top considerations

Upload: arcturus91

Post on 07-Jul-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Top Considerations

    1/27

    Commissioning ofCommissioning ofCombined Heat and Power Plants:Combined Heat and Power Plants:

    Lessons LearnedLessons Learned

    July 1, 2008

    Presented by

    Abbe Bjorklund, PE, LEED AP

    Sebesta Blomberg & Associates

    and 

    Bruce Nicholson

    Cooperative Consulting Services, Inc.

  • 8/18/2019 Top Considerations

    2/27

    Topics Covered

    • Beneficial commissioning processes

    • Roles and responsibilities

    • Benefits, costs and challenges of a formal

    startup/commissioning process

    • Coordination and conflict betweenconstruction startup/commissioning

    • OEM coordination issues and how to address

  • 8/18/2019 Top Considerations

    3/27

    Beneficial Commissioning ProcessesBeneficial Commissioning Processesfrom Construction through Systemsfrom Construction through Systems

    Testing, Performance Testing,Testing, Performance Testing,Environmental Testing, and ReliabilityEnvironmental Testing, and Reliability

    TestingTesting

  • 8/18/2019 Top Considerations

    4/27

    Beneficial Commissioning

    Processes

    • Design• Purchase

    • Install

    • Construct

    • Turnover to startup/commissioning

    • Equipment checkout

    • System testing/initial operation and system functional testing

    • Integrated system/plant functional testing

    • Performance testing• Environmental/compliance testing

    • Reliability/acceptance testing

    • Turnover to the Owners/plant final acceptance

  • 8/18/2019 Top Considerations

    5/27

    Roles and ResponsibilitiesRoles and Responsibilities

  • 8/18/2019 Top Considerations

    6/27

    Roles and Responsibilities

    • Clearly define roles and responsibilities

    through design, construction,

    startup/commissioning – Designer 

     – Constructor  – Independent Commissioning Authority/Agent

     – Startup Engineer 

     – Owner 

  • 8/18/2019 Top Considerations

    7/27

    Roles and Responsibilities

    • Construction and Startup

     – Where does construction end?

     – Where does startup begin?

     – Need to define formally for

    each project – Construction testing vs.

    Startup testing

  • 8/18/2019 Top Considerations

    8/27

    Roles and Responsibilities

    • Startup and Commissioning

     – Where does startup end?

     – Where does commissioning begin?

     – Need to define formally for each project

  • 8/18/2019 Top Considerations

    9/27

    Roles and Responsibilities

    • Examples from typical projects

     – Project Organization Chart

     – Roles & Responsibilities by Major Phase

     – Responsibility Matrix – Construction Phase

     – Responsibility Matrix – Startup & CommissioningPhase

  • 8/18/2019 Top Considerations

    10/27

    Example:

    Project Organization Chart

  • 8/18/2019 Top Considerations

    11/27

    Example

    Roles & Responsibil ities

    Major Phases  Design Phase

    Construction Phase

    Startup & Commissioning Phase

    Design Procure Install Construction

    Completion

    Construction

    Testing

    Turnover

    Package

    Turnover

    to SU&C

    Component

    Testing

    System

    Testing

    Plant

    Testing

    Turnover

    to Owners

    Engineering Engineer of record

    CommissioningAgent Startup & Commissioning Management

    ConstructionManager

    Construction Management

    GTG Vendor Construction Startup & Commissioning Support

    HRSG Vendor Construction Startup & Commissioning Support

    General

    Contractor

    Construction Startup & Commissioning Support

    Inst & Controls Construction Startup & Commissioning Support

    Electrical

    Contractor

    Construction Startup & CommissioningSupport

    Mechanical

    Contractor

    Construction Startup & CommissioningSupport

    Piping

    Contractor

    Construction Startup & CommissioningSupport

  • 8/18/2019 Top Considerations

    12/27

    Example

    Responsibil ity Matrix

    Construction Phase Activity SU&C CONSTRUCTION ORGANIZATION  OWNER

    Startup and Commissioning ProgramDevelopment

    CXing Agent

    CM Mech Piping Elec I&C HRSG GTG Representative

    Typically 50 to 75 items such as:

    Review systems turnover package list X X X X X X X X X

    Review scoped turnover package documents X X X X X X X X X

    Review Project Punchlist procedure X X X X X X X X X

    Construction Completion

    Typically 20 to 30 items such as:

    Complete Required Data Sheets and Test Records X X X X X X X

    Prepare System Completion punchlists X X X X X X X

    Perform System As-Built X X X X X X X

    Construction TestingTypically 25 to 50 items such as:

    Perform Nondestructive Testing X X X X

    Perform Pressure Testing X X

    Verify Installation of Instruments and Controls X X

    Schedule Vendors Required for Construction Testing X

     Alignment of Rotating Equipment X X XMegger Cables and Equipment X X

    Verify Installation is in accordance with Design X X X X X X X

    Required Equipment Maintenance X X X X X X X

    Interface with Startup on Systems Ready for Turnover X X X X

     Assemble Initial Turnover Packages and records X X X X X X

    Perform Turnover Walkdown and Exception Lists X X X X X X X X X

    Initial System Turnover (to SU&C) X X X X X X X X X

  • 8/18/2019 Top Considerations

    13/27

    Example: Responsibil ity Matrix

    Startup & Commissioning PhaseSU&C Startup & Commissioning Support Team Owner

     Activity CXing Agent CM Mech Piping Elec I&C HRSG GTGOperations

    Component Testing

    Typically 40 to 50 items such as:

