topic 7a-aggregate planning (1)
TRANSCRIPT
-
8/10/2019 Topic 7A-Aggregate Planning (1)
1/51
10/15/2014 1
Operat ionsManagement
Top ic 7AProduct ionPlann ing and Contro l
(Aggregate Plann ing)
-
8/10/2019 Topic 7A-Aggregate Planning (1)
2/51
10/15/2014 NY - KJP 585 2009 2
Organizational Strategy and
Production Planning
Decision Level Decision Process Forecast NeededProduction
Planning and
Allocation
Determines
seasonal plan by
product type
Determines
monthly itemproduction
schedules
Monthly Demandfor 6 mths by items
Monthly Demand
for 12 mths by
product types
Annual Demand by
Item and Region
Corporate
(Top Management)
ShopSupervisor
Plant Manager
It explains the relationship between planning structure and organizational structure
It also tells who are responsible for the for the decision making.
-
8/10/2019 Topic 7A-Aggregate Planning (1)
3/51
10/15/2014 NY - KJP 585 2009 3
The Planning Process
Long Range Planning
Covers a period of 5 years and made up of :
Product & Market Planning
Financial Planning Resource Planning
Medium Range Planning
Covers 3 18 months and made up of :
Aggregate Planning Item Forecasting
Master Production Schedule (MPS)
Capacity Planning
-
8/10/2019 Topic 7A-Aggregate Planning (1)
4/51
10/15/2014 NY - KJP 585 2009 4
The Planning Process
Short Range Planning Covers from 1 day to a few weeks and consists of :
Material Requirement Planning (MRP)
(Speci fy w hen prod uct ion and p urchase orders must be made)
Capacity Requirement Planning(Provid e detai led schedu le wh en each operat ion is to b e run on each
wo rk center and how long i t wi l l take to proc ess).
Final Assembly Scheduling
(Operat ion s required to pu t prod uct in its f inal form ).
Production Planning and Control
(Schedu l ing and shop -f loo r contro l act iv i t ies) .
Purchase Planning and Control
(Acq uis i t ion and c ontro l of purch ased i tems) .
-
8/10/2019 Topic 7A-Aggregate Planning (1)
5/51
10/15/2014 5
Planning Horizons
-
8/10/2019 Topic 7A-Aggregate Planning (1)
6/51
Example: Snapper, produces many different models of lawnmowers, for a total of 145 models. For each month in the
upcoming 3 quarters, the aggregate plan for Snapper might
have the following units of production.
10/15/2014 6
Aggregate Planning
Operations personnel
build an aggregate
plan using the total
expected demand for
all of the familyproducts.
-
8/10/2019 Topic 7A-Aggregate Planning (1)
7/51
10/15/2014 NY - KJP 585 2009 7
-
8/10/2019 Topic 7A-Aggregate Planning (1)
8/51
10/15/2014 8
Aggregate Planning
The objective of aggregate planning is
to meet forecasted demand while
minimizing cost over the planning
period
-
8/10/2019 Topic 7A-Aggregate Planning (1)
9/51
10/15/2014 9
The Planning Process
Objective is to minimize cost over the
planning period by adjusting
Production rates
Labor levels
Inventory levels
Overtime work
Subcontracting rates
Other controllable variables
Determine the quantity and timing ofproduction for the intermediate future
-
8/10/2019 Topic 7A-Aggregate Planning (1)
10/51
10/15/2014 10
Aggregate Planning
Combines appropriate resourcesinto general terms
Part of a larger production planningsystem
Disaggregation breaks the plan
down into greater detail
Disaggregation results in a masterproduction schedule
-
8/10/2019 Topic 7A-Aggregate Planning (1)
11/51
10/15/2014 11
Aggregate Planning Strategies
1. Use inventories to absorb changes indemand
2. Accommodate changes by varyingworkforce size
3. Use part-timers, overtime, or idle time toabsorb changes
4. Use subcontractors and maintain a stableworkforce
5. Change prices or other factors to
influence demand
-
8/10/2019 Topic 7A-Aggregate Planning (1)
12/51
12
Aggregate Planning Strategies
1)Capacity Option do not try to change demand but attempt to absorbdemand fluctuations
Changing inv entory levels
Varying w ork fo rce size by h ir ing or layoffs.
