BOYERTOWN AREA SCHOOL DISTRICT
ADDITIONS & RENOVATIONS
To
BOYERTOWN AREA SENIOR HIGH SCHOOL
MONTHLY PROGRESS REPORT No. 11
January 2016
Construction Manager Architect
D’Huy Engineering, Inc. KCBA Architects
View of New Cub Gymnasium & Gymnasium Main Entrance
From
Student Parking
TABLE OF CONTENTS 1. Brief Summary of Each Prime Contractor Over The Last Month
2. Project Status Summary
3. Total Project Budget Summary Through January 2016
4. Construction Contract Summary By Phase & Allowance Expenditures Through January 2016
5. Community Involvement
Brief Summary
The General Contractor (GC), E.R. Stuebner: The GC has completed 95% of all Phase 2 & 3 shop drawing and product submittals to the Design Team for review and approval. Site work on the infiltration basins has completed with the exception of top soil and seed. The new Cub Gym concrete curbs, sidewalk, steps and entrance plaza are complete. Concrete sidewalk surrounding the additions will
resume in warmer weather. The new loading dock and railings are 90%complete, cold weather has prevented the final concrete placement for the loading dock drive.
Phase 1 construction is complete with the exception of punch list items. All of Phase 1 areas have been turned over to BASD and are occupied. This includes the new Cub Gym & Lobby as well as the new Art Wing Classrooms.
The new Stair Tower #6 in the old Cub Gym Lobby is 95% complete with terrazzo treads now set. This stair tower complete with handrails is being used by students to access the New Ceramics Studio from the 500’s Classroom Corridor.
The new Cub Gym roofing is complete and 40% of the entire building roof is complete with the exception of the metal roof edge. Area ‘K’ (Life Skills & Consumer Sciences) roof membrane is complete with the exception of stone and flood coat which is planned to be installed as weather permits. All Roof areas are water tight.
Phase two of the project includes the new bus loop and the resurfacing of the tennis courts. This along with the interior work is scheduled to complete in its entirety in August of this year is currently underway. The interior work consists of the complete renovation of the old three story Area ‘A’, constructing the new music suite, renovating the locker rooms, wrestling room, training and team room areas as well as renovating 17 classrooms.
General demolition in the Phase 2 Cub Gym Boys and Girls locker room is 98% complete. New masonry wall construction for the Phase 2 Instrument Storage, Keyboard Lab, Custodial and IDF Room is 95% complete. Selective demolition in the old three story Area ‘A’ is currently underway on all floors.
The Mechanical Contractor (MC), Worth & Company: The MC has completed 95% of all Phase 2 & 3 shop drawing and product submittals to the Design Team for review and approval. HVAC piping installation in the pipe tunnels is 100% complete. Final testing & balancing and final commissioning for the Phase 1 heating, air conditioning & ventilation 98% complete. Final Balancing and
commissioning cannot occur until the entire building mechanical system is complete August/September 2017. The new chillers have been installed and piping continues. Mechanical demolition of the Phase 2 Boys and Girls Locker Room is 100% complete and mechanical systems installation is underway. Selective mechanical demolition in the old three story Area ‘A’ is currently underway.
The Electrical Contractor (EC), Pagoda Electric: The EC has completed 98% of all Phase 2 & 3 shop drawing and product submittals to the Design Team for review and approval.
Electrical demolition of the Phase 2 Boys and Girls Locker Room is 95% complete.
Electrical rough-in in the above area is underway
Selective electrical demolition in old three story Area ‘A’, in ongoing and scheduled to complete in February. Rough in of new systems will follow.
The new emergency oil fired generator has been set and tied the boilers and associated pumps.
The Plumbing Contractor (PC), Apex Plumbing: The PC has completed 98% of all Phase 2 & 3 shop drawing and product submittals to the Design Team for review and approval.
Plumbing demolition of the Phase 2 Boys and Girls Locker Room is 100% complete and underground rough in is currently underway.
Selective plumbing demolition in old three story Area ‘A’ is underway.
Fire protection, plumbing and drain piping coordination drawings are completed.
