tomelleri s.r.l. ® copyright 2007 © astronomy and research september 19th 2008 vst meeting1
TRANSCRIPT
Tomelleri S.r.l. ® Copyright 2007 ©
ASTRONOMY AND RESEARCH
September 19th 2008 VST Meeting 1
VST ProjectPrimary Mirror Support System
Progress MeetingVillafranca, September 19th, 2008
2September 19th 2008 VST Meeting
All Design Descriptions and Test Procedures related to the Axial Force Actuators, the Axial Fixed Points, the Astatic Levers and the Lateral Fixed Points, have been delivered also including the Final Design of Safety Devices foreseen to accept both the Teflon with springs and the Elastomer solutions, even though their stiffness and stroke need to be defined as a result of the earthquake analysis. The documents related to Harness will be completed with the As Built after completion of the accommodation of cables into the mirror cell foreseen within September 26. 36 Axial Force Actuators of the second and third rings have been integrated into the mirror cell while all remaining axial actuators have been tested and will be integrated within end September. The assembling and testing of the Axial Fixed Points will be ready before firmware delivery foreseen within end September. The Lateral Fixed Points have been assembled and tested and are ready to be integrated in the mirror cell. The Astatic Levers have been assembled and are being tested and therefore will be ready for the integration.Mirror Cell and the Dummy have been tested, and are positioned under the crane. All procedures for integration and testing of the Support System have been prepared and will be released after approval.
September 19th 2008 VST Meeting 3
PROGRESS SUMMARY
AXIAL FORCE ACTUATORS
September 19th 2008 VST Meeting 4
81 Axial Force Actuators have been tested and they all satisfy the requirements and particularly:- Maximum force range up 400 N can be obtained also when the sphere starts at a distance 1.6 mm from the mirror pad- Accuracy is better than 0.3 N with step 1 N.- Passive stroke is at least 3.2 mm when the actuator supplies 400 N, and the force is in any case less than 1500 N- Maximum force rate more than 20N/sec- Axial stiffness 200 N/mm- Maximum current < 0.1 A (nominal value 0.95A)Each actuator is certificated every 0.5 mm with the proper force-displacement diagram. 36 actuators have been integrated into the mirror cell while the remaining are ready for integration.
Axial Force Actuator on the test bench
September 19th 2008 VST Meeting 5
September 19th 2008 VST Meeting 6
36 Axial Force Actuators on the Mirror Cell
September 19th 2008 VST Meeting 7
Axial Force Actuators before integration
The prototype of the Axial Fixed Point has been assembled and tested on the appropriate test bench, and it has satisfied the requirements and particularly:- Stiffness is 13300 N/mm more than 9000 N/mm- Passive stroke 3.2 mm with maximum load less than 1500 N- Preload between 580 N and 700 N Positioning accuracy has not been measured because the related software is not yet available but it has been verified that the two LVDTs measure the axial position with the required accuracy.The firmware to test positioning will be ready within end September.After this all remaining test will be done.
September 19th 2008 VST Meeting 8
AXIAL FIXED POINTS
Three Axial Fixed Points during assembling
9September 19th 2008 VST Meeting
All Astatic Levers has been assembled and now are being tested.The tested Astatic Levers satisfy the requirements and particularly:- Force accuracy better than + 5 N - Force adjusting range over 50 N- Accessibility for adjusting and mountingAll 24 Astatic Levers will be integrated into the mirror cell within end September. Tests to verify the accessibility to mount and adjust the Astatic Levers, have been foreseen to perform after the mounting in the mirror cell.
September 19th 2008 VST Meetin 10
ASTATIC LEVERS
September 19th 2008 VST Meeting 11
Astatic Lever on the Test Bench
September 19th 2008 VST Meeting 12
Astatic levers after assembling
The four Lateral Fixed Points, included spare, have been assembled and tested on the appropriate test bench.Performance achieved:- Preload between from 600 up 800 N in both directions- Stiffness 25000 N/mm (requirement > 20000 N/mm)- Passive stroke 5 mm in all directions- Maximum force on the mirror is 1300 N The three Axial Fixee Points are now ready to be integrated into the mirror cell within end September.
September 19th 2008 VST Meeting 13
LATERAL FIXED POINTS
September 19th 2008 VST Meeting 14
Lateral Fixed Points after assembling and testing
The system integration and test activities of M1 cell is being carried out at our facilities in our workshop. A crane, 3 ton capacity and 4 m radial stroke, equipped with non standard gearboxes to have a velocity of 1 m/min, has been installed. The handling of dummy is foreseen to be done by three adjustable tie rods and moved by the Hydra-set.The supports for the rotation system have been prepared to accept the drive system.
