top considerations
TRANSCRIPT
-
8/18/2019 Top Considerations
1/27
Commissioning ofCommissioning ofCombined Heat and Power Plants:Combined Heat and Power Plants:
Lessons LearnedLessons Learned
July 1, 2008
Presented by
Abbe Bjorklund, PE, LEED AP
Sebesta Blomberg & Associates
and
Bruce Nicholson
Cooperative Consulting Services, Inc.
-
8/18/2019 Top Considerations
2/27
Topics Covered
• Beneficial commissioning processes
• Roles and responsibilities
• Benefits, costs and challenges of a formal
startup/commissioning process
• Coordination and conflict betweenconstruction startup/commissioning
• OEM coordination issues and how to address
-
8/18/2019 Top Considerations
3/27
Beneficial Commissioning ProcessesBeneficial Commissioning Processesfrom Construction through Systemsfrom Construction through Systems
Testing, Performance Testing,Testing, Performance Testing,Environmental Testing, and ReliabilityEnvironmental Testing, and Reliability
TestingTesting
-
8/18/2019 Top Considerations
4/27
Beneficial Commissioning
Processes
• Design• Purchase
• Install
• Construct
• Turnover to startup/commissioning
• Equipment checkout
• System testing/initial operation and system functional testing
• Integrated system/plant functional testing
• Performance testing• Environmental/compliance testing
• Reliability/acceptance testing
• Turnover to the Owners/plant final acceptance
-
8/18/2019 Top Considerations
5/27
Roles and ResponsibilitiesRoles and Responsibilities
-
8/18/2019 Top Considerations
6/27
Roles and Responsibilities
• Clearly define roles and responsibilities
through design, construction,
startup/commissioning – Designer
– Constructor – Independent Commissioning Authority/Agent
– Startup Engineer
– Owner
-
8/18/2019 Top Considerations
7/27
Roles and Responsibilities
• Construction and Startup
– Where does construction end?
– Where does startup begin?
– Need to define formally for
each project – Construction testing vs.
Startup testing
-
8/18/2019 Top Considerations
8/27
Roles and Responsibilities
• Startup and Commissioning
– Where does startup end?
– Where does commissioning begin?
– Need to define formally for each project
-
8/18/2019 Top Considerations
9/27
Roles and Responsibilities
• Examples from typical projects
– Project Organization Chart
– Roles & Responsibilities by Major Phase
– Responsibility Matrix – Construction Phase
– Responsibility Matrix – Startup & CommissioningPhase
-
8/18/2019 Top Considerations
10/27
Example:
Project Organization Chart
-
8/18/2019 Top Considerations
11/27
Example
Roles & Responsibil ities
Major Phases Design Phase
Construction Phase
Startup & Commissioning Phase
Design Procure Install Construction
Completion
Construction
Testing
Turnover
Package
Turnover
to SU&C
Component
Testing
System
Testing
Plant
Testing
Turnover
to Owners
Engineering Engineer of record
CommissioningAgent Startup & Commissioning Management
ConstructionManager
Construction Management
GTG Vendor Construction Startup & Commissioning Support
HRSG Vendor Construction Startup & Commissioning Support
General
Contractor
Construction Startup & Commissioning Support
Inst & Controls Construction Startup & Commissioning Support
Electrical
Contractor
Construction Startup & CommissioningSupport
Mechanical
Contractor
Construction Startup & CommissioningSupport
Piping
Contractor
Construction Startup & CommissioningSupport
-
8/18/2019 Top Considerations
12/27
Example
Responsibil ity Matrix
Construction Phase Activity SU&C CONSTRUCTION ORGANIZATION OWNER
Startup and Commissioning ProgramDevelopment
CXing Agent
CM Mech Piping Elec I&C HRSG GTG Representative
Typically 50 to 75 items such as:
Review systems turnover package list X X X X X X X X X
Review scoped turnover package documents X X X X X X X X X
Review Project Punchlist procedure X X X X X X X X X
Construction Completion
Typically 20 to 30 items such as:
Complete Required Data Sheets and Test Records X X X X X X X
Prepare System Completion punchlists X X X X X X X
Perform System As-Built X X X X X X X
Construction TestingTypically 25 to 50 items such as:
Perform Nondestructive Testing X X X X
Perform Pressure Testing X X
Verify Installation of Instruments and Controls X X
Schedule Vendors Required for Construction Testing X
Alignment of Rotating Equipment X X XMegger Cables and Equipment X X
Verify Installation is in accordance with Design X X X X X X X
Required Equipment Maintenance X X X X X X X
Interface with Startup on Systems Ready for Turnover X X X X
Assemble Initial Turnover Packages and records X X X X X X
Perform Turnover Walkdown and Exception Lists X X X X X X X X X
Initial System Turnover (to SU&C) X X X X X X X X X
-
8/18/2019 Top Considerations
13/27
Example: Responsibil ity Matrix
Startup & Commissioning PhaseSU&C Startup & Commissioning Support Team Owner
Activity CXing Agent CM Mech Piping Elec I&C HRSG GTGOperations
Component Testing
Typically 40 to 50 items such as:
Administer Startup Safety Tagging Program X X
Inspect, Test, and Calibrate Instruments and Loops X X X
Test major Electrical Equipment X X
Megger Testing, Motor Rotation XX
System Testing
Typically 10 to 20 items such as:
Interface with local Utilities X XLineup System for Operation X X X X X X X XInitial Energization of Power Supply Systems, X XRotating Equipment Initial Run In X X X