The Environmental Abatement Contractor, Sargent Enterprises: The Abatement work has completed on all three floors with the exception of the Auditorium floor tile. This abatement is currently underway
and scheduled to complete the first week in February. Air samples from all three floors of the building have come back as ‘non-detected’ thus exceeding EPA clearance criteria.
COMMUNITY INVOLVEMENT
On December 28 & 29 2015 BASD hosted their annual basketball tournament utilizing the New Cub Gymnasium. The remaining Phase 1 construction including the five new Art Classrooms with support spaces, completely new Boiler Room, and A New Mechanical Room were turned over to BASD January 4, 2015 per contract schedule.
The Auditorium chairs have been removed and distributed to community members who purchased the chairs as a memento or repurposing. The original wood classroom doors that could not be reused based on current building codes have been removed and distributed to community members for repurposing. The original classroom wood chalkboard trim has been removed by BASD and will be refinished and reinstalled around the new marker boards.
School District: Boyertown School District Report Submission Date: January 31, 2016
Project Name: Boyertown High School Report Period: January 2016
Project Number: 90025 Report Author: John Hartman / Zach Zazo
J F M A M J J A S O N D J F M A M J J
Contract
Remaining Material
Allowance
General Contract - ER Stuebner 65,110$
Electrical Contract - Pagoda 32,712$
Plumbing Contract - Apex Plumbing 32,712$
HVAC Contract - Worth & Co 87,694$
Environmental Contract - Sargent Ent. -$
Total 218,228$
Current Remaining Project Contingency (1)
(1) Includes contingency of $1.8M for unforeseen conditions in the 1920's building, contingency for offsite roadway improvements, and general construction contingency.
d
Status CommentsOverall Project Schedule Status
0% Completion at end of August.
Phase 1: New Gym, Science Labs & Classroom and HVAC Reno
Phase 2A: Renovate 9th Grade Academy (1920's Building)
Phase 2B: Music & Corridors
Phase 2C: Locker Room & Wrestling Room Reno
Phase 2D: Reno Health & Dev, Aud. Spaces & Bear Gym Lobby
100%
Phase 1 is substantially complete and occupied, the
Certificate of Occupancy has been issued.
5%
Abatement has been started. Abatement is scheduled to
be complete By Tuesday, February 10, 2016. Selective
demolition has begun the 3rd and 2nd floor of the 9th
Grade Academy.
0% Completion in September 2016.
Work started early (Demolition in Cubs Gym Girls Locker
room) & MEP rough-in has started.15%
% CompleteStatus CommentsCurrent Phase and Schedule Status
0%
0%
0% Completion at end of August.
30%
Work started early, Stair #6 is 90% complete & being
used to access Ceramics
Phase 2E: Classroom Renovations
Phase 3A: Stair Tower, Classrooms and Admin Reno
Phase 3B: Renovate ROTC, Business Lab, Guidance & Toilet Rams
Phase 3C: Renovate LibraryPhase 3D: Renovate Kitchen/Café and Toilet Rooms 0%
Phase 2 2016
2015 2016 2017% Complete
Other Discussions:
Abatement is complete in the 9th Grade Academy (1920's building) two weeks ahead of schedule. The
Montgomery Avenue road widening is scheduled to bid April 6, 2016. The Notice to Procced should be issued May 31, 2016
and the Montgomery Avenue road widening / Monroe Street intersection should be complete October 31, 2016. The Monroe
Street Extension shall continue to be used as a construction access and will not be available for district use until the
September 2017 start of school.
48,338$
484,082$
356,540$
47,238$
Science Lab are 100% complete.
Waiting for Twp. Eng. to complete offsite road design and provide estimate.
Rock removal has remained below the Alternate amount.
Phase 1 is substantially complete and occupied. The New Cubs Gym is
complete and currently being used full time. Phase 2 construction has begun on the scheduled
January 4, 2016 date.
Phase 2 & 3 known electrical issues are being addressed and resolved prior to work beginning. Cost
proposal have been received, the Change Order for this work is being presented to the Board at the
February 2016 Board meeting.
Planning to bid Montgomery Ave. / Monroe St. intersection improvements in May 2016.