Varying p roduct io n rates through overt ime or idle t ime.
Subcontract ing. Using part-t ime workers.
2)Demand Option firms try to smooth out changes in the demand patternover the planning period
Inf luencin g demand.
Back order ing dur ing h igh demand periods.
Coun ter-seasonal prod uct m ixing.
These 8 options, along their advantages and disadvantages are summarized
in Table 13.1.(Please refer Heizer and Render textbook)
-
8/10/2019 Topic 7A-Aggregate Planning (1)
13/51
10/15/2014 13
Methods for Aggregate
Planning A mixed strategy may be the best
way to achieve minimum costs
There are many possible mixedstrategies
Finding the optimal plan is notalways possible
-
8/10/2019 Topic 7A-Aggregate Planning (1)
14/51
10/15/2014 NY - KJP 585 2009 14
Mixing Options toDevelop a Plan
Chase strategy
Match output rates to demand forecast foreach period
Vary workforce levels or vary productionrate
Favored by many service organizations
Disadvantages constantly changingshort term capacity. (hire/fire, overtime,part time, subcontract)
-
8/10/2019 Topic 7A-Aggregate Planning (1)
15/51
10/15/2014 15
Mixing Options toDevelop a Plan
Level strategy Daily production is uniform
Maintains a constant workforce
Stable production leads to better qualityand productivity
Disadvantages Build inventory, or uses
back orders, lost sales.
Some combination of capacityoptions, a mixed strategy, might be
the best solution
-
8/10/2019 Topic 7A-Aggregate Planning (1)
16/51
10/15/2014 NY - KJP 585 2009 16
Aggregate Planning Strategies
-
8/10/2019 Topic 7A-Aggregate Planning (1)
17/51
10/15/2014 NY - KJP 585 2009 17
Summary of Planning Techniques
Technique Solution Characteristics
Spreadsheet Heuristic (trial
and error)
Intuitively appealing, easy to
understand; solution not
necessarily optimal.
Linearprogramming
Optimizing Computerized; linear assumptionsnot always valid.
Simulation Heuristic (trial
and error)
Computerized models can be
examined under a variety of
conditions.
-
8/10/2019 Topic 7A-Aggregate Planning (1)
18/51
Technique for Aggregate
Planning
10/15/2014 18
1. Determine demand for each period.
2. Determine capacities for each period. (regular time,overtime and subcontracting for each period)
3. Consider company policies that may apply to
the workers or to stock levels
4. Determine units costs. (Find also labour costs, hire/lay offcosts, inventory holding costs)
5. Develop alternative plans and examine total
costs
-
8/10/2019 Topic 7A-Aggregate Planning (1)
19/51
10/15/2014 19
Example of spreadsheet for Aggregate Planning
Period 1 2 3 4 5 6 Total
Demand
Output
Regular workerPart time
Overtime
Subcontract
Hire/Lay off
Output (O) - Demand (D)
Inventory
Beginning
Ending
Average
Backlog
Costs:
Output
Regular worker
Part time
Overtime
Subcontract
Hire/Lay off
Inventory
Backorders
Total
-
8/10/2019 Topic 7A-Aggregate Planning (1)
20/51
10/15/2014 NY - KJP 585 2009 20
Aggregate Planning
Example 1:
Period 1 2 3 4 5 6 Total
Forecast 200 200 300 400 500 200 1800
Planners for a company that makes several models of skateboards have gathered
the following information:
Associated data and costs:
Current work force = 15 peopleRegular time labour = RM0.25 per hour
Overtime labour = RM3.00 per unit
Inventory = RM1.00 per unit per period on average inventory.
Back orders = RM5.00 per unit per period
Hire workers = RM50 per worker.
(A temporary worker can produce 15 units per period).
Layoff workers = RM50 per worker.