September 19th 2008 VST Meeting 15
INTEGRATION AREA
September 19th 2008 VST Meeting 16
Mirror cell and Dummy under the crane
September 19th 2008 VST Meeting 17
Handling for Dummy before Hydra-Set supply
September 19th 2008 VST Meetin 18
Rotating support modified for the drive system
• Testing of accuracy of the mirror cell: measures have shown astatic levers interface, M8 holes and derotator interface are within + 0.1 mm, while the interfaces to actuators have been corrected by the flanges height
• Adjusting and testing of the axial actuators interface within + 0.1mm, and the height of the sphere of the 36 actuators is within + 0.1 mm
• Testing of the dummy: on the first and second ring the height is within 0.1 mm, on the third and fourth ring 0.2 mm; lateral pads within 0.2 mm.
• Reworking of the mirror cell. Threaded holes to apply the lateral fixed points, safety devices and absolute transducers will be referred to the exixting threaded holes, and will be done (within end Sept. )
• The pads under the dummy will be applied (within end Sept. )• Completion of the axial actuators integration and height verification (end Sept.)• Lateral fixed points integration (within end Sept. )• Astatic levers integration(within end Sept. )• Absolute transducers integration(within end Sept. )• Integration of dummy in the mirror cell foreseen to be done at 10 October• Safety devices will be integrated within November 8 with Teflon pads
September 19th 2008 VST Meeting 19
Integration Procedures
Mirror cell testing
September 19th 2008 VST Meeting 20
Dummy testing
September 19th 2008 VST Meeting 21
Flange height verification
September 19th 2008 VST Meeting 22
Integration of some axial actuators
September 19th 2008 VST Meeting 23
Height of the actuators
September 19th 2008 VST Meeting 24
Testing of the height of the Axial Force Actuators
September 19th 2008 VST Meeting 25
The diagrams of the harness have been completed, while the as-built drawings will be prepared within September 26.All power connection to the actuators have been done with the proper accommodation under the mirror cell, while the Can Bus will be connected within September 26.Distribution boxes and the repeater box have been fixed to the mirror cell ready for connection.
September 19th 2008 VST Meeting 26
HARNESS
Testing of axial actuators connected
September 19th 2008 VST Meeting 27
September 19th 2008 VST Meeting 28
Power cables to connect to all axial actuators
The design of the mechanical supports of the safety devices have been completed and they foresee to accept both Teflon pads with springs and Elastomer pads.The safety devices include:- 16 upper axial safety devices- 14 lower safety devices- 18 lateral safety devices- 2 special lateral safety devices, in the East and West positions, that can be moved away from an accessible location.In order to get the safety devices ready for mirror demounting it is enough to rotate the upper part of the safety devices and bring the supports back ca 10 mm, so to avoid any interference with the mirror and with the handling.Four safety devices need to be demounted. Repositioning doesn’t require any backlash adjusting. September 19th 2008 VST Meeting 29
SAFETY DEVICES
September 19th 2008 VST Meeting 30
Safety devices general view
Safety devices general assembly
September 19th 2008 VST Meeting 31
Safety device in East-West positions
September 19th 2008 VST Meeting 32
Safety device lateral view
September 19th 2008 VST Meeting 33
Teflon pads with springs:- Shorter delivery time- Lower costElastomer pads:- Better pressure distribution- More damping- Smaller encumbrancesWe have had a meeting at Exsto facilities in France in order to answer all questions. All requirements seem to be satisfied, that will be confirmed in written form: stability, amount of permanent deformation, linear behaviour, two different kinds of elastomer. With the Elastomer solution the test on the mirror cell on the rotation system will be done with Teflon pads without springs. The elastomer pads will be tested in our facility before sending them to Paranal.
September 19th 2008 VST Meeting 34
Teflon-spring pads vs. Elastomer
September 19th 2008 VST Meeting 35
Eladip applications
June 5th 2008 VST Meeting 36
Eladip stiffness
TEST PROCEDURES AFTER INTEGRATIONTest Procedures phase 1.A
September 19th 2008 VST Meeting 37
Integration Test Phase 1-A: tests at ground with the M1 Mirror Cell that lays horizontally on the four supports and before Dummy Integration • T1. Geometry of the Axial Actuators (both Axial Force Actuators and Axial Fixed Points)• T2. Reading of the Absolute Transducers• T3. Software-Hardware Communication• T4. Axial Actuator Manual Control System
Detailed procedures are available in the proper document
Test Procedures phase 1.B
September 19th 2008 VST Meeting 38
Integration Test Phase 1-B: tests at ground with the M1 Mirror Cell that lays horizontally on the four supports and after Dummy Integration
• T5. Geometry Test of the Lateral Fixed Points• T6. Geometry Test of the Astatic Levers• T7. Radial Dummy stroke • T8. Load Control of the Axial Force Actuators• T9. Accessibility to all devices for Maintenance
Detailed procedures are available in the proper document