a “man-made structure, usually anearthen embankment, designed and constructed in accordancewith sound engineering practices to contain, control, or divert theflow of water so as to provide protection from temporaryflooding.”
Determination of Bund Height from Inundation Depth
Flood plainFlood plain
Main ChannelMain Channel
BUND DESIGN AND CONSTRUCTION
Bund Height = 3 m (Freeboard = 1 m)
BUND DESIGN AND CONSTRUCTION
Bund Height = 3 m (Freeboard = 1 m)
BUND DESIGN AND CONSTRUCTION
Bund Height = 3 m (Freeboard = 1 m)
BUND CONSTRUCTION AT LAHAR TIANG 2B (HULU)
BUND CONSTRUCTION AT PANTAI KAMLOON 2B (HULU)