Functional checks of Controls, Equipment & Systems X XPlant Testing
Typically 40 to 50 items such as:
Perform Final HVAC Balancing X XFine Tune Combustion Controls X X XFinal Tuning of Instruments, Controls, and Valves X X Finalize controls & tuning settings, software X X X X XExecute System Functional Test Procedures X X X X XPerformance, Emissions, Reliability Testing X X X X
Project Completion
Typically 20 to 40 items such as:
Finalize System Turnover Packages X X X X X X X XFinalize Project Punchlist X
Perform Turnover Walkdowns with Owners X X
-
8/18/2019 Top Considerations
14/27
Benefits, costs and challenges of aBenefits, costs and challenges of aformal startup and commissioningformal startup and commissioning
processprocess
-
8/18/2019 Top Considerations
15/27
Benefits
• A formal program ensures that an organization
with commissioning experience is put in place
• Formal program includes• Formal turnover process
• Well-documented functional performance criteria
• O&M documentation
• Operator training program
-
8/18/2019 Top Considerations
16/27
Benefits
• Track deliverables
– Identified early in the project
– Are a part of the Contract Specifications
– Are formally tracked
-
8/18/2019 Top Considerations
17/27
Benefits
• Track progress of construction and commissioning
with tools developed and implemented which allow
for easily tracking the overall process – Master Tracking Matrix
– Notification schedule
– Deliverables list – Integrated Construction and Startup/Commissioning
schedule
– Project punchlist – System turnover exceptions lists
-
8/18/2019 Top Considerations
18/27
Costs
• Turnover process may require an additional person to manage
• Formal documentation of testing activities – Time to develop formal test procedures, checklists
and datasheets
– Staff hours for testing are relatively the same
– Additional time to formally document test data and
results• Startup & Commissioning Program is typically
2 to 5% of the overall project.
-
8/18/2019 Top Considerations
19/27
Costs
• Any cost increase should be offset at the end of the project – System turnover packages and documentation streamlines the
review and acceptance
– Documentation can be reviewed on a system by system basis• System boundaries are defined
• Each organization has same understanding of the scope of each system.
• Owner's representatives spot checks the progress and results
– Warranty claims can be handled smoothly both during thestartup/commissioning phase and after acceptance by the owners
• Typically vendors will ask for test data such as: – vibration analysis, meggar records, system cleaning records, lubrication
records• Troubleshooting performed more quickly and accurately
– The controls system historian and test data used to help identify root cause
-
8/18/2019 Top Considerations
20/27
Challenges
• Proper planning early in the project with the right people
– Cxing plan that clearly defines roles and responsibilities
– Detailed commissioning specifications which are included inthe RFP
– All parties embrace a formal startup and commissioning
program – and fulfill specified roles and responsibilities• Need an Owner that fully supports a formal startup and
commissioning program
• General Contractor develops purchase orders andequipment specifications that include requirements forstartup & commissioning
-
8/18/2019 Top Considerations
21/27
Challenges
• Involvement of Owner’s operators in the
startup/cxing process
• Initial operation of equipment and testing on acampus
– Some activities are loud, some are sudden and may appear
unusual. – Campus events can impact the activities of the project
– Communicate a well thought out startup/commissioning
plan and schedule to the general campus population
-
8/18/2019 Top Considerations
22/27
Coordination and conflicts betweenCoordination and conflicts between
construction andconstruction and
startup/commissioning organizationsstartup/commissioning organizations
-
8/18/2019 Top Considerations
23/27
Coordination and Conflict
• Startup Engineer/Cxing entity should reportdirectly to the Project Manager
– The Startup & Commissioning team should be a peer of the Construction team
– Each group has a direct line to the Project Manager
• Detailed specifications issued with the RFPhelp minimize conflicts later
– Detailed lists of deliverables and trackingmechanisms
-
8/18/2019 Top Considerations
24/27
OEM coordination issuesOEM coordination issues
and how to addressand how to address
-
8/18/2019 Top Considerations
25/27
OEM Coordination Issues
• From pre-purchase through construction and
startup/commissioning:
– Need to coordinate vendors forstartup/commissioning
– Must work as a team
– Startup Manager must be able to coordinate and
direct the OEMs
-
8/18/2019 Top Considerations
26/27
Beneficial Commissioning
Processes• Design
• Purchase
• Install
• Construct• Turnover to startup/commissioning
• Equipment checkout
• System testing/initial operation and system functional testing• Integrated system/plant functional testing
• Performance testing
• Environmental/compliance testing
• Reliability/acceptance testing
• Turnover to the Owners/plant final acceptance
-
8/18/2019 Top Considerations
27/27
Thank you!Thank you!
Questions???