Labour hours = 8 hour per unit
Workdays = 20 days per period
Subcontract = RM6.00 /unit
-
8/10/2019 Topic 7A-Aggregate Planning (1)
21/51
-
8/10/2019 Topic 7A-Aggregate Planning (1)
22/51
10/15/2014 NY - KJP 585 2009 22
Aggregate Planning
Example 4: Month Jul Aug Sept Oct Nov Dec
Forecast 400 500 550 800 700 700
Cost:
Holding Cost = RM6 per DVD per mth
Normal time labour = RM8 per hr
Overtime = RM12 per hr
Hiring = RM 400 per worker
Layoff = RM 800 per worker
Current work force = 8 workers
Labour hrs per DVD = 4 hrs
Work days per mth = 20 days
Begin inventory = 100
DVDs
No backlog is allowed
Labour hr per day = 8hrs
Max hrs for OT are 50% of
the normal working hrs
Solutions
http://localhost/var/www/apps/conversion/tmp/scratch_2/Aggrgt%20plan_ex4.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_2/aggre_examples.dochttp://localhost/var/www/apps/conversion/tmp/scratch_2/Aggrgt%20plan_ex4.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_2/aggre_examples.doc -
8/10/2019 Topic 7A-Aggregate Planning (1)
23/51
10/15/2014 NY - KJP 585 2009 23
Master Production Schedule
(MPS) A time table that specif ies what is to be
made and w hen
Must be in acco rdance w ith the agg regate
product ion plan
The MPS is the resul t of the product ion
plann ing process
The AP is establ ished in overal l terms, the
MPS is establ ished in terms o f speci f ic
produc ts
The MPS is a statement o f what is to be
produced, no t a forecast of demand
-
8/10/2019 Topic 7A-Aggregate Planning (1)
24/51
10/15/2014 NY - KJP 585 2009 24
MPS Example
-
8/10/2019 Topic 7A-Aggregate Planning (1)
25/51
10/15/2014 NY - KJP 585 2009 25
Material Requirements
Planning (MRP) A sys tem of planning and schedul ing the
materials requ irements for prod uct ion operat ions
Material Requirement Plann ing is a tool gearedspeci f ical ly to assemb led operat ions
MRP provides answers fo r several quest ions for
the suppl iers:
What items are required?
How many are requ ired?
When are requ ired ?
MRP is common techn ique for dependent demand
-
8/10/2019 Topic 7A-Aggregate Planning (1)
26/51
MRP
The structure of the system:
10/15/2014 NY - KJP 585 2009 26
MRP
-
8/10/2019 Topic 7A-Aggregate Planning (1)
27/51
MRP requires 3 main inpu ts:
1. Mas ter Product ion Schedu le(what is to
be made and when)
This governs the MRP systems actions on the timing of procuringmaterials and producing sub-components so that it meets the MPS
output schedule.
2. B il l of materials (materials and parts
required to make the product) Bill of materials is a listing of the components, their description, and
the quantity of each required to make one unit of a product.
This provides the product structure information to the MRP system.
10/15/2014 NY - KJP 585 2009 27
MRP
-
8/10/2019 Topic 7A-Aggregate Planning (1)
28/51
-
8/10/2019 Topic 7A-Aggregate Planning (1)
29/51
10/15/2014 NY - KJP 585 2009 29
Bills of Material
List o f components, ingredients,
and mater ials needed to make
product
Prov ides product structure
Items above given level are cal led
parents