0%
Phase 2B: Convert Exist. Gym and Lockers into the Music Academy
Phase 2E: 1st & 2nd floor Area 'I' Classroom renovations
Phase 2A: Convert the existing 1920's building into the 9th Grade Academy
Phase 2C: Renovate exist. Locker Room, Wrestling Room & CorridorPhase 2D: Health / Development Academy Reno's,. , Aud. & Bears Gym
Lobby renovations Work scheduled to begin in June.
10% Work has begun on schedule
20% Demo and MEP rough-in continues on schedule
0% Work scheduled to begin in May.
9,561,371$
Contract Amount
24,561,000$
5,322,700$
3,627,000$
9,678,500$
140,625$
43,329,825$
31,966$
Allowance
Adjustment to Date
Original Material
Allowance
421,650$
79,950$
81,050$
119,660$
-$
702,310$
82,030$ -$
172,753$
Paid to Date (with
10% retained)
11,279,285$
2,994,116$
1,694,355$
4,129,147$
0% Work scheduled for Summer of 2016.
Issues Resolved Issues in Progress
20,178,933$
Executed Change
Orders
59,798$
112,955$
-$
-$
76%
20%
2%0% 2%
Submittals
Approved
Rejected
Outstanding
Voided
Overdue
94%
3%
0%
3%
Requests for Information
Complete
Outstanding
Voided
Overdue
G:\SD-Projects\90025 Boyertown High School\Monthly Progress Reports\January 2016\Contract Status and Payment Log_90025
Boyertown Area School District
Additions Renovations to Senior High School
Budget Summary
January 31, 2016
DEI Project No. 90025
Item Description Approved Budget Contract Amount Change Orders
to Date Billed to Date Difference from Budget to Bid
General Construction $ 23,262,537 24,561,000$ 59,798$ 11,279,285$ 1,298,463$
Mechanical Construction $ 12,099,200 9,678,500$ 4,129,147$ ($2,420,700)
Plumbing Construction $ 4,560,000 3,627,000$ 1,694,355$ ($933,000)
Electrical Construction $ 8,094,000 5,322,700$ 112,955$ 2,994,116$ ($2,771,300)
Environmental (Contract 5) $ 160,000 140,625$ 82,030$ ($19,375)
Budget vs.Bid Total $ 48,175,737 43,329,825$ 20,178,933$ -$4,845,912.00
Soft Costs Comments
Architect & Engineers (6% of Construction Cost) 2,748,718$ $ 2,968,157 Architect Reimbursable 35,000$ 35,000$ Based on KCBA's estimate
Construction Manager Base Fee 975,000$ 975,000$ 506,130$
Construction Manager Pre-Design Fee 75,000$ 75,000$ 75,000$
Construction Testing 150,000$ $ 60,000 $ 54,515 HVAC Testing & Balancing 250,000$ $ 170,500 $ 12,304 Cost proposals rec'd 11/5/2014
Geotechnical 40,000$ 40,000$ 40,000$ Based on fees for completed geotech report
Asbestos Consultant/Lead Paint/Air Monitoring 25,000$ 25,000$ Based on contracts with TMS Consulting
Miscellaneous investigations (Piping, Pest Inspection) 20,000$ $ 4,000 $ 4,000 Budgeted Allowance ($4000 spent to date)
Phase 1 Site Assessment 4,000$ 4,000$ 4,000$ Based on fees spent at initial project developmentTraffic Impact Study 50,000$ $ 55,000 $ 55,000 Based on fees spent up to 9/9/2014
Land Survey 20,000$ 20,000$ 20,000$ Budgeted Allowance
Zoning/Land Development/E&S Fees 20,000$ 20,000$ 20,000$ Budgeted Allowance
Sewage Tap Fee 100,000$ 100,000$ Budgeted Allowance
Water Tap Fee 50,000$ 50,000$ Budgeted Allowance
Electric Company Fee 30,000$ 30,000$ Budgeted Allowance
Owner Controlled Insurance Program (OCIP) 2.5% 1,145,299$ 1,204,394$ 1,204,395$ Estimate based on percent of the updated construction costs