     Administer Startup Safety Tagging Program X X

    Inspect, Test, and Calibrate Instruments and Loops X X X

    Test major Electrical Equipment X X

    Megger Testing, Motor Rotation XX

    System Testing

    Typically 10 to 20 items such as:

    Interface with local Utilities X XLineup System for Operation X X X X X X X XInitial Energization of Power Supply Systems, X XRotating Equipment Initial Run In X X X

    Functional checks of Controls, Equipment & Systems X XPlant Testing

    Typically 40 to 50 items such as:

    Perform Final HVAC Balancing X XFine Tune Combustion Controls X X XFinal Tuning of Instruments, Controls, and Valves X X  Finalize controls & tuning settings, software X X X X XExecute System Functional Test Procedures X X X X XPerformance, Emissions, Reliability Testing X X X X

    Project Completion

    Typically 20 to 40 items such as:

    Finalize System Turnover Packages X X X X X X X XFinalize Project Punchlist X

    Perform Turnover Walkdowns with Owners X X

  • 8/18/2019 Top Considerations

    14/27

    Benefits, costs and challenges of aBenefits, costs and challenges of aformal startup and commissioningformal startup and commissioning

    processprocess

  • 8/18/2019 Top Considerations

    15/27

    Benefits

    • A formal program ensures that an organization

    with commissioning experience is put in place

    • Formal program includes• Formal turnover process

    • Well-documented functional performance criteria

    • O&M documentation

    • Operator training program

  • 8/18/2019 Top Considerations

    16/27

    Benefits

    • Track deliverables

     – Identified early in the project

     – Are a part of the Contract Specifications

     – Are formally tracked 

  • 8/18/2019 Top Considerations

    17/27

    Benefits

    • Track progress of construction and commissioning

    with tools developed and implemented which allow

    for easily tracking the overall process – Master Tracking Matrix

     –  Notification schedule

     – Deliverables list – Integrated Construction and Startup/Commissioning

    schedule

     – Project punchlist – System turnover exceptions lists

  • 8/18/2019 Top Considerations

    18/27

    Costs

    • Turnover process may require an additional person to manage

    • Formal documentation of testing activities – Time to develop formal test procedures, checklists

    and datasheets

     – Staff hours for testing are relatively the same

     – Additional time to formally document test data and

    results• Startup & Commissioning Program is typically

    2 to 5% of the overall project.

  • 8/18/2019 Top Considerations

    19/27

    Costs

    • Any cost increase should be offset at the end of the project – System turnover packages and documentation streamlines the

    review and acceptance

     – Documentation can be reviewed on a system by system basis• System boundaries are defined 

    • Each organization has same understanding of the scope of each system.

    • Owner's representatives spot checks the progress and results

     – Warranty claims can be handled smoothly both during thestartup/commissioning phase and after acceptance by the owners

    • Typically vendors will ask for test data such as: – vibration analysis, meggar records, system cleaning records, lubrication

    records• Troubleshooting performed more quickly and accurately

     – The controls system historian and test data used to help identify root cause

  • 8/18/2019 Top Considerations

    20/27

    Challenges

    • Proper planning early in the project with the right people

     – Cxing plan that clearly defines roles and responsibilities

     – Detailed commissioning specifications which are included inthe RFP

     – All parties embrace a formal startup and commissioning

     program – and fulfill specified roles and responsibilities•  Need an Owner that fully supports a formal startup and

    commissioning program

    • General Contractor develops purchase orders andequipment specifications that include requirements forstartup & commissioning

  • 8/18/2019 Top Considerations

    21/27

    Challenges

    • Involvement of Owner’s operators in the

    startup/cxing process

    • Initial operation of equipment and testing on acampus

     – Some activities are loud, some are sudden and may appear

    unusual. – Campus events can impact the activities of the project

     – Communicate a well thought out startup/commissioning

     plan and schedule to the general campus population

  • 8/18/2019 Top Considerations

    22/27

    Coordination and conflicts betweenCoordination and conflicts between

    construction andconstruction and

    startup/commissioning organizationsstartup/commissioning organizations

  • 8/18/2019 Top Considerations

    23/27

    Coordination and Conflict

    • Startup Engineer/Cxing entity should reportdirectly to the Project Manager 

     – The Startup & Commissioning team should be a peer of the Construction team

     – Each group has a direct line to the Project Manager 

    • Detailed specifications issued with the RFPhelp minimize conflicts later 

     – Detailed lists of deliverables and trackingmechanisms

  • 8/18/2019 Top Considerations

    24/27

    OEM coordination issuesOEM coordination issues

    and how to addressand how to address

  • 8/18/2019 Top Considerations

    25/27

    OEM Coordination Issues

    • From pre-purchase through construction and

    startup/commissioning:

     – Need to coordinate vendors forstartup/commissioning

     – Must work as a team

     – Startup Manager must be able to coordinate and

    direct the OEMs

  • 8/18/2019 Top Considerations

    26/27

    Beneficial Commissioning

    Processes• Design

    • Purchase

    • Install

    • Construct• Turnover to startup/commissioning

    • Equipment checkout

    • System testing/initial operation and system functional testing• Integrated system/plant functional testing

    • Performance testing

    • Environmental/compliance testing

    • Reliability/acceptance testing

    • Turnover to the Owners/plant final acceptance

  • 8/18/2019 Top Considerations

    27/27

    Thank you!Thank you!

    Questions???