Items below given level are cal led
chi ldren
-
8/10/2019 Topic 7A-Aggregate Planning (1)
30/51
-
8/10/2019 Topic 7A-Aggregate Planning (1)
31/51
10/15/2014 NY - KJP 585 2009 31
BOM Example 2
B(2)Std. 12 Speaker kit C(3)Std. 12 Speaker kit w/amp-booster
1
E(2)E(2) F(2)
Pack ing bo x and
instal lat ion ki t of wire,bol ts , and sc rews
Std. 12 Speakerboo ster assembly
2
D(2)
12 Speaker
D(2)
12 Speaker
G(1)
Amp-booster
3
Product structure for Awesome (A )
A
Level
0
Independent Demand
Dependent Demand
-
8/10/2019 Topic 7A-Aggregate Planning (1)
32/51
10/15/2014 NY - KJP 585 2009 32
BOM Example
B(2)Std. 12 Speaker kit C(3)Std. 12 Speaker kit w/amp-booster
1
E(2)E(2) F(2)
Pack ing bo x and
instal lat ion ki t of wire,bol ts , and sc rews
Std. 12 Speakerboo ster assembly
2
D(2)
12 Speaker
D(2)
12 Speaker
G(1)
Amp-booster
3
Product structure for Awesome (A )
A
Level
0
Part B : 2x num ber of As = (2)(50) = 100
Part C: 3x num ber of As = (3)(50) = 150
Part D: 2x number of Bs+ 2x number of Fs = (2)(100) + (2)(300) = 800
Part E: 2x number of Bs
+ 2x num ber of Cs = (2)(100) + (2)(150) = 500
Part F: 2x num ber of Cs = (2)(150) = 300
Part G: 1x number of Fs = (1)(300) = 300
-
8/10/2019 Topic 7A-Aggregate Planning (1)
33/51
-
8/10/2019 Topic 7A-Aggregate Planning (1)
34/51
10/15/2014 NY - KJP 585 2009 34
The Planning Process
Figure 14.1
-
8/10/2019 Topic 7A-Aggregate Planning (1)
35/51
10/15/2014 NY - KJP 585 2009 35
Time-Phased Product Structure
| | | | | | | |
1 2 3 4 5 6 7 8Time in w eeks
F
2 weeks
3 weeks
1 week
A
2 weeks
1 week
D
E
2 weeks
D
G
1 week
1 week
2 weeks toproduce
B
C
E
Start produ ct ion of DMust h ave D and Ecom pleted here soproduct ion can
begin on B
Figure 14.4
-
8/10/2019 Topic 7A-Aggregate Planning (1)
36/51
10/15/2014 NY - KJP 585 2009 36
MRP Structure
Figure 14.5
Output Reports
MRP byper iod repor t
MRP bydate report
Planned orderrepor t
Purchase advice
Except ion repor ts
Order early or lateor not needed
Order quant i ty toosmal l or too large
Data Files
Purchasing d ata
BOM
Lead t imes
(Item m aster file)
Inventory d ata
Masterproduct ion schedu le
Materialrequirementplanningprograms
(computer andsoftware)
-
8/10/2019 Topic 7A-Aggregate Planning (1)
37/51
10/15/2014 NY - KJP 585 2009 37
Material Resource Planning II
(MRP II)
Once an MRP system is in p lace, inventory
data can be augmented by other useful
in format ion
Labor hours
Material co sts
Capital costs
Virtual ly anyresource
System is general ly cal led MRP II or
Material Resource Planning
-
8/10/2019 Topic 7A-Aggregate Planning (1)
38/51
10/15/2014 NY - KJP 585 2009 38
Is an integrated information system that shares data amongand synchronizes the activities of production and otherfunctional areas of the business.
MRP II is an extension of MRP to synchronize all aspects ofthe business (i.e. not only manufacturing).
Therefore MRP II system coordinates sales, purchasing,
manufacturing, finance, engineering by adopting a focal
production plan and by using one unified data base to plan andupdate the activities in all the systems.