Building Permits/Inspections 150,000$ 150,000$ 44,913$ Budgeted Allowance bases on preliminary scope
FF&E 1,500,000$ 1,500,000$ $3.95/sf - Allowance based budget restrictionsEnergy for construction 150,000$ 150,000$ Budgeted Allowance
Moving & Phasing Costs 300,000$ 300,000$ Budgeted Allowance bases on preliminary scope
Project Soft Cost Budget 7,838,017$ 7,936,051$ 2,040,256$
BUILDING TOTAL 56,013,754$ 51,265,876$ 22,219,189$
Project Contingency & Off Site Roadway Improvements (1) 3,186,246$ 7,761,371$ 172,753$
9th Grade Academy Contingency 1,800,000$ 1,800,000$
Project Total Budget 61,000,000$ 60,827,247$ 172,753$ 22,219,189$
1. Includes: Montgomery Ave. HOP Improvements
Colebrookdale Township Off-Site Intersection Costs
TPD's Fee to Engineer Off-Site Intersection
BOYERTOWN AREA SENIOR HIGH SCHOOL - TOTAL PROJECT BUDGET SUMMARY AS OF JANUARY 31, 2016
BOYERTOWN AREA SENIOR HIGH SCHOOL - CONSTRUCTION CONTRACT SUMMARY BY PHASE THROUGH JANUARY 31, 2016
Contract
Amount
Completed &
Stored to Date
Contract
Balance
%
Complete
Contract
Amount
Completed
& Stored to
Date
Contract
Balance
%
Complete
Contract
Amount
Completed
& Stored to
Date
Contract
Balance% Complete
General Contract 10,562,986$ 10,274,694$ 288,292$ 92% 8,819,783$ 1,774,484$ 7,045,299$ 20% 5,238,028$ 424,286$ 4,813,742$ 8% 12,473,464$ 24,620,797$ 51%
Mechanical Contract 4,303,037$ 3,962,084$ 340,953$ 92% 3,106,787$ 352,050$ 2,754,737$ 11% 2,268,677$ 120,300$ 2,148,377$ 5% 4,434,434$ 9,678,501$ 46%
Plumbing Contract 1,392,167$ 1,382,450$ 9,717$ 99% 1,366,892$ 330,142$ 1,036,750$ 24% 867,942$ 87,399$ 780,543$ 10% 1,799,991$ 3,627,001$ 50%
Electrical Contract 2,367,144$ 2,300,000$ 67,144$ 97% 1,795,805$ 404,000$ 1,391,805$ 22% 1,272,705$ 381,100$ 891,605$ 30% 3,085,100$ 5,435,654$ 57%
Abatement Contract -$ -$ -$ 0% 140,625$ 91,144$ 49,481$ 65% -$ -$ -$ 0% 91,144$ 140,625$ 65%
TOTALS 18,625,334$ 17,919,228$ 706,106$ 96% 15,229,892$ 2,951,820$ 12,278,072$ 19% 9,647,352$ 1,013,085$ 8,634,267$ 11% 21,884,133$ 43,502,578$ 50%
Total %
Completed &
Stored to Date
PHASE 1 PHASE 2 PHASE 3
Total
Completed &
Stored to Date
Total
Contract
Amount
AllowanceContract Allowance
Amount
Remaining
Balance
General Construction Contract 421,650$ (356,540)$ 1
65,110$
Electrical Construction Contract 79,950$ (47,238)$ 32,712$
Plumbing Construction Contract 81,050$ (48,338)$ 2
32,712$
Mechanical Construction Contract 119,660$ (31,966)$ 87,694$ 3,000$ 3
Environmental Construction Contract -$ -$ -$
TOTALS 702,310$ (484,082)$ 218,228$ 3,000$
3 Estimated costs to relocate Lab
Fume exhayst motors to roof.
BOYERTOWN AREA SENIOR HIGH SCHOOL - ALLOWANCE EXPENDITURE AS OF JANUARY 31, 2015
Allowance
Adjustment
to Date
Potential
Adjustments
Pending Review
1 $123,250 for rock excavation
2 $4135 for rock excavation
eot
Warm January Allows for Sidewalks to Continue Old Cub Gym Boys Locker Room Demolition
ACM Abatement in Old Three Story Existing Wood Structure within Old Three Story
Existing Cub Gym Begins Transformation Plaster Ceiling Removal in Old Three Story
Boyertown Senior High School
Renovations and Additions
Boyertown, PA