MRP IIMaterial Resource Planning II(MRP II)
-
8/10/2019 Topic 7A-Aggregate Planning (1)
39/51
10/15/2014 NY - KJP 585 2009 39
Material Requirements Planning
ExampleDraw up a product ion schedule for 2000 uni ts o f prod uct A.As sum e the units are required on week 20
DB
A
C
E
E E
DC E E
I tem LT BatchQty
OnHand
A 4 - 0
B 4 100 200
C 3 500 750
D 4 200 400
E 3 400 2000
Solution
-
8/10/2019 Topic 7A-Aggregate Planning (1)
40/51
10/15/2014 NY - KJP 585 2009 40
Material Requirements Planning
DB
A
C
E
E E
DC E E
-
8/10/2019 Topic 7A-Aggregate Planning (1)
41/51
10/15/2014 NY - KJP 585 2009 41
Material Requirements Planning
Week Item Gross
Reqmt
On
Hand
Net
Reqmt
LT Order
Week
Order
Qty
Remain
20 A 2000 0 2000 4 16 2000 0
-
8/10/2019 Topic 7A-Aggregate Planning (1)
42/51
10/15/2014 NY - KJP 585 2009 42
Material Requirements Planning
DB
A
C
E
E E
DC E E
-
8/10/2019 Topic 7A-Aggregate Planning (1)
43/51
10/15/2014 NY - KJP 585 2009 43
Material Requirements Planning
Week Item Gross
Reqmt
On
Hand
Net
Reqmt
LT Order
Week
Order
Qty
Remain
20 A 2000 0 2000 4 16 2000 0
16 B 2000 200 1800 4 12 18(100) 0
16 C 2000 750 1250 3 13 3(500) 250
16 D 2000 400 1600 4 12 8(200) 0
-
8/10/2019 Topic 7A-Aggregate Planning (1)
44/51
10/15/2014 NY - KJP 585 2009 44
Material Requirements Planning
DB
A
C
E
E E
DC E E
-
8/10/2019 Topic 7A-Aggregate Planning (1)
45/51
10/15/2014 NY - KJP 585 2009 45
Material Requirements Planning
Week Item Gross
Reqmt
On
Hand
Net
Reqmt
LT Order
Week
Order
Qty
Remain
20 A 2000 0 2000 4 16 2000 0
16 B 2000 200 1800 4 12 18(100) 0
16 C 2000 750 1250 3 13 3(500) 250
16 D 2000 400 1600 4 12 8(200) 0
12 C 1800 0 1800 3 9 4(500) 200
12 D 1800 0 1800 4 8 9(200) 0
-
8/10/2019 Topic 7A-Aggregate Planning (1)
46/51
10/15/2014 NY - KJP 585 2009 46
Material Requirements Planning
DB
A
C
E
E E
DC E E
-
8/10/2019 Topic 7A-Aggregate Planning (1)
47/51
10/15/2014 NY - KJP 585 2009 47
Material Requirements Planning
Week Item Gross
Reqmt
On
Hand
Net
Reqmt
LT Order
Week
Order
Qty
Remain
20 A 2000 0 2000 4 16 2000 0
16 B 2000 200 1800 4 12 18(100) 0
16 C 2000 750 1250 3 13 3(500) 250
16 D 2000 400 1600 4 12 8(200) 0
12 C 1800 0 1800 3 9 4(500) 200
12 D 1800 0 1800 4 8 9(200) 0
13 E 1250 1250 0 3 - - 0
-
8/10/2019 Topic 7A-Aggregate Planning (1)
48/51
10/15/2014 NY - KJP 585 2009 48
Material Requirements Planning
DB
A
C
E
E E
DC E E
-
8/10/2019 Topic 7A-Aggregate Planning (1)
49/51
10/15/2014 NY - KJP 585 2009 49
Material Requirements Planning
Week Item Gross
Reqmt
On
Hand
Net
Reqmt
LT Order
Week
Order
Qty
Remain
20 A 2000 0 2000 4 16 2000 0
16 B 2000 200 1800 4 12 18(100) 0
16 C 2000 750 1250 3 13 3(500) 250
16 D 2000 400 1600 4 12 8(200) 0
12 C 1800 0 1800 3 9 4(500) 200
12 D 1800 0 1800 4 8 9(200) 0
13 E 1250 1250 0 3 - - 0
12 E 2(1600) 750 2450 3 9 7(400) 350
-
8/10/2019 Topic 7A-Aggregate Planning (1)
50/51
-
8/10/2019 Topic 7A-Aggregate Planning (1)
51/51
10/15/2014 NY - KJP 585 2009 51
Material Requirements Planning
Week Item Gross
Reqmt
On
Hand
Net
Reqmt
LT Order
Week
Order
Qty
Remain
20 A 2000 0 2000 4 16 2000 0
16 B 2000 200 1800 4 12 18(100) 0
16 C 2000 750 1250 3 13 3(500) 250
16 D 2000 400 1600 4 12 8(200) 0
12 C 1800 0 1800 3 9 4(400) 200
12 D 1800 0 1800 4 8 9(200) 0
13 E 1250 1250 0 3 - - 0
12 E 2(1600) 750 2450 3 9 7(400) 350
8 E 2(1800) 0 3600 3 5 9(